Given the economic data for an investment proposal:
I= $500 S=$100
t= 0 1 2 5
i*=r=15%
1. Compute NPV for this project.
2. Is this project acceptable?
Question two:
The cash flow profile for an investment proposal is as follows:
t= 0 1 2 3 4 5
i*=r=15%
1. Compute NPV.
2. Would you consider this project profitable?
Question three:
The cash flow profiles for two mutually projects are as follows:
Project A
(lump sum at t=0)
I= $15000 S=$0
A=$25000
t= 0 1 3
i*=r= 15%
Project B
(lump sum at t=2)
I= $125000 S=$0
A=$50000
t= 0 2 6
i*=r= 15%
1. Compute NPV for both project.
2. Based on NPV; which project would you choose.
Question four:
The time diagram for an investment proposal is as follows.
A=$60 S=$0
t= 0 1 2 3 9
i*=r=13%
1. Calculate NPV and ROR for this project.