WSS G&A DEMONSTRATION RE!
Unitor Galley & Accommodation Mixing stations 4-4 & 4-14:WSS G&A DEMONSTRATION REPORT
DELIVERY ITEMS:
Unitor mixing station 4 - 4 & Unitor mixing station 4 - 14 are delivered in very good condition.WSS G&A DEMONSTRATION REPORT
MIXING STATION INSTALLATION:
According to C/O Masalov and crew's convenience we decided to install the Mixing units 4-4 & 4-14
inside crew changing room on main deck. Where enough space and good pressure of water supply
around 1.7- 3 bar is ensured. With the assistance of fitter we assembled the units, We placed labels
‘on each hoses and selector with corresponding chemicals name to make sure that the crew will not
be confuse in the operation of units.WSS G&A DEMONSTRATION REPORT
ORIENTATION AND DEMONSTRATION OF THE UNITS 4-4 & 4-14 MIXING
STATION:
We oriented the crew regarding the purpose and operation of the mixing stations.
Familiarize the crew regarding the tip selection and chemicals. Provided soft copy of
literatures and videos.