Sr Description Qty UoM Unit rate Total

1 Power & energy meter with RS 485 5 no. 12500 62500

2 CTs 15 no. 500 7500


3 Data cabling 25 Metres 750 18750
4 Monitor & keyboard 1 set 12500 12500
5 UPS 1 no. 5000 5000
6 LAN connectivity 1 set 5000 5000
7 EnMS module embeded on PC 1 set 0 0
8 One time installation cost 1 lot 10000 10000
0
A Cost of installation 121250
Rental per month with MIS
B reporting 6 month 10000 60000

Total A & B 181250