LPG LIQUID & VAPOUR PIPELINE REPLACEMENT AT

PIPELINE DG BERTH
(28 - 30 AUGUST 2022)
DAY DAY 3 DAY 4 DAY 5
Time
DATE 28/8/2022 29/8/2022 30/8/2022
07.00am
Isolate 18m pipe
08.00am (new fabricated) and
purge the line Pipe Wrapping &
09.00am
Scaffolding repair Holiday test new
10.00am fabricated pipe
Pipe Wrapping &
11.00am Holiday test new
fabricated pipe
12.00pm
ACTIVITY 1.00pm
2.00pm
3.00pm
4.00pm
5.00pm
Pipe Wrapping &
6.00pm Holiday test new
fabricated pipe
7.00pm