You are on page 1of 121

Atechnical history of the Rio Tinto mines:

some notes on exploitation from pre-Phoenician times


to the 1950s
Atechnical history of the Rio Tinto mines:
some notes on exploitation from pre-Phoenician
times to the 1950s

Leonard Unthank Salkield

Edited by Maurice J. Cahalan

()I I
nrnr;Jrnr;J[ The Institution of
L..:J.JULlJ.JUU Mining and Metallurgy
I I
Published at the office of
.illl.lil \The Institution of Mining and Metallurgy
44 Portland Place London WlN 4BR England
© The tnstitution of Mining and Metallurgy 1987
ISBN-13: 978-94-01 0-8017-0 e-ISBN-13: 978-94-009-3377-4
001: 10.1007/978-94-009-3377-4
Contents
page
Editor's note IX 6 Copper production 1849- 72 97
7 Formation and corporate evolution of The Rio
Introduction 1 Tinto Company LId 97
Chapter 1 8 Environmental - land. forestry and farming 100
The pre-Roman period 5 102
9 fundicion Mina - furnace charge 1880- 1889
Chapter 2 10 The Bessemer smelter and its operations
The Roman period 9 1901 - 14 102
Chapter 3 11 Pyritic smelting - furnace charge 1913 104
from rediscovery in the sixteenth century until
12 Summary of production and manpower during
the eighteenth century 18 the period of RTC operations. 1874- 1954 105
Chapter 4 References 108
The mines under Government control 24
Index lIO
Chapter 5
Private control. 1829- 49, the Marquis de
Remisa 27 Illustrations
Plans (folded; inside back cover)
Chapter 6
Reproduction of Rio Tinta Mines general plan of works. 1878
The mines returned to Government control. Reproduction of RTM plan of works, 1932;
1849-73 32 corrected March 1935
Chapter 7 fi9 , 1 Map of part of the Province of Hue!va, Spain 3
Early mining operations of The RIO Tinto
Fig. 2 Proposed workings - Rio Tinto Mines, 1873 4
Company limited 39
Fig. l Niebla - walled Roman town 7
Chapter 8
Early metallurgical operations of RTC 43 Fig. 4 Reconstructed Roman water-lifting whee! 12
Chapter 9 Fig. 5 Entrance to Cueva del Lago circd 1880 16
Infrastructure for the RTC operations 45 Fig. 6 Roman shafts exposed in early operations of
RTC 16
Chapter 10
Mining at San Dionisio and North Lode 51 Fig. 7 Ancient workings at Rio Tinlo Mines 17
Chapter 11 Fig. 8 Blast furnace used by Remisa. 1840s 28
Ore classification and preparation for f i9· 9 Refining furnace. 18405 29
shipment 59 Fig. 10 Opencast operations exposing old workings II
Chapter 12 fi9, II SOuth Lode opencast circd 1890 41
HydrometallurgiCal development 61
Fig. 12 Heap roasting circd 1890 42
Chapter 13
Pyrometallurgical development 68 Fig. 13 ·The Rio Tinto Mines in Southern Spain' from
The lIIustrdted London News 1875 47
Chapter 14 Fig. 14 Rio Tinlo Pueblo, early 19005 50
Sulphur production - the Orkla process 79
fig. 15 Plan of the Rio Tinto orebodies 52
Chapter 15
Miscellaneous activities 83 Fig. 16 Steam shovel - Atalaya opencasl 54
Fig. 17 Train approaching Zarandas Naya from 16th
Appendices floor tunnel. 1950s 60
I Roman activity elsewhere in the Iberian Fig. 18 General plan of leaching grounds 66
Peninsula 88 Fig. 19 Cerda precipitation tanks, 1900 68
2 Translation of report by Diego Delgado 89
fi9·20 Bessemer smelter 70
l Report of 1727 by Robert Sitee 91 fi9. 21 ·Bisbee' converter 71
4 Copper production 1829- 1849 94 Fig. 22 Bessemer smelter. Mar asmilla Dam and
5 Commentaries relating to the Remisa era 95 Cerda leaching area 78

vii
Editor's note
leonard Salkield was born in Hoddesdon. To us has fallen the stimulating and challenging
Hertfordshire. in 1901 and graduated Irom the Royal opportunity of editing and presenting the informaUon
School 01 Mines. london. in 1922. He worked at that he collected in a lorm 01 which we hope that he
Enthoven's lead refinery in Rotherhithe and Eastern would have approved. It was never his aim to
Smelting Company's tin smelter in Penang (Malaysia) duplicate the history 01 The Rio Tinto Company
belore joining the Rio Tinto Company In 1928 to work activities so ably presented in David Avery's book. but
at its copper smelter at Port Talbot In Wales. He he lelt that a volume recording important technical
translerred to the Company's Ewell laboratory in 1929 information would be of value and we agree
and to the Rio Tinto Mines in 1930. He returned to wholeheartedly with him on that. This is not intended
England in 1937 during the Spanish Civil War and. as a history in the accepted sense: rather. it is a
after working on a wartime magnesium metal project. volume of technical notes set in a chronological order.
returned to Rio Tinto Mines in 1946 to spend the roughly to the end 01 the Rio Tinto Company
remainder of his professional career there. operations. Even so. there is a conSiderable amount of
relerence lorward and back. especially since places
He became interested in the history of activities at
and areas are frequently identified by names that they
the site soon after first going to Rio Tinto and his work
on the development of metallurgical processes was a assumed in recent times.
natural complement to his enquiry into the nature of Whereas David Avery drew mainly on records from
the earlier operations. which had lelt so much the old London oflice 01 the Rio Tinto Company In
evidence of smelting on a very large scale. In 1957 he writing his history 01 the Company. leonard Salkield
began to assemble notes for Eric linklater, who had searched through records at the mines and dinering
been invited to write a company history. ThaI project perspectives are given on some episodes. Clerical staff
did not proceed and when David Avery was at the mines kept meticulous operating records. and
commissioned to write a history of the Company· it although it must be said that many 01 the numbers
was natural that the then Chairman of Rio Tinto-linc. contain far fewer significant figures than decimal
Sir Val Duncan. should ask Leonard to assist in points suggest. such records have provided a wealth of
providing inSight into the prehistory of the mines. interesting detail for those technical notes.
This involvement stimulated him to further efforts in The great interest of Rio Tinto to industrial
tracking down information relating to the 4000 or archaeologists has been in unravelling the metallurgy
more years of activities. work by professional employed there and. even in comparatively recent
archaeologists on copper smelting had started at Rio times. metallurgical process development and
Tinto around this time. following earlier dramatic operation has be.n 01 special interest because 01 the
successes in unravelling the ancient technology in the unusual complexity 01 the ores and the novelty 01
Middle East. and l eonard collaborated enthusiastically processes to treat them. With his unrivalled insight into
with the various groups that become involved - his metallurgy at Rio Tinlo. Leonard naturally emphasized
unrivalled knowledge 01 the changes made by the metallurgy in his writings. but he also assembled
operations of the past century was of considerable interesting information on mining and infrastructure.
assistance to them. We have edited the notes to provide a general
In 1962 he received the O.B.E. He continued as a account. albeit slanted towards metallurgical
consultant to Rio Tinto Patino. one of the successor operations. supplemented with more detailed
companies to The Rio Tinto Company. for many years appendices. There are instances where Spanish words
after ·retirement'. living in Spain near Gibraltar and or phrases are not translated because no English
pursuing the collection of information relative to words convey quite the same meaning. or the Spanish
activities at the Rio Tinto mines. When he finally retired is widely used and understood in the mineral industry.
to live in England near his family he embarked on the or for both reasons. For place names for which there is
task 01 preparing his assembled material lor a widely used anglicized version. such as Seville for
publication. With his keen deSire to resolve all possible Sevilla. we have used the anglicized version. Rio Tinto.
ambiguities. access to the British Museum and other literally "fed river", was used as the name of quite
sources of additional information delayed him in this separate townships in the mining area. in referring to
task and. sadly. it was not completed before his death the general area of the mines. and sometimes as an
in 1985. abbreviation lor company names. l eonard Salkield
always referred to the stream itself as ·the Tinto river'
and we have also used that convention; other
• Avery D. Not on Queen Victorld·S birthddY the story of the Rio references to Rio Tinto should be clear from their
Tinfo mines (lOndon: Collins. 1974). 464 p. context.

i,
Many of the references listed are not readily For more detailed archaeological information the:
available to the general reader. An exception is David reader is referred to the publications of the Institute for
Avery's Not on Queen Victoria 'Sbirthday; which Archaeo -Metallurgical Studies attached to the
covers much of the subject matter of these notes for UnNersity of London, 31 -34 Gordon Square, London
the lay reader and provides an admirable account of WClH OPY, England, and to its volume Studies in
social, political and economic issues concerning ancient mining and metallurgy in South-West Spain.·
operation of the Rio Tinto mines from the sixteenth Most of the old plans and photographs used to
century, We have not been able to check some of Ihe illustrate thiS volume have been copied from archives
original documents and Leonard Salkield's translations in the possession of RTZ Limited and from publications
and deductions from such sources are given verbatim. of the Institution of Mining and Metallurgy; exceptions
We have established that Rua Figueroa" is a major are acknowledged in the text.
source for the detailed information and statistics given
in Chapters 3-5. The Institution of Mining and Metallurgy is grateful
to RTZ LId for providing the financial support needed
Some of the terminology used at Rio Tinto may to enable it to undertake publication.
need a little explanation. In mining, levels are
invariably referred to as 'fioars': whether this derives M J Cahalan
from the Spanish 'piso' or was introduced from United 44 Portland Place
Kingdom coal mining is not clear. The massive pyrites, London
as mined, is referred to as 'mineral', 'ore:' or 'pyrites'; if
of significant copper content. it is called cupreous January 1987
mineral or 'cupreous'; low copper pyrites is thus non-
cupreous. Country rock enclosing the lodes is
porphyry; in some areas the copper content means
Ihat this is copper ore. Heap leaching of copper from
massive pyrites is known as 'washing', hence 'washed
are' is pyrites recovered from the leaching heaps.
In a preface to his draft Leonard drew attention to
the help that he had received in compiling his notes
from the late Professor David Williams on geology,
Mr Stanley Tong on the Atalaya openeast.
Dr P.T. Craddock on archaeology, the late
Cot. R.F, Lethbridge, Mr John Hunt. Sr D. Eduardo
Figueroa Poyatos and Mr Ivor Herbert, In preparing
the material that he left for publication I have been
greatly assisted by Professor R.F, Tyleeote and
Dr Lynn Willies.
The author's draft includes considerably more
material than has been published here. Some of the
additional material concerns the RTC copper smelting
operations in South Wales, there is mOTe information
on the: ancient slags. a significant section concerning
the developments in sulphuric acid production, and
more sodal history.
In the expectation that publication of this edited
version could stimulate interest in the further
information, a copy of the draft is lodged in the
Institution of Mining and Metallurgy and can be
examined by arrangement with the Head of Library
and Information Services.

• Rothenberg 6. and 6lanOO-Freljelro A. et al. Studies in ancient


mining and metdlfurgy In South-West Spain: exp/OfdtiOnS dnd
• Rua Figueroa RamOn. MindS de RIo Timo: eSludios sobre /d excdvdtlons in the Province of Hue/va (london: lAMS. 1981).
explotdC/on y e/ benefiCIO de sus mlnerdles (Coruna. 1868). 320 p.

x
Introduction
In the south-west of the Iberian Whether the Phoenicians and t he
Pen i nsula there is a vast pyritic Carthaginians ever actually worked
minera l ised zone , known as the the mines , or were merely traders , is
Andevallo , extending from near not certain , but after 205 BC , when
Seville to south of Lisbon , an area they defeated the Carthagi ni ans, the
some 150 kilometres long and 30 Romans brought their own men s killed
kilomet r es wide. in mining and metallurgy .

The Rio Tinta Mines , which are the The Romans occ upied most of the
l argest of this "pyrites belt" , lie Iberian Peninsula for 600 years ,
in the region known as Andalusia, until about 425 AD - the most recent
some 90 kilometres north-west of Roman coins found at Rio Tinto show
Seville and 75 kilometres north-east the head of Honorius who was emperor
of Huelv8 . They have a very long from 395 to 423 AD. Mining must
history , dating back to pre-Iberian have declined with the invasion of
times; then came the Iberians , a race Barbarians in the 5th century and the
of North African origin (Turdetarian subsequent ent r y of the Visigoths who
and Tartessian) , the Phoenicians , the were eventually absorbed into the
Carthaginians , the Romans , the Moors, people of Spain. In 711 AD the
the Span i ards and the British . It Moors invaded the Peninsula from
is believed that copper was first North Africa. Little min i ng was
recovered from the ores in the third done after the departure of the
millenium BC and that silver . was Romans; the Moors probahly recovered
mined in the late Bronze Age , 12th to some copper from acid drainage waters
9th centur i es BC onwards. by deposition on iron.

The Phoenicians established a trading The Moors were driven out of Spain in
station at Gades (Cadiz) about 1000 1492 and the first extant report on
BC and found the hinterland rich i n the Rio Tinto mines is dated 1556 .
both agriculture and metals - gold , In 1725 a Swede , Liebert Wolters
silver , copper, tin , lead and iron. Sjo hjelm , was granted a licence to
Thei r efforts to dominate the country work five mines in the region, one of
were f r ustrated by the resistance of which was Rio Tinto - the documented
the Tartessians liv i ng to the history of operation of the Rio Tinto
north-west but they apparently traded Mines begins from that date .
successfully and are believed to have
used the fabled port of Tartessos . Over two and a half centuries the
The exact location of Tartessos has mines were worked both directly by
not been identified but jt was Government and by private companies.
pr obably on the estuary of the Tinto In general , Government operations
and Odiel r i vers near Hue lva . wer e unsuccessful , despite the
outstanding men who served Gove r nment
as adminstrators at Rio Tinto. The
In 535 BC , with the dec l ine in power Treasury in Madrid was reluctant to
of the Phoenicians, the Carthaginians supply funds for desirable
conquered southern Spain . They too investment , for example when steam
traded in agricultural produce and power became available it was not
metals and also experienced difficult- i nstalled ; miners could not work
ies with the Tartessians . They lower than the Roman adits , yet steam
we r e r esponsible for the destruction powered pumps could have resolved
of the port of Tartessos. dewatering problems .

- I -
In Ap r i l 1867 a Royal Commission made depressions , until 20 J une 1954 when
recommendations to develop the mines two-thirds of its Spanish assets were
but the Treasury ~as, as ever, sold to a Spanish group of bankers
reluctant to fund the recommended and the company was renamed "Campania
programme and the Gover nment decided Espanola de las Minas de Rio Tinto".
to sell the mines. During a period
of great political turmoil, an Few mines have such a history as Rio
authorising law was passed by the Tinto . These notes concentrate on
Cortes in June 1870 and bids were technical aspects of mining and
invited in the following year. An metal lurgical activities using
offer by a consortium of British and information obtained from a wide
German bankers was accepted and The variety of sources , some well
Rio Tinto Company Limited was documented , some anecdotal. There
registered in London in March 1873. is inevitably a degree of speculation
The events leading to the purchase by about many aspects but, on the whole,
this new company have been chronicled we can deduce a fairly convincing
in detail in David Avery ' s "Not on picture of the activities which have
Queen Victoria's Birthday"(I). taken place over more than 4,000
years .
The purchase price for the mines, in
the form of the freehold of an area It will simplify later references to
of some 1, 900 hectares, was locations to give at this stage some
£3,600,000 equal to 92,800 , 000 genera l description of the mining
pesetas . This was a huge sum at area as it has taken shape in recent,
that time and , although slightly recorded history . Figures 1 and 2,
below the Spanish Government ' s taken from the pr ospectus for the
valuation , was regarded by others who sale of Rio Tinto Company shares to
had contemplated purchase as the public , give details of the local
excessive . geography.

The Chairman of the Rio Tinto The Rio Tinto Mines (Minas de Rio
Company , Mr Hugh Matheson, clearly Tinto) are situated in t he western
had great faith in the reports he foothills of the Sierra Morena , in an
received on the mines from Dr Roemar , area sometimes referred to as the
a German mineralogist, Mr David Sierra de Aracena, with the main
Forbes, a British mining engineer, lodes divided by a ridge which
and Messrs Sundheim and Doetsch , contained four peaks - Colorado ,
general merchants operating from Salomon , Retamar and San Dionisio.
Huelva with interests in mining. Between Retamar and San Dionisio is a
Doetsch was the catalyst who brought pass called Puerto Rubio. The
German finance to join Matheson's highest peak. Cerro Colorado, was 534
marketing and management experience. metres above sea level but has now
been lost through opencast mining .
It certainly did not appear to be a The most impressive peak was Cerro
propitious time to make such a Salomon , 515 metres , but this too
massive investment in Spain - the will soon be mined away . Ea rl ier
State was bankrupt , a Republic had writers about the area thought t hat
just been declared and the country the name Salomon came from the
was in a state of virtual anarchy . biblical King Solomon who came to the
Howeve r there was a rapidly growing throne of David about 970 BC; howeve r
demand for pyrites for sulphuric acid the earliest recorded r eference to
production in Europe for the Cerro Salomon comes from the 17th
expanding chemical industry. century .

The Rio Tinto Company continued The British company began its
mining and smelting in Spain, through operations in 1873 with opencast
two world wars and a civil war , mining of the South Lode , followed by
economic booms but more long lasting underground min ing at South Lode and

- 2 -
San Dionisio in 1880. In 1883 a
start was made on opencast working of Mining f r om 1873 relied on rail
North Lode and three further opencast transport to and from the port of
mines came into operation at the Huelva, and for mineral, waste and
beginning of this century - Lago in supplies movement in the mining area.
1903, Dehesa in 1906 and Atalaya in Installation of the railway was a
1909. Since Campania Espanola de major commitment for the new company
las Minas de Rio Tinto took over in and , seen in retrospect , railway
1954 major opencast mining of gas sans development added to the opportun-
for gold and porphyry for copper has ities to uncover early mining and
transformed the landscape. metallurgical activity.

MAP OF PART or THE PROYINCE OF HUElVA, SPAIN, SHOWING POSITION, ETC, OF THE
RIO TINTO COMP...,.'Y'S PROPERTY, MID OF THE RAILWAY TO THE PORT Of HUELVA

Figure 1

- 3 -
RIO t
.. ~
tI
,

/
X
,I
,
:·! '
·• • .
< .
~.
• 0 •

••
<

- 4 -
[ CHAPTER 1 [ The pre-Roman period
Native copper was probably the first as prills by cr ushing the mass of
discovery at Rio Tinto by man using slag , or as a "bun" where the
metals. It would be produced from smelting temperature and slag
the copper sulphate in acid drainage fluidity were sufficiently high.
waters by reduction with sugars from
decaying vegetable matter. Such Analysis of copper ca r bonate ore
native copper would have been found found in recent times at Rio Tinto
in filamentous or lace- like form, gave:
requiring consolidation into
artefacts, such as pins and fish eu 11.30 % As 0.054 %
hooks , by hammering a nd possibly Pb 0. 28 " Sb 0.054 "
heating. Zn 0.01 " Bi 0.043 "
Sn 0.006" S trace
The ea rl iest metallurgical activity Au 0.20 grams per tonne
in Spain was probably t hat of the Ag 285.0 " " "
Western Neolithic culture in the
province of Almeria. some 350 It is probable that the ancient
kilometres to the east of Rio Tinto. worker s, by careful selection of what
This area was settled by people with would have been mineral specimens,
crafts and habits similar to those of were able to feed considerably higher
the people of the Nile valley . By grade mineral to their smelting
2,500 Be they were extracting copper . furnaces.

Ores used in this copper production Recent arc heological work has
were probably basic copper carbonates confirmed that Rio Tinto was a major
and the technique for smelting such source of silver in ancient times and
ores may have spread fairly readily it is interesting to speculate on how
to the west. An alternative the original discove r y of the silver
possibility advocated by some ores was made , especially as for the
archaeologists is that production of first twenty years of mining by the
copper in Andalusia may have been Rio Tinto Company the silver rich
indigenous and developed earlier than jarosites were discarded in opencast
in Almeria. There is little doubt mining.
that basic copper carbonates ,
produced by secondary enrichment from Copper ores were , of course, readily
the cupreous pyrites, would have been identifiable by their bright green
available . and blue colours but the silver ore,
argento- jarosite, is usually
Methods used for the reduction of described as a "coloured eart h" and
copper carbonate ores in antiquity the discovery of its value as a
have been widely studied and there is source of silver could probably only
now a clear understandi ng of the have been made by heating it, alone
techniques used. Furnaces , the or mixed with charcoal . The source
remains of which consisted of a hole of the Tinto river was apparently in
in the ground lined with clay, were a cave in an area known as Lago where
charged with ore and charcoal . the coloured earths occurred and it
Combustion air was supplied initially is assumed that it was here that the
by blowpipe but the use of bellows ancients made their discovery .
from about 1,200 BC was an important
advance. The smelted charge was Neil Kennedy, a m1nlng engineer
cooled in the bowl , after which employed by the Rio Tinto Company
metallic copper was obtained either from the beginning of its operations ,

- 5 -
wrote in 1893(2): lead anchors were traded with the
silver producers in return for
"When the open-cutting of the South their product."
lode was being made a stone was
found 14 metres below the surface If that interpretation is correct,
(in a cave) in the exact line of the Phoenicians had a remarkably well
contact between the iron pyrites developed approach to optimising
and the capping which superimposes transport costs and to the provision
it. This capping is generally a of lead for the silver producing
coarse iron ore, but in this operations. In cupelling, the
particular spot where the stone was classical process fo r obtaining
found , it was formed of an ochrish silver from the lead bullion in which
looking earth. The porphyry stone it is concentrated in smelting, a
was 38 cm long by 30 wide and 11 cm considerable amount of lead is lost,
deep with eight holes cut in its quite apart from the oxidation of the
surface, each 7.5 cm diameter and 3 lead to form l itharge and that
cm deep , accompanying it was a absorbed in the cupels.
pestle also of porphyry which had a InCidentally the smelting to bullion
rounded head to fit the circular was probably accomplished in
holes. Another very similar stone primitive furnaces with charcoal fuel
was found some little distance as indicated above for carbonate
off. II copper ore.

A geologist who examined the stones Although many had believed that
thought the primitive inhabitants silver, gold and electrum (the alloy
must have employed them for mixing of the two) had been produced at Rio
pigments for body decoration . It Tinto in very ancient times, the
must have been soon after th i s first convincing evidence was
discovery that it was again realised established in 1966 by archaeologists
that the "ochrish-looking earths" from the University of Seville(4 , S).
were silver ore . On the south side of Cerro Salomon
they found foundations of a village
Lead is an essential requirement in extending along the side of the ridge
the recovery of silver from ores by for a total length of 900 metres.
smelting but it is generally assumed Water for this village, high above
that there was little at Rio Tinto the surrounding terrain, was obtained
and elsewhere in the region, and the from a spring in the saddle between
jarosites found at Rio Tinto are the two summits , Cerro Colorado and
usually low in lead . J C Allen(3), Cerro Salomon.
writing in 1970 , referred to this
deficit of lead in relation to the The houses consisted of collections
role of the Phoenicians! of small rooms with walls made of
undressed stone; the period of
"Even if there is no archaeological occupation has been dated as c. 800
evidence of eastern Phoenicians' BC . Stone pestles and mortars were
influence earlier than Be 800 th i s found and the earth floor contained
does not seem to be a valid reason stringers of lead which had leaked
for supposing there was no export from a smelting hearth. Numerous
of s i lver earlier than this date ••• clay tuyeres were fo und and the slag
on some of them had a green
"Interesting in this connection is colouration , as though they had been
the comment by Timacus c. 400 BC used in smelting copper are. No
that the Phoenicians on their furnaces were found , but in one room
return journey substituted silver there was a hearth , about a metre in
anchors for the usual lead ones ••• diameter and 40 ems deep, containing
Thus this ••• • can be considered as partly calcined bones and ashes -
the record of a perfectly normal could this hearth , and others like it
commercial transaction in which the found in the Lago area , have been

- 6 -
used to smelt charges in crucibles? Sierra of Aracena, but its exact
And did these ancients know that bone position could not be explained.
ash was the best material for cupels? Two or three samples were found
like those in the cyclopean wall on
A considerable quantity of shards of the Desembarcadero (wharf) in
the Phoenician period was found and a 1924."
large amphora standing on a piece of
grey slag. This slag was unusual - The Niebla museum was founded by Mrs
it was of greyish colour and Elena Whishaw, the widow of an
obviously only semi-fused, with many American archaeologist who lived in
holes and embedded silica particles Seville. After her husband's death
of the type known locally as she moved to Niebla and built a house
"guijarro". The silica particles in the old Moorish walls. She was
ranged in size between 5 and 15 mm a friend of Lord Milner, who was
and the silver content of the slag Chairman of The Rio Tinto Company
was high - 575 gms per tonne. from 1923-25, and was much respected
Earlier reports, of Courtney(6) and by the local people who she employed
Gonzalo y Tarin(7), mention s lags of in continuing archaeological
this type. Gonzalo y Tarin excavations and in producing sand for
mentions seeing conical mounds of sale. She was responsible for the
wrinkled, sponge-like slag, greyish discovery of the ancient port of
in colour and imperfectly melted, in Niebla.
association with well fused black
slag, at some mines in the province It seems probable, based on the
of Huelva. Niebla slag specimen, that smelting
of silver are was also carried out
More significantly, Courtney wrote: there. Several specimens of the
poorly fused slags from around
"There is no distinct evidence of Huelva, Niebla and Rio Tinto mines
the mines having been worked about have been analysed in recent years
this time (500 BC), although the and show low copper and lead
fact of several heaps of a rough contents, with total silica contents
and spongy class of scorial being over 40% and silver contents of
in close proximity to the lodes, several hundred grammes per tonne.
and always near abundant spring
water, has strengthened the belief
that the heaps are the refuse of
Phoenician smelting."

As so often happens, after the


importance of this slag type had been
recognised following the 1966
discovery at Cerro Salomon, other
samples have been identified. One
was found in the museum at Niebla, a
village on the site of an old Roman
town on railway between the Rio Tinto
mines and the port of Huelva. This Figure 3 Nieb la - Wall ed Roman Town
specimen was described as follows:

"Slag found loose in the soil in In 1973, a slag of this type found at
the course of the excavation of the Calle Palos near Huelva was dated at
"Campi", but never in the cave 400 Be by thermo luminescent dating.
retorts at Niebla. Similar A portion of the same specimen was
samples of slag given to the museum examined to establish its fusibility
some years ago, with the - at 10OO·C the edges of the s~ecimen
information that it had been found were tending to round; at 1200 C the
on the by-pass leading up to the specimen was becoming plastic and

- 7 -
changing shape; it was only when the whose "bajel" was blown through the
temperature reached 1400 C that it Straits of Gibraltar in a severe gale
became molten. Such a temperature to landfall at the port of Tartessos.
could not have been obtained in a This has generally been assumed to
primitive furnace and no satisfactory have been near the mouth of the river
explanation is yet available for Guadalquivir but a much more logical
appa r ently adding silica particles in location would be in the Huelva
such large quantities to the fused estuary . Luzon(S) supports the
mass. Huelva hypothesis and identifies the
site with the biblical Tarshish - at
Elucidating pre-Roman activity on the least two passages in the Bible(9)
basis of examination of slags has state that ships came to Tyre from
made major progress in recent years . Tarshish every three years bringing ,
The vast tonnages of slags from Roman among other items , gold and silver.
exploitation created considerable Bronze items, dated at c.700 BC were
difficulties which were further dredged from the Huelva estuary in
compounded by the superimposition of 1923 and are on display in the museum
workings after the rediscovery of the in the town .
mines in the 16th century.
The Greeks wrote that Tartessos was
Exploitation by the Phoenicians on, or near , a river whose source was
created some infrastructure and a cave in a silver mountain . This
references from early literature can could have been the Tinto river and
be pieced together to suggest the the Lago cave . However, early
identity of some of the places named reports of this river mentioned that
in Greek and Biblical sources. particles of tin were seen in it;
there is no tin- stone or cassiterite
Silver metal, perhaps in the form of in the Tinto river but there could
bars weighing between 4 and 15 minas have been grains of ilmenite, whose
(a mina was a weight of about 400gms) colour and appearance are not very
must have been collected from mines, different from those of cassiterite.
large and small , and sent to depots Before the Romans opened up the mines
from which it could be delivered to a and thus provided the conditions to
port capable of handling sea-going promote oxidation of the pyrites
vessels and providing shelter from which was the first stage in
severe weather. There may also have producing the red coloration of the
been movement of jarositic ore , from drainage waters, the river would have
small mines to larger mines with been only slightly coloured.
smelting facilities, or possibly for
export, although that seems less By 400 BC t he port of Tartessos was
likely. already in decline, perhaps because
of silting or because the island on
In the province of Huelva there were which it was built was sinking. It
two places suitable for depots; one was finally destroyed by the
was Niebla which, on the evidence of Carthaginia ns.
the excavated port , would have been
capable of taking the large boats. There was probably another depot
The other possible site is Araraque, further west on the Guadiana river,
on the west side of the estuary of near the present day town of
the rivers Odiel and Tinto and Ayamonte. where tin or tin ore was
opposite the present town of Huelva. stored . Alluvial cassiterite was
certainly to be seen in the bed of
The historian Herodotus (c . 484-425 the Guadiana and has been observed
BC) wrote about Colaeus of Samos there in recent times .

- 8 -
I CHAPTER 2 I The Roman period

When the Rio Tinto Company Limited incalculab l e" and no doubt the
(hereafte r normally abb r eviated as ca l culation would have proved a
RTC) started its operations in 1873 , daunting one with the facili t ies
the r e must have been some evidence of available to those compiling that
mining pri or to entry of the Romans. inventory .
Unfortunately, little notice seems to
have been taken of such evidence, the Not much is visible of those slag
staff being fully involved in the heaps today ; they have largely been
exciting new activities , and it was c overed with overburden f r om recent ,
probably obli t erated . In any case post 1960 , open - cast mining. From
interest in pre-history was not at the evidence of the coins found, many
all common in the I870s . tn the slag heaps, it has always been
assumed that the Romans occupied the
The evidence of Roman occupation was , Mines from the time of Augustus (27
and still is, much more substantial , BC to 14 AD) to that of Honorius
notably in the extensive slag heaps, (395 to 423) . A sample of charcoal
although there has been some taken from a slag heap at 2 metres
exaggeration about the size of such above ground level and under a
heaps . Diego Delgado, in the first further 4 metres of slag gave a
extant report(lO) on the Rio Tinta carbon 14 dating of 140 AD + 95 years
mines dated 1556, wrote : which fits reasonably the assumed
time frame but some authorities now
"These slag heaps are so massive believe the period of occupation was
that they appear to be large hills somewhat longer , perhaps as much as
and mountains . Could these slag 600 years .
heaps which we saw up to two
leagues long and two leagues wide Strabo(12) , who lived from 63 BC
wit hout do ubt be those wh i ch we until 19 AD , indicated the position
we r e told were more than eight of the mining field. He wrote :
l eagues long? "
" A chain of mountains parallel to
Again , in 1632 Caro(ll) wrote : the Boetis (Guadalquivir) exte nd ing
towards the north . . . . they enclose
" Near the mine can be seen hills of a quantity of mines .... Near the
charcoal and slag for many leagues , site called Cotinas is produced
a simple glance gives a terrorizing gold and copper. These mountains
aspect causing apprehension and are to the left of those which
dismay to the casual and infrequent ascend the river . . . .. The Anas
visi t or . For leagues it covers (Guadiana) is also navigable , but
the ground and rises to hills ." not for such a length , nor with
such large vessels . Its edges
Since a Spanish league of that time are also bordered by mountains
was about 5 . 5 kilomet r es, in the which contain mines. !!
light of what we have now established
of the Roman ope r ations , both the Some people believe that Cotinas is
above authors must have taken Rio Tinto; certainly the mountains
considerable licence in their enclOSing Rio Tinto can be seen from
descriptions . Later. at the time Italica near Seville . The probable
of the offer of the mines for sale in importance of the Guadiana as a
1871, the of fi cial inventory stated : mineral route fo r tin, coppe r, gold
"The amount of slag accumulated in and silver has been referred to in
the place ca l led Dehesa is Chapter :t.

- 9 -
In Roman times the Tinto river was province of Huelva in 1865 and has
named Urium , meaning burning, provided one of the few detailed
because, presumably, of the corrosive impressions of Rio Tinto prior to the
nature of its water. Its source commencement of operations by RTC .
was said to be in a place named Gran Two extracts from his report are
Bitania and the port at its mouth, relevant here:
now Huelva, was known as Onuba.
" In many mines of the district,
There are several accounts of the amongst them El Tharsis, Buitron
mine workings provided by visitors and Rio Tinto, I observed a very
after the rediscovery by Diego marked depression in the ground
Delgado. According to Gonzalo y immediately over the deposit, the
Tarin(7), who apparently produced a walls of which rose above its level
geological survey of the area in the and defined clearly the width of
1880s, soon after RTC began exposing the mineral below . Where these
old workings in the course of its depressions are observable, I
operations, there were no less than myself have no doubts that the
thirteen Roman adits; nine to the Romans, or their predecessors,
east of Cerro Salomon and four to the worked the mines by means of
north. open-cutting. This view is
confirmed by the character of the
The Romans worked the jarosite filling in the cases in question,
formation for silver and the main the oxide of iron (gossan) is found
sulphide bodies for copper . The in detached masses, and the
exposed area of green malachite and decomposed porphyry and slat~
blue azurite might, according to some predominate. The line of
geologists, have always been quite junction between the covering and
small. However, Gonzalo y Tarin(7), mineral is regular and unbroken and
wrote: looks more like the work of human
hands than a natural formation .
liThe ancient mining consisted of At the Lagunazo mine, where works
shal low opencast workings following have lately been commenced by an
the direction of the ore. The English company, ore has been cut
very similar disposition and layout to a depth of seven metres from the
of all these work ings presupposes surface ; this I am inclined to
that the ore outcropped, which believe is no special instance, and
naturally helped the miners to find that in cases where the depressions
the best places for extracting the described above are observed, the
ore." ore has been found near the surface
and taken away by old men. In
He was reporting on the many small many instances old shafts are found
opencasts that he saw at a number of perforating the filling-in which
mines in the province of Huelva cove rs the mineral. These I am
where, in the main, copper carbonate inclined to regard as the work of
ores had been extracted Romans, and that when they came
to Spain they found the backs of
In 1856, Anciola and de Cassio(13) the lodes had already been taken
reported seeing opencasts on the spur away by the Phoenicians and
north of Cerro Colorado, at Dehesa, Carthaginians and were compelled to
south of San Dionisio and at other have recourse to shafts and adits
places and concluded they had been to continue the working of them."
made by Romans . Rua Figueroa, who
was resident at the mines from the "In the vicinity of most of the
1850s and manager from 1859 until deposits of pyrites , there are
1863, also refers to such opencasts quantities of old slag, bu t at Rio
in his publications( 14 ,15 ) . Of Tinto the extent of the ground
particular interest is a report of cove red with them is immense: there
Lee Thomas(l6). He visited the are hills composed entirely of

- 10 -
them, which lite r ally cover a in 1887(17) :
considerable sur f ace of country ;
the quantity appears fabulous, and "The Roman m~nl. n g works a r e on a
must be seen to be cr edited •••• In gigantic scale , consi dering the
comparison with Rio Tinto the means at their disposal , adits at
mounds of slag to be seen at the various levels are still open and
other mines of t he district are large cav i ties are found . The
insignificant, and almost lead one largest workings are set near the
to the conc l usion that the former walls of t he lodes where the copper
must have been a centre of smelting minerals are r i chest and easiest to
operations , on account of the work. The upper levels of the
abundance of fuel in the vicinity . mines contain secondary enrichment
This theo r y is rather borne out by and chalcocite was found near the
the occu rr ence of lead slags at Rio walls of the lode. "
Tinto. "
Adits were employed to drain the
Despite the impression made on him by operations , a relati vely simp l e
the vast accumu l ations of slag , matter for the jar osite mining
Thomas was "struck with the seeming operations but copper min i ng extended
insignificance of the Roman workings, below adit level and wa t er whee l s
in those parts of these mines were used to lift wate r. Some
recently opened, compared with what I thirty such wheels have been found in
had expected ." This would have the workings at Rio Tinto, the
reinforced his supposition that Rio l argest 4 . 6 metres in diameter .
Tinto had been a smelting centre; as The hubs of the wheels were made of
became clear in later years and was oak , the spokes , buckets and rims of
probably not obvious at the time of pine , and the assemblies fitted
his visit , underground operations had together with wooden pegs and mounted
been conducted in several areas and on a bronze axles. Motive power
the full extent of them was not was provided by men standing on
apparent until the RTC operations cleats attached to both sides of the
were well advanced . wheels .

Kennedy(2) , wrote shortly after RTC In 1919- 20 in the Pl anes mine , a rich
began operations : copper area of Rio Tinto which had
been extensively mined by the Romans ,
"The opening of these mines in a set of eight such wheels was fou nd .
modern times has shown that the Th i s installation was arranged to
ancients simply worked the richest lift water almost 30 metres.
spots • •• . Now these rich pockets Palmer(18) has written an accou nt of
were not easi l y or quickly found by some of the old workings and of this
a race who had no knowledge of discovery - he tested a reconstructed
blasti ng operations and although wheel and establ i shed that it needed
the main masses of pyrites are , as a force of about 70 kilos to operate ,
a rule, easily discovered , yet raising water about 3 . 7 met r es .
those of themselves were not rich
enough for the'ancients" On the Roman mining methods Palmer
wrote :
There would have been some secondary
enrichment and Rua Figueroa(15) , "Although the are bodies were
reported finding chalcocite penetrated by ma ny ramifications of
containing 68 % Cu near a mine shaft. small galleries, the author knows
That was no doubt very exceptional; of no large stapes having been
it is usually assumed that the Romans found , and thus he can produce no
smelted ore of between 10 and 22% Cu . detailed evidence of the general
mining methods adopted. In the
John F Allan , another of the early oxidised zone , from which apparent -
mining engineers with RTC, reported ly the ancients obtained most of

- I I -
the minerals mined , and where the The significance of the oper ations
over lying burden was more or less for silver was not appreciat ed by
shallow , the system adopted appears Gonzalo y Tarin . It is t r ue that
to have been that of sinking a the opencast operations we r e the
shaf t, or possibly a pair of source of a large part of the copper
shafts, into the zone , extracting ore smelted by the Romans and the
all the are which could easily be Phoenicians ; we now know that a l arge
r eached from these shafts, and then fraction of the slags were the result
sinking othe r shafts in the of si l ver production from t he
immediate vicinity . jarosite formation and most of th e
shafts which early 19th century
"When the overburden , however , was visitors saw were used in mi ning the
greater than the shaft system jarosite silver ores .
warranted , the system appears to
have consisted of providing It is easy to understand why those
timbered galleries which radiated examining the mining areas of the
in all directions, and extracting province in the 17 - 19th centuries
what could be reached from these . did not appreciate the significance
This system was apparently ve r y of the exploitation of the Rio Tinto
effec t ive, as not much of any value deposits for silver ; the obvious
appears to have been left in those association was with treatment of
places where the gallery system was copper. There was contin uing mystery
complete ." associated with the very low copper
content of much of the slag - that
derived from silve r reco very - and
other evidence of silver recovery was
sometimes assumed , for example by Rua
Figueroa(l5) to indicate only that
the Romans recovered the silver from
the copper ; they were known to ha ve
done that elsewhere .

However, Fernando Bernaldez , who was


employed at Rio Tinto as a metal l ur g-
ist , wrote in 1853(18) putting
forward the view that the slags at
Dehesa arose f r om smelting lead are .
He found metallic lead containing
about 1700 gms per tonne of silve r in
the Dehesa heaps , whereas copper
found on wha t he considered to be
slag heaps f r om copper smelting ,
contained only the same amount of
silver as that in the coppe r are , say
about 50 gms per tonne. Because of
these investigations he wrote : li Sa we
are not making foolish statements
when we say that the original miners
recovered silve r and gold ."

In recent times , the location of some


slags , clearly from copper smelting ,
underlying slags from silver
production was a puzzle unti l 1979 ,
when a team of archaeologists under
Figure 4 Reconstructed Roman Dr P T Craddock , found a very large
Water- l i fting Wheel accumulation of copper slag , much of
it in the form of larg e di scs such as

- 12 -
would have been formed in tapping the arsenic and lead contents of the
copper and slag into a bowl. The massive gossan are approximately
significance of these s l ag discs ha s 0 . 7% ; copper ave r ages 0 .1 %.
been described by Tylecote(20) . Jarosites do not appea r until the
base of the gossa n is reached ... •.
The l ocation of thi s s lag, which wa s t he lower part of the gossa n is
far removed fr om t he main su lphide commonly marked by an earthy layer,
bodies , is now assumed to indica te up to 1.25 metres t hic kness, whi ch
that it was derived from the is comparari vely rich i n gold and
smelti ng of carbonate ores. si lver, lead, antimony (a r senic) ,
Although geologists ea rlier this bismuth and selenium . Locally.
cen tury were of t he opinion that the this laye r incl udes bands of
original fo rmations contained little yel low , red, grey and black earths
suc h oxidised ore, thi s find s uppor ts whose relative positions are not
the views put fo rward by Gonzalo y always constant.
Tarin and Lee Thomas that sig nifi ca nt
ex ploita tion based on opencasts had "In most places , the yellow variety
taken place in ancient times - by predominates , often to the
Tartessians , and possi bl y Phoenicians exc lusion of others • . •. in hand
a nd Ca rthaginian s , as well as Romans. specimens the yellowish material
It now seems that t he Romans did might easily be mistaken for
con tinue to work oxide deposi ts where och reous limonite , or some i ron
t he y were available, but their majo r s tained earthy material . Much of
tec hnolog i ca l achievement was in it ca n be cru shed with the
underground mining of the s ulphide fingers ."
coppe r and jarositic silve r ores.
David Williams estimated that 3
It is important to understand a million tonnes of jarosite had been
l i t t le of the geology to app reciat e present before mining began and that
t he significance of the si lver perhaps 2 million had been extracted
operations. Pr ofesso r David by the Ancients a nd the Romans .
Williams spent many years at Rio However , the vast to nnage of slag
Tinto from the late 1920s and fo und at Rio Tinto. until recently
published several papers on its estimated at 20 million tonnes,
geology . From one of t hese indicated the smelti ng of a
publications(21) , the fol l owing conSide rably grea ter qua ntity of ore.
ex tract has been taken : Ca l culati ons i nd icate that about 4 . 5
tonnes of slag would normally be
"The thick mantles of gossan produced in smelting one tonne of ore
formerly overlay the massive so t hat 2 mi llion ton nes of jarosite
deposits (of pyr ites) at Sa n would yi eld 9 mi llion tonnes of s lag .
Dionisio, Sout h Lode , North Lode To this s hould be added an allowance
and Planes, wh i l st the co nspicuous for re smel ting of high sil i ca
reddi s h gas san crown of Cerro Phoenician slags and for smelting
Col orad o represents t he oxidi sed ores brought to Rio Tinto from other
remains of long vanished or e mining sites, still suggesti ng a
bodies . The base of t he gossan l arge discrepa ncy.
is generally flat lying and is
us ua lly more s ha rpl y def ined when Although RTC was not immediately
resting upon massive pyrites than conce rned with unravelling the early
when covering heavily i ron s t ained hi s tory of operations at the site , a
porphyry. Ove r a wide area of sur vey of the old slag heaps wa s made
Cerro Colorado the gossa n, for a in 1880 and a further s urvey in 1924;
thickness of about 24 metres , meanwhi l e large quantit ies of the
contains the equ i valent of more s lags had been used as ballast on the
than 50% iron together with 1 . 25 oz exte nsi ve railway s ystem . I t is
(43 gms per tonne) of si lver and 1 estimated that as much as 4 million
dwt (1.7 gms) of gol d. Both the tonnes was used for r a ilway and other

- 13 -
construction purposes before the 1924 base of the gas san examined.
survey which listed 1 million tonnes Some of the i r onstone filling ran
of copper smelti ng slags assaying 8.4 gms Au and 198 . 8 gms Ag per
0.74% Cu and 4.7 gms per tonne Ag, 1000 kilos . I t looks as if the
and 15 million tonnes of silver slags majority of the ore , in the
assaying 0.13% Cu , 0 . 40 % Pb and 54.3 immediate vicinity of t he shaft,
gms per tonne Ag . has been mined out by the Ancients
"
The figures for copper slags include
slags made in the 18th and early 19th Between about 700 BC and the entry of
centuries. A significant tonnage the Romans to Rio Tinto. the primit-
of copper slags was burien by 18th ive batch furnace slowly developed
century operations and hence not into the blast furnace . With this
included by the survey. [Since advance, it was no longer necessary
Leonard Salkield's death, a new to allow the furnace to cool before
survey of the ancient slags has been removing the slag and metal , instead
completed under the direction of the the molten materials could be
Institute for Archeo-Metallurgical discharged into pits , allowing the
Studies and this has established a furnace to receive another charge
much lower figure of around 6 million while sti l l hot .
tonnes which accords quite well with
the smelting of some 2 million tonnes Rua Figueroa obs'e rved that the Romans
of jarosite plus lesser amounts of usually built their furnaces on top
copper are - Ed . ] of mounds, as near the source of are
as possible , and. because of lack of
The calculation of a slag make of 4. 5 water , the bellows were hand
tonnes per tonne of silver are operated. This type of furnace was
smelted is based on an assumed 50-60% used to smelt both copper and silver
silica in the jarosite are . In fact ores and it remained in use in Spain
the jarosites found at Rio Tinto and until the middle of the ninteenth
analysed since 1893 show wide century . John F Allan(l7) also
variations for all key constituents, noted details of Roman furnaces he
as follows: saw at Rio Tinto in the 1880s:

Silica 0 to 92% Bi tr to 0 . 25% "One side appears to be formed by


Fe 2 " 33% Barytes 0 to 9% excavating in the solid rock, with
eu 0 " 0 . 16% CaO 0.2 to 0.5% a semi-circular wall about 7 feet
Pb 0 " 40% MgO tr to 0.5% high built in front of it , leaving
Sn 0.05 " I. 7% Mn " " 0 . 12% a circular section 2.5 feet in
As tr " 36% Alumina 0.7to 2.5% diameter, with openings below for
Sb tr " 5% the overflow of the slag and the
Au 2 to 50 gms per tonne admission of blast."
Ag 160 " 6800 " " "
The fuel used was charcoal , produced
In 1933, the RTC ~Iining Department from the indigenous evergreen oak ,
Annual Report referred to an quercus ilex. Smelting basic copper
investigation of old Roman workings carbonates with some chalcocite was
in explor i ng the gold-silver layer at relatively straightforward ; there
the base of the gossan . would not have been any need to
F N Spettigue wrote: remove sulphur as there was
sufficient copper oxide to react with
"The area between South Lode and the sulphide during smelting.
Dehesa is full of old Roman Neither would smelting of silver have
workings and it was decided to presented serious problems as most of
explore these workings to find the lead was present as sulphate,
further deposits . A Roman shaft easily reduced by charcoal to produce
in this vicinity was cleared out the lead-silver alloy .
and the extensive workings at the

- 14 -
Smelting galena was more difficult, The establishment by the Romans of
probably involving roasting to oxide substantial operations and a large
because the sulphide is not easily resident community required assured
reduced by charcoal. Possibly i t water supply in a relatively arid
was insufficient roasting of galena area. This was obtained from
which, in Roman slags , is associated springs and also by sinking wells in
with high lead contents. Curiously, the slate, applying the recognised
the slags at Rio Tinto are low in expertise of the Romans in water
lead compared with slags at Laurion, engineering . These same sources of
up to 10% Pb, Cartagena, 8 to 17%, supply were later used well into the
and Sardinia, up to 30% . One of 18th century . One of the Roman
the reasons why there was some installations to the northeast of
reluctance to accept that so much of Cueva del Lago was described around
the slag at Rio Tinto arose from 1900 by William Nash(23):
lead-silver smelting is its low lead
content, average around 0 . 4%. Ult consisted of an adit driven
into the hill some 140 yards, a
The deficiency of lead at Rio Tinto , cross-cut was put in at every 15
and in the nearby areas, has been yards, each arm extended 8 yards,
referred to in Chapter 1 . The at each of these junctions a well
Romans used lead extensively for was sunk and so on regularly
plumbing and had well established through the whole length of the
producing centres. It is recorded adit. The work is Quadrangular
by Rickard(22) that two ingots of in form, and has the reputation of
lead, marked NOVA CARTHAGO, were being Arabic in origin; but
found in a slag pile and the probably the Arabs only bettered
inference is that the Romans brought the condition of some much older
lead from Cartagena for the work . Of the few permanent and
metallurgical operations. [Rickard, substantial sources of supply this
in a written contribution to the was one of the most important, and
discussion of Palmer's paper (18), no doubt was always carefully
referred to export by RrC of "several looked after . u
thousands of tons of ore containing
34% Pb , 1. 22% Sn u with no indication This was the Huerta de la Cana, the
of whence it came . Salkield verified garden of the palm tree - soon to be
this as an 1895 shipment of silver obliterated by the operations of RTC.
are - plumbo-jarosite - containing
1460 grams Ag per tonne . In all RTC [Today very little remains of the
operations , the total quantity of Roman mining operations. Howeve r on
such jarosites extracted is thought the uisland" of gossan between Lago
not to exceed 10,000 tonnes . Ed . ] and Salomon opencasts , a number of
workings at two or more levels in the
A considerable collection of Roman jarosite have been investigated
tools has been assembled from the recently (1981-85) - they vary
workings . Iron tools have been between less than a metre and two
found in the jarosite workings , in metres high , worked by a form of
slag heaps and in the houses of longwall method, with access from
workers, but not in the sulphide more or less square galleries a metre
workings where oxidation led to acid high, and 70 cm or so wide . In one
copper solutions; these dissolve iron a heap of jarosite was found, and
i n the cementation reaction. In nearby a perfect example of a Roman
common with other contemporaneous lamp . These workings are due to be
non-ferrous smelting operations, the destroyed , but others at the east end
Romans are presumed to have had a of Lago will be preserved . Included
smelter to produce iron from gas san in the latter is a part of the Cueva
somewhere nearby but the site has not del Lago , with large chambers ,
been identified. galleries up to two metres high , and

- 15 -
circular shafts (all blocked to
surface) of a metre diameter . There
is evidence that firesetting was used
to break the rock, and also of use of
both large and small hamme r gads or
chisels . Willies , Lynn 1981
Report on Mining at Rio Tinto
Institute of Archaeology , London
Hu elva Archaeo-metall urgical
Project. ]

Figure 7 shows the location of many


of the Roman workings - it is based
on a plan made by RTC c irca 1890.
Appendix 1 contains information on
Roman activity el sewhere in the
I berian Peninsula .

After the Romans left , soon after 400


AD , mining must have declined very
rapidly , and yet t he knowledge that
they recovered gold and si lver and
the type of ore worked for the metals
persisted - thi s wa s made c lear when
Diego Delgado visited Rio Tinto in
1556 .

Figure 6 Roman Shafts Exposed i n


Figure 5 Entrance to Cueva del Lago Early operations of RTC
Above : Timbered shaft approximately
From a photograph taken around 1880 . 86 em square .
The cave was the source of the Tinto Below : Round shaf t with hand/foot holes
river and probably the place where
valuable minerals were first di.scover-
ed by the Ancients.

- 16 -
,
.i :
l j
\ ti 1j
.i j ,
(J
i
I.

! ----\t--+-lII !,

.. I- -
.. ,.... -

I
1

- 17 -
I CHAPTER 3 I From rediscovery in the sixteenth
century until the eighteenth century
Nothing much is known about the fate rich silver mines at Guadalcanal,
of the mines during the incursion of near Seville , and at the time
the Barbarians who are assumed to Administrador General de las Minas de
have reached southern Spain in the Espana , to carry out a search and one
second half of the 5th century . of Mendoza ' s surveys covered the
districts of Zalamea , Aracena and
The Moors entered the Iberian Valverde in the province of Huelva .
Peninsula in 710 AD. There is Following the r ediscovery of the
little evidence of their presence at mines in June of that year , Mendoza
Rio Tinta, although some coins have left one of his pa rt y , Don Diego
been found, and it is assumed that Delgado, a priest from Madrid, to
they were not interested in mining . make a more detailed examination of
Perhaps some copper was recovered by the site and Delgado ' s report(10),
them by cementation on iron immersed to which re ference was made in
in the acid drainage waters but any Chapter 1, provides a remarkable
such activity must have been on a account of the mines as his party
small scale . found them. Appendix 2 is a
translation of that report .
Following the success of Ferdinand
and Isabella in freeing Spain of the For reasons at which we can now only
Moors in 1492, there was an awakening guess , and despite the enthusiasm of
of interest in mining for precious Delgado in investigation , the
metals. It seems probable that at Treasury did not pursue possibilities
that time any activities at Rio Tinto of exploitation. There was
had been related to recovery of probably some difficulty in
copperas - ferrous sulphate - identifying the valuable ore because
deposited on the stream banks by of limited knowledge of the jarosites
evaporation of the acid drainage as silver ores; at Guadalcanal , for
waters in summer months and used in example , the main silver mineral was
dyeing, tanning and ink making. proustite, light red in colour,
associated with ga lena. As already
There is an interesting story Quoted noted, it was some years before RTC
by Pe r cy(24) that Bartolome de geologists recognised jarosite and
Medina, who left Seville for t he its significance as a silver a r e .
Americas in 1554, took with him
details of an amalgamation process Delgado died in August 1557 and his
for silver recovery involving the use report attracted attention in other
of copperas and that the original Quarters , as indicated by extracts
discovery of the process had been from the Mines Register of the Crown
made by a German using copperas from of Castille(25) :
Rio Tinto. A version of this
process, known as the Patio pr ocess , "On 19 April 1565 before H M' s
was widely practised i n Mexico. Officials at the Guadalcanal Mine,
Alonso Gomez Adalid registered an
The search for mines for precious old mine which was situated in t he
metals intensified in the reign of district of Zalamea in the Province
Philip II who had inherited a of Extremedura at 2 or 3 s hot s of a
virtually bankrupt treasury from cross-bow along a road from the
Charles I of Spain in 1556. Philip above going to Higuera, which mine
commissioned Don Francisco de crossed the road and was situated
Mendoza, who had earlier been between a founta in and a cross . "
associated with the rediscovery of

- 18 -
"On 25 February 1567, before the November , King Philip IV directed
same officials, Alonso Criado , of that the Rio Tinto mines should again
Aracena, registered in his own name be inspected and appointed Don
and that of Anton Criado, a mine of Gregorio Lopez Madera, a member of
gol d and silver, lead and tin and the Mining Council , and Captain Tomas
any other metal, situated in the de Cardona to make a general survey
district of Zalamea which is called of the Sierra de Zalamea and to
the "Arroya de las Puercas" in a "study a certain metal found in great
ravine of the charcoal burners . " quantities and containing some
silver".
"On 8 April of the same year ,
before the same officials, the same No report by Madera has been found
Alonso Criado , in the name of but some views put forward by
Bartolome Criado, registered Cardona are quoted by Rua
another mine in the district of Figueroa(14). According to Cardona ,
Zalamea which is called the the "metal blanquillo", as he called
"Cabezas Altas" on the left- hand it , of Zalamea was actually a new
side of the road which goes from metal and he considered that it could
Zalamea to Segunderal." replace tin, which at that time was
brought from Cornwall, for making
"In Madrid on 20 September 1569, bronze castings .
before H Mis members of the
Accounts Office, Juan de Cabrera Cardona gave an analysis of the
registered various ancient mines "metal blanquillo" - about 2,800
and shafts of gold, silver and grams of silve r pe r tonne but little
other metals at sites in the copper - and said it was produced by
district of Zalamea . " the Ancients when recovering s ilver.
The Royal Council, to which Cardona ' s
"On 13 January 1570, before H Mis findings were reported , decided that
Officials at the Guadalcanal Mine, the "metal blanquillo" was a slag of
Francisco Perez de Canales , for and no value , despite the silver content
in the name of Diego Blanco , of which would be difficult to extract.
Valencia , registered some large and
small slag heaps in the district of It is possible that Ca rdona's sample
Zalamea la Real, from the source of was of speiss which is likely to be
the Rio Tinto and the Salitre Cave formed in sme l ting ores containing
to what they call the house "de los arsenic and antimony ; substantial
franceses." quantities of speiss are associated
with the slag heaps at Rio Tinto.
"On the 17th of the same month,
before t he same OffiCials, In 1637 a certificate was granted by
Bartolome Hernandez r egistered in the King to Captain Francisco Moreno
the name of Juan del Valle a metal de Busto to "go to Rio Tinto and work
min e in the district of Zalamea . " some mines and galleries in that
district in the province of Sevilla ."
"On 30 June 1575, before Officials [Provincial boundaries were probably
of H Mis Accounts Office, Gabriel not clearly delineated in this period
de Lujan, in the name of Bartolome s ince Rio Tinto is described
Sanchez Gigueno, Diego Ru i z, Mart i n variously as in the province of
Vazquez, Vasco Yanez , Lorenzo Sevilla and in Extremadura , and is
Vazquez and partners, registered a today in the province of Huelva. Ed.]
mine of some metals in the district The mines were described as situated
of Zalamea , called "Canada de los on a hill on which there was an old
Bonigos." castle cal l ed Salomon •.• with a cave
to the west called Murcielago and
Despite this ev i dence of interest , no were found full of water.
serious operations seem to have been
undertaken until 1627 when , on 1 In 1661 a certificate was granted to

- 19 -
Don Alvaro Alonso Grafias to use the is not as accurate in many respects
source of the Tinto river and the as that of the priest Diego Delgado.
slag and metal blanquillo of Zalamea Delgado was not an "expert" but he
la Real and the hamlet of Rio Tinto found, or was led to, the silver ore,
to collect copperas and to convert took samples and had them assayed -
iron thrown into that water to copper Shee ' s report gives no indication of
- the first reference to recovery of his taking samples and he seems to
copper by cementation although have relied heavily on the views of
reports suggest that recovery by this another "expert II who examined the old
method was not pursued . mining activities between 1648 and
1651.
In 1693 a certificate was granted to
Manuel Fernandez Valle "to continue Archaeologically, Sheets observations
the exploration of the two mines of are interesting . He saw the
copper and silver in the boundary of foundations of a rather large town
Zalamea and the pasture land of supposed to have been the
Malparido, that of silver runs in Celto-Iberic city of Gr an Bitania ,
north to south direction and is sometimes called Betulia, and later a
called San Benito, the other of Roman town . The foundations were
copper with some silver is called lost some time after SheeTs visit and
Senora del Rosario ." rediscovered by Luzon(4) in 1967 .
Since 1967 the area has been covered
The efforts of these, and other entre- with a stockpile of gossan awaiting
preneurs and prospectors of the day, treatment for gold and silver
show an increasing interest being extraction.
taken in the Rio Tinto area and its
mineral wealth. The official Liebert Wolters' company had a
reports shed some interesting light turbulent history, described in
on their activities; unfortunately it detail by Avery(l) , and following the
seems that the knowledge accumulated receipt of Shee ' s report it was
in this period was either overlooked dissolved and two new companies were
or ignored by those eventually formed - one, the Compania Espanola ,
responsible for reopening the mines. in which Wolters had no interest ,
taking over the mines of Guadalcanal ,
It was almost two centuries after the Cazalla and Galaroza, and the
rediscovery of the mines before a Compania de las Minas de Rio Tinto y
decisive step to rework them was Aracena with Wolters as the only
taken. In 1725 a licence was shareholder. On 26 July 1727, only
issued to a Liebert Wolters Sjohjelm , 20 days after his new company was
probably of Swedish origin , to work formed, Wolters was killed in a mine
five mines in the region for a period accident at Rio Tinto and his rights
of thirty years; the mines were in the new company passed to his
Guadalcanal , Cazalla, Galaroza, nephew, Samuel Tiquet Sjohjelm.
Aracena and Rio Tinto and a company
was formed to work them for gold and Rua Figueraa(15), writing in 1859.
silver. mentions that the place where Wolters
was buried was still identified as
A mining expert , Robert Shee, the "Hoya de Liberto" - the grave of
probably an Eng lishman , was called in Liberto; Wolters would have been
to inspect the old mines and advise known by a Spanish equivalent of
on the working of them and his report Liebert as Don Liberto. He was 62
has been quoted , in translation from years of age when he died and might
the Spanish, by William Nash(23). His well be considered the father of Rio
t ranslation is given in Appendix 3. Tinto as he initiated the reworking
of the mines and that working has
This peculiar and rambling report has continued uninterrupted until the
been said to be one of the earliest present day. He died thinking that
modern "mining expert ' s" reports but Rio Tinta was a rich gold and silver

- 20 -
deposit. management between 1747 and 1758,
only about 5 tonnes was produced by
Also in 1727, the Campania Espanola smelting ores.
entered into a contract with Lady
Maria Herbert of Powis to drain the Rua Figueroa(14) has provided a
Guadalcanal mine, work which was wealth of information about
completed in June 1732. Following operati ons at Rio Tinto from the
the failure of the Company to pay for Wolters era onwards. He found an
the work, Lady Herbert sued and i n old report showing the iron usage for
March 1740 obtained control of the cementation over an 11 day period, as
Campania Espanola . In the follows:
following month she laid claim to the
mines run by the Campania de las 9 May 1752 at midday 273 kilos of
Minas de Rio Tinto y Aracena, on the Viscaya ingots
grounds that no work had been done at 9 May at midday 77 " "
either of the mines. Her claim wa s scrap i ron
upheld and, in June 1742, by royal 10 May at 11 am 26 " "
licence, she obtained control of Viscaya ingots
them. 15 May at 7 pm 557 " "
Viscaya ingots
Tiquet appealed against the decree 16 May at 10 am 40 " "
and his appeal was rejected i n March Viscaya ingots
1743 . After further appeals and 19 May at 10 am 272 " "
long and costly representations, Viscaya ingots
Tiquet succeeded in getting the
decree annulled in July 1746. He That consumption of 1245 kilos could,
was then granted an extension of the theoretically, have produced a
lease, for a total of 30 years from roughly similar weight of copper but,
that date. Lady Herbert had since the total copper production for
exploited the mines at Rio 'finto 1752 was only 6 tonnes, it is a safe
during the four years interregnum and assumption that iron consumption was
abandoned the workings in a sorry several times the theoretical, due
state. Tiquet was forced to raise probably to high acid and ferric iron
money to return the mines to working concentrations in dilute solutions.
condition by issuing shares - among The cost of iron is known to have
the new shareholders was a tailor been a major burden on the
from Valencia, Francisco Tomas Sanz operations .
who became a close associate of
Tiquet. The cement copper was melted in a
German blast hearth or refining
Tiquet was the first to recognise the hearth furnace, known at Rio Tinto as
potential of Rio Tinto as a copper "Horno de Capel" . It consisted of
mine. In 1737 he had started a hemispherical bowl with a tuyere
experimenting with copper recovery projecting over the rim at an
from the drainage waters by inclined angle, so that the blast
cementation with iron and had struck the burning fuel and melted
recovered 300 kilos; another 300 copper. A furnace was capable of
kilos were recovered in the period of melting 100 kilos of copper at a
Lady Herbert I s control. When time, producing black copper of about
Tiquet regained control, he 95% Cu. This metal was sent to
concentrated on copper production. either the Royal Mint or the
Initially he used scrap iron; later, Armaments Factory, both of which were
about 1749, he introduced virgin iron in Seville.
from producers in Viscaya in northern
Spain. Copper production increased In 1750, Tiquet erected a small blast
from a few hundred kilos in 1747 to furnace on a piece of ground that had
35 tonnes in 1756 - of some 146 been levelled near the river bank
tonnes produced under Tiquet's below Lago and used a water wheel to

- 21 -
operate the bellows. The site was force at Rio Tinto was a mere 14 men
known as Nuestra Senora de los and it is remarkable the tenacity
Desamp ~ ados - Our Lady of the which had been shown under his
For saken - and it was here that the management, with very limi ted
smelting of copper ores was gradually resources in an extremely isolated
developed , in combination with the situation.
melting of the cement copper. Ore
f or smelting was probably mined from Francisco Sanz succeeded Tiquet who
the area later developed by RTC as had nominated him trustee and
South Lode . administrator. He had been well
trained by Tiquet in mining, smelting
Some 15 years later , after Sanz had and administration ; he also had
inherited management , four further natural cunning. The company was in
flat areas were prepared in terraces a disast r ous financial condition when
so that the water could be used in he assumed control in 1758 : when the
descending stages. This site came lease reverted to the State in 1776 ,
t o be known as "Los Planes" and the all the debts had been paid off, the
four smelters , each consisting of one work force expanded to more than 700
furnace, were known as San Gabriel, and a substantial community created:
San Jose, San Francisco del Paula and the production of black copper
Nuestra Senora del Rosario. An increased , averaging 67 tonnes pa
extraordinary thing about the Planes over the period .
site was that it was 2 , 500 metres
from the mouth of the mine exit , the Reference has already been made to
adit San Roque , where the drainage the development of smelting of ore on
water was treated by cementation. the Planes site under Tiquet. In
1765 Sanz drove a new adit, at the
Each f urnace wou l d have been no more east end of the lode and at a level
than 1. 5 metres in height, square in 51 . 7 metres above the Roman adit of
plan with sides of about 60 cm. San Luis , and named it Santa Barbara
The design would have been little - this adit was joined to a shaft of
changed from Roman times , although the same name up which ore was raised
the Romans smelted chalcocite and by hand winch and taken to the Planes
Tiquet had only a small proportion of area for roasting and smelting .
chalcoc i te in a charge which
consisted mainly of cupreous pyrites . Sanz made an interesting contribution
Germans were brought from Mansfeld to the archaeology of Rio Tinto when ,
to operate the furnaces but they in continuing the clearing of the San
found smelting of the Rio Tinto ores Luis adit begun by Tiquet , at 110
more difficult than smelting of metres from its entrance , he
German ores. Whereas the German uncovered a copper plate dedicated to
ores required roasting only once to the Emperor Nerva and fixing its date
give matte of sufficiently high at about 97 AD . Later the a r ea to
copper content , Rio Tinto ores needed the east of the mine was named Nerva ,
three roasting treatments and still and remains so today .
prod uced a matte of lower grade which
required roasting and smelting a After the Wolters/Tiquet lease
number of times in order to make expired in 1776 , Sanz was retained as
black copper . the State ' s Administ r ator , a title
which thereafter was the official one
Tiquet cleaned out the Roman adits , for t he Government ap pointed manager ,
f i rst San Roque and later San Luis, until August 1783 and for those
as t he basis for his mining further 5 years average copper
operations for copper a r e . He had pr oduction rose f urther to 92 tonnes
diffic ul ty i n finding are of pa,
s uff i ciently high grade , a pro blem
not sol ved in his lifet i me. When The relative prosperity at t his time
he died in Se ptember 1758 the work br ought social changes, most

- 22 -
importantly in housing and amen l t les producing fine fruit . These
for the work force. Sanz developed efforts at cultivation we have
a site near the mine on the slopes of witnessed with much satisfaction
Cerro Salomon which became the aldea and we understand from several
or hamlet of Rio Tinto; also referred people knowledgeable in this matter
to as pueblo la Mina. He built 40 that the copper ob t ained f r om this
houses, a chapel (the Hermita de San mine is good quality and not much
Roque), stables, a shop and a tavern . blended with iron , as has been
Communal ovens were provided for falsely stated with notable
bread making, fountains wer e prejudice to the material and best
installed for drinking water, market interest of Spain."
gardens developed and reafforestation
started. There is no doubt that during Sanz's
management the mines were brought
Two Franciscan brothers from Granada, into good working order, although he
Father Gabriel and Brother Pedro feathered his own nest and practised
Mohedanos , visited the mine s in 1780 nepotism on a rather large scale .
and wrote glowingly of what they saw : Many slande r ous statements were made
agai nst him, especially about private
" In the neighbourhood of Rio Tinto sales of copper and concealing copper
some evergreen oak trees are fo und, stocks. There may have been some
but the greater part of the t ruth i n statements about the latter
locality is covered with a dense - in 1852 black copper was found in
growth of jara and other useless the ventilating shafts of the San
scrub , not a single pine, but D. Luis adit.
Francisco Sanz, principal
Administrator of the Mines , After successfully withstanding his
obta i ned a supply of seeds from critics and opponents for a number of
Niebla and sowed them broadcast. years , sta rting with opposition to
Today , you can see the development his appointment in 1776 as the
of a fine pine grove from which, Government ' s Administrator , Sanz was
some day , the wood will be used for dismissed in August 1783 and thus , at
construction and fo r the mine rs. the end of the 18th century , a new
He has also planted an area with era began with the mines operated
vines and fruit trees tha t grow directly by Government .
well, serving for recrea tio n and

- 23 -
I CHAPTER 4 I The mines under Government
control
After the dismi ssal of Sanz , D Manuel Aguirre had little expertise in
de Aguirre y Hor casta was a ppoin ted smelti ng but he tried to smelt the
Gove rnment Administrator at t he end fine ca lcined or e which at that time
of 1784 or early in 1785 . His was discarded. In an ex periment in
fi r st period of ser vice at the mines 1786 he obtained 46 ki l os of black
was short, because he appa r ent l y copper from smelti ng 1,400 kilos of
lacked tact and few co uld work calci ned ore but the f urnace was
effectively with him. The Director severely damaged in the process.
General of Mines , D Francisco Angulo, This co nfirms a lack of progress
appointed D Mel chor Jiminez to since Roberto Shee ' s report of 1727,
replace Aguirre in December 1786 and wh ich included t he following
he, a lthough respected and presumably foo tn ote : "Various attempts have
effecti ve, had to leave i n 1789 been made to smelt smal l size mineral
suffe ring from malaria . Aguirre at Rio Ti nto , but without profit,
and Jiminez each had a second te rm whether t he mineral was roasted or
and the s uccession of administ r ators un r oas ted."
was as follows:
When Melchor Jimi nez became
Manuel de Aguirr e 1785 - 1786 administ rator in 1786, the Director
Melchor Jiminez 1786 - 1789 of Mines , Francisco Angulo , with two
Manuel de Aguirre 1789 - 1793 assistants , vi s ited Rio Tinto and
Melchor Jiminez 1793 - 1796 iss ued a most comprehen si ve report in
Vicente Letona 1798 - 1825 J uly 1788 , dealing with all the
Jose Martinez technical improvements required a nd
Marcos 1825 - 1829 recommending mea ns for imp r oving the
social we lfare of the employees .
Fr om 1829 the mines were leased to
t he Marques de Remisa until 1849 , Angulo found t hat the buildings and
thereaf ter Gove rnment again furnaces were badly in need of repair
co ntr ol led operations di r ectly . and that the adi t s a nd water channels
required cleaning, so t hat they could
As mentioned in Chapter 3 , the be used for cementation . He
community working the mines from the co nsidered that the roasting of the
time of Wo lters a nd Tiquet was housed mi neral was being done without
on the s l opes of Cerr o Salomon in the sufficient thought of eco nomy and
pueb l o l a Mina. The village of Rio noted that l arge quantities of
Tinto, with the parish church and t he roas t ed mineral were left in heaps .
registrar of bi rths , marriages a nd He appa ren tly noticed that copper was
deaths, was 3 kilometres distant . being l eached out of these heap s by
Sa nz had built a chapel at the hamlet rain and this led him to consider
at the mine , in 1786 Aguirre obtained whether roasted ore could be was hed
State permission to appoint two by the mine drainage wate r s , or other
chap lains to attend to the spi r itual water from some other source , to
needs of the mine community and in dissolve out the cop per.
1789 land was given to the hamlet for
a church , the church of Sa nta He proposed to conce nt r ate the
Barbara, which wa s consecra ted in so lution by natural evapo r ation until
1793 and became the parish chu r ch . copper and iron su l phates ( vitri ol s)
[This church was demolished in 191 8 crystallised out . The vitriols
to accomodate the South Lode opencast were to be redissolved and copper
and a new ch ur ch of Sa nta Barbara wa s reco vered by cementatio n with iron.
built in the new village of El Hi s was the first r ecor ded suggestion
Valle .J

- 24 -
that artificial cementation , as this recovery in refining was around 76% .
process came to be known, should be The refining slag would no doubt have
used at Rio Tinto, but over 50 years been returned to the blast furnaces
were to pass before it was used. and the copper recovered from i t
included in the 185 tonnes . Refined
Among other recommendations he made copper obtained from cemented copper
was one that horse whims should be precipitate was 11 tonnes pa .
used instead of hand winches to raise
ore from the mine, and another that Villagers from both Zalamea and E1
copper should be refined rather than Campi1lo had regularly encroached on
sold as black copper . the mining lease with their pigs,
taking timber , and once were
A remarkably far sighted responsible for burning a large part
recommendation concerning employee of the woodland . When Aguirre
welfare was for the creation of a returned as Administrator in 1789 he
fund to help the sick and infirm. went to some trouble to establish the
He proposed that contributions should lease boundaries - with full
be collected from the workmen cooperation from representatives of
according to their wages on the the local interests , Andres de
following scale: Canete, a surveyor from Seville , was
appointed to conduct the survey and
1.Those earning from one to two-and- he produced a plan acceptable to all
a-quarter reales a day to pay a parties in August 1791. Rua
quarter of a real a week and when Figueroa wrote that a copy of the
sick to receive a real a day. plan was held in the town hall of
Zalamea when he worked at Rio Tinto
2.Those earning from two-and-a-half in the mid-19th century but the two
to four reales a day to pay half a copies given to Rio Tinto could not
real a week and when sick to be located.
receive one-and-a-half reales a
day . Vicente Letona was appointed
administrator in November 1798. He
3.Those earning four-and-a-half had been employed at the mines for
reales a day and over to pay a real many years, having arrived there in
a week and receive three reales a Sanz's time and had married his
day when sick. granddaughter. His appointment
covered 27 years and spanned the
[ A real , one quarter of a peseta, difficult period of the Peninsular
was probably worth 2 or 3 pennies Wars, during which the country was
in contemporary English money. ] frequently overrun by the French.
During such times he had great
Very little notice seems to have been difficulty in maintaining production
taken of Angulo ' s report by the and all too frequently Madrid could
authorities in Madrid, but the not supply funds - in such extremes
furnaces and canals were repaired and he used his own on many occasions.
copper refining was introduced.
About the time of his report, a new Copper production from 1793 until
smelter, Los Chaparrales , consisting 1800 averaged 15.5 tonnes pa; the
of one blast furnace, was built on difficulties created by the War are
the Tinto river, not far from the ref l ected in the fal l to an average
village then called Rio Tinto of 8.2 tonnes for the years 1801 to
(subsequently Nerva). 1809. Production of copper
precipitate stopped in 1810 and the
Between 1788 and 1792, the average smelting furnaces ceased operation in
annual production of black copper was 1811. Seville was captured by
185 tonnes , average copper content French troops in 1810 and their
94.2%. Refined copper production commanding general, Jean Pierre
averaged 132 tonnes pa so that Maransin, requisitioned all available

- 25 -
copper for munitions. At about 19 tonnes of copper a nd paid
conside rable risk to all involved , the administration 400,000 reales,
most of the copper at the mines was say £4,000. [The economics of this
sent to Cadiz, for some time the only operation are intriguing - according
bastion holding out against the to Avery , copper was worth just over
French . It was 1814 before any £100 per ton in Spai n about that time
further production of copper so it appears to have been a good
precipitate and a further 10 years deal for the administration - Ed .]
before smelting r estarted in 1824.
Jose Martinez succeeded Letona as
Throughout this period, the administ rator in 1825 and about this
population at the mines suffe red time the Planes smelti ng furnaces
severe hardship and many, including were rebuilt c l oser to the village of
the skilled workers, left to seek Rio Tinto , alongside the Rio Agrio,
work elsewhere . By 1812 the mines upstream of its junction with the
and works were in a ruinous Tinto river . Water flow on the Rio
con dition and rumours reaching Madrid Agrio was not sufficient to drive the
suggested that Letona was bellows for the smelte r s through the
responsible. In January 1813, year - at times manpower was used -
Domingo Ibarrola , a Government and the feasibility of bringing water
accountant based at Algeciras , was from Cueva del Lago was examined but
sent to i nvestigate - hi s repo rt gave not pursued ..
credit t o Letona for hi s effo r ts
under difficulties and recommended That feasibility study was based on a
further support for him . detailed survey made of the mines
area in 1828 by Joaquin Esquerra , and
A technical manager, Jose Miaja y still in use in the 1920s; Esquerra ' s
Pingarron, was appointed with an survey had been commissioned by D
assistant , Jose Martinez Marcos, but Fausto de Elhuyar de Zubi ce , Director
alas no financial aid was of Mines, who had visited the mines
forthcoming . Jose Martinez made in 1823. At that time of deep
changes to the cementation ca nals and depression , he believed that
started using scrap iron i nstead of government management could be
new metal, although even sc rap was successful if funds were provided,
difficult to obtain. Production of and expressed confidence in finding a
precipitate copper improved but was means of recove r ing copper from the
erratic - 27 tonnes in 1820 , 12 "small size mineral found in the
tonnes in 1823. Stalactites formed mine". Because of lack of funds ,
in the mine, conta ining 4 to 12 % Cu gove rnment did nothing to restore the
and 2 to 10 % Zn , were fi rst used at mines; instead it was decided to
this time as vitriol , dissolved in lease them to private ente rpr ise and
water and the copper recovered by it ~as for that reason that the
cementation , a practice which wa s to survey of 1828 wa s commissioned.
continue until 1893.
The 45 years of state control covered
Despite improvements made by Jose some of the most difficult years in
Martinez, recovery of co pper from the country ' s history, ~ith the
acid waters was not good and , in Peninsular Wars bringing widespread
1822, D Juan Santana Bolanas was eco nomic ruin and this aspect of the
granted permission to treat the waste period is covered in some detail by
water from the cementation canals . Avery(l) .
Between 1824 and 1827 he produced

- 26 -
I CHAPTER 5 I Private control, 1829-49, the
Marquis de Remisa
Following the advertising of the at the other smelter sites . Since
lease in April 1828, three offers the Santa Ana shaft was qui t e close
were received by the end of August , to the pueblo la Mina , it may have
the closing date. The offer been persistent objections to the
accept ed was made by the Marquis of sulphurous r oasting gases which
Remisa and he obtained a lease of 20 eventually brought the operations to
years from 24 April 1829 at a renta l an end .
of 67 ,000 pesetas pa for the first 10
years and 125,000 ptas for the next The scale of operations was
10, say £3 , 000 and £6,000 pa substantially increased , notably in
respectively. the heap roasting of are for smelting
some details were reported(26) by
The lease carried a number of the Director of Mines, D Luis de la
conditions which , in the light of Escosura who visited Rio Tinto in
what followed , might be better 1844 or 1845 . Initially roasting
described as " best endeavours" was done in conical heaps a bout 5
directions . These were based on metres in diameter and 2 metres high
recommmendations made by Fausto de containing about 44 tonnes of are .
Elhuyar de Zubice , Director of Mines, Larger , rectalinear heaps with
in May 1829. Remisa was to install rounded ends we r e developed and were
a new shaft with ho is t, wheelbarrows proved more economical of fuel -
were to be used to convey ore to the these heaps were known as " teleras"
hoisting shaft to replace the because their shape was simila r to a
practice of moving it along galleries loaf of br ead of that name made
in wooden containers passed from man locally . The fue~ used was wood -
to man. He was also to imp rove the the local oak - and vast quantities
drainage of acid waters from the San were required. Escosura gave the
Roque adit to facilitate treatment following figures :
for copper recovery .
Conical Teleras
Remisa did only what he considered Heaps
important ; since he appears to have Pyrites , kilos 5,000 5, 000
had influential friends in Madrid no ~~ood, kilos 490 390
sanctions were used against him . Labour , reales 9.0 6. 5
Although the new shaft was not sunk, Roast time , hours 110 ?
the ol d Santa Ana shaft was improved
and fitted with a whim .
Single roasting achieved only par t ial
A retired army officer , D Alejandro removal of sulphur and three roasts
Vi viente Espeleta, was appointed by in all were needed to produce calcine
Remisa as administrator of the mi nes for blast f urnace smelting , as
and he introduced his own ideas. expla i ned in Chapter 3. The t hree
For example, assuming costs would be roasts took 20 , 8- 10 and 8-10 days
reduced by roasting ore and smelting respectively for the conical heaps
the resulting calcines as close as and 30, 20 and 15 days fo r the
possible to the Santa Ana shaft , he teleras . Like his predecessors ,
built two blast furnaces there . It Remisa used blast furnaces to smelt
cannot have been only the lack of calcines to black cop per but he
wate r power to operate the bellows introduced r everberatory f urnaces for
which led to the failure of this refining the black copper .
project afte r 3 years of working - Details of t he blast fur naces used
bel l ows were commonly worked manually are shown in Fig ure 8. The f urnaces

- 27 -
were built in pairs , enclosed in a A daily smelting charge to a furnace
strong stone built wall on three consisted of :
sides and with linings of refractory
slate. The front wall was Calcine 1140 kilos
removable , with an arch above to help Ancient slag 1600 "
support the chimney. The front, 35 Charcoal 1370 "
cms thick , was also made of slate,
with separate tap holes for slag and This charge produced 70 to 80 kilos
copper . The charging port was of black copper. Ancient slag was
about 1.7 metres above floor level , the only source of silica used and
probably a convenient height at which Escosura refers to sows of i r on
to discharge baskets or wooden trays produced in the furnace because of
carried on the heads of the workmen. the lack of sufficient silica to s l ag
Hearth dimensions were 50 cms by 83 all of it. Furnace campaigns were
cms and the tuyere entered through of about 5 days - the front wall was
the back wall at a height of about 40 then taken down and the hearth
cms above the hearth - the hearth remade .
itself was made of clay mixed with
charcoal and appea r s to have been The reverbera t ory or "spleiss"
rather easily eroded by slag . furnace used for refining black
copper was also of German design and
The furnaces were known locally as details are shown in Figure 9. The
"Alemanes". a name probably dating round hearth was about 1.7 metres in
back to the period afte r 1750 when diameter , with a tuyere at "c"
Ge r man smelting specialists from connected to a bellows . Wood was
Mansfeld were brought to Rio Tinto the fuel; flue gases escaped through
by Tiquet . The drawings in Figures the semi- spherical roof at ports
8 and 9 are taken from Escosura ' s marked "x".
paper of 1845 .

,I
I
I

--.:..-

Flgure 8 Blast Furnace used by Remlsa 18405

- 28 -
Black and cement copper ~ere melted When a small spoon sample sho~ed a
slowly to oxidise arsenic and rose-red colour the copper ~as tapped
sulphur. Once the copper was and cast into rosetting pots; the
melted , the temperature was raised. surface ~as cooled by ~ater and thin
slag removed and ai r blown on to the circles of copper, rosettes. removed.
surface to oxidise some of the Refining slags ~ere resmelted from
copper , at the same time oxidising time to time to black copper.
further arsenic , iron and other
impurities. The temperature of the This method of refining was used up
bath was lo~ered to remove dissolved to the time of the RTC and was still
sulphur dioxide , slag ~as aga i n used at a much later date in Germany
removed , and the surface ~a s covered and Hungary . Ho~ever , Escosura ~as
with charcoal to reduce the copper not satisfied with the quality of
ox i de . refined copper produced at Rio Tinto;
at that time it may have contained
residual arsenic and was further
I refined at the armaments works in
Seville .

The major technical developments of


..l' the Remisa era we r e associated with
, the production of copper by cement-
ation. In 1839 Remisa formed a
separate company , operating at Planes
under the direction of D Vicente
" Lopez Probe, to ext r act copper from
c r ystalline vitriol , the most
important sources of which were
stalactites and "tierras vitriol-
"
,,.' icas" , small sized , oxidised minera l
also recovered from mine workings.
, The vitriol and "tierras vitriolicas"
, , we r e leached , or "washed!! in the
local terminology, and the copper
cemented from the resulting solution
. . . .-..-:. . . ~'-r'
,"-..,-.J by iron .
,....
"'--. ;
-'
\ .
-
;'

'.
Copper produced by cementation in
this way was more pure than that
obtained by cementation from mine
drainage wa t er and was separately
refined; the latter , known as
"cascaria de la caneria!! and
containing significant arsenic, was
refined in the reverberatory furnace
with black copper.

Around 1841 , a D Felipe Prieto


visited the mines and saw the
roasting of the cupreous pyrites for
the smelter - he claimed he knew a
process which could recover copper
from the l ow copper content pyrites
r- ,
,I
then being discarded . Remisa gave
him the opportunity to prove this
-J process, generally known as
!!artificial cementation"; it consists
Figure 9 Refining Furnace 1840s
of r oasting at low temperature , which

- 29 -
converted copper sulphides to water From 1842 the production of copper
solu ble sulphates , and leaching the from vitriols had increased
copper from the r oasted mineral. conside rably. Although less are
The roasting , called "slow roasting" , was smelted , total copper productio n
involves a higher degree of sulphur increased from 72 tonnes in 1829, the
elimination compared with the high first year of Remisa's lease , to 427
temperature r oasting for matte tonnes in 1848 ; the annual figures
smelting. varied widely and are given in
Appendix 4.
Acid water from the Cueva del I~go
was preferred for the leaching and up Of many conditions of the lease with
to 70% recovery of copper from ores which Remisa did not comply was one
of less than 3% Cu wa s obtained - concerning woodlands . When he took
with higher grade ore reco very was over the property the trees were
lower; as little as half that figure. valued at 3.8 million pesetas and
Copper remainin g in the calcines or consisted of 440 ,000 pines , 170 oaks
cinders after the leaching operation and 300 poplars , all planted by Sanz o
was s lowly solubilised by natural Quite apart from the damage done by
oxidation . The ci nders dumps were s ulphur dioxide, Remisa consumed
known as "Barbasco Heaps " aft er RTC s ubstantially more timber in
took over , earlier they were known as su pplying wood for roasting and
"terreros", the name used later by copper refining than was provided fo r
RTC for the areas used for natu r al in the lease agreement .
cementation.
Parallel wi t h developments in copper
Prieto was granted a patent for his ext raction, the pueblo la Mina,
process for 15 years , commencing 9 founded by Sanz in 1772 , grew to
September 1845 and a new company, the accommoda te the increasing workforce ,
Compania de los Planes , took over the to the poin t where Remisa felt it
business of the earl ie r com pan y sho uld become independent of the
recovering copper from vitriols and jurisdiction of Zalamea la Rea l.
oxidised mineral. Provi ncia l Za lamea had always jealously guarded
a uthorities in Hu el va objected to the its rights to co ntr ol mi ning in the
operations of the new company ; it had a rea and did everything in its power
not been registered i n Madr id and to hinder mining by out siders , yet
ca used serious damage to State its i nhabitants , who were
property, destroy ing tree s Idth agric ulturalists, were unwilling to
s ulphurous smoke from the burning ta ke the risk of financing mining
heaps. Remis8, with hi s influential operations themselves.
friends in Madrid, persuaded the
authorities there to approve the On 12 February 1841 the Government
company and its operations and it ag r eed to the formation of a new
continued in profita ble acti vi ty municipali ty . This was inaugurated
after his lease on the mine itself on 3 May and the hamlet or aldea was
had expi r ed . renamed the Pueblo of Rio Tinto .
The original village of Rio Tinto
The Prieto patent expired in changed i ts name to Ventosa, later to
September 1860 : thereafter the Luga r de Rio Tinto , and then , in 1891
process was used by all the when it too gained independence from
significa nt pyritic mines in the Zalamea , it was renamed Nerva.
south- west of the Iberian peninsula.
However , open air roastin g was The administrator of the mines had ,
prohibited in Portugal in 1878 and a from the days of Sanz , exercised
simi lar prohibition was made by the com prehensive judicial authority
Spanish Cortes (parliament) in 1888 which was now re nounced and a new
and this greatly curtailed the use of council took over the ci vil
the process . responsibilities . Government still

- 30 -
maintained that the village was Cr own During the twenty years of control of
property and , as such , was included the mines by Remisa, considerable , if
in the lease of the mines, even uneven, progress was made . The
though at that time many of the operations were undoubtedly
people living in the Pueblo owned profitable and fu ll pa yment of lease
their houses . charges was made. Government
inspectors were well aware of
Two interesting comme ntaries relating infringements of lease conditions and
to the mines during this period are the reduction of the woodlands and in
quoted in Appendix 5 . The first is the value of the mines i nstallations
by Richard Ford, an Englishman who ha s been clearly recorded in their
visited the Rio Tinto area in 1832 or reports . Remisa's operations must
1833 - even before Prieto's process have been responsi ble for major
was introduced the impression was damage to the enviro nment , a lthou gh
ce rtainly not of a green and pleasant that was probably not taken into
land . The second commenta r y by account by officials i n Madrid. It
Fernando Bernaldez co nce rns the is no surprise that on termination of
metallurgical operations as he the lease in 1849, hi s application
interpreted them a few years after for an extension was rejected and the
the termination of the Remisa lease. mines reverted to government control .

rigure 10 Opencast Operations Exposing Old WOrkings


19th century pillar and stall workings clearly visible, Roman
shafts not positively identifiable in this early 19005 photograph.

- 31 -
I CHAPTER 6 I The mines returned to
Government control, 1849-73
When the Remisa lease expired in somewhat less than the contracted
1849, D Casiano de Prada was amount, and Prieto had delivered an
appointed to take over the administ- average of almost 25 tonnes of copper
ration of the mines . He was no per month •
stranger to Rio Tinta, having been
there in 1847 on an inspection for Prieto's Planes Company used drainage
the government; he was soon in water from the Cueva del Lago for
difficulties, as he later wrote(27): leaching, and the location of its
works, Fabrica de los Planes, is
"On 24 April 1849 the contract for clearly shown on an 1878 RTC plan, a
leasing the Mine terminated. reproduction of which is inserted
On the following day I put into inside the back cover of this volume.
working order and operation all It seems probable that the Company
sections of the works as on account leased the Chaparreles smelter to
and on behalf of the Government, melt and refine copper precipitate -
without being able to count upon, not far from the site of this smelter
or being furnished with, the the river bank consists of dumped
necessary funds for even the most slag which is high in copper ,
urgent and important matter£, approaching 2%. It is known that
although I did not anticipate that Prieto's slags were high enough in
many days would pass without such copper to justify re-smelting in
being sent to me. But I was later government operations.
mistaken and if the labours in the
mine and all the works and office About 1850, the Treasury made an
did not suffer any interruption agreement with D Mariano la Cerda, a
that was due only to my determinat priest attached at one time to the
ion and to my occasionally church at Rio Tinto and with
procuring funds and loans from influential friends in Madrid. He
Seville, obtained however under my claimed to have an electrochemical
personal guarantee and employing process for recovery of copper from
my own private means, sometimes liquors obtained by leaching calcined
even remaining without any money at cupreous pyrites, a process vastly
all." superior to other known methods .
His claims were received with
He expressed the difficulties and enthusiasm by the Treasury, although
frustrations experienced by many not necessarily by the Minister of
administrators, both before and after Mines.
his time, caused by the utter and
complete lack of understanding by the Without any serious investigation of
government officials in Madrid of the the claims, Cerda was granted a
problems of operating the mines . patent and began exploitation under
the agreement entered into with the
Treasury. Exploitation required
Felipe Prieto signed a new contract the use of Prieto's slow roasting
on 23 January 1849 which enabled him method; how he got over that
to continue working until the expiry difficulty is not known. As far as
of his patent in September 1860 - the electro-chemical label is
under the contract the mines were to concerned, it would have been
supply 2,300 tonnes of suitable are fashionable and impressive at that
per month and he was to return 17 time since it had been introduced
tonnes of copper monthly. By the when Michael Faraday published his
end of the contract period the mines paper on !!Electrochemical decompos-
had supplied 270,000 tonnes of ore, ition!! in 1834.

- 32 -
The Treasury agreed to Cerda taking cementation continued.
half the resid ual mined ore after the
obligation to supply the Planes Several administrators were involved
Company had been met and to leasing in the running of the mines during
the Desamparados smelter. It is this period of State control but real
thought that Cerda took delivery of progress was not made until the
ore near the Roman adit of San Pedro appointment of Rua Figueroa in
and, to save transport , roasted it in January 1859. Although he
the same area , very near the village, understood the barriers imposed by
Rio Tinto pueblo. The location of Treasury control, he and his
his Fabrica de Cerda is sho~n on the assistants made great efforts to
1878 plan. increase extraction from the mine and
to improve the metallurgy. Output
Cerda's story is told in some detail of ore increased in his first year by
by David Avery(l); his operations 23% to 15,700 tonnes and by the time
ceased in 1858 when it was recognised he left in 1863 had reached 89 , 000
that they were similar to those of tonnes , an output never again
the Planes Company. His enduring achieved under State control.
legacy to Rio Tinto is that the area
to the south-east where his roasting Lee Thomas gave an interesting
heaps were located has been known as account(16) of the metallurgical
Cerda for generations . operations at the time of his visit
in 1862 or 1863:
In 1856, two mlnlng engineers, D
Antonio Anciola and D Eloy Cassio , "The adoption of the cementation
inspected the mines and in their process, as it is now practised ,
report(13) suggested that opencast arose necessarily out of the
mining would be cheaper and safer inc rea si ng scarcity and dearness of
than the pillar and stall method then fuel. In the vicinity of Rio
employed. That method had been Tinto, indeed throughout those
introduced in 1830 and was not parts of the province of Huelva I
successful because of the large have visited , a more than unusual
number of Roman galleries and caves dearth of such timber as would be
~hich made it impossible to leave the applicable to the manufacture of
pillars at each level one above the charcoal is observed. The
other and accidents had occurred due country is covered with brushwood
to collapse of galleries . (gumcistus) of an inferior quality,
but one may travel for miles
Ancio1a and Cassio also suggested without meeting with an encina tree
that higher copper recoveries would of any kind . The teleras are
be achieved by smelting copper-rich open to the air •••• .. The
pyrites; the overall recovery at the prevalence of wind and rain
time from roasting and leaching seems consequently exercises a
to have been significantly less than considerable influence over the
50% and decreased with increasing calcination . The exposure to
copper in the are . They carried strong currents of air gives rise
out sampling in the mine and to fusion of a considerable portion
concluded that the average coppe r of the sulphurets and the
content was 4.44% , a figure thought decomposition of the sulphates
too high by most engineers at the which pass into oxides and
time. insoluble salts and during the
heavy rains the sulphate of copper
Other engineers also advocated must be washed away as soon as
smelting copper rich pyrites but the formed.
advice was not put into practice ,
presumably because of the scarcity "The calcined mineral is carried on
and cost of charcoal , and heap the backs of mules or donkeys to
roasting followed by leaching and the lixiviation tanks. These

- 33 -
are made of rough masonry and 1 cubic met r e of water was required
lined with asphalt, the common for 1.5 cubic metres of ca l cines
size is 7 metres long by 4.25 washed .
metres wide by 1 deep . They are
two-thirds filled with calcines The wash waters were run into
and contain about 17 tons." settling tanks, to deposit as much as
possible of the suspended matter , and
Of the mine itself , Lee Thomas wrote : so manipulated to have a final copper
content of about 8 , 000 gm per cubic
"It contains six levels . The metre and a density of between 12 and
first and second are in a very bad 15 degrees Baume. This liquor went
condition. The third , fourth and to ceme ntati on tanks, of the same
fifth run into one another in such dimensions as the leaching tanks and
a way as to make it difficult to filled with pi g iron. Cementation
say where one begins and the other was a batch process and the time
ends . The sixth, which is on the taken to precipitate the copper
level with the San Roque adit , has varied from 24 to 30 hours in summer
been opened up of late years and to 40 to 48 hours in winter. In
the plan of work ing adopted has cold weather the liquor needed
been systematically carried out. agitating . The disch~rge from the
The dimensions of the levels are 3 ceme ntation tanks contained about 200
varas wide and 2.5 varas high, and 8m Cu per cubic metre (ie 200 ppm);
the pillars left are 4 varas it was mixed with natural drainage
square. The measurement from mine waters, for example from San
level to level is about 9.5 vara s Luis adit, and directed along a
and is made up thus: channel containing iron and the final
exi t water contained about 20 gm Cu
Height of level 2. 5 varas per c ubic metre. The fine
Underhand stope 4.0 " precipi tate, papucha, collected from
Floor left 3.0 " this ca nal contained abo ut 10% Cu -
prior to about 1864 little could have
The method of working necessitates been done with this material because
the leaving in the mine about 58% of its high arsenic conten t .
of the ore for floors and pillars. n
The cementation or precipitating
A vara is 83 . 5 cm. Thomas is tanks were cleaned out after having
thought to have been mistaken about been fi l led three or four times , when
the levels and there were a total of the coating of copper on the pig iron
nine , with only eight whi ch could be was thick enough to be removed by
drained by the San Luis adit hand or pick . The tanks were then
effectively used. emptied, all the pig iron with copper
attac hed removed and the fine
Rua Figueroa(14) has provided a precipitate on the tank bottoms was
wealth of technical information on shovelled out. Each uni t of copper
leaching and smelting operations in precipitated consumed about 2. 2 units
his time. For instance, the of pig iron .
calcines were washed seven times and
the average copper co ntent of the Rua Figueroa gives analyses of two
liquors taken off was: precipitates ; the first removed from
pig iron, the second collected as
Wash Duration Cu gm/m3 ° Baume sludge from ceme ntation tank bottoms ,
as follows :
1st 18 hours 18 ,210 32
2nd 24 " 10,818 15 Cu 65 . 47% 29.72%
3rd 30 " 4,971 6 As 2.48% 2.77%
4th 34 " 2,786 3 Sb 0.64% 1. 13%
5th 40 " 1, 241 2 Metallic Fe 3. 64% ND
6th 40 " 778 S ND 2. 14%

- 34 -
Graphite C 2. 15% ND kernels , the nature and source of
Insoluble 6 . 25% 7.66% which are explained below. The
mixture was smelted with Roman slag
ND = not dete r mined in a small blast furnace , with charge
and output as follows:
The pr ecipitate was made into balls
of about 10 cm diameter and dried, Roasted mixture & slags 1025 kg
either in the sun or on a hot floor Roman slag 1360 II
heated by brushwood, then calcined in Charcoal 600 II
a vertical brick furnace fired with Black copper produced 227 "
brushwood. The depth of charge in
this furnace was about 1. 5 metres, Slag contained about 0 . 7% Cu
the brushwood burned for about 5-6
hours) by which time the charge was Operations of smelting precipitate
hot enough to continue calcining and refining copper were labour
autogenously for 6-8 days. Weight intensive by modern standards . The
loss on ca l cination was 28-32% for crew for the refining hearth was 5
precipitate from artificial men per shi f t of 12 ho urs; 2 worked
cementation and 34-40% for the bellows . The reverbe r atory
precipitate from natural cementation. employed 6 men per shift , although at
Calcination was a very unpleasant the melting stage the demands on them
operation because of partial removal were light.
of sulphur , arsenic and antimony in
fume. It was Lee Thomas who noticed that
kernels formed during roasting in the
Calcined precipitate was melted in a teleras were not coll ected separatel y
refinery hearth of the type used and used a valuable so urce of copper
since the days of Sanz and the to the blast furnaces and he pointed
process required large amounts of this out to Rua Figueroa . These
charcoal . Producing black copper, kernels , called "nucleos" at Rio
2 , 500 kg of precipitate yielded 1600 Tinto , are formed in the slow
kg in 24 hours for a consumption of roasting of cupreous pyrites by
640 kg of charcoal; producing refined preferential oxidation at the
copper the output in 24 hours was particle surface of iron sulphide -
between 400 and 620 kg , depending on cupreous sulphide diffuses slowly to
whether it was copper for alloying , the centre to give concentrations as
containing cupreous oxide and known high as 40% CuS in a cent r al core,
as "punta de martinete ll , or refined encased in a soft shell of iron oxide
copper for rolling , Charcoal which is easily detached.
consumption in refining was 500 and
620 kg respectively . The artificial cementation process
produced copper relatively cheaply
Black copper was normally refined in from low copper content pyrites .
the reverbe r atory "spleiss ll furnace There were a number of disadvantages
installed by Remisa in 1831 . The to its use at Rio Tinto and Rua
charge was 4 , 400 kg of black copper Figueroa listed them as follows:
and 1,000 kilos of copper recovered
from melting or smelting refinery A considerable amo unt of fuel wood
slags and ladle skulls. Recovery was required .
into refined copper was 88%, the
melting and refining time 18 to 20 All the s ulphu r in the are was
hours and fuel used was 4 , 200 kg of lost.
logs .
It was diffic ult to roast teleras
Slags from the r efinery hearth and uniformlYi some or e was over
the reve r be r atory furnace were mixed roasted , some not roasted at all .
with roasted "matte, papucha or other
hi gh- arsenic precipitate and roasted Soluble cop per was lost during the

- 35 -
rainy season. The furnaces were blown in on 9
January 1865 and, after experiencing
Sulphur dioxide emissions killed some of the difficulties common to
the vegetation. such start-ups, demonstrated an
improved performance . Campaigns
Rua Figueroa observed that pyrites lasted up to 10 days, double that of
lying on the floor of the mine the earlier furnaces. and the two
released soluble copper, the basis furnaces were capable of smelting a
for natural cementation, but did not total of 14 tonnes of charge per day.
pursue experiments to test such comprising :
possibilities.
29.0% calcined are of 7.2% eu
In this period , smelting was still 10 . 2% crude are 6.0% II
applied to ca l cined high grade ore 14.8% siliceous ore 5.6% II
but on a reduced scale . By 1864 9.3% kernels 20.0% II
there was only one small blast 37.7% slag 1. 6% "
furnace working - it was 90 cm long
by 60 cm wide and 270 cm high and it Charcoal consumption was 20% of the
had a hearth 60 cm deep made of the charge , compared with 29% on the
usual mixture of fine charcoal and older furnace . Daily matte
clay . It had one 4 cm diameter production was about 3 . 5 tonnes
tuyere placed 60 cm above the hearth, containing 20- 25% Cu .
with blast supplied by a bellows
worked by 2 men when water power was Treating low grade matte had always
not available. Figures from 1841, been a problem and it became more
in Remisa's time, show that the serious with this lower grade matte
furnace was then smelting 1,350 kg of which had to be roasted as many as 8
ca l cined ore per 24 hours, using 29% times. This was done in heaps with
charcoal in the charge and producing all the disadvantages already
67 kg of black copper containing identified by Rua Figueroa for
about 92% Cu and probably performance roasting cupreous pyrites.
had changed little over 2 decades.
At Rio Tinto the base of the matte
At last , in 1864, an effort was made heap had a diameter of between 4 and
to act on the recommendations made by 5 metres and for the first two
many engineers over the years , and roastings the height was not greater
notably by Anciola and Cassio in than 30 cm. The heaps were then
1856, to develop matte smelting for made cone shaped for subsequent
higher grade cupreous are. The old roasts and reached a height of 2
Los Desamparados smelter, which had metres before the eighth roast.
been used by Cerda until 1858, was The heaps were built on a bed of logs
chosen as the site for another and brushwood - for the earlier
smelter and two furnaces were roasts little fuel was used to avoid
erected, one 100 cm long by 60cm wide melting the matte; as the sulphur was
and the other 80 cm by 56 cm, removed more fuel and higher
internal measurements; the height of temperatures were used .
both was 350 cm. Each had a single
tuyere of 13 mm diameter placed 250 Among examples of matte roasting
cm below the top and the hearth given by RUB Figueroa is one for
tamped from clay and charcoal had a matte obtained from smelting kernels
depth of 50 cm. The furnace walls or papucha involving five stages.
were of porphyry lined with Roasting 30 tonnes of such matte
firebrick. Two tapholes were consumed about 2.5 tons each of
provided for slag and one for matte . brushwood and logs and the
A new waterwheel was built, with an complicated series of operations
output of about 2 HP to drive bellows extended in time over at least two
able to delive r 4 cubic metres at months . Rua Figueroa compared this
15-19 cm water gauge . process un favourably with that used

- 36 -
in South Wales where, at t hat time , brimstone wa s slowly being replaced
roasting 36 tonnes took about 12 days by pyri t es for this purpose and in
and the resultant product was lower 1852 Leblanc manufacturers used about
in sulphur than at Rio Tinto. 270 , 000 tonnes for acid making.

Roasted matte was smel t ed i n the same A commission was appointed on 5


blast f urnaces used to smelt calcined January 1860 to investigate the
cupreous pyrites and t he smel t ing and const ruction of a ra ilway . It
the re sultant black copper was recommend ed that the railway should
refined in the reverberatory furnace , go to the port of Huelva , at that
in much the same way as de sc ribed time only a very small fi shing port .
above for coppe r from smel t ing Lee Thomas(lS) wa s a ppointed as
precipitate . advisor and was in Spain in 1862-63.
Anciola a nd Cassio had suggested
In 1865 the cos t of produ cing refined transport for 470 , 000 tonnes but,
copper from cementation was 1.39 si nce the total mi ned in 1863 wa s
ptas/kg, compared with 1.29 from only aroud 90 , 000 t onnes , a figure of
smelting are . The co pper from 240 , 000 tonnes pa was adopted .
smelting was also of bette r quality
as a result of more effecti ve The railway would bring sto res, and
elimination of impurities in matte fuel collected en route, t o the mi nes
roasting . Compa rat i ve analyses - it was pla nned t o run from Rio
were: Ti nto to Pozuel o, Valverde , Tr i gueros
Cementation Smelting and Huelva, a distance of 61
eu 99.004% 99 .711% kilometres , and to be cons tructed as
S 0 . 059" Tr a tramway, meaning that no passengers
Sb 0 . 297" 0 . 289 11 were to be carried, using 40 lb
As 0.640 Tr r a ils , at an estimated cos t of
£238,000, as f ollows :
Arsenic was an important impurity in
copper produced at Rio Tinto , and 26 miles railway between Huelva and
elsewhere in Spain, and presumably Valverde at £4 , 000 per mile
the copper from ore smelting was £104 , 000
vastly s uperior material for the 12 miles railway be tween Valverde
Seville armaments factory's rolli ng and Rio Tinto at £7,000 per mile
mill. £ 84 ,000
Compensation fo r land not belonging
Production of co pper r eached a peak to the Gov t. £ 20 ,000
of 1, 335 t onnes in 1863 in Rua Plant, waggons , engines, horses ,
Figue r oa ' s final year in charge of etc. £ 30 ,000
operations and gradual l y declined
thereafter . Details of prod uct ion £238 ,000
fo r this period of gove rnment con t rol
are given in Appendi x 6 . This i s an early example of the
i ntroduction of British units to Rio
Transport of copper to Sevi lle by Tinto; the lump sum estimate was
horses and mules over t r acks was translated to 23 million pese tas .
always troublesome a nd in 1840 the As with so ma ny rec ommenda tion s ,
build ing of a road was suggested but nothin g was done, yet the mining
the sc heme did not materialise . In operatio n by a Britis h company at
their 1856 report , Anciola and Cassio Tharsis received permission for a
recommended t he construction of a railway which was ope ra ti ng by 1866 ,
railway to a port ; this showed and in 1867 the Buitron mine was
conside rable foresight on the part of granted a co ncessio n to build a
these two enginee r s who probably railway to San Juan del Puerto , a
envisaged the use of sulphur in t he distance of 40 kilometres . [This
pyrites for t he product ion of latter railway wa s s ub seq uently
s ulphur ic acid . From the 1840s extended to Zalamea and proved useful

- 37 -
to RTC - it finally closed in 1969.] the further recommendations. Some
work was done on enlarging the San
Another commission was formed in 1867 Luis adit and , in 1870 , a new shaft ,
under the Inspector of Mines, Los Inocentes, was started but lack
Salazar, and with Cassio as one of of funding from the Treasury
its members . Among its prevented any significant
recommendations were: development.

The San Luis adit and other Production costs for 1869, when 233
galleries should be enlarged to teleras were roasting and 822 tonnes
install rail transport for ore, of copper were recovered by
with an estimated cost saving of 20 cementation , were as follows:
reales per tonne .
ptas
Opencast working should be Mining 7.15
introduced , for an estimated Roasting ,cementation
further cost saving of 20 reales and refining 15.02
per tonne and providing opportunity Administration 1.40
to increase output .
Total,for producing
Smelting of cupreous pyrites should 11.70 kg copper
be increased - for better copper from 1 tonne ore 24.34
recovery, saving in pig iron for Cost per kg Cu 2.08
cementation and increased copper Per tonne 2,080
production.
At that time the price realised for
A large adit or tunnel should be copper in Seville was 1,400 ptas per
constructed to traverse all the tonne and the Treasury concluded that
lodes at a level 196 metres below it would not be wise for the State to
the Santa Ana pithead - this tunnel finance further development; the
being capable of taking waggons to mines were put up to auction and a
be moved directly to Huelva on the new era in control and operation was
projected railway . about to start. As Gonzalo y
Tarin(7) wrote a few years later:
It was believed that by making these lithe bad luck which always
improvements the cost of copper would accompanied State management was the
be reduced from 5,600 reales per reason why the idea of its sale
tonne to 4,400 if the first acquired a great many backers, even
recommendation was implemented , to among the Mining Engineers at Rio
3,200 if recommendations 1 and 2 were Tinto , who came to the conclusion
implemented, and progressively to that there was no other way to make
2,800 and 2,500 by implementation of the mines viable in the future."

- 38 -
I CHAPTER 7 I Early mining operations of The
Rio Tinto Company Limited
In February 1873 the bid of a t he mineralised sections .
consortium of British and Germa n
business men was accepted and soon The map issued with the new company ' s
afterwards the Rio Tinto Company was prospectus in July 1873, and reprod-
formed . Hugh Matheson was the uced in the Introduction as Figure 2,
chairma n and financial driving force; indicated the positions of the lodes
his confidence in seeking to acquire of massive pyrites, marked as South ,
the mines had been based largely on San Ped ro, Middle and North Lodes .
advice from Heinrich Doetsch and W It was soon appreciated that the plan
Sundheim, general merchants in Huelva was somewhat inaccurate - the San
with mining interests in the Pedro and Middle Lodes did not exist ,
province, David Forbes FRS, a British Spanish engineers having assumed
consulting mining eng ineer , George their existence because of the Roman
Bruce, a British consultant on workings on the northern and southern
railway planning and construction, s lopes of Salomo n; we now know those
and Dr Romer, an eminent German workings were concerned with
mineralogist - Forbes and Bruce were extracting jarosite for silver . An
appointed consultants to RTC on its important lode to the west of South
formation and played major roles in Lode , the San Dionisio Lode , was not
its development. The success of recognised until after operations
the British company which took over began.
control of operations at Tharsis
from French interests some years Forbes, recommended that m1n1ng
earlier would also have been an should continue at t he South Lode and
important sou rc e of co nfidence. that opencast working should be
The purchase price was the equivalent introduced; this latter recommend-
of £3,850,000. Details of the atio n had previously been made by
financial arrangements, a summary of Anciola and Cassia in 1856.
corporate evolution of RTC and some Theodor Blum, the first engineer
related comments a re given in appointed to the property by RTC as
Appendix 7. head of the mining and extraction
department, was responsible for
The maximum annual production of implementation of this, and other,
mined are at the mines prior to 1873 mining plans in the early years of
was 89 ,700 tonnes under the RTC. Production of the quantities
management of Rua Fig ueroa in 1863. of pyrites envisaged by the company
All previous operations at Rio Tinto required the opening up of other
had been concerned only with copper mining areas and the North Lode was
production - the new Company was also brought to production by 1880 .
founded to supply the rapidly growing Detailed examination of the
market for pyrites for su lphuric acid mineralised areas in 1873 no doubt
production, as well as to continue led to some revision of the plans
copper production at the mines, and suggested in the company 's prospectus
envisaged shipping 500,000 tpa to - ce rtainly early working revealed a
northern Europe. From the different, but not necessarily
reopening of the mines by Wolters, displeasing. disposition of the
operations had been conce ntrated on enormous mineral wealth.
what became known as the South Lode
and miners were no doubt initially In 1873 Rio Tinto had no road or ra il
attracted to that deposit by the links to bring in heavy equipment,
extensive system of adits driven by nor indeed was much mechanisation i n
the Romans and providing access to use anywhere in mining. Imports for

- 39 -
the mine were taken by barge from Cuatro Molinos adit, 31 metres
Huelva to San Juan del Puerto, thence below San Luis adit and used by the
to a site about 7 kilometres north of Romans for draining the mine; about
Valverde on the Buitron railway and 2 kilometres long .
by bullock cart the final 20 or so
kilometres to the mines area. The The railway entrance to the mine
operation depended on mules and workings of South Lode was driven on
donkeys for transport of overburden the 319.8 metre level and proved more
and are and, while the mining difficult than expected , the rock
operation was progressing on that being porphyry and not slate as had
basis, railway connections to the been assumed. Attempts to speed
mine were under construction. progress by driving also from within
the lode encountered difficulties
Railway transport was crucial to the with acid water, delaying work until
enterprise. The contract for the a Cornish engine with bronze pump
railway was undertaken by Clark , fittings was delivered. The tunnel
Pun chard and Company to plans was not completed until November
prepared by Bruce. Pier 1876; initially it was known as the
construction at Huelva, again to a Main Tunnel; after 1900 it became the
design by Bruce, was also entrusted 11th Floor Tunnel .
initially to Clark, Punchard but they
found the task beyond their Delays in completing the Main Tunnel
experience and the contract was rendered significant exports of
transferred to John Dixon and pyrites impossible. Forbes had the
Company. The design of the system railway extended from Rio Tinto
envisaged loading mineral into Station towards the San Roque adit
railway trucks at the mine and and an inclined plane was built to
hauling the same trucks to discharge bring pyrites from the opencast to
to ship loading hoppers on the pier railway waggons at its foot. This
and this required extensive tunnell- was in operation by the time the
ing to access the mine workings . railway link to Huelva was completed
For almost a century, rail transport in July 1875.
was virtually the only means of
transporting are and waste from the Customers for pyrites were concerned
mining operations and the levels and about the value of the roasted
layout of the haulage tunnels were of cinders, which they usually sold to
vital concern to all concerned in associated companies for the recovery
planning and operations. of copper and iron by the Henderson
process - Checkland(28) gives an
In working the South Lode prior to interesting account of the structure
1873, three Roman adits were used in of the pyrites burning acid producers
extraction operations and a fourth of the time. This lead to a need for
for drainage . Since these adits selective mining to produce the high
are frequently referred to in copper content pyrites required and
reporting on activities at the mines this proved difficult in the South
they are listed below: Lode opencast .

San Pedro adit, at a level 362.4 The topmost portion of the orebody.
metres above Huelva datum and 44 . 7 although not as badly affected by
metres above the San Luis adit oxidation as Forbes had feared, was
still relatively low in copper as the
San Roque adit, 16.6 metres above Romans and Spaniards had removed the
the San Luis adit. richer parts. Because copper
content increased with depth,
San Luis adit , the Roman 8th floor, underground mining was started in
317 metres above Huelva and 10 . 3 1878 using an improved version of the
metres above the railway at Rio pillar and stall method used prior to
Tinto Station.

- 40 -
r igure 11 South Lode Opencast circa 1890

1873. The interval between fl oors underground mi ne was served by two


was extended from 10 to 12. 5 metres, shafts - the Main or Haestro shaft at
with galleries, 3m high by 3m wide, the east end for hoisting are , and
and pillars 6m square, as pre viousl y the Victoria at the west end, a
but with more attent i on to acc urate s ervice shaft .
vertical alignment.
By 1882 , North Lode was in production
Underground mining in a body worked but production from it and South Lode
from Roman times i nvolved the was inadequate to meet rising needs
problems with acid waters already and work to extend underground
encountered in driving the railway operations to the San Dionisio
tunnel and the engineers developed orebody began with extending the Main
the use of bronze fittings and wooden Tunnel westwards . It reached the
pipe linings to deal with the western extremity of the ore body by
problems, much as the Roman s had done the end of 1885 and for most of its
with their bronze shafted, wooden length was in pyrite. The mining
water wheels - extensive use was now method used in San Dionis io was
made of Cornish engines of the i ni tially the same as used in South
Trevithick design(29). Lode. San Dionisi o proved to be
the most important of the lodes in
After completion of the Main Tunnel, RTC's operations although not
overburden and mineral were loaded i dentified by the company unt i l after
directly to rail waggons by hand. it began operations at the mines -
From underground workings, they were because of its importance its mining
delivered to the 9th floor and fed to is dealt with in detail in a separate
waggons in the Tunnel. The chapter.

- 41 -
By 1893, umderground working at South 1891, to authorise the introduction
Lode had reached its limit westward of the more costly cut and fi l l
and some 5 million tonnes of pyrite methods.
of 2.86% average copper content had
been extracted by mining down t o the The new mining method was implemented
22nd floor, that is 185 m above rapidly and effectively, but much of
Huelva datum . Some 9 . 5 million the workings was still unfi l led when ,
tonnes averaging 3.1% Cu had by this in 1907 , a torrential rainstorm
time been mined from the open cast and washed much of the slate footwall of
it was decided to extend the opencast the opencast on to the roof of the
westwards to its limit , a decision underground mine, cru shing the
which implied the destruction in due unfilled workings down to the 22nd
course of Rio Tinto pueblo. floor , the bottom of the mine. A
fire resulted , with sulphur dioxide
Julian(30) , writing in 1939, refers passing to otherwise unaffected
to the low extraction obtained by the sections of the mine a nd it was many
underground mining method used at the years before full recovery from the
turn of the century and the inherent damage was achie ved , meantime
instability of the workings where any production fell to around 140 , 000
pillar robbing had been conducted. tonnes pa.
In 1856 Ancio l a and Cassio had
suggested use of overburden from Average annual mine production is
their proposed opencast to fill given by Avery(l) as 763 , 000 tonnes
underground cavities; back filling for the period lS76- S0 and 1 ,1 53 , 000
was introduced at the Tharsis mine in tonnes for the period lS81-S5, a
lS95 but, despite earlier suggestions steady but not spectacular build-up,
from both engineers a nd managers , it with exports for the second period ,
was not introduced until 1900 at Ri o at an average of some 308,000 tonnes
Tinto. By that time the pa still su bstantially below the
underground workings were honeycombed level of 500,000 tonnes forecast in
down to the 22nd floor and , with some the prospectus of 1873 and, not
20 million tonnes remaining in pl ace surprisingly shareholders were
in South Lode , the difficult i es of anxious about their investments, as
maintaining production at the then related in Appendix 7. More
current levels were sufficiently detailed information on production is
serious for the Board , in Oc tober contained in Appendix 10.

Figure 12 Heap Roasting cir ca 1890

- 42 -
I CHAPTER 8 I Early metallurgical operations
ofRTC
When RTC took over operations , the cover). Teleras were built 100 ft
Prieto process had been in use for long, with a maximum width of 16 ft,
copper production for over 35 years between 10 and 15 ft high, and with
with considerable success, against a hemispherical ends. In building a
decline in the roasting and smelting telera , rough flues were made on the
of ores. Among the difficulties levelled ground, using loose stones
for the smelting route, which have to give a cross section of about 15
been referred to earlier, were the in wide and 18 in high. These
cost of charcoal and the lack of ore flues ran across the telera, at about
of copper grade sufficiently high to 15 ft intervals, and connected to two
work economically by the smelting chimneys, one at each end; the
route. The Prieto roasting and chimneys were raised in rough stones
leaching process achieved higher in the course of building the telera.
extraction with lower grade ore and Lump pyrites was laid on the floor
the conditions were therefore greatly between the flues and the
in its favour . construction of the telera was then
carried out by women and boys who
Thus continued use of the Prieto carried the mineral in baskets on
process was attractive to RTC for their heads, walking up wooden ramps.
treating the large tonnage of pyrites
of lower copper content which was not On completion, the surface was
readily saleable abroad. Although covered with fine pyrites and allowed
during the Remisa era adverse effects to settle for a few days before it
of sulphurous gases on the was fired by brushwood and logs which
countryside and its inhabitants had had been placed in the flues. Fuel
become apparent, protests had use was about 2.5% of the weight of
seemingly not been so great as to pyrites . Steam, tar and free
cause concern; indeed two beneficial sulphur produced during the initial
effects were observed - the firing condensed on the outer
inhabitants of Rio Tinto remained surface, forming a hard crust - where
healthy during a number of cholera it cracked, it was sealed with fine
epidemics in the region and the pyrites . Some control of roasting
acidity of stagnant waters was such was possible by damping the flue
as to inhibit the breeding of inlets and chimney outlets, the off
mosquitoes and the spread of malaria . gases commonly ran 3 - 4% sulphur
dioxide and roasting took about 6
In 1872 the size of the teleras was months , depending on the weather.
between 180 and 230 tonnes and much On completion, the telera was broken
larger heaps were desirable for down and, while still hot, hand
handling the vastly increased loaded into 2 tonne side tipping
tonnages of ore thereafter. Trials steel railway waggons. Any
with very large teleras showed that unroasted ore and kernels were set
one of 1,500 tonnes, while economis- aside for later treatment.
ing on fuel, took 12 months to roast
and some central parts still remained The roasted ore was taken to one of
inadequately roasted. A decision three installations of washing tanks
was made to limit the size to 500 to - Estacion, Marasmilla and Nerva.
1,000 tonnes. The waggons tipped directly into
tanks, intially 2 ft deep, 10 to 14
The calcination ground was located on ft wide and 30 ft long, but later
an impervious slate formation to the deepened to 3 ft and narrowed to 8
east of the railway, as shown in ft; each tank held about 40 tonnes of
the reproduced 1878 plan (inside back calcines . There followed the

- 43 -
complicated washing cycle lasting 7 to summon employees. Occasionally
or 8 days , as described on page 34, work could not begin before 2 pm -
after which the washed calcines were after a serious railway accident,
reloaded in waggons and dumped on traffic was stopped if the visibility
Barbasco heaps, or, as they were fell to 2 metres!
originally called, "terreros" .
Further copper extraction occurred Apart from the effect on the local
very slowly, as a result of air people , especially those in Nerva who
oxidation and washing, the latter lived closest to the calcination
usually only by rain - with are area , damage to agriculture was
containing 2.5% Cu it was normal to considerable and the prevailing wind
recover 60% in the tank washing. in the winter months carried the
sulphurous smoke towards the best
A significant discovery made in the agricultural land near Zalamea la
early years of operation was that Real. Lack of protection from
passing the "brown liquorTl obtained in government and seeming indifference
the leaching or washing operation on the part of the Company to the
through a bed of small sized pyrites farmers' plight led to the formatiom
before transfer to the cementation of an anti-smoke league which
tanks reduced the ferric iron content encouraged agitators . Finall y a
and increased the copper content - meeting was arranged in the Town Hall
reduction in ferric iron content led at Rio Tinto on 4 February 1888.
to a useful reduction in iron Unhappily , the crowd got out of
consumption. The role of ferric control and shots fired by the
iron in heap leaching was a topic of military resulted in serious loss of
intense interest, particularly in the life - fearing repercussions,
role of Heinrich Doetsch in promoting relatives furtively buried many of
use of patented processes for heap those who died in the "terreros",
leaching. their skeletons to be found many
years later when those heaps were
The work was labour intensive and lifted.
very arduous , especially the loading
of hot calcines into waggons. This loss of life so shocked Spain
About 1,000 tonnes of pyrites was that within the space of 24 days the
built into teleras daily and, at the government issued a decree banning
end of the cycle, about 800tonnes per open-air roasting. The RTC Board
day of washed calcines was loaded for saw this as a direct attack on the
dumping. Before 1873 there were Company , despite all the evidence of
233 teleras roasting a maximum of the damage and distress the roasting
65,000 tonnes of pyrites annually; operations were causing - it believed
this was increased to 159,000 tonnes the Company had acquired the right to
in 1876 and again to 300,000 tonnes use the process when it purchased the
in 1880 - water supply was the main mines and made official protests to
obstacle to expansion. the Government. After some
resistance, resulting in a dramatic
This considerable increase in the reduction in roasting in 1889, the
roasting of pyrites was responsible Government yielded and agreed to
for smoke damage over an increasing continued roasting with a request
area . On many mornings there was a that the tonnage be reduced.
very heavy blanket of sulphurous
smoke over the calcination grounds Whereas Remisa in his operations in
and in Nerva it was sometimes the 1830s had shown no concern for
impossible for people to see their the impact of operations on the
way about. In summer this blanket environment , RTC became concerned and
of smoke , which also carried arsen- from 1877 experimented with tree
ious oxide, would disperse soon after planting. Details of the continuing
sunrise but in winter conditions were concern about its lands are given in
so bad that work could not start Appendix 8 .
until bells were rung by the Company

- 44 -
I CHAPTER 9 I Infrastructure for the RTC
operations
RAILWAY From there trains of 50 waggons were
hauled to Huelva over t he nearly
The rail system introduced by RTC was level track, either by two "c" class
essential for export of pyrites, it locos or one bigger loco. In
provided transport to the mines for 1905 , "K" class locos were purchased
imported eq uipment and supplies and, from the North British Locomotive
because roads in the province were Company and these could haul 44 " A"
rudimentary, it provided passenger type waggons of 11 tonnes individual
services for company employees . capacity directly from the mines to
Huelva - in 1920 the trains were
From Huelva , the railway, of 3ft 6in increased to 74 waggons .
gauge and single track except at
stations, followed the course of the Two Garrett locos were acquired in
Tinta river and the distance from 1929 and these each hauled trains of
Huelva to Rio Tinta station is 83 km . 1 , 500 tonnes of mineral in 30 tonne
The first 14 km crosses marshy waggons. In 1953 six 200 class
ground , the next 11 is through locos from Robert Stephenson of
f ertil e country to Las Mallas Darlington were introduced and these
station, after which it begins pulled trains of 1, 000 tonnes. All
cl imbing on its sinuous course beside the locomotives to this time were
the river. At the station of Los coal fired steam engines - subsequent-
FraileSt 72 km from Huelva , the track ly diesel l ocomotives were introduced
is 152.5 m above sea level; f r om to service.
t here the grade increases and at
kilometre 79 (Naya station) the track The railway system provided passenger
is 257.8 m above sea level. At the transport, notably for the emp l oyees
Rio Tinto station, kilometre 83 , it living in Zalamea and Nerva, services
is 318.6 m above sea level. which operated until 1968 .

The original planning withstood the


test of time and few changes were HUELVA PORT AND PIER
made as the demands of traffic
increased. There were five tunnels Huelva was a small fishing village
original ly ; the Chico tunnel at until the middle of the 19th century
kilometre 65 was subsequently made when Ernesto Deligny, who represented
into a cutting . The longest tunnel French financial i nterests in
is Salomon , 150 m, and the line establishing mining activities in the
leaving this tunnel is supported on a Province of Huelva and whose
bridge , originally of three spans involvement the r ein has been
totalling 67 m. This bridge was recounted by Checkland(28) , was
washed away in a serio us flood on New responsible for st udies which
Year's Day 1888 and was replaced by a resulted in its rapid development for
single span construction - the shipment of pyrites . In 1867 the
repairs cost £25 , 82 1! Tharsis company built a pier for
shipment of their pyrites on the west
50 lb rails were used initially and side of the estuary at Corrales at
upgrading to 75 lb was gradually the mouth of the Odiel but in 1873
carried out. The first there was no dock or wharfage
locomotives , "c" class, weighed 25 accommodation fo r shipping in Huelva
tonnes and hauled 25 hopper waggons , and cargo was transported between
each carrying 10 tonnes , as far as vessels and shore by barges .
Gades station, 45 km from the mines . Checkland has end- paper maps which

- 45 -
show the railways of Tharsis and RTC ensure speedy loading of ships .
in relation to others in the region. This was especially useful when
Bruce , RTC's consultant, considered trains could not reach Huelva, as,
two schemes - a low level pier for example . when the Salomon bridge
requiring lifting arrangements to was destroyed in 1888.
discharge the contents of individual
waggons into the receiving vessels, In 1974 shipment of pyrites was
and a pier with rising gradient transferred to a new port on the east
allowing automatic discharge of side of the estuary of the Tinto
waggons at a height sufficient for river. For a time pyrites
the discharged mineral to flow by continued to be hauled by the
gravity into the vessels. The original railway to Las Mallas , the
second scheme , though significantly junction of the old RTC main line
more costly, was selected . with the State system . Since the
old main line closed in 1984, all
There followed conside r able debate transport of mineral to Huelva has
with the regulating authorities who been by road .
had doubts about the novel design .
Additionally, the bearing
characteristics of the estuarial muds HOUSING
meant that considerable attention was
needed to achieve satisfactory piling In 1860 the population of Rio Tinto
support for the structures. These pueblo was 1 , 976 and that of the
difficulties were overcome and, after original Rio Tioto (Nerva since 1891)
transferring the construction was about the same. In 1873 the
contract, as mentioned on page 40, RTC's labou r force, including staff,
the pier was completed on 23 March was 950, but this figure exc luded
1876 (and remained in service those employed by Clark Punchard on
continuously until April 1974). railway construction and the South
Lode Tunnel. Ten years later , in
It was 1,900 ft long and approached 1883 , the labour force was 9,801.
by an embankment 1,500 ft long; 700 The British company was proving a
ft of the embankment was carried on a much more attractive employer than
steel structure supported by piling the previous state enterprise and
because ground conditions would not there was a shortage of accommodation
support a conventional earth to match the inflow; many lived in
embankment . The pier itself was a temporary shelters and nearby caves .
two-decked strucure, with the lower
deck handling inwards goods and RTC undertook the building of houses
export of small tonnage materials - soon after it began its operations,
matte, copper , copper precipitate firstly at Rio Tinto pueblo and then
and, in later years , sulphur . above it on the Mesa de los Pinos -
this new village came to be known as
The pier was designed to take ships Alto de la Mesa and included a
of 4 , 000 tonnes but it was able to hospital. Some houses were also
accept vessels of 8 , 000 tonnes and built opposite the railway station in
even larger ships co uld have been the mine area, Rio Tinto Estacion .
accepted but the bar at the entrance
to the river was the limiting factor . A small hospital existed in Rio Tinto
The maximum tonnage shipped in any pueblo at the time of RTC's purchase
week was 48,000 and the pier was and it appears to have been under the
capable of handling 1 million tonnes control of Jesus Alonso Lopez who
pa, double the nominal design figure . stayed with RTC until his death in
1894. The first British doctor , J
A mineral store, known as the Sutherland Mackay, joined the company
"polvorin", was erected in 1876, with in 1879 and moved to Huelva in 1888
storage for 50 , 000 tonnes aod to the company ' s hospital there.
intended to provide buffer stock to He is particularly remembered for his

- 46 -
Figure 13 "The Rio Tinto M~nes i n Southern Spain"
(reproduced from The Illustrated London News August 7, 1875)

- 47 -
interest in football and the founding In the 1880s many thought that the
of the Huelva Spanish Football Club. port of Huelva could compete with
Lisbon and become as large and
In 1880 two further villages were important; the climate was good and
built - Atalaya for the men employed it had obvious possibilities as a
at the San Dionisio lode and Naya for seaside resort . A hotel was buil t,
men working at the east end of the financed by the Matheson Bank, London
property where export mineral was and Messrs Sundheim and Doetsch , the
crushed prior to shipment and where Huelva merchants who supported
the cementation operations were Matheson in setting up RTC . It was
carried out. A further village was opened in 1892 with great ceremony
built at Dehesa in 1887 for men coinciding with the 400th anniversary
working at North Lode. of the departure of Christopher
Columbus from nearby Palos . As a
In 1882 houses were built for the grand hotel it was a failure and RTC
general manager and senior staff on a purchased it in 1894 to accomodate
site to the west of the operations senior Huelva staff and to use as
with, at that time, a magnificent offices; thereafter it was known as
view to the sierras to the north , Casa Colon .
hence the name - Bella Vista . In
1891 a club and an Anglican church
were built and over the years further WATER SUPPLY
houses added. This was the British
community and eventually most of the At the time of acquisition by RTC,
expatriate employees lived there . water was obtained from springs ,
wells and the Huerta de la Cana, all
With th~ rapid expansion of South sources in the slate and providing
Lode westward , it was obvious that good uncontaminated water but very
Rio Tinto pueblo would have to be limited in supply. With the rapid
abandoned and EI Valle was the town increase in population of Rio Tinto
built to replace it . The new pueblo, the immediate needs for water
church of Santa Barbara was opened were met by driving an adit into the
there in 1918 and the mines slate below the ironstone capping of
Administration building (Direccion) the Mesa de los Pinos and water from
was finally relocated there in 1938; this still flows .
thereafter Rio Tinto pueblo was
virtually a ghost town. In the operations, wel l s were sunk at
convenient sites to provide water for
No large Andalusian community would boilers driving steam operated
have been complete without its bull equipment but the supply from these
ring and RTC built a ring in Rio frequently became contaminated by
Tinto pueblo. It apparently acid drainage , mainly from heap
attracted undesirable elements in the leaching operations. For the
community and was demolished in 1884. leaching operations, acid water from
Thereafter the local people were the Cueva del Lago was used.
still able to attend bull fights in
Zalamea , Nerva and Campofrio. Average annual rainfall at the mines ,
as measured from 1875 to 1974, was
At Huelva, which had developed as a 29.1 in , but it varies quite sharply
consequence of ot;ler mining from year to year and seasonally .
operations in the province , there was 1874 and 1875 were years of
at first no RTC housing but a exceptionally low rainfall and in
hospital was built in 1884. Soon 1876 two dams were built; both are
after the turn of the century the shown in the 1878 plan . The South
company built employee housing, in a Dam was the larger with the smaller
development known as TIEl Barrio Reina Railway Dam below it - this latter
Victoria Tl and another hospital was dam was filled with overburden from
built here in 1931 . the South Lode opencast in 1909.

- 48 -
Expansion of heap leaching led to the the houses in the Spanish villages.
building of a third and larger dam, Water borne sewage service was
Marasmilla, completed in 1879 across installed in Bella Vista in 1926
the Tinto river, and also shown on after the chairman had suffered a
the 1878 plan. bout of colitis while visiting the
mines!
Marasmilla water was markedly acid
and was pumped by steam driven bronze
pumps - in 1892 a large Cornish pump ELECTRICITY SUPPLY
was installed to elevate water to a
tank, usually referred to at Rio Early operations of RTC were powered
Tinto as a "deposit", Spanish by large numbers of individual steam
"deposito" , from which it was engines and electric power was first
distributed to leaching heaps by used in 1901 at the Bessemer smelter
gravity . The pump operated until (see page 72) to operate a 60 tonne
1920. crane. Electricity was supplied at
220 v dc by a Siemens of Germany 80
In 1882, after a further period of hp dynamo, belt driven by a steam
very low rainfall, a decision was engine .
made to build a much larger dam at
Campofrio, some distance to the north Central generation of electricity
of the mining area. This was commenced on 1 January 1909 at a
completed in the spring of 1883 and power station, "Central Electrica",
had a capacity of 3 million cubic located near the South Dam which
metres and was at an elevation such provided cooling water, although this
that it supplied the calcination site suffered a disadvantage in that
ground by gravity through a 15 in coal had to be brought in from Rio
cast iron pipeline via Quebranto Tinto station at an elevation 100 m
Huesos, at which point a pump was below it - this required 2 km of
installed to raise water to Rio Tinto railway. Generation was at 3,150 v
pueblo and the operations at higher AC and transmission at 3,000 volts;
levels at Cerda. initially the generators were driven
by two Bellis and Morcom triple
Until 1900 there was no domestic expansion vertical engines using
supply in any of the villages; at steam at 190 pounds per square inch
that time standpipes were provided. and each coupled to 750 kw
Once again, at this time, shortage of alternators. Turbo-alternators were
water for operations led to a plan subsequently installed; the first in
for another dam on the Jaramar river 1911 was of 1,500 kW and the fourth
to the east of Rio Tinto and the and last of 10,000 kW.
boundary between the provinces of
Huelva and Seville but it proved The original boilers were of
impossible to obtain the consent of cylindrical shell type supplied by
the Seville authorities. RTC Babcock and Wilcox, each designed to
reverted to an earlier plan for a dam provide 8,200 kilos per hour at 190
at Zumajo on company owned land psi. These were replaced in 1928
this had a capacity of almost 2 and 1930 by John Thompson water tube
million cubic metres and was boilers but it was not until 1955
completed in 1907, another year of that these boilers were modified to
drought during which the com pany deliver steam at 350 psi for which
obtained permission to pump water the 10,000 kW turbo-alternator was
from the Jaramar river. designed.

Direct water mains to the houses at The first connection was for
Bella Vista were provided in 1907 but Guillermo shaft at the San Dionisio
it was not until RTC had sold out to ore body (see page 53) and in 1912 a
CEMRT that running water and water 600 hp air compressor was installed
borne sewage service were provided to on surface between Guillermo shaft

- 49 -
and Bella Vista to provide air at 100 make a road into the mines from the
psi for the mine - many years later Huelva to Badajoz road , connecting
this installation was greatly with that road at a point near
improved by excavating a large air Zalamea . A second road was
receiver in the porphyry so that a similarly built via the Puerto Rubia
reserve of compressed air could be Pass to Aracena and a third from
built up on night shift when the Nerva to Castillo de los Guardas, to
demand was neglible . join the road from Seville to
Aracena. Roads in the mining area
Electric lighting was installed i n were then developed and by 1930 all
Bella Vista in 1909 but, for operating departments were served by
political reasons, public lighting roads.
was not used in El Valle until 1920,
nor was the use of electricity for Prior to this time, the normal mode
domestic cooking permitted in Bella of transport for staff was walking or
Vista until 1929. Central by horse , with those living in Bella
Electrica was closed down in January Vista travelling by train to the main
1966, since when electricity has been administrative office, Direccion, in
supplied from the regional Rio Tinto pueblo . The train, known
electricity utility, Sevillana de as the Ubatea U or tray, because the
Electricidad SA. passenger accommodation usually
consisted of a platform with seats
attached, left Bella Vista at 7.30
ROADS am, returned to Bella Vista at noon,
returned to the office at 1.30 pm and
In 1873 there were no roads for finally returned to Bella Vista at
wheeled vehicles entering Rio Tinto , the end of the working day at 5.00
only mule tracks and, with the pm. In later years the batea
successful development of the carried staff further afield, through
railway, it was not until a very the central operations area east to
damaging strike in 1920 that any the pyrites crushing and
modern road was built . At this time classification plant at Naya .
the Government employed strikers to

f i gure 14 Rio Tinto Pueblo , early 1900s

- 50 -
ICHAPTER 10 I Mining at San Dionisio and
North Lode
SAN DIONISIO Eduardo
Victor ia, service shaft fo r South
Development of San Dionisio for Lode workings .
copper by the Romans seems to have San Dionisio, which made connection
been limited but they undoubtedly with the extension of the Main
extracted silver from the ores below Tunnel in 1882 and was used for
the gossan, in which process some hoisting mineral.
300,000 tonnes of slag were Alfonso. another shaf t for hoisting
accumulated nearby. The y made mineral.
four adits into the mass and
Palmer(18) noted the co nnections of Another shaft , No 6 Shaft . was being
these adits to surface shafts. sunk in 1882.
probably for alignment.
Mining of San Dionisio began using
Williams(21) emphasised the the pillar and stall method as it had
importance of San Dionisio as evolved in South Lode and by 1900, as
follows: described by Julian(30), the mine
"had been almost completely chambered
"the San Dionisio Lode, which is to below the 20th floor, and work was
the largest single deposit at Rio proceeding on the s ucceeding floors
Tinta, has a maximum length of 1060 down to the 26th, and below that
mo; on its upper levels it is level at intervals of 125 ft. on the
continuous with the Ed uardo Mass 29th and 32nd floors. By this pillar
which extends for a further 100 m. and stall method, carried out at
to the east. In places the solid vertical intervals of 41 ft . , 20 per
ore is unbroken over a width of 280 cent only of the whole mass of ore
m., and drilling has proved it to could, theoretically, be extracted.
persist for at least 485 m. below .•.• It was thus urgently necessary
the pre-opencast surface •..•. • The that some other method be devised for
upper part of the deposit lies exploiting the remaining 70 or 80 per
between s late and porphyry wall s , cent of the orebodies."
but where its base has been
verified the massive ore is J ulian goes on to describe in some
completely enclosed within porphyry detail the effo rts made from about
walls . " 1900 to stabilise the workings by
filling from the lower levels upwards
The position of San Dionisio relative in preparation for mining the pillars
to South Lode is shown in Figure 15, from the upper levels downward. It
a plan prepared i n 1939 and hence was estimated that it would require
showing features introduced in later some 7 million tonnes of waste rock
stages of RTC development . to fill the voids created by the
Although at its formation, RTC was mining to that date of about 18
apparently unaware of the existence million tonnes of ore and that would
of the San Dionisio Lode, it soon take seve ral years. Julian
became a major factor in its continues :
operations and 5 shafts had been sunk
into it by 1882 ; they were: "It was, therefore, decided by the
mining engineers in charge to fill
Alberto, the most easterly, which with waste the openings in a number
did not make contact with the ore of transve rse col umns extending
because it went through the Eduardo from the lowest floors to the top
fault which is an unmineralised gap floor, and from foot- to hanging-
between the South and Edua rdo Lodes wall, each column so filled being

- 51 -
{
I I
, \'! II
ii II
Im OI
I
I

\\. 1

I"
1

- 52 -
about 80 ft. in its dimension parallel to the orebody.
parallel with the strike of the
orebody. The columns thus filled Working began by taking ar e f r om the
were at first about 300 to 375 ft. weak slate contact side , retreating
apart . On each floor the towards the porphyry galle r y at each
longitudinal openings, or gangways, level. Drilling was by hand
were maintained through the filling machine , and all loading in the 1920s
by building masonry arches about 7 was done by hand, using a hoe -l ike
to 8 ft. high and 5 ft. wide. In tool - the rod a - to pull ore into a
each of these columns stapes were two handled basket, or espuerta.
started to take out the are This basket was then used to carry
completely from wall to wall and in the ore into 1.5 tonne box-cars
slices 50 ft. wide , beginning on running on 2 ft ga uge rails. Some
the second floor from the top and attempts were made to use jigger
removing first the pillars falling conveyors (especially in conjunction
within the stope limits , and then with the "gun") and air-winch
the are overhead in ascending scrapers, but these , and Eimco-Finlay
horizontal cuts about 7 ft. high , loaders were not generally adopted
and fi ll ing with waste rock above . until the 1940s .

In practice this did not wo r k out Selectivity in mining, to maintain


satisfactorily. II sulphur and copper contents for
direct shipping ore , was always a
The pillars left behind as work requirement with pyrite production
extended upwards began to collapse, and some of the undoubtedly high cost
crushing both the remaining are, and of the method was justified by the
the masonry built tram roads. grade control it achieved.
Worse , as the ore crushed, it began
to oxidise and ove r heat, creating In 1900 the Main Tunnel was diverted
sulphur dioxide gas in the wo r kings , around the orebody through the
and raising the already high porphyry and renamed the 11th Floor
temperature of the air still further. Tunnel. A new shaft was sunk to
There was a lways the risk of fire in connect with the realigned tunnel
such circ umstances , paticularly if some 250 m north of the San Dionisio
any timber was left in. shaft - it was named the Guillermo
shaft, probab l y in honour of the
Further modifications in the mining General Manager of the time, William
method were necessary and a form of A Carlyle. The shaft was equipped
horizontal cut- and-fill was adopted with electrically dr iven winding
in the 1920s. Julian describes the gear , ventilating fans and pumps and
method in detail - it achieved a very did not come into use until 1909 when
high extraction and less than 8% of the Central Electrica powe r station
the original ore was left in the was commissioned at Rio Tinto .
mined out sections.
Two further shafts were sunk about
Stoping took place on up to three this time . Alfredo, cl ose to the
floors , one above the other, to Guille r mo shaft, extended down to the
maintain output . The cuts made were 32nd floor and was the main
fi l led with waste rock or gossan - dewatering s haft for San Dionisio
placed either by hand or , for a mine and pr ovided services for men
period in the 1950s , by a compressed and materials . Roberto was a
air "gun". Despite backfilling , in replacement for the Alfonso shaft for
r emoving three f l oors , a settlement hauling ore to the 9th f l oo r fo r
of up to 9 met r es took place , so that transfer i nto waggons on the 11 t h
access to the working areas was via floor .
chutes and crosscuts , in the porphyry
rather than the ore , each crosscut In 1896, the Gene r a l Manager, William
connecting to a main gallery running Rich , co nsidered opencast minin g at

- 53 -
San Dionisio but did not press for At first it was decided to work a
its introduction and it was not until small opencast in parallel with the
1907 that it was seriously proposed underground mine for some few years
to the Deputation from the Board on to assess accurately the relative
its visit to the mines . At that merits of the two and the Atalaya
time there were three important opencast was initiated by ordering 4
factors favouring opencast working: steam driven Bucyrus 3.5 cubic yard
shovels from the United States.
1. Experience with steam shovels These were to operate from rail track
introduced to the Dehesa opencast of the 3 ft 6 in gauge used
on North Lode in 1904 (see page throughout the RTC operations.
57) confirmed that overburden These shovels were similar to those
stripping rates could be increased in use on cutting the Panama Canal;
with cost savings. the story that they were obtained
secondhand from that project is
2. A subsidence near the Alfonso apocryphal.
shaft had underlined the
difficulties of mining using the Two shovels were delivered in
underground method then employed. mid-1907 and one was in operation by
the year end . All four were in
3. Output from North Lode was falling operation towards the end of the
and it seemed unlikely that following year and a fifth was
underground mining from San ordered. They were used only for
Dionisio could be increased loading slate overburden and worked
sufficiently to compensate. only day shift . Each had a crew of

Figure 16 Steam Shovel Atalaya Opencast

- 54 -
7 men, of whom one arrived early to From 1930, steam shovels were
raise steam by the 8 am general start gradually replaced by electric
of work - the team was made up of two shovels mounted on caterpillar
drivers, two trackmen, a greaser and tracks. In turn, electric shovels
a stoker; one driver was responsible were replaced by diesel machines.
for the swivel, the other for The last steam shovel at Rio Tinto,
crowding the bucket, a division of after being used on work outside
duties which presumably was Atalaya opencast, was finally
understood by those involved! scrapped in 1961, there being no
preservation society to take on what
A team of 7 or 8 was involved in was by then a machine of historical
drilling and blasting ahead of the interest.
shovel, on a bench of 25 to 30 metres
with lifts of about 2.5 metres per The first production from Atalaya was
blast. Prior to 1912, when 72,000 tonnes averaging 2.82% Cu in
compressed air drilling was 1910; thereafter it became an
introduced, all drilling was by hand increasingly important source of low
- 3 men were expected to drill 5 to 8 cost production.
metres in a 6 hour shift. A shovel
advanced about 10 m along the bench Pyrites extracted from San Dionisio
each shift, loading about 750 cubic and Eduardo Lodes up to 1954 was:
metres of broken slate into 10 tonne
waggons, a total of about 170 waggons Alfredo underground 26,800,000 tonnes
for the shift. The waste was
hauled away by 40 tonne locomotives Atalaya opencast 11,300,000 tonnes
in 20 waggon trains through tunnels
to waste tips to the west. Total 38,100,000 tonnes

The north side of the opencast was in


porphyry and waste from here was used NORTH LODE
as fill in the underground mines,
which by this time were served by the Preliminary assessment of the
Alfredo shaft, the older mines having orebodies prior to acquisition had
been cut through by the rapidly concluded that North Lode was the
widening opencast. Blast hole largest of them and when the mining
drilling here was closer spaced to of it began in 1877 it was expected
give better fragmentation and the that it would be shown to join with
loading of the broken waste was done the postulated Middle Lode. At the
by hand into rail waggons for company's AGM in 1880 the Chairman,
movement on the 11th and, later, the Hugh Matheson said: "It is estimated
16th floors. On the intermediate that there is enough pyrites in North
bench levels, waste was loaded into Lode to last the Company, at the
smaller waggons working on 2ft gauge present rate of extraction, for a
track for ultimate delivery by the hundred years." At that time the
appropriate shafts to the underground rate of extraction was about 900,000
workings. tonnes pa.

Ore, following drilling and blasting, It was found in due course that North
was moved by scrapers over grizzlies Lode was not continuous, there was no
to glory holes on the 20th floor. Middle Lode and North Lode was three
From there it was delivered by chutes isolated and relatively small
and loading hoppers into 4 tonne "masses"; the sub-lodes were:
waggons on the 23rd floor, hauled to
Roberto shaft, raised to the 14th Mass No I, later called Lago
floor, delivered through surge bins Mass No 2, later called Salomon
to 10 tonne waggons in the 16th floor Mass No 3, first named Balcon del
tunnel and hauled away. Mora and later Dehesa

- 55 -
Lago lode had been worked by the the north side of the Tinto river
ancients and the Romans, mainly the valley. Initially called the North
former , for the extraction of silver, Lode Heading (its position is shown
but not for copper . They drove in the 1868 plan) , its level was 34.8
adits from the north slope of Cerro metres above Rio Tinto station and
Salomon , these were expanded to 352 . 5 metres above Huelva datum . It
caverns in good are, and the old came to be known as the North Lode or
workings connected a number of caves, 5th Floor Tunnel .
man made or natural , several of which
were filled with water . The most By July 1880 the adit was north of
famous of the caves were Tabaco and Cueva del Lago and within 10 metres
Lago. The Roman workings consisted of the pyrites when considerable
of shafts and galleries and some of ingress of water occurred . Neil
the shafts were filled with slag from Kennedy , the mining engineer in
sil ver are . cha r ge of the work, reported on 4
August : "The water level in Cueva del
Salomon Lode had been extensively Lago is falling since the heading has
worked by the Romans for silver and reached the lode and there is so much
copper and their main operations water that the men cannot stay
probably took place there , a underground the full eight hours. II
judgement based on the evidence of Next week he wrote: "The level of the
their working encountered in removal Lago water has fallen 1. 26 metres
of overburden by RTC . Two major during this week . " In the
Roman adits , the Upp er and Lower following week it had fallen a
Nerva adits, ran in an easterly further 2.02 metres and on 25 August
direction at 55 . 5 and 24.7 metres he wrot e : "The lake is completely
respectively above the Rio Tinto empty . "
station level . It was in Salomon
that some of the Roman wa ter wheels Production of pyrites started that
were found . year and the 5th floor tunnel was
continued in a large loop into
Above the Dehesa Lode there was an Salomon and Dehesa . In June 1894
area called Balcon del Mora in which underground working of the Lago lode
many Roman shafts had been su nk ceased ; working had reached the 10th
through the gossan, either down to floor , the limit of the sub-lode in
the pyrites or to the surface of the depth and the deepest of the North
porphyry. These shafts or pits were Lode bodies . The operations had
found southward to the Cerro Colorado produced some 1.3 million tonnes of
ridge and to the west as fa r as Cerro copper are averaging 2.04% Cu and
Retamar and the whole area had been about 7 million tonnes of pyrites .
extensively worked by the Romans, Working was by pillar and stall , in
extracting both silver and coppe r, which only about 20% of the mineral
the latter from oxidised ores . was extracted. Opencast working of
There were a number of opencasts North Lode began in 1901.
scattered along the Balcon del Moro ,
extending from Lago to Retamar, and Salomon was mined from 1881 to June
slag from silver smelting had been 1894 and during this period some
dumped in many of them . [After the 900,000 tonnes of pyrites were
Cerro Colorado opencast was started ~emoved via the 5th floor tunnel .
by Rio Tinto Patino in the 1960s, Opencast working started in 1889 .
galleries and caves were found in the In 1904 an inclined plane was
gossan - in section they looked installed to remove both pyrites and
exactly like the model of Roman work- overburden , the latter being dumped
ings made by the Tharsis company and on the old Roman slag heaps and
illustrated in Checkland(28), p 64]. burying the Huerta de la Cana walls .

RTC began operations at North Lode by The Dehesa sub-lode proved to be the
driving an adit from the east along shallowest of the th r ee comprising

- 56 -
North Lode and the 5th floor tunnel repo r ts and not i dentified in the RTC
entered below the are . Six shafts prospectus .
were sunk in to t he lode, with
underground working starting in 1882 When it was rediscove r ed by RTC is
and ending , with Salomon and Lago , in not clear but development work on it
June 1894 - only 550,000 tonnes of started only in 1918 and it was then
are were extracted . found to have been wo rked extensively
by the Romans and, relatively
In 1882 a tunnel was driven from the recently , by modern pillar and stal l
Main Tunnel , at the 11th floor level methods . The r e is one reference by
and 31.25 metres below the 5th floor ear l ier Spanish engineers to the
level , northwards to the Dehesa lode. finding of an adit of over 1.5 km in
This came to be known as the Central length and this adit was lost in the
Tunnel and was little used until much construction of the Marasmilla Dam by
later . It did, however , have one RTC aro und 1879 .
early use - it connected with an old
Roman shaft and waggons were loaded Roman operations are assumed to have
with ancient silver smelting slag , extracted rich chalcocite and
used for railway ballast, from about covellite ores found near the slate
1890 to 1931. hanging wall and many remains from
their working were found, notably a
This phase of ope r ations at North set of water lifting wheels on the
Lode must have been a severe 311 m level referred to in Chapter 2
disappointment to RTC which had on page 11 . There is convincing
initial ly believed North Lode to be evidence that the Romans worked the
the la r gest, quite apart from the si l ver ores at Planes - this evidence
presumed existence of Middle Lode * is the presence in the area of low
being disproved. Some higher grade , coppe r slags now generally recognised
quartzitic copper are was found and as produced in smelting t he jarositic
proved of some value as a smelter silver ore .
flux .
The RTC Boa r d decided in 1921 that
Dehesa opencast, started in 1900 , has liThe exploration of the new lode
already been mentioned as the proving should be pushed ahead at all speed
ground for the first serious to ascertain the cupreous content of
mechanisation of mining operations the ore , the tonnage in the lode and
and leading to the decision to embark its avai l ability for the purpose of
on the Ata l aya opencast. The first annua l pr oduction ," Mineral
steam navvies used at Dehesa from extraction by underground mining was
1904 had shovel capacities of 1. 5 started in 1922 and by 1933 950 , 000
cubic yards and were designed to load tonnes of pyrites and 85 , 000 tonnes
400 rail waggons, a total of 760 of qua r tzitic copper are had been
cubic metres , daily and substantially recovered. Some silver ore was
exceeded design performance , hence also recovered , normally of about 10%
the ready agreement to embark on the Pb and 1,000 to 1 , 300 gpt Ag and 20
Atalaya project . to 33 gpt Au , however one batch
assayed 6,800 gpt Ag!
OTHER LODES Mining operations ceased at Planes
about 1954 , by wh i ch time a total of
The Planes Lode is located at the 2.2 million tonnes of are had been
extreme eastern end of the Salomon mined , and the mine was allowed to
ridge - at higher levels it is flood as the first stage in a plan to
enclosed between slate and porphyry , recover copper by dissolution in the
at lower levels it lies entirely in acid waters. Ore skips were
the porphyry . This lode must have replaced by stainl ess steel buckets
been known to the Spanish engineers of 5 cubic met r es capacity and
alt hough it is not mentioned in their bailing of the liquor was carried out
* Middle Lode of Figure 2, page 4, soon came to be known as Centre Lode
and is thus designated on the 1878 General Plan of Works

- 57 -
in the summer months from 1956 until long and its width reduced with
1963, by which time the copper depth, from about 10 m to 2 m.
content of the waters hoisted was no Underground mining began in 1922 and
longer high enough to justify continued until 1933, with total
cementation. 1957 was the best year production of 190,000 toones of
of operation and 825 tonnes of copper pyrites. Following the end of
were raised in 151,000 cubic metres mining, copper recovery by
of water. cementation of the mine water was
practised until 1940 for a production
An extension of the ore body easterly of 525 toones of metal.
from Planes was predicted by Dr David
Williams and geophysical work began Three further lodes, all quite small,
in 1960. Following the were found - Mal Ano, Argamasilla and
identification of anomalies, drilling Quebranta Huesos. They are shown
confirmed the existence of further on Figure 11. Mal Ana was mined in
are contiguous with the Planes body - the early days of RTC and proved a
this is known as the San Antonio disappointment with only 8,260 tonnes
Lode. of pyrites with 1.9% Cu being
extracted. The other two lodes
Another lode neglected by the were found to be similar and of no
Spaniards, although noted by de economic importance.
Cassio in 1867, was the Valle Lode.
It was a very small lode, entirely The total output of pyrites by RTC in
enclosed io slate, marked by patches its 81 years of operation at the
of gossan and located near the mines (1873-1954) was almost 109
residential area developed by RTC as million tonnes and details are given
Bella Vista. The deposit was 230 m in Table 1 below.

TABLE 1 PYRITES PRODUCTION BY THE RIO TINTO COMPANY LTD


long tons
Underground Open cast Total

South Lode 18,192,713 24,201,493 42,394,206

North Lode 2,754,064 22,928,632 25,682,696

San Dionisio 26,780,834 11,350,589 38,131,423


Valle Lode 193,037
Planes Lode 2,123,798
Mal Ano 8,260 2,323,095
-------------
108,531,420
Notes: San Dionisio underground production came from the
Alfredo Mine and open cast production from Atalaya.

See also Appendix 12

RTC used long tons; throughout these notes tonnes are used
except when reporting detailed RTC production statistics.

- 58 -
ICHAPTER 111Ore classification and preparation
for shipment
RTC operations , and t hose of other f rom the standard. Typical
pyrites producers in the Andevallo, ana lyses f r om thi s early period were:
were unus ual in comparison with most 1 23 4
mining operations in that a high Cu 3. 06 2. 20 4. 46 2.25
pro port ion of the outp ut was sold S 48.98 30 . 19 47.25 50 . 00
with no physical beneficiation , Fe 41. 91 42 .86 42.35 41.05
although much of it wa s , in the fi r st Pb 1.47 1. 26 Tr
half of this century . leached or Zn 0. 02 0 . 24 Tr
"washed" to recover much of its As 1. 00 0 . 92 0 . 61 0 .25
copper. Consequently selection and Sb 0 . 06 0 . 10 Tr Tr
classification of "mineral " wa s based Silica 0.28 Tr 2,40 2.60
on both analysis and physical Ag varied betwee n 17 and 35 gpt
condition. At least 10 categories Au " " 0 . 4 " 0.6 "
were rec ognised in 1888 , and recorded Notes:
by Col1i ns(31) , as follows : 1 Expo rt ore 1878
2 Ore to calcination 1884
1. Pyri tes containing less tha n 0 . 5% 3 San Dionisio 1881
Cu , sold as poor or e . 4 North Lode . Lago 1881
2 . Pyrites mixed with earthy matter All fig ures , except Ag & Au, in %
and low in copper ; it was value-
less , hence known as "es teril", I nitially pyrites wa s s hipped in lump
3. Soft powdery or pulverised fo rm and customers did their own
mate rial of similar composition to crushing, either by hand or
poor ore, origi na lly valueless, mechanical l y, to mee t the needs of
later ca lled "azufro n". thei r roasting plants. Large sized
4. Com pact ore co ntai ni ng 1 to 2. 5% lum ps were r equi r ed , fines being
CUt initially treated on teleras , detrimental to the roasters of the
later heap leached . time in obstructing air flow . The
5. Compact ore co ntai ning up t o 3.75% shipped are wa s ro ughly minus 8 plus
CUt originally exported. 1 i nches, known locally as " tal cual"
6. High copper co nten t ore, usually or so- so .
around 4%, occasio nal l y as ri ch as
12-14%; smelted at Rio Tinto. In early operations , mineral which
7. Quartzitic copper or e , 3-4% Cu . was less than 1 inch acc umulated at
Used as flux i n copper smelting ; site, providing incentive fo r
some dumped for heap leachi ng . devel opment of means of realising
8 . Soft decomposed black mineral, values from s uch "smalls ".
high co pper, known as "negr illo"
and se nt to the smelter. The demands of the market changed as
9. Compac t mineral contai ning galena , new roasting equipme nt, notably
blende and pyrite; 6-12% Pb+Zn, multi-hearth furnaces with mechanical
3-4% Cu, known as "plomizos" and rabbling, came i nto use towa rd s the
dumped. end of the century . Two crushing
IO.Crystal s in the fo rm of stalact- and sc reen i ng plants were used before
ites or stalagmites with 4-1 2% Cu 1918 ; one at the Muelle de San
and 2-10% Zn; "vit r iolas" fr om Antonio, abou t 1. 5 kilomet res from
whic h copper was r ecove red i n the the Rio Tinto station and used later
washing tanks . to sc reen or e fo r t he smelter , the
ot her near Naya station on the
For export ore, s ulphur con tent wa s rai lway leaving the mines fo r Huelva .
cr itical. Such are was normally
sold on the basis of 48% S, with I n t he development of cr ushing and
premiums and pena lties for depar t ures sizing prior to shipment, it was

- 59 -
necessary to reorganise rail circuit with screens . This unit
transport out of the mine. For could crush and screen 1200 tonnes
many years the 11th floor tunnel had per 8 hour shift and employed 13 men.
been the main outlet for ore from The second unit was somewhat larger,
South Lode and San Dionisio but having two Traylor crushers, one 5 ft
another tunnel was now needed to 6 in Symons cone crusher, a 48 in
deliver to a convenient site for Symons disc crusher and three pairs
crushing and screening . Several of rolls - its output was 1500 tonnes
possibilities were considered; the per shift employing 17 men .
one chosen was at 16th floor level,
taking a straight line from Naya As designed, Zarandas had 6 product
village to the east end of South storage bins of 3,000 tonnes capacity
Lode, all in slate, there turning and 2 of 2 , 000 tonnes, discharging
westerly and continuing in porphyry, directly into main line waggons for
following the whole length of South haulage to Huelva. There the
Lode to San Dionisio . waggons went directly to the pier for
loading to ship, or discharged to a
~~ork started in 1912 and the tunnel, large storage installation of 110,000
7 . 6 km long , was completed in 1918. tonnes capacity about 1.5 km from the
Spoil from the Naya end was used to pier. From Zarandas to the pier at
create the site for a new crushing Huelva is 80 km and the railway
and screening plant, Zarandas Naya handled a maximum of 4,500 tonnes
(zaranda is Spanish for sieve or daily.
screen). The 16th floor or Naya
tunnel then became the main outlet Zarandas was designed to supply
for pyrites and was electrified in furnace size, -2 . 5 in + 1 in, and
1924 with battery locos and later fines, - 0.5 in, but demand for fines
with trolley locos hauling trains of increased and, despite modifications,
forty 10 tonne Granby type waggons to Zarandas was unable to meet the needs
the crushing plant. and another plant, Lavadora, was
brought into service . Much later,
Delivery into the crushing plant was about 1970 , the Compania Espanola de
into four 250 tonne bins. The first Minas de Rio Tinto installed a new
unit consisted of a 36 x 18 in crushing and screening plant to the
Traylor gyratory crusher, and two east of the original one .
sets of 42 x 18 in rolls, in closed

't;~~2-;T;;r:;ain Approaching Zarandas Naya from 16th Floor Tunnel 1950s

- 60 -
1CHAPTER 12 1Hydrometallurgical development

DOETSCH PROCESSES of which was the difficulty of making


the chlorine required for the
leaching solution . J H Collins, who
From the outset of operations, RTC was at Rio Tinto from 1880 to 1884 ,
disliked the loss of sulphur values subsequently wrote(39) voicing
resulting from heap roasting; criticisms of the process and the
additionally the problems associated following extract from his paper
with large scale roasting were illustrates some of the difficulties :
recognised . Heinrich Doetsch , of
Sundheim and Doetsch, had been !lTo produce what was supposed to be
appointed a dire tor of RTC in 1873 a very effective ferric liquor
and was especially concerned about without the use of burnt or e
this problem. Also in 1873 , M.Joly several methods were adopted.
had patented a process for extracting
copper from pyrites using a solution I.Sulphate of iron was heated i n a
of ferric chloride. By slightly reverberatory furnace, and the
modifying Joly's process, Doetsch !lferric salt!l so produced was
obtained a separate patent and the mixed with the raw mineral before
Board agreed in May 1879 to use "his" it was lixivated.
new wet process - this process
eventually became known as the First 2 . Sulphate of iron was mixed with
Doetsch Process; by 1882 Doetsch was salt and similarly heated , the
receiving royalties from its use . fumes produced being carried into
a condensing tower , through which
The process began with crushing the "spent liquor" from the coppe r
pyrites to about 10 mm and placing precipitating tanks was made to
the crushed material in heaps 15 m fall, thus producing a
square by 4 m high incorporating a "regenerated liquor!l which was
series of dry stone horizontal and used for washing raw are .
vertical flues . Salt, amounting to
2% of the weight of the pyrites, was 3 .The sulphate of iron was
spread over the flat top of each similarly mixed with peroxide of
heap, after which a basin of about manganese, and the fumes were
1. 7 m square was made on the top, similarly employed in producing
using the are to form the walls . " regenerated liquor".
Chlorine solution was pumped into the
basin and trickled through the are "In modifications 2 and 3 the
dissolving copper and the solution vapour was supposed to contain free
leaving the bottom of the heaps was chlorine, which , as well as
collected in launders for recovery of ferric chloride , has a very
copper by cementation with iron . energetic action on cupreous
Theoretically, 1 unit of copper pyrites . This was , of course , not
required only 0.44 units of iron for the case with No 2 , though large
precipitation; in practice it was quantities of hydrochloric acid
found that 1.1 to 1.2 units were were present . In No 3, some
used , but this was still chlorine was produced at certain
significantly less than used at that stages of heating , but only to a
time for precipitating copper from very small extent .
cupric sulphate solution.
"How little effective this process
Unfortunately the process was not as in its various modifications
simple as the above description proved itself at Rio Tinto may be
implies , for many reasons, the chief seen by the fact that the great

- 61 -
"Estacion" heap , after three years' di s cussion between Johnstone , chief
washing , still contai ns more than chemist at Rio Tinto , and Mohr ,
half its copper in its original manager of RTC's Cwm Avon smelter in
insoluble state . Still the copper Wales and communicated to the head
liberated was obtai ned very office . A year previously , in
cheaply, and without the serious 1886 , Sundheim and Doetsch had
inconvenience of the sulphur smoke renewed their contract with RTC to
from open- air calcination , which, supply 20,000 tonnes of manganese ore
as already stated, co uld not be for 4 years ~ Despite the
extended however much it was opposition of staff at the mines to
desired • . • " the process , it was maintained in
operation for as long as Doetsch was
By the time those comments appeared a member of the Board - soon after
attempts to implement the process had hi s death in 1894 a Deputation of the
been abandoned . Experiments on Board to the mines reported :
recovery of the labile sulphur driven
off when pyrites is heated were made "The Process by which c rude mineral
about this time and were also is washed with brown liquor
unsuccessful , the sulphur recovery obtained from washing burnt ore is
was only 2 tonnes per day from used with best effect and has given
heating 20-25 tonnes of pyrites and excellent results not only in
the cha r coal consumption was an increasi ng copper returns,but in a
excessive cost. marked reduction of the consumption
of iron . This is the grou nd work
Doetsch patented a second process , of the Doetsch Process , which was
known as the F C Pi:ocess , in which a understood to be covered by Patent
mixture of 3 parts small are and 1 under which royalty has been paid
part calcines was leached after since 1882 . The question of the
ad dition of 1% salt and 0.25% ground validity of the Patents is being
manganese are. It seems likely that investiga t ed by the Board.
the idea for this process came
largely from a paper presented to the "The application of a mixture of
Mining Institution of Cornwall by salt and manganese to the mine ral
Brenton Symon , who wrote: "My heaps was commenced in 1882 and
experiments have concl usively proved continued unt il June 1894 . After
that a better result is obtained when going fully into the merits of the
burnt are is used to wash the crude application with the General
smalls. " Symon ' s connection with Technical Manager and Mines
Rio Tinto is not known; at that time Manage r, we are of the opinion that
there was considerable interest in the benefit to be derived from it
copper dissolution at the several is not so clear as to render it
mines in Spain and Portugal ad vi sable to resume it and we
exploiting cupreous pyrites . r ecommend that the stocks of salt
and manganese be sold ."
In 1887 Doetsch received £2,325.15 . 0
in roya l ties for the use of this The RTC Board ' s support of Doetsch in
process by RTC . Again, technical his involvement in the promotion of
staff at the mines were not impressed processes from which he derived
by the process and i n 1887 made substantial benefit , both from
experiments to test the significance royalties and from the sale to RTC by
of adding salt and manganese ore, the Sundheim and Doetsch of salt and
basis of Doetsc h's patent , and found manganese ar e, and in the face of
that straight washi ng with dilute dissatisfaction wi th the performance
sulphuric acid gave simila r result s of the processes by technica l staff
to the Doetsch F C Process . at the mines , was an episode which
ca n only be judged by the business
The conc lusions from this ethics of t he day.
investigation were co nfirmed by

- 62 -
Apart f r om those commercial iss ues , in 1887 , by H F Coll i ns , son of J H
insistence on t he conti nued use of Coll ins whose c r iticism of the
Doetsch processes delayed the Doetsch process is quoted above , and
introduction of "na t ur al ceme ntat ion " F John son , the chief chemist .
which had been devel oped at San Because thei r advocacy of the process
Dom ingos when Portugal banned open was opposed by Doetsch . Collins and
air r oasting in 1878 and introduced Johnson r esigned, t he latter to join
at Tharsis in t he l 880s. Accordi ng Tharsis .
to Harvey(32), Mason and Ba rr y,
managers of San Domingos, offered the Des pi te the pressures f r om Government
process to RTC in 1878 , before to stop roasting i n teleras , it wa s
Doetsch proposed his first process , not until af ter Doetsch ' s death in
and wh ile he was a member of the RTC 1894 that se r ious efforts were made
Board. It appears that no serious to i nt r oduce natural cementation -
conside r ation was gi ven at t hat time and a co nt r i butor y facto r then wa s
to the process which subseq uent l y th e realisation that copper was being
became the basis of the company ' s slowl y leached from dumps of ore
vast and profitable heap leaching which had been set asi de as too low
opera tio ns . in coppe r conten t to j ustify
treatment. A repo rt by the gene r al
From 1894, when the use of t he mana ger , William Ri ch , in 1895 gives
Doetsch process was discontinued , important details of the plans to
the ferr ic s ulphate leaching process int roduce t he "new" process :
was used - this wa s the process
outlined by Brenton Symon . This "The present proposa l i s not to
still r eq uired r oasted ore to s upply calcine any mineral ave raging 1 per
the fe rri c component and roas t i ng of cent copper in the ai r, but to l ay
ore for heap leaching contin ued until it down i n a heap f or natural
1900 by which time there was a large oxidation and is based on the
accumulation of the mixture of following consideration. During
calcined ore and raw pyrites smalls , the yea r s 1889 and 1890 , in
20 million tonnes according to Avery. conseq uence of the forcible
These heaps of pa rtl y calcined r estriction of open air cal cin-
mineral were locally called ation, l ar ge heaps of poor rough
"morrongos ", though the pr ecise ore, averag ing 0 . 75 per ce nt
ori gi n of the term is not clea r. copper , were formed and allowed to
It seems t hat neither the Doetsch decompose naturall y. For the
process nor the fer r ic sulphate first t wo or three years the action
process was s uccessful in conse r vi ng seemed to be s low, but since then
t he s ulphur content of t he ore in there is undoubted evidence of
saleable form , which was a prime active decomposition, and,
objective in int rodu cing the former - although from the situation of the
i n later years considerable effo r t heaps , no absolute measurements can
was devoted to recovery of marketable be taken of the l iq uors resulting
pyrites from the mar r on gas heaps. from t he washings , there is s tr ong
evidence t o show that probabl y 20
to 25 per cent of t he copper
NATURAL CEMENTATION con t ents remainin g in the heaps is
being recovered each yea r .
Method s for accelerating the natural
oxidation of pyrites gene r ating an liThe proportion of co pper rec overed
acid liquor in which copper was by ca l cinin g in the open ai r is
dissolved had been successfully us ua lly take n as 70 per cent of
developed at Sa n Domingos, and t he total, and the r es ult s obtained
Tharsis had sta rted to reduce in practice agree with this , but
roasting and introduce natural that is when deal i ng wit h an ore
cementation in the early 1880s. At averagi ng about 2 per ce nt copper,
Rio Tinto expe rimen ts were con du cted the washed re s idues of which

- 63 -
usually contain about 0 . 6 per cent. copper could be maintained over a
No extended results are available transition period until all open- air
of the value of the washed residues calcination could cease . He
from are containing only 1 per continued:
cent, but from the various
observations made from time to "It is perhaps unnecessary to dwell
time, there is good reason to on the excellent effect that will
suppose that they probably contain be produced throughout the entire
not less than 0.5 per cent, in Province and even in Madrid , when
which case the copper recoverable it becomes known that the Company
from the poorer cl asses of ore has reduced the calcination from
would not exceed 50 per cent of the 300,000 tons per annum to 100,000
total, which, I am inclined to tons, ·besides which the area
think, is about the result obtained damaged by smoke will then be
on a large scale. undoubtedly reduced, and
consequently the smoke indemnities
"From an examination of the in the outlying districts will also
extraction returns for the present be reduced .
year, it is probable that about
200,000 tons of rough are can be "A very considerable saving will be
selected during 1896, averaging effected in the traffic expenses.
about 1 per cent copper , and It is well known that the very
therefore containing a total of roughest usage to which the waggons
2,000 tons of copper. If this are subjected in the whole
mineral were calcined in the open establishment is in carrying the
air, 50 per cent or 1,000 tons of hot calcined mineral to the tanks,
copper might be expected to be and then removing it after washing,
recovered at the end of 12 months, dripping with acid liquors, to its
whereas if put into a heap and ultimate destination . When the
allowed to decompose naturally, new arrangement comes into
about 25 per cent or 500 tons of operation it will result in
copper might be expected to be diminution of 400 ,000 tons of the
recovered at the end of two or worst kind of traffic (200,000 tons
three years. The total to the tanks and 200,000 tons from
difference, therefore, would them), thus effecting a very large
probably not be more than 500 tons saving in repairs and setting free
of fine copper , and I am inclined the waggons and locomotives for
to think , would very likely be service elsewhere.
less, as I believe the proportions
given above are less in favour of "The quantity of ferric iron in
the present proposal than the the liquors for cementation will
actual results will prove to be . ultimately be lessened. The
A point not to be lost sight of is excessive consumption of pig iron
this, that whereas after during recent years at Naya was due
calcination and washing , the to the large pr opor tion of ferric
residue yields up its remaining 50 iron in the liquors, and although
per cent of copper extremely this has happily been reduced in
slowly, the uncalcined heaps, on consequence of washing the heaps
the other hand, would continue to with less water, the consumption of
decompose for several years at an iron there is still 2 tons per unit
increasing rate, and consequently of copper produced . At Cerda it
the total copper recovered from is about 1 . 5 . ••• "
these heaps would be for several
years an increasing quantity."
Heap Leaching
Rich continued to show that with a
reduction of 200,000 tonnes annually Rich ' s report and recommendations
in open- air calcination, output of were accepted and the first of the

- 64 -
natural leaching heaps or IIterreros" 1942 . Heaps, after the first of
was put down in 1896-7 at Correlejos, 290,000 tonnes at Correlejos, were
an area between Cerda and Naya. It normally of about 100,000 tonnes
contained some 290,000 tonnes, which until 1928 when 50,000 tonnes was
proved to be far too large, with adopted as standard. They were
chimneys similar to those for built initially on a base of large
teleras, but now to provide natural stones but, again from 1928, selected
ventilation to oxidise the pyrites , large lumps of pyrites provided the
and with drains carrying the leach base which was laid out carefully to
liquor to cementatation tanks at provide channels for entry and
Naya . Rich ' s predictions were circulation of air. Run-of-mine
fully realised and from 1900 no more ore, containing a substantial plus 9
low copper content ore was roasted in inch fraction, was used, the benefits
the open air . of crushing and sizing shown in the
Tharsis work presumably not being
The Tharsis Copper and Sulphur sufficient to offset the added cost
Company was well established before and complication entailed; there seem
RTC was formed and there was to have been late doubts about that
naturally considerable rivalry judgement since a trial heap made in
between them . However mutual 1934 using crushed pyrites leached
interests in the orderly marketing of rapidly and efficiently.
pyrites had reconciled them to a
considerable extent and in 1899 a It originally took about 5 years to
party of RTC directors accompanied by extract most of the copper but by
Rich and Carlyle, who succeeded Rich 1932, with more careful control,
the following year, visited the especially of temperature , leaching
operations at Tharsis . At that time was reduced to 24 months and it
time Tharsis had been operating only took 3 months to build a heap and 3
natural cementation for 10 years and months to remove the leached ore to
had improved leaching performance the crushing and screening plant.
considerably in that time - they had Minus three-eights of an inch was
shown that a reduction of copper sold as IIwashed ore", sometimes the
content from 1-1.5% in the ore to fraction minus one and a half inches ,
0.2% in "washed ore" could be if sufficiently low in copper was
achieved in three years. crushed and also sold as washed ore;
the rest was returned to be
Key factors in the process which they incorporated in new heaps for further
had demonstrated were crushing the leaching . About 20% weight loss
ore to - 50 mm, initial washing with occurred during the cycle of
acid liquors, controlling heap operations .
temperature to about 50 degrees C, by
ventilating and intermittent washing, Heap leaching was carried out in
and passing leach liquor through a three areas - Tejonera, Cerda and
bed of crushed pyrites to reduce Naya . The first two areas were used
ferric iron content. RTC practice in the earlier years and Naya became
benefitted from the visit, following the main centre after the 16th floor
which there was considerable tunnel came into operation in 1918.
experimentation at Rio Tinto on heap An average of about 2,000 tonnes of
height - it seems that Tharsis had, ore per day was sent to the heaps;
perhaps fortuitously, chosen a near the maximum was about 4,000 tonnes.
optimum of 10 m - the lower heaps Ore was delivered from the mines by
tried at Rio Tinto were abandoned and railway waggons and all transport to
the height used subsequently ranged and from the screening and crushing
from 7 to 10 m. plant was also by railway waggons,
thus the heap leaching operations
A very detailed account of operation involved a major railway network with
of heap leaching and cementation was 40 km of track.
published by Taylor and Whelan(33) in

- 65 -
Originally , most of the a r e came via Between 1903 and 1953 a l most 20
the 11th floo r t unnel which was at a million tonnes of washed ore was
leve l 319.8 m and above all the sold ; af ter 1951 very little freshly
ter r er os ; when the 16th floor tunnel mi ned mineral was heap leached .
came into use at 252 m it was too low
to provide direct distribution to the Over many years it ha d been observed
heaps and an inclined plane was built that the rate of formatio n of ferric
at 2 km from the t unnel mouth - this s ulphate in the heaps wa s greater
cou ld raise a r e to fou r levels at the than cou ld be accounted for on the
Naya te rrer os ; 265 , 278 , 292 and basis of no rmal chemical react io n.
310m . The i nclined pla ne sloped at I n 1961 . Dr Pa ul Trussell of the B C
35 degrees and two 7 tonne skips Resea r ch Council, Va nco uver , visited
hoisted 200 tph , dumping into 300 Rio Tinto . He diagnosed bacterial
ton ne bunkers , one at each level , for acceleratio n in the leach proce ss and
distribution to t he heaps . Over subsequently identified thiobaci llus
400,000 tonnes were hoisted annually , ferrooxida ns in the liquors at th e
at an average power cons umption of mines . This wa s one of the fir s t
0 . 45 kWH per tonne . The 11th floor confirmed ident ificatio ns of the r ole
tunnel co ntinued to ser ve Cerda of micro-orga ni sms i n leachi ng
terre r os , usually with ores of below pr ocesses - conditions in the mine
average grade. water s at Rio Tinto , with pH 2 to 3
a nd temperatu r e about 35 degree s C
a r e near ideal for thiobaci llus
oxidation of sulphide and t he process
has bee n ope ra ting since the sulphide
bodies were exposed to air and
mois ture; certainly since Roman
times .
" "
, . -...'-
~.

t,
~'.- I(
Water Su pply

As mentioned i n Chapte r 9 on
infras tructur e , supplying water for
the leac hing heaps was a major
cons ideration: the natural leach i ng
heap s were j ust as demanding of water
as were the operations of Pr ieto ' s
artif icial cementation process.
Wherever possibl e acidic mine waters
...................... ,, were used but t he fresh water
r equiremen t in a typica l yea r, 1932 ,
was about 4 million tonnes,
addi tional to some 1.7 million tonnes
pum ped to the heaps from mine
workings.
I
, ! Ci r culation of liquors by pumping
involved special materials of
constr uction . Reference has already
been ma de to the introduction of
, phosphor br onze for pumps in the
mines . When ce nt rifuga l pumps were
introduced to the heap leaching
operation s they used bodies of
antimonial lead with phosphor bronze
Figure 18 im pellers and steel shafts protected
by bronze sleeves , then in 1930
General Plan of Leaching Gr ounds

- 66 -
impellers and shafts of stainless installation at Naya was
steel were introduced. The main substantially rebuilt in 1925; after
distribution pipes were of cast iron, 1927 only the Naya tanks were used
lead lined, 16 to 18 in in diameter, and liquors from Tejoneras and Cerda
with secondary distribution through were t r ansferred there by wooden
pipes of simil ar construction 6 or 8 launder at the 292 m level and
in in diameter. Moving pipes was recirculated on the heaps there ;
an extremely arduous job since no their copper content was no longer
mechanical lifting gear was available separately recovered .
for most of the work .
Liquor leaving the heaps was
The four largest ci r culation pumps collected in several dams , from which
had the following characteristics: liquor was drawn off through a series
of thick walled lead pipes operated
Size 8 in as syphons with wooden plugs inserted
Stages 4 or withdrawn to stop or start flow.
Capacity 200 cubic metres/hr The liquors contained about 2 , 000 ppm
Head 50-60 m of ferric iron . In early
Motor HP 60-85 operations this was reduced by
RPM 1450 passage through lump pyrites, as
Voltage 3000 practised in Figueroa ' s time and
reconfirmed by Tharsis work in the
Cont r ol of rain-water was a problem. 1880s.
Occasional heavy rainstorms occur at
Rio Tinto and an inch of rain was In 1929 reduction by sulphur dioxide
roughly equivalent , when the heap was introd uced; the reaction , which
leaching was in full operation, to produces fe r rous sulphate and
100 , 000 cubic metres or tonnes of sulphuric acid , is very slow in cold
water. This amount could normally acid solution . Sulphur dioxide was
be comfortably absorbed in the heaps produced by roasting "furnace size"
over a day or so but greater falls pyrites , about 2. 25 in , in lump
resulted in diversions to the river . burners; 40 of these were installed
Maintenance of storm drains was of in two sets of 20 each . The burner
great importance so that diversions flues connected to an absorption
could be made without serious tower, 6 .4 m high by 2.2 m square,
interference. lined with lead sheet and filled with
heat and acid resistant packing. A
lead covered and lined fan sucked the
Cementation (Precipitation) gases upward against liquor
descending in the tower and
Precipitation was ca r ried out at the discharged the gases through a stack .
three heap leaching sites at the turn Liquor was fed to the tower by
of the cent ury , much as it had been gravity from No 2 dam and the su l phur
at Planes and Cerda at the time RTC dioxide charged liquor returned
acquired t he mines . Liquors from through lead pipes below the surface
Prieto's process had been treated at of the liquor in No 3 dam.
Planes , the Doetsch process liquors
were t r eated at Cerda . In 1937 , to hasten and complete
reduct i on , a submerged wal l
Once the natural cementation pr ocess containing 8 , 000 t onnes of pyrites
was establ ished , precipitation was was built a bout midway across No 3
confined to Cerda and Naya. The dam , which became dams Nos 3 and 4.

- 67 -
ICHAPTER 131Pyrometallurgical development
By 1872 the smelting of cupreous In December 1880 , the Board
pyrites in blast furnaces had recommended that further blast
virtually ceased because of the furnaces should be erected using,
shortage of charcoal. The size of instead of s late, the best available
the blast fu rnaces was limited to the Stourbridge firebricks for furnace
water power available to drive the lining . By the end of 1884 eight
bellows; very often the bellows had furnaces had been built and the
to be worked manually . The advent smelter was known as Fundicion Mina .
of the RTC using steam power revived
interest in smelting pyrites. A second smelter also came into
operation in 1884 . Located below
Alexander Hill was responsible for the South Dam wall in the area known
starting the first blast furnace for as Huerta Romano, it was known as
RTC in 1879. It was sited to the Fundicion Huerta Romano and consisted
west of the inclined plane near the of a further twelve furnaces .
San Luis ad it and in 1879 it produced
39 tonnes of matte of 35% Cu . Matte from smelting was usually
shipped to South Wales, sometimes to
Feed to this furnace was described by Liverpool; both places operated metal
Collins(3!) as liThe rich cupreous markets where smelte r-refiner s
pyrites and quartz mineral , selected purchased offe rin gs . The unfavourable
from the Calcination Heaps , .... terms on which its matte was sold led
roasted and smelted together with to RTC leasing its own smelters ;
se l ected kernels from the Teleras and first in 1884 at Cwm Avon near Port
washing tanks and certain inferior Talbot and second, in 1887, the
copper precipitate washings". Grange Metal Works at Jarrow .

Figure 19 Cerda Precipi tation Tanks 1900

- 68 -
At the mines, the cupreous pyrites that appointment he was complaining
and "quartz mineral" (quartzitic of the quality of the ma t te received
copper are as defined on p 59) were from the Mines !
roasted together before smelting,
the aim being to remove sufficient
su l phur to produce a matte containing Fundicion Mina 1879-1899
between 31 and 38 per cent copper.
This roasting was done in the Cerda No drawings of the small blast
area in what was call~d No 2 Teleras. furnaces have been found but they
Again according to Collins: were probably similar in gene r a l
design to those used ear l ie r at the
"The richer and most siliceous Swedish Falum Smelter i n 1833 and
minera l s . •• were made into small described by Bernaldez(19) . A
teleras of 200 to 300 tons and sketch , probably made in 1884 , shows
roasted in the open. The method eight furnaces built in pa i rs.
of construction is somewhat Acco r ding to Gonzalo y Tarin(7), the
different to that employed for smelte r had two piston blowe r s , each
ordinary roasting and more fuel is of 120 hp , and steam was provided by
r equired . The ground chosen is two Corn i sh boilers , one of which was
covered to a depth of two feet with a stand-by; it is believed the
brushwood and several bundles are blowers we re driven by Trevithick
placed in a sheaf in the centre to vertical beam engines .
form a chimney when burnt out .
Ore is then piled around and the Each f urnace was capable of smelting
wood kindled, no layer of fine 12 tonnes of burden per day. Slag
mineral being placed on the was tapped into small conical cast
outside , as i n the case of ordinary iron pots carried on two wheels and
heap calcination . Such a telera was dumped in front of the smel ter
will continue to burn for about building . Matte was cast into sand
t hree months ." beds and then broken up fo r shipment
to South Wales .
Roasting tempe r ature was higher than
for artificial cementation , copper Between 1880 and 1889 matte
sulphides were oxidised to cupreous containing some 15 , 000 tonnes of
oxide and any copper sulphate formed copper was produced f r om this smelter
as an intermediate was decomposed to - production and burden details are
the oxide. summarised in Appendix 9.

In December 1882, William Edmonds


came from a South Wales copper Fundicion Huerta Romano 1884- 1901
smelter to take charge of smelting
and refining and was responsible for Origi nally planned, in 1884, f or ten
starting up Fundicion Huerta Romano furnaces , t wel ve were buil t and
in 1884- 5. He suggested that the are operati onal by the end of 1885.
shou l d be roasted in teleras of the They were similar in design to the
same shape and size as those used for furnaces at Fundicion Mina , with
artific i al cementation , believing blast air pr ovided by one large
that roasting time would be reduced blower driven by a 220 hp steam
and , with increased s ulphur engine. Coke requirements for
elimination , higher matte grade would smelting were now significant ,
be achievable. La r ge r roasting amounting to 2 , 000 tonnes per month .
heaps were apparently used , possibly
with improved fuel consumption , but Fol l owing a s uccessful trial wit h a
matte grade was not improved . In circ ular water - jacketed furnace at
1886 he r et ur ned to South Wales to the Company's Cwm Avon smel te r, two
super vise smelting and refining at such furnaces were installed early in
the RTC ' s recently acquired Cwm Avon 1888, followed by another ten in
smelte r - shortly after taking up 1890 . No details of the furnaces

- 69 -
Figure 20 Bessemer Smelter

have been found in the RTC records Smelting Precipitate


but they were probably of 3 ft
diameter at the tuyeres, a size of RTC scrapped the sp1eiss furnace
furnace in common use around this which had been used since installed
time . Air was supplied to each by Remisa in 1831 and replaced it by
furnace by its own Roots blower the more common type of reverberatory
driven by a 13 hp steam engine. furnace with an open hearth . As
early as 1879 it was suggested that
In 1888 the total copper output from the precipitate should be melted and
Rio Tinto was 5,792 tonnes in the cast into ingots of black copper for
form of matte and 12,730 tonnes in export to the Swansea and Liverpool
precipitate. Both smelters were markets. However it was not until
working and the numbers employed in March 1883 that William Edmonds was
the metallurgical departments were: authorised to engage two Welsh
ref i ners. Initial instructions to
Men Women Boys send the ingots to Garston, near
Liverpool were changed in favour of
Teleras 420 II 34 shipment to Wales, probably in
Washing calcines , anticipation of taking up the lease
leaching. etc 280 46 94 on the Cwm Avon smelter.
Doetsch&FC Process
at Planes 110 2 II
at Naya 242 5 14 Bessemer Smelter 1901 - 1914
Roasting ores
for smelters 95 23 50 Before 1900, the time to make refined
In the smelters 352 10 43 copper from the Rio Tinto ores must
------------------- have been between 4 and 5 months .
Totals 1,499 97 246 The are was roasted in No 2 Teleras,
an operation which took 3 months,

- 70 -
then smelted to matte and the matte stands by a 60 tonne, electrically
shipped to South Wales. The years driven, overhead crane; they were
from 1880 were ones of rapid progress turned on their stands by vertical
in copper smelting, most notably i n rack and pinion gear, operated
the successful application of the hydraulically.
Bessemer converting principle to
treatment of copper matte. Flue gases from both blast furnaces
and converters passed into a settling
The rapid development of th i s chamber, thence to a mountain flue,
process , following the initial much of which still remains.
demonstration by Manhes, must have
impressed the RTC Board and a small The design for the converters came
converter was installed at Cwm Avon . from the Copper Queen smelter,
Tests there showed that matte could Bisbee , Arizona and they were known
be converted directly to copper and locally as Bisbees. No doubt it was
the method was much quicker and James Douglas who advised RTC and
cheaper than the classical Welsh arranged for two men from Copper
process. In addition, arsenical Queen to start up the smelter .
copper precipitate could be added to
the converter with eliminat i on of More detailed information about the
most of the arsenic. Bessemer smelter and its operations
is contained in Appendix 10.
In 1899 RTC placed an order for a new
smelter, at an estimated cost of
£60 , 000 . Construction began on a
site along the Tinto river, just
below the Marasmilla dam, and was
completed in November 1901. At that
time Fundicion Huerta Romana ceased
operation .

The new smelter was housed in


Victorian-style stone buildings
(which subsequently became the Mines
Workshops) and the main equipment
was:

1. Two water jacketed rectangular


blast furnaces (a third was added
later) each 12ft long, 3ft 7in
across the tuyeres , 13ft 4in high
and 4ft 4in wide at the top.
Each side had 3 vertical water
jackets , each with 3x4in dia
tuyeres. Above these jackets were
2 horizontal ones . One of the end
jackets was fitted with a water
cooled spout for continuous
discharge of slag and matte into a
circular settler/forehearth of
35- 40 tonnes capacity .

2. Six converter stands and twelve


horizontal converter shells, each
8ft long and 5ft dia; for ease of
relining made in two sections,
bolted together . These were Figure 21 "Bisbee" Converter
fitted to or removed from the

- 71 -
Pyritic Smelting
The site chosen was an area of flat
In December 1900. Charles Fiel ding , ground , about 2 km from the Bessemer
an RTC director then i n Huelva . wrote Smelter, at the foot of the Sierra
a memorandum about a new method of Madronal and again convenient for the
smelting cupreous pyrites in blast co nstruction of a mountain fl ue .
fur naces using little or no coke and This f lue was somewhat larger than
utilising the heat of reaction from that for the Bessemer Smelter and had
the oxidation of sulphide . He an interna l cross section 4 . 5 m
realised that it was far too late to square and a total le ngth of 380 m.
make alterations to the Bessemer risi ng to a hei gh t of 159 . 3 m above
s melter, then under co nstruction , and the f urnace feed floor . In practice ,
s ugges ted that tests be made once the the flue gases were diluted by
Bessemer smelter was operational . adventitous air to arou nd 0 . 3%
s ulphur dioxide at disc harge and, by
In 1904 , a third blast furnace was the standa rd s of the times , ca used
erected at the Bessemer smelter for little pollution.
the tests and these must have been
encouraging since , in Decembe r of The six blast furnaces were housed in
that year , permission was given to a structural steel building , wi th
design and erect a new smel ter. space left fo r a co nverter aisle. A
This was blown in in April 1907 - boiler house, built in stone and with
originally ca lled the Bessemer six Lancashire boilers , provided
Extension , it later became known as steam to drive blower s pr oviding
Fundicion Pi r ita . With many blast air . Initially t here were four
modifications, it operated until Parsons t ur bo-blowe r s , each capable
1970. of 660 c ubic metres free ai r per
minute at 20 mm Hg pressure , and
The plan called for the erection of three othe r blowers, eac h 450 cubi c
six water-cooled blast furnaces to metres at 103 mm Hg . In 1917 a
smelt a cha r ge of high s ulph ur Ge r man AEG t urb i ne drive n bl owe r was
conte nt cupreous pyrites and fines- i nsta l led and in 1929 the fi r st
free silica . This burden was elect rically driven blowers were
designed to promote an even i nstal led - four Oerliko n tu r bo
distribution of the ai r flowing up blowe r s, each driven by a 450 HP
through it and the charge col umn wa s motor and capable of 480 cubic metres
to be about 12 ft , a height ass umed at 735 mm Hg.
to give good heat exchange between
the hot gases produced at the focus Electric power wa s not used at the
of the furnace and the cold cha rge smelter un til 1914 and then it was
descending, th us minimising coke only used for two cranes transfer r ed
consumption . The low copper content from the Bessemer Smelter whe n that
matte produced was to be sent to the sh ut down.
Bessemer Smelter to be up grad ed by
resmelting before converting . In operatio ns smelting cupreous
fines , the pyrites contai ned between
Howeve r, it was not until 1917 that 3 and 4 % Cu, and the si liceous
pyritic smelting according to this copper ore used as flux , co ntained a
plan was practised. Until that time similar copper conte nt and 14 to 15 %
the blast f ur naces were used for S. With thi s small sized burden,
scavenge r smelting of small size the smelt ing height above tuyeres was
cupreous pyrites, containing a large on ly about 5 ft , compared with the
percentage of -6mm fi nes , of which a designed 12 ft for pyritic smelting ,
large tonnage had accumulated because and blast pressure was 83 to 100 mm
they were not saleable in the export Hg . Each f urnace smelted about 300
trade . A means of realising value tons of burden per day and the
from such fines had been sought for average number of furnaces in blast
some years. was just under four .

- 72 -
Appendix 11 lists the charge smelted
in 1913 and gives some details of Coke was reduced to 0 . 5 % of burden
operating practice at that time. and , for one short period,
Further details of smelting practice eliminated . Campaign life for the
are given by Potts (34) . blast furnaces under these conditions
was short - 5 to 7 days. Increasing
In 1913 a structural steel building coke to 1.8 %of burden increased
was erected immediately in front of campaign life to 29 days - these
the blast furnaces an d the converters latter conditions were adopted for
were i nstalled by 1914; these were subseque nt operations.
two 12 ft Great Falls type and two 14
ft long by 8 ft 5 in horizontal In this time of hostilities between
conve rters. After experience with Britain and Germany, there were
both types, the Great Falls was found effort s on behalf of German interests
to perform better on the low grade to hinder the development. The
mattes and a further three were smelter superintendent, Arthur J
installed . Caddick , wrote later:

Air for the converters was s upplied " Throughout the experiments, owing
by two steam driven blowing engines to enemy propaganda , difficulty was
sup plied by Fullerton, Hodgart and experienced with labour, so much
Barclay of Paisley at a cost of so , that alterations in practice
£5,250 cif Huelva. They were were published in the local
impressive machines - each had two Sindicalist pamphlets , comparing
steam cylinders , 17 and 34 in dia, in the old amount of fuel used with
tandem , driving two 36 in dia air that which we were using . At
cyli nders at 100 stokes per min, with times the campaign reached such an
stroke length 36in. Superheated intensity that over some months I
steam pressure was 10 kilos per was frequently threatened on
square centimetre and each engi ne account of what was termed "El
supplied 230 cubic metres of free air conflicto de ca rbon". Granted the
per min at about 2 kilos per square work was more arduous and the
centimetre . Converting operations furnaces had to be cleaned out more
have been described by Potts (35,36). frequently . .• "

True pyritic smelting commenced in Successful pyritic smelting required


1917. It was thought that high good quality pyrites and quartz -
blowing rates would be needed and the typical analyses were :
installation of the AEG turbine
driven blower in that year was the Pyrites Quartz
prerequisite - it was capable of 2270 % %
c ubic metres free air at 100 to 130
mm Hg pressure. This blower had Copper 4.44 1.40
been ordered in 191 3, it seems to Iron 40.18 12.54
have arrived at Hu elva around the Silica 2.15 65 . 20
start of World War I and clearance Sulphur 47.37 14 . 16
through Customs wa s delayed by the Arsenic 0.70 0 . 38
Ge rman consul there. Lead 1.88 0 . 79
Zi nc 1. 75 0.80
Efficient pyritic smelting required
caref ul screening of the pyrites Difficulty in supplying such feed led
burden at one quarter of an i nch. to the cessation of pyritic smelting
Good quality silica and limestone of in 1924, following a meeting at the
about 4in and free of fines were also smelter between Walter Browning,
needed and were delivered by rail general manager, R E Palmer , chief
from the Muelle San Dioni sio mining engineer, John Black, chief
screening plant near the Bessemer accountant, and Herbert Potts,
smelter.

- 73 -
smelter superintendent . Palmer's needed . In the period 1924 - 29
comments to Potts are said to have operating results were as follows:
been: "The smelter will have to take
what is sent to it and like i t, Average number of furnaces
because we (the mining engineers) in blast 2. 27
haven't time to be running around Average daily burden per
looking for prize packets of fancy furnace , tonnes 342
are tied up with ribbons". Obviously Coke on burden 3 . 45%
cupreous pyrites of the quality No 3 precipitate smelted
sought by the smelter had become per day, tonnes 4.57
increasingly difficult to extract . Copper in matte 20.08%
Copper in slag 0.41%
Operating results during the pyritic Average production of blister,
smelting era are given below; column tonnes pe r day 40.1
1 gives overall average figures but
excludes two periods - 1921, when Comparing pyritic and semi-pyritic
pyritic smelting was not practised smelting on the basis of burden
because of the need to smelt smelted per square foot of hearth
considerable tonnages of precipitate area per day gives figures of 4.47
and for which figures are given in and 5.44. At this time the blast
column 2, and a 6 months period in furnaces were 18 ft long by 4 ft wide
1922 when no precipitate was smelted - each furnace had 6 steel jackets
and coke usage was thereby minimised per side , 2 back jackets and a bronze
- figures for this period are give in breast jacket fitted with a steel
column 3. spout; all the jackets were
I 2 3 watercooled. The height , from sale
Average number of plate in the hearth to feed floor,
furnaces in blast 3.55 2.20 2.65 was 17 ft 4 in , settlers were 14 ft
Tonnes of pyrites diameter by 4 ft 10 in high .
smelted 80,025
Copper content % 2.92
Tons of quartz 29,996 Smelting Flotation Concentrates
Copper content 3.02
Total tonnes of The presence of copper in the country
burden/furnace/day 322 317 361 rock at the contact with the pyrites
Total burden,tonnes 132,970 was first seriously examined by H H
Coke,% on burden 1.83 4.76 0.9 Knox with exploratory drillings in
Precipitate smelted , 1910 but it was not until 1926 that
tonnes per day 11 . 5 72 . 3 nil the applicability of flotation was
Matte produced, tested in a pilot plant at the
tonnes per day 83 Lavadora site and the decision to
Matte Cu % 22.1 32 . 0 20.4 build a flotation concentrator to
Slag Cu % 0.55 0.64 0 . 63 treat the chloritic are was taken.
Blister produced,
tonnes per day 27.3 46.0 25.5 Sintering was an essential first
stage to smelting the fine sulphide
The average length of a furnace concentrates and two standard Dwight-
campaign was 29 days, the height of Lloyd machines were installed to the
charge in the furnace was 12 ft, each west of the mountain flues and some
furnace used 400 cubic metres of free 450 m east of the new concentrator .
air per minute with blast pressure Concentrate pulp, at 72 - 74% solids,
110 mm of mercury. 80% -325mesh, was pumped through a 4
in steel pipeline t o the sintering
plant where it was filtered on a
After January 1924, the smelter Dorrco drum filter to 8 - 11%
practised semi-pyritic smelting; the moisture.
sulphur content of the cupreous
pyrites was lower and more coke was The flotation concentrator began

- 74 -
operations in July 1930 and , in a inadequate and so did the single
period of very depressed copper Dorrco filter of the original
prices, was shut down in March 1932 - sintering plant . Although another
flotation concentrates were not filter was purchased, it was not
produced again until 1942 . The possible to buy a second press from
sintering plant operated only until Germany in the middle of the Second
June 1931 and failed to achieve the \~orld War and a copy of the original
expected performance. Concentrates was successfully constructed in the
containing 17% Cu and 42% S needed RTC workshops at Huelva.
dilution with inerts to reduce
sulphur to around 18% to avoid A small coke fired lime kiln was
overheating - the mixture used was : built at site, large enough only to
supply the needs of the briquetting
Concentrates 29.5% plant which required fresh lime; lime
Fine converter slag 2.5% for the concentrator was brought from
Fine sinter return 47.4% Niebla where it was pr oduced in wood
Acid works cinders 1.1% fired kilns; limestone for the
No 3 precipitate 1.0% briquetting plant kiln also came from
Converter flue dust 5. 0% Niebla.
Fi ne quartz & oxide are 13.5%
Each briquetting press consisted of
The plant was designed to make 150 twelve moulds on a rotating table
tonnes of sinter per 24 hour day but 1.75 m in diameter, with each mould
it never achieved more than 100 charged in turn with the feed
tonnes . Eliminations of 80% of the mixture . Upper and lower plungers
arsenic , 75% of the zinc , 60% of the compressed the charge at 300 kg per
sulphur and 20% of the lead were square centimetre for a period of 2. 5
achieved. Operating costs, at ptas seconds; the compressed briquettes
22 per tonne , were four times the were discharged on to the table by
estimated figure! The plant was the lower plunger.
scrapped in 1937 and replaced by a
briquetting plant. The feed mixture consisted of about
86% concentrates, 7% flue dust and
75% lime. It was mixed in a pug
Briguetting Plant mill and "conditioned " in a storage
pit for about 24 hours; in this time
The idea of briquetting copper the heat generated by slaking of the
precipitate as a means of reducing lime reduced the moisture content to
losses when adding it the converters about 6%.
or smelting it in a rotary furnace
must have originated in the London Each machine produced about 35 tonnes
office. In 1937. a briquetting of briquettes per 8 hour shift,
press was purchased from Bruck equivalent to 1 , 000 briquettes, of
Kretsher of Osnabruck , Germany - it 4 . 7 kilos each, per hour. The
was designed for a dual purpose : to briquettes were t r ansferred on
make briquettes either 80 mm diameter platform waggons to open sided sheds
and 65 mm high from precipitate or and stacked to a height of about 2 m.
110 mm in diameter and 80 mm high They were left to harden for a
from concentrate. A substantial minimum of 24 hours; longer in
tonnage of copper concentrates had winter.
been impounded in ponds in 1931-32.
Although the briquettes were never as
The briquetting plant was built on hard and strong as the smelter
the site of the sintering plant . It wished, the pla nt worked continuously
proved ineffective on precipitate but from 1942 until 1965 . Maintenance
worked reasonably well on costs were high, mainly because of
concentrate . When the concentrator the wear on the pressure pistons and
restarted in 1942 one press proved the inserted sleeves in the dies.

- 75 -
Herbert Potts, superintendent of the The Momoda Process
smelter for many years until his
retirement in 1948, wrote:
In 1960, after RTC had transferred
"The briquetting plant is a costly management to CEMRT , news of a
"White Elephant" and introduces a process developed by Sumitomo Metal
superfluous intermediary process; Mining in Japan attracted attention
if it could be eliminated it would at Rio Tinto and, after a visit to
represent a very worthwhile the Japanese smelter and a meeting
economy." with the in ventor (Mr Ryochi Momoda)
in July 1963, a successful trial was
Smelting After 1932 made at Sumitomo' s Shisakajima
smelter on concentrates of the type
Although 6 blast furnaces were then being smelted at Rio Tinto.
originally installed in the Bessemer
Smelter, the average number in blast Two blast furnaces were altered to
during the pyritic smelting period the Momoda design, with a centrally
was 4.5 and it dropped to 3 when placed hopper through which the
working with a semi-pyritic burden. burden and coke were fed in alternate
By 1931, only one furnace was layers, and the fi rst was blown in on
required with another maintained as 12 December 1965.
spare. The 1I 0r dinary" furnace , as
it came to be called to distinguish The Momoda process proved a
it from the Orkla furnaces (described significant improvement on the
in Chapter 14), smelted any cupreous "ordinary" furnace operation - it was
material that was available; for seriously considered for a new
example, cupreous pyrites,sinter, smelter of 40,000 tonnes pa ca pacity
briquettes , copper precipitate and at Huelva; when the decision was made
low grade Orkla matte. Table 2 to build an even larger smelter the
shows the average burden smelted over Out okumpu process was chosen .
the period 1939-57 and it will be
appreciated that such average figures That new smelter came into operation
conceal wide variations. in 1970 and smelting at the mines
ceased in April of that year.

TABLE 2 AVERAGE BURDEN 1939-57


Tons/day % on burden Cu % Tons copper
In
Cupreous pyrites 39.1 10.35 2.42 0.95
Briquettes 77.3 20 . 47 12 . 82 9.91
No 3 precipitate 5.8 1.54 60 . 76 3 .52
Orkla matte 108.0 28.59 7. 56 8.16
Converter slag 66.1 17.50 6.49 4 .29
Flue dust 0.4 0.10 15.79 0.06
Silica flux 69 . 7 18.45
Limestone 11.3 3.00
------
Burden 377.7 7. 1 26.89
Coke 28 . 7 7.6

Out

Matte 101.6 23 . 84 24 . 22
Slag 224.2 0 .4 0.92
Flue dust 13. 6 8.91 1.21

Unaccounted 0.47

- 76 -
Some General Observations removed and blowing continued until
there were signs of coppe r on the
The complex mineralisation of the Rio punch rods . Blowing continued for a
Tinto ores leads to the presence of further 5 minutes before the
minor elements in the copper produced impoverished white metal was poured
and the problems of arsenic have been off slowly into ladles and added to
referred to at several points in another hot converter , perhaps with
these notes. Antimony is also an the addition of one or two ladles of
important impurity although it was fresh matte - the enriched copper in
rarely reported in RTC analyses of the first converter was blown for a
precipitate; at the Port Talbot few minutes and then cast.
smelter, the antimony content of fire
refined copper varied from 0.018 to Normal blister at this time contained
0.028%. This low level did not about 17 gm Au and 670 gm Ag per
adversely affect mechanical tonne - using selective converting
properties of the metal. the gold content of the enriched
blister could be raised above 80 gm.
Rua Figueroa referred to the high Between June 1934 and December 1935,
antimony content of the black copper 375 selective blows were made and 40%
produced; in his time at the mines, of these blows produced copper of
mid-19th century, it was always more than 80 gm per tonne Au .
reported as higher than the arsenic
content and he Quotes an analysis of Smelting of the fine No 3 precipitate
94.22% Cu , 2. 0% Sb and 0.69% As. was always troublesome. At one time
This may have been due to the a cupola was tried but without
difficulty of separating arsenic and success and the best method seems to
antimony in the assay. In recent have been the addition of dried
times , the antimony content of "cakes" to the converters. Adding
pyrites at Rio Tinto has varied precipitate to the blast furnaces
between 0.005 and 0.06%. gave recoveries of only 88-89%.
whereas converter smelting gave 92%.
Gold and silver are important
impurities in Rio Tinto copper. In In 1932 , when a large stock of No 3
early operations with reverberatory precipitate had been accumulated. one
smelting of precipitate it was of the converte r s was altered; the
established that gold, silver and mouth was removed and replaced by a
some other impurities concentrated in domed roof, with an exit placed
the first metallic copper separating centrally in the roof for the flue
from the white metal . When the gases. Thus modified it smelted some
Bessemer smelter came into operation , 7,500 kg of precipitate daily, using
selective converting was investigated 1960 kg of oil . Although ineffic-
and referred to by Collins (31) in ient , this operation reduced the
1885 . stockpile over the "n ext two years.

It was not, however, practised until About this time a trial at Port
1934-35. Normally blister copper Talbot smelting No 3 precipitate in a
was shipped to the RTC smelter at reverberatory furnace gave a recovery
Port Talbot for fire refining but at of only 77.5%. with slag containing
that time, and presumably for 14 . 5% Cu and unaccounted losses of
political/commercial reasons, RTe 17%. the latter possibly due. at
sold blister copper to two Spanish least in part,to difficulties in
refineries, only one of whi ch paid sampling the precipitate.
for gold and silver .
Typical analyses of blister copper
A method was developed converting 9 produced in the Fundicion Pirita era
ladles of matte to make about 15 were as follows:
tonnes of white metal; slag was

- 77 -
1934 1964 Fundicion Mina 1879-89

Cu % 99 . 01 99.30 48,629 tonnes matte containing


As " 0 . 165 0 . 03 31.80% Cu.
Sb II 0 . 020 o 012
Bi " 0.0012 0 . 0003 Fundicion Huerta Romana 1884-1901
Pb II 0.120 0.097
Fe " 0.080 0.025 236 ,638 tonnes matte containing
Zn II 0 . 008 0 . 025 32.98% Cu .
Ni " 0 . 038 0 . 064
Co " 0.0015 0 . 005 Fundicion Bessemer 1901 -14
Se " 0 . 0012 0 . 015
Ag gm p t 669 812 164,312 tonnes blister contain in g
Au " " II 17 13 about 98% Cu .
S about O. 061throughout
Fundicion Pirita 1907- 70
Note : 1934 operation was on Rio
Tin ta ores only ; in 1964 custom 190 , 714 tonnes matte sent to
concentrates were smelted . Fundicion Bessemer 1907- 14

550,673 ton nes blister containing


Co pper Production , RTC Sme l ters about 99% Cu 1914-70

From the star t of the RTC operations 15,205 tonnes black copper
the output of the smelters it containing abo ut 97.5% Co 1936-44
establ i shed was as follows :

Figure 22 Bessemer Smelter , Marasml lla Dam and Cerda Leaching Area

- 78 -
1CHAPTER 141Sulphur production - the Orkla
process
Although t he Rio Tinta mines are Labile sulphur distills off as the
perhaps most widely associated with charge descends and sufficient coke
copper production, it should be borne is charged to reduce some of the
in mind that it was the demand for sulphur dioxide with hot carbon . Hot
sulphur that stimulated the major gases leaving the furnace are cleaned
development of the mines of the by electrostatic precipita t ors and
Iberian Pyrites Belt and the search cooled to condense the sulphur .
for means of maximising the return
from the sulphur content of the ore RTC had followed the Orkla
has never been far from the mjncts of development closely and ore f r om Rio
t hose operating there . Tinto was smelted at the insta l lation
at Orkla Grube ' s Lokken mine , with
Elemental sulphur is a more successful r esults . However , the
attractive starting point for sulphur produced contained a
producing sulphuric acid in the substantial amount of arsenic -
chemical industry and many processes Lokken pyrites contained less than
have been proposed for its production 0 . 1% As; Rio Tinto pyrites more than
from mineral sulphides . The 0.5% and arsenic content was no
decomposition of pyrites into problem with sulphur produced from
pyr r hot i te and elemental sulphur on the former .
heating - the separation of the
labile su l phur atom - has long been Following the successful smelting
recognised as the potential basis for trial at Lokken , RTC decided to
a pr ocess ; as recorded on page 62 , proceed wit h a new smelter to use the
experiments were carried out and six pr ocess. Wisely , before that major
furnaces built in the mid-18BOs but commitment was entered into , one of
that attempt failed. the furnaces of the existing smel ter
was modified for extended t r ials
For a time efforts were directed to which began in August 1930.
possibilities of a process based on
the Claus reaction of sulphur dioxide No 6 fu r nace was used ; the height of
and hydrogen sulphide - the idea was the shaft was increased to get
to produce a mixture of the two gases effective heat transfer and reduce
by passing steam over heated py r ites . the off - gas temperatu r e to below 460
Among other potential obstacles to degrees C. Four charging bells were
the deve l opment of such a process , fitted and two sets of electrostatic
imp urities in the pyrites introduced filters installed , with a cooling
probl ems which , even if a technical stage between to condense sulphur .
soluti on could be found. would make The first gas filtration stage was to
the process hopelessly uneconomic . remove impu r ities such as lead, zinc ,
arseniC , iron and silica and the
Orkla Grube- Aktiebolag , operating a second to remove uncondensed sul phur
pyrites mine in Norway we r e similarly mist befo r e discharging gas to
interested in recovering elemental atmosphere .
s ulphur and by 1929 had demonstrated
a process in which c upreous pyrites Early opera t ion encounte r ed many
is smelted i n an enclosed blast problems . The fur nace settler
furnace , designed to prevent ingress rapidly fi lled with magnetite and had
of ai r at the top , to recover both to be dug out f r equently. High
matte and el eme ntal sulphur . arsenical sulphur was deposited in
Pyr ites , fluxes and coke are fed the electrosta tic pr ecipitators a nd
th r ough double bells , simi l a r to mixed with t he dust which was a l so
those used on the iron blast f urnace. deposited making remova l extremely

- 79 -
difficult. The plate type achieved with a pressure process but
electrodes of mild steel were badly the London management was not
corroded and the Quartz insulators convinced until it was learned that
failed. Orkla had independently developed an
autoclave process.
It had been recognised following the
Lokken trials that arsenic in the A batch autoclave process was
sulphur gave rise to two related installed, although the continuous
problems - it was an impurity which process developed by Orkla offered
could render the sulphur unsaleable advantages, particularly since in the
and it significantly increased the batch process operated at Rio Tinto a
viscosity of the molten sulphur. It stable emulsion was formed as a layer
was soon established that the arsen i c intermediate between the sulphur and
content could be lowered to around 5 the arsenical liquor , leading to
ppm by stirring milk of lime with the complications in discharging the
molten sulphur; it was some time vessel .
before the problems associated with
increased viscosity were resolved. The cause of the emulsion formation
was traced to lead sulphide impurity
In the early operation at Rio Tinto in the crude sulphur and no such
it was found that the gas temperature problem of emulsion formation was
had to be raised above 400' degrees C experienced at Orkla Grube's
in the first electrostatic operations - Rio Tinto pyrites
precipitator to prevent deposition of contained over 1% Pb , Orkla pyrites
sulphur there and this meant that around 0.05% .
viscous sulphur containing about 20%
As then deposited in the exit pipes - In 1931 only 200 tonnes of "washed",
it was certainly easier to remove it that is , dearsenif i ed, sulphur was
from there but problems with viscous produced but this increased to 7 , 146
sulphur plagued the operation. tonnes in 1932 . No new smelter for
the process was built, largely
Corrosion of the electrodes was because of the difficulties the
overcome by replacing the mild steel company faced in operating during the
with 18% chrome steel, and redesign Spanish Civil War . In 1932 No 5
of the quartz insulators overcame the furnace was altered to the Orkla
initial problems with those. design and a third furnace , No 4 , was
similarly altered in 1942.
A technique for removal of arsenic
from the product sulphur had been It is of interest to note that Orkla
devised in RTC's English laboratory built a "greenfield site ll plant at
and , as first applied, consisted of Thamshavn which used catalytic
stirring milk of lime into sulphur in reduction of the sulphur dioxide in
two steam heated tanks, each of about the off-gases, thereby achieving a
20 tonnes capacity . The operation much greater recovery of the feed
depended on heat from the steam coils sulphur. Catalytic reduction was
evaporating the water introduced with never a possibility for Rio Tinto
the milk of lime and was carried out because of the poisoning of the
at ambient temperature. catalyst by arsenic.
The design time was 5 hours per batch A detailed account of the operation
treatment , but actual time required of the Orkla process at Rio Tinto is
proved to be 24 hours , due largely to provided by Potts and Lawford(37).
the poor heat transfer from the steam Tables 3 and 4 give operating data
coils . Experiments at the mines for the Rio Tinto plant in 1935 and a
using an autoclave indicated comparison with the Orkla Thamshavn
significant improvements could be operation.

- 80 -
TABLE 3 ORKLA PLANT DATA FOR 1935

Sme l ting

In Tons Burden % Cu % S % Tons Cu Tons S

Pyrites 104,499 68 . 54 3 . 74 48 . 43 3, 904 50,609

Silica flux 26,636 17. 47


Converter slag 8,863 5. 82 4.66 1.47 413 130
Matte 184 0. 12 9.24 25.00 17 46
Limest one 9 ,824 0. 44
Sulphur residues 2, 450
------- ----- -
152,457 4,334 53,063
Coke 10,603 6.95
Out
Matte 24 ,534 16.07 24 . 48 3,943 6 ,005
Slag 81 , 450 0. 48 2.90 391 2, 362
Flue dust * 637 2. 43 20.03 15 128
Crude sulphur 35,600 97.17 34 ,600
------
4, 349 43 , 095
* Flue dust contained 22.0% Pb

Sul phur Washing Plant

In As % Ash %
Crude su l phur 35 ,000 2. 22 0.59 97 . 19 34 , 600
Quicklime 1, 323
Out
Washed su l phur 28 , 889 0.0005 0.01 28 ,889
Sulphur residues 2,450 93 . 0 2, 278
Fil ter cakes 2,408 65.0 1, 565
Arsenical liquor 19,890 m3 92 .1 kg / rn 3 1,832
------
34 , 564

- 81 -
TABLE 4 COMPARISON BETWEEN THE SULPHUR DISTRIBUTION FOR THE ORKLA FORNACES
AT THAMSHAVN IN 1949 AND RIO TINTO IN 1935

In Thamshavn Rio Tinto


Tons Recovery % Tons Recovery %

Sulphur in pyrites 99,945 50,609


Sulphur in converter
slags , etc 176
Sulphur in residues 2,278

Total 99,945 53,063


Out
Sulphur from pyrites 66,945 66.98 28,889 54.44
Sulphur from matte 2,998 3.00
Sulphur from hot cata lyser 6,635 6.64
Su lphur from cold catalyser 4,608 4.61
Total sulphur recovered 81 ,184 81.23 28,889 54.44

Su lphur in matte 2,953 2.93 6,005 11.32


Sulphur in slag 5, 284 5.29 2,362 4.45
Sulphur in dust 432 0.43 128 0.24
Su lphur in gases 11,258 11.26 8 ,761 16.51
Sulphur in arsenical liquor 446 0.45 1,832 3.45
Sulphur in residues 2,278 4.29
Sulphur in filter cakes 1,565 2.95
------- ------ ------
Total sulphur 101 ,556 101.61 51 ,280 97.65
Gain/[Loss) 1,612 [I,243J

- 82 -
ICHAPTER 151 Miscellaneous activities

Although the emphasis in exploitation total of 2 . 806.000 tonnes was sold.


of the Rio Tinta deposits was Though containing about 60% Fe . it
initially on silver, then on copper presumably sold at well below market
and, in recent times , on pyrites, price for high grade are.
there have been notable instances of
working for other values. Some of In the 19205 and early 1930s, some
these other activities are summarised bog iron are was mined from the Mesa
here. de los Pinos, but again proved
uncompetitive against ores of higher
purity. 1,496,000 tonnes was
GOSSANS; IRON ORE , GOLD AND SILVER shipped .

Extensive gossan capping is a feature RTC made a thorough investigation of


of the sulphide lodes and interest in the possibilities of prodUCing iron
gossan as a source of iron production at the Mines for use in cementation
seems certain to go back to of copper . In 1896, two 3,000 tonne
prehistory . As reported on page parcels of ore, one gossan and the
15, the Romans used iron tools; they other bog iron are . were sent to the
were experienced in smelting the steel company, Bolckow Vaughan of
metal and can confidently be assumed Middlesborough , for the production of
to have established local production. pig iron . Limestone from Nieb1a was
used for the trial.
According to Williams(21), there are
two types of iron ore. The gossans Pig iron produced by the trial gave
are predominant and initially covered the following analyses . all figures
large areas of the North and South in per cent:
Lodes , varying in depth from 10 to 40
metres. The other type is a Pig Iron Source
"pseudo gossan" or bog iron are, and Gossan Bog Iron Bilbao
the largest formation of this type is Ore
the capping on slate, the Mesa de los Fe 93.52 92.94 92.95
Pinos. [It was here that Sanzo in Graphite 3.49 4 . 61 3.42
the late 18th century. planted the Combined C 0.55 0.35 0 .52
pine trees which so impressed the Si 0.67 0.77 2. 23
Franciscan brothers whose visit is As l. 21 O.ll
referred to on page 23.] P 0.08 0.19 0.05
S O.ll 0.23
David Forbes. the consulting ffilnlng Mn 0.75
engineer. recognised the potential
value of the overlying gossan and The Rio Tinto ores assayed . in per
recommended separate dumping in cent . as follows:
removing it in the course of RTC's
early opencast operations. Earlier , Gossan Bog Iron Ore
Spanish engineers had suggested that
it could be used to make sponge iron Fe 54.!! 54.51
for use in cementation of copper. Silica 6 . 00 12 . 5
As 0 . 74 0 . 15
The mineralogical composition of the P 0 . 025 0.07
gas san is complex and, unfortunately S 0 . 58 0 . 30
as far as use as iron are is
concerned. it contains arsenic and The pig iron from gossan was
lead. A trial shipment was made in unsuitable for use in the copper
1881 and between 1887 and 1893 a precipitating tanks because of its

- 83 -
arsenic content; that from bog iron process.
ore was acceptable for the later
stages. Between 1937 and 1941, just over one
million tonnes of gossan averaging
In 1897 , moves to build an iron 3 .21 gpt Au and 49 gpt Ag were
smelter began but were frustrated by treated. Some 3 , 700 tonnes of
difficulties in obtaining title to concentrate , obtained by calcining
the mineral rights over the Niebla the flotation concentrate, and
limestone deposit. This, combined assaying about 550 gpt Au and 2 , 400
with a failure to identify a suitable gpt Ag , was produced and sold .
coal deposit , following exploration Gold recovery was only 60 . 56% and
at Villanueva de las Minas (to the sil ver recovery 17 . 3%; operating
east of Rio Tinto and 40 km from difficulties were considerable with a
Seville) led to the project being then novel process under Civil War
abandoned. conditions.

As far as the activities of the In recent years, RTC ' s successors


Ancients are concerned, no slags have have embarked on gold and silver
been positively identified as from recovery on a large scale. Their
iron smelting , but the vast operations confirm the difficulty of
accumulations of slag from si lver and silve r recovery , possibly because it
copper production could readily occurs in jarosites not amenable to
conceal the small quantities of slags cyanide dissolution.
from making iron for tools. An
obvious place for iron smelting would
have been along the Salomon ridge, PHYSICAL CONCENTRATION
where both brownish coloured and
black slags were reported in early Most of the production of the mines
surveys. at Rio Tinto to the end of the RTC
era was in the form of direct
Slags found in this area have shipping or direct smelting mineral.
generally been assumed to be from One exception has been mentioned on
silver production. Smelting of page 74 - the concentration of copper
gossan would produce a slag similar from the cupreous stockwork. The
in chemical composition but would second was the Lavadora plant for
require a much higher temperature. upgrading low grade pyrites to
An alternative possibility is that marketable level.
bog iron ore was smelted but no slags
have been found in the vicinity of As described on page 63, the ferric
the Mesa de los Pinos. A third sulphate leaching process used in the
possibilty is that iron wa s produced 1890s led to an accumulation of a
by the Romans at another site and mixture of partly roasted, partly
there is evidence of iron smelting at leached mineral , known as morrongos .
a site a few kilometres to the north. It was estimated that about 20
million tonnes had accumulated and
The gossan contains small amounts of represented a substantial potential
gold and silver . After the copper source of pyrites "smalls".
concentrator was closed down in 1932
(page 75) , consideration was given to In 1910 , as the demand for smalls
gold recovery using that plant. The continued to grow , a pilot plant was
Edquist process - cyanidation with built to separate the pyrites from
gold adsorbed on activated charcoal the cinders, using Hancock jigs and a
recovered by flotation - was adopted . No 5 Wilfley table.
This required only modest investment
in additional plant, avoiding the The success of the pilot plant in
requirement for liquid-solid producing 48% S concentrate led to
separation associated with the con- the building of the Lavadora gravity
ventional "all sliming" cyanidation concentrator. It was located on the

- 84 -
side of the hill to the north of Stockwork are had been located in
Zarandas Naya, on a steeply sloping four main areas - South Lode,
site and embodied the design Salomon, Quebranta Huesos and San
philosophy then popular of gravity Dionisio . In the RTC era, most of
flow. It was equipped with Wilfley the ore was mined from Salomon; the
tables and jigs and underwent various San Dionisio ore was not mined
modif i cations before shutting down in because of difficult access through
1935 . the pyritic mass still to be mined.
Pryor(38) has given a fu l l account of
Between 1912 and 1918 it treated the mining of the cupreous stockwork.
2,434,000 tonnes of morrongos to
produce 1,039,000 tonnes of pyrites After the transfer of the Mines to
containing 42.5% S. Sy 1918, the Spanish control in 1956, exploration
impact of the First World War had led established a sufficient tonnage of
to a stock of 200,000 tonnes of copper porphyry to justify large
product and the plant closed. It scale open pit exploitation.
operated occasionally thereafter but
was not a great success .
SULPHURIC ACID, SUPERPHOSPHATE
In 1954 , a time of revived demand for
pyrites because of brimstone Initially , chemicals required by RTC
shortage , Lavadora was rehabilitated were sent from the UK by ship -
using heavy media separation followed relatively small quantities were
by flotation; all installed in the involved. In November 1883 the
original building. The plant company was approached by a potential
proved difficult in operation, the customer fo r sulphuric acid in Spain
steeply sloping site was , on balance, and, after taking a consultant's
a disadvantage , and the plant finally advice, told the potential customer
closed around 1960 . in February 1884 that production
would start in six months' time!
Testwork on concentration of the
chloritic copper stockwork ore was There were delays , chiefly due to
done at Lavadora and the 1, 000 tpd difficulty in choosing plant suitable
plant, built near the Fundicion for the Mines , and it was not until
Pirita , came into operation in 1930. January 1885 that discussions with
It was of conventional design , with 2 Slaydon Manure Company of Newcastle-
stage crushing to about half-an-inch, upon-Tyne led to purchase from them
single stage grinding in Hardinge of design details for a fee of £500 .
mills to 80% minus 200 mesh, rougher
flotation in pneumatic cells, The lead chamber plant was
followed by regrinding and operational by the end of 1889. It
different i al flotation at high pH. had 66 burners , taking pyrites
screened -2.5 in + 1. 0 in, assaying 4
The high sulphur to copper ratio and to 5% Cu and 44 .5% S. Cinders were
close association of pyrite and smelted at Fundicion Huerta Romano.
chalcopyrite in the feed made it In 1891 , 8,850 tonnes of py r ites was
diff i cult to obtain high concentrate roasted and 13 , 125 tonnes of 51 Baume
grade at high recovery. It was only acid, equivalent to 8 , 400 tonnes of
by regrinding to 85 to 90% minus 325 100% acid , was made.
mesh , that a recovery of approaching
90% could be obtained with a In 1902 a McDougall multi-hearth
concentrate grade of 14 to 15% Cu. roaster was installed . By 1906 ,
four McDougall roasters were in
The concentrator shut down in 1932 operation , taking ha l f - inch pyrites ,
and restarted in 1942 , when the and the or iginal l ump burners were
Spanish government r equired maximum all scrapped. Fine cinders now went
domestic production of copper . to the heaps fo r copper recovery by
leaching.

- 85 -
the mildew which had recently become
By 1925 the condition of this acid a serious problem in their vineyards.
plant had deteriorated to the point Production of copper sulphate was an
where it was decided to build a new attractive commercial opportunity for
one. This was again a lead chamber RTC and was actively pursued .
plant and it was commissioned in
1929. Sulphuric acid production At first it was thought that copper
became increasingly inefficient precipitate (cement copper) could be
through the Civil War . RTC sold its converted to a suitable sulphate
interest in acid production in 1941. crystal but the product was too high
in iron. Two reverberatory furnaces
Just prior to transferring control of were installed and No 2 precipitate
the mines to Spanish interests, RTC was refined and granulated to copper
had embarked on plans to build a shot. This was partially oxidised
sulphuric acid plant to utilise the in a small furnace, then dissolved in
off-gases from the Orkla smelter. hot sulphuric acid , with air
These plans were brought to fruition sparging. The hot solution passed
with the commissioning of a contact to crystallizing pans, from which the
plant, built by Chemiebau of Germany , mother liquor returned to the
in 1960 . That was a sophisticated precipitating tanks .
plant , designed to accept dirty gases
of low and fluctuating strength , but The process was developed at RTC's
it still encountered operating smelter at Cwm Avon in Wales and
difficulties and did not reach design operation of it commenced at the
performance before the Orkla furnaces Mines late in 1889. Production
were shut down in 1965. reached a maximum of 5,889 tonnes in
1903 and then declined. presumably
Around 1900 , RTC was interested in with competition from producers based
the possibilities of superphosphate on copper scrap closer to the
production and William Nash, head of consumers. The decline in copper
RTC's Lands Department, made what we sulphate production , which had
would now call a market survey. He provided the main offtake for
reported that farmers in the region sulphuric acid, influenced the
could be expected to use chemical decision to enter superphosphate
manures from a reliable supplier. production.
In 1898 , a German firm had begun
purchasing acid for their small In the 16th century . and probably
artificial fertilizer plant in earlier, copperas had been collected
Huelva. The attractions of this from the banks of the Tinto river.
outlet led to RTC purchasing the In recent times the quantities of
operation in 1906. It was twice iron discharged to the river
enlarged , but was still a rather increased enormously but it was not
small operation , producing 240,000 until the 1930s that a serious
tonnes of superphosphate in a ten interest in recovery of ferrous
year period , 1931 to 1940. sulphate developed . At that time
it was found that the soil s of the
In 1941 , when RTC was short of local Canary Islands are deficient in iron;
funds, the fertiliser plant was sold, Spanish producers supplying
together with the acid plant at the fertilisers there required a suitable
Mines. The latter operated until means of adding iron to their
1960. product.

A simple me t hod of production , based


COPPER SULPHATE , FERROUS SULPHATE on solar evaporation, was used and
the product was impure; it contained
About 1882, Bordeaux vignerons a few percent of ferric sulphate,
discovered that copper containing more than 1% Zn and approaching 0.1%
sprays provided protection against Cu. Such impurities were

- 86 -
apparently of no great concern in the
fertiliser additive ; the copper is
significant in relation to use i n the
Patio process referred to on page 18
and the zinc content was certa i nly
the subject of attention about 1930.

At that time, attempts were made to


recover zi nc from the effluent from
the precipitating tanks, where the
level was about 2 gpl . The com pany
had considerable experience with
hydrogen sulphide in precipitating
copper and extended the work to strip
both copper and zinc , separately ,
from the effluent. While
technically successful for zinc,
because the sulphide precipitate wa s
readily filterable , precipitated
copper sulphide was extremely fine
and difficult to filter and the
process development was abandoned .

- 87 -
Both tablets refer to Rcrran mllring law, rut of
different periods. The first relates to
Jao",; of the reign of Augustus . althoogh datal
\<oell after his death; the secaxl was insc.ribed
in the reign of lI3drian (AD 117-138) . In a
The activities of the Rcmms in others mining lecture to the University of Durham
areas of the Peninsula have hem investigata:i fhllosoIhlral Society in February 1921 on
by individuals and by official bodies . "Sene Aspects of Mining Laws under the Rarnn
Ernpirell , J-erry I..cuis rrade extenda:i reference
A Camrissioo of Mining Engineers in Portugal to the 1876 tablet . The reventh clause on
\o3Sset up in 1865 under the Ori.ef Inspoctor that tablet has usually been translated ac:; "As
of Mines , Joso M:uia Leitao , to consider to the Vbrkers of Slag and Minerals" and
activity in the Algares area - ere following states:
is a translated excerpt fran that Cannissioo I s
reJXlrt : ''He who in the mining district of Vip:lOC8,
with the authority of the Procurator , rray
' ~ Algares fJESS does not outcrop as does wish to srelt, clean , break up, s:reen and
that of San Joso do ~o . mr is it ....ash slags of silver and co~ , dust fran
accessible by either ancient or rTXXiem \;Ork. slags . and ore bought by ""ight and
The contact at the ~ end is seen , lxlt rrmsure:I , as well as re who similarl y takes
that at the east was mt found , being up the carrying on of sane ...urk in the
covered with slag. The Algares valley is quarries, must declare before the lessee
large1 Y covered •• . by nUTEroUS slag heaps, within three days the ntJrlber of slaves and
in ~ch copper is visible as carbonates. pnd ",,{)limEn going to be J)rid by him • •• •
The average assay of five S3ITIples of poroos denarii per head on the last day of each
slag h:Evily charged with copper C8rronates month ; and if they should not lEY then . they
is 3.85% Cu. Flaky . lmcllar slag contains must p3y double .
as fIlJch as 3.8)% Cu but the average of
twelve samples is al:nit 2%; this is not the "fu .....tn my bring ores of copper and silver
average of the dtlllpS because the rrost into the district of the mines fran other
abundant slags contain only a few places , must )By the lessee 1 denarius for
"rnil1esirral" pllts of copper. Finally, a every hundred JXXlIlds in ;.,eight.
CClTl{ECt slag did not reach 0.4% Cu ."
''lli:! lessee has the right to seize any
The Camrissioo thooght that the last rraltioned article as security, and if re is mt J)rid
slag \...as attributable to the Rarans and the what is a..e:l to him , the lessee rray
richer slags \oRe 8SSlJYE!d to have resulted coofiscate any slag and any rn:irera1 that
fran operations by the Fhoenicians. The sOOuld be 3Telte1, cleaned , brckm up,
Camrissioo did not attE:lT1pt an estinate of the s:reened , or washed , as ;.,ell as any slabs
qoontity of slag , contenting themselves with a of stone ~ch rray be found dressed in the
stataTalt to the effect that it /lllJSt EmJUnt to qoorries; those slaves and fr a:rlren
.serre hundreds of thousands of tomes . belonging to the coprer and silver srelters
who are ...urking at the furnaces of their
An assay of a S3ITIple of slag collected in the rrasters or p3trons are exEmpted fran this
valley in 1m gave 0.6% Cu and 3.0 ~ per p3yrrerJt . "
tonne silver , mt rrmkedly different fran
copper srelting slags at Rio Tinto . The Rman heading of the translated clause is
"Scripturae scaurariorun et testariorun".
It was in the Algares valley that t\..u brooze Henry l.ruis thooght the usual translation
tablets \a'e found buried in the slag heaps ; incorrect and that "testariOn.IJ1" cccld apply
they are kno,.rn as the Aljustrel Tablets, after to rren ...urking at the "test" or cupel in
the I\9IlE of the mine of recent tirres . The refining silver, an operation l ikely to have
first , 7(JJ nm long by :o::mn wide and 9.5 nm been carried out under state control . Other
thick \...as found in 1876 and is no.. .i n the interpretations are that silver slag refers to
Museun of the Goverrrrent Geological Services , litharge produced during cupe1latioo . but the
LisOOn. The secood was found in ICX6 and is dis:overy of a highly silicOOJS grey slag ,
in the Ethnological!'1Jseun, Eelan , LisOOn. possibly flx:lerUcian, suggests that the

- 88 -
dressing of the slag probably refers to APJ"'l'lix 2
crushing to remve rore of the (X:lrticulate
silica before re9Tel.ting with added irrn 1RANSlATICN CF Rll'CIrr BY DIHD lH.GAlX)
oxide. An:ient copper slags prol:ably carried
cOp):ef as carlxnate or rretallic globules and
...ould oove bee1 dressed to recover mineral and "Written refXlrt in the too.m of Aracela, 15
""tal. August 15:6, by rre, Diego Mgado, priest fran
M:Klrid, of the veins ...tUch \..e \..ere
Henry l..oois considered that the ~ood tablet camlissioned to survey and check by rtn
was the f1Dre imp:>rtant because it gres into Francisco de r-Bldcrz.a and with Pedro de
nore details aboot the laws governing the Aguilar . of Castro Nuno within the district of
mi.ning operations. ~ are a.o clauses Zal.area 1a Vieja and other districts. In
referring specifically to silver mining Zal.area, D:::n Frarrisco de t1!rxIcrz.a had seen
shafts. Che translates: '\hasoever oot of large ""ridngs am buildings am equiJl""1t and
the mrnber of five shafts shall have s..mk ale tunnels and shafts .tUch !-ad been ""rked in
do,...n to the ore shall IotIrk without ancient tines and large slag hea~ fran the
intennissioo in the others as is written old foundries and '-Urkings. Having seen the
above ; unless he shall do 9J atta's shall have layoot of the area and of the larK:! and
the JX7WeC of occupying the sare. II 'Ire lx:lurKiaries and having seen that there \..ere
other: '~ works silver shafts shall ""'y veins . I. Diego Delgado am I'€dro Aguilar
keep away fran the drift and shall leave not ~ camri.ssioned to particularly oote,
not less than EO feet on either side exanine. check , find and discover as rrany
thereof. " The drift ""'-Ild be the dr~ rretalliferous veins as were '«Irked and
t1.l!lre1 carryi.ng \<tI8ter out through a lCl'¥.eI' recovered by the ancient people. Having
level of the mine, This suggests that the de:ked these rTJ?:tal ores, Sr D:::n Fraocisco de
silver ore was aoove that of copper and darage floldoza will send the rrost useful for his
to the drainage drifts I<.I:JUld have adversely M3.jesty ' s service.
affected the mining of copper ore.
''1terefore, in cc:rrq>liance with the above
M:i.neralisatioo at Aljustrel incllXles veins of provisioo , Ioe set forth at the eM of July
galem am tetrahedr:ite. 'l1en the mines ..".. 1556 to the district of Zalanea am "" lodged
visited by Leitao , copper- rich slags, such as ourselves in SCIre 00uses on a rroontain called
we f'Oo{ knJ,.r to have been pnxh.ced in srelting Nuestra Seoora de Rio Unto alx:lut a quarter of
to recover silver. were to be found in a leegue fran the tunnels and shafts ""de by
substantial tonnage; these slags ~ re..urked the ancients. 'Ire day after our arrival I<.e
in the seccnd half of last century for copper I;61t to one of the caves, known as Salitre,
recovery. and ~ entered it. This cave rreasures 70
paces wide and over 00 ]l3Ces long. Its
height is like a church and it is ardBI. and
within this cave there are great cavities and
ventilatioo channels which care out in nany
places on the top of the hill . We believe
the height of sare of these ventilation
chanrels is IOOre than 15 estadoo( 1) am light
for the ...orkings was obtained thraJgh these
ventilatioo shafts. l..ikewi.se, witlrin the
cave there are SOlE shafts which go downwards.
I I;61t down one of these to discover the
reasoo why it was IIl3de by the arrients and in
this shaft fOlJl'li a vein covered by earth ...trich
had been l'It there by hand. I cleered "'""y
this earth and d:i9:overed the vein and several
openings in it I and fran this vein and several
I>oles I extrncted an arrobe(2) of ""tal in the
tine it takes to say six creeds. I felt
th3t this \o'8S ~ the ancients carried oot
their ""ridngs.

- 89 -
"Having left ~ shaft, we 'W8lked the entire told than and infonre:l than that it was
length of ~ cave and saw that the aocients because it springs fran vitriol, although
follo..e:l. four or five different rretals in it, trere is anotrer secret in this which I kept
all of which started fran one ITI)t.her vein to myself and did not di.s:lose to them. As
..mch ran aloog tre cave(3) . We S3w that "" they saw and see that this river flo..e:l. tinted
\<O..ild not be able to dis:over the netal in ~ it cannot be called anything else but Rio
cave due to ~ large aoount of earth and Tinto.
stone left in it and we h:td to try and find i t
in the Ill'llltains, alt1uJgh the ground was very ''No fish or other life existed in this river,
overgro...n. As it was 10 days si..oce em- neither do people or anirrals drink it, oor are
arrival at the cave and district of Zal.cm:a, its waters used for anything else. ~
tre Foost fuy of St Laurence (10 August), I, water has a property that if ~ with a
Diego Mgado , hired a IIBn with a pick-axe and living organisn in his bOOy should drink it,
...elt to a place where sore days previcusly I the organisn will die and be expelled fran the
1m noted signs of a different netal and there body . Aoot:her property ..mch I told than
I ordered him to dig and after n.o or three a1x:ut and of which they \\ere anxicus to hear
strcl<es I clli<:overed neta1. I ordered trim was that if any pers::n had d:Lgeased eyes and
to dig deeper up to knee--height and discovered wa.sI'a:i t:hanselves in that water they ....ould be
a groot quantity of rretal of which I ordered healed. This I gave than as rtEdical advice
an arrom to be t:akm for IXn Frarcisco: this and they \\ere very pleased, h=call9'> it was
vein is little ITI)re than the throw of a later proved to be trn= by experience. It
harq1.eOOs fran the Ill'llltain. Having seen has another property that if you place iroo in
the rretal which I discovered, we deduced that tre water it dissolves in a few days . This
it was all of me kin1 I>kdch the ancients had I tested and proved myself . I tack a live
v.orked ooth in the cave and in the shafts . frog and t:hrew it in the river and it died
It was all of ooe material which I dis::overed without being able to leave the ....ater. In
and this I reJXlrted to IXn Frarcis::o so that all this river , no sard or loose rrateria1 can
he could order it to be exmd..ned, ro that he be foond because all tre stooes are fiJ<ed and
cruld detennine what sOCcld be recovered . sttr.k together and if a loose stone is thro,...n
in, it too is stock to the botton of the river
''In this way, \ooalk::i.ng in the exanined arm and after a few days like the otrer stooes.
in otrer areas, we saw very large foundatioos
and srelter buildings and slog heaps fran tre ''toW..king in SE!iTCh. of
these veins,~ found M
veins wch the ancients v.orked and recovered. groot hills in which ~ found other rreth:xls of
'These slag heaps are ro rmssi ve they appoor to worldng tre veins and shafts , ""'" of ..mch
be large hills and ""'"tams. Coold these shsfts \\ere v.orldng for veins and others
slag heaps wch we saw up to n.o l~ long giving light and others of ..mch had been
and two leagtES wide without doubt be t:I-Ja:;e we ~ in a different IlBlUler and had no rretal,
were told were roore than eight leagues long? because as we fcuxl these had hem rrade to
de..ater the veins which \\ere being ~rked.
' We also visited anot.her cave which was full 'These shafts intercoonect one another. We
of water and fran under "'*rich sprang a river foond mre than fifty shafts in a very large
said to be tre Rio Tinto(4). 1re reason why hill(S) ..mch ""'" used for dewatering, ""
it is koo.n as the Rio Tinto is broruse it ...elt into one of these for further informatioo
springs fron vitriol, which in another part is am it was seen to be about 15 estados deep.
krD.n as copperas, used for ink. All the Next to this shaft at aOOut eight paces
sides of the river are covered with copperas another river had its source and produced sour
nBinlY during tre """th of August and water which I also called Rio Tinto. 'Irere
trerefore in all the district throogh \ohlch ~ lJBIly otrer things which we did not see
the river fl<M.3, tEms of \<KJTBJ. and lasses and awing to tre very thick undergrowth 00 the
lads are sent , during the IIDI1th of August, to hills and because ~ ....ere told alxxrt: them.
collect this copperas with which they p3y
certain taxes ..mch trey """ to tre Archbishop ''\Ie also sem:l>3l 10here tre ancients had their
of Seville. No ot.her cotmcils or othar refineries to see if ~ could d:is:over
perOCllS are allo..e:l. to collect it at any tine """'thing ..mch >OOld &led light 00 tre way
urxI.er p:rin of grievous Pffialty because it they extrocted silver or EDIE other rretal , rut
beloogs to tre ArchbisOOp. Up to now trey ~ could rot di.s:over anything h>ca L9? the
did not kn::w \Jl.y the river was stained until I hills could oot be reached . Returning to oor

- 90 -
lodglilgs "" found at the very top of a hill(6)
W signs of a building. tie ordered ~ rren
to dig there and at ratrer" nnre than the
height of a !TBJl ~ foond a certain OOI)UIlt of
lead fran ...trich \Ie dedoced tlat the ancients
had \lUrked in lead and that their aim I.8S to "In the district of Za.1area la Rml is the
extract silver . rrountain and location kno,.,rn in these days as
the ''Castillo Viejo!! where are still to be
"ASdng lIBfly old people who had heard 8b::lut seen walls and ruins, remins of Wildings
these ancient OOildings , thay replied that created by the ancients , on its sumrit , and
they had heard S3y that in ancient t:ilres Sp3in which app:m- once to have been a castle or a
U9:!d to give the Rarans certain silver and fortress. Fran its elevated situation it
gold tal€!lts as taxes and that they were taken was difficult of approoch and caJlTBl'l:led a goOO
fran there, but they knew nothing rrore th3n view of the surrounding COlD1try below. and it
tJ-at. nust have been a place of 9.:JIE strength .

''laving seen all the aoove and having obtained "Fran tJris hill , in two different places, on
all the infomatioo I could . we returned to the north and oouth sides, exude strEBIB of
Aracena where Sr D::n Francisco de M.:n:loza was strongly dis:oloura:l and mineralized W3.ter,
staying . to give him an acro..tn.t and rep:>rt :in highly charge:! with foreign m3tter and
accordance with cur camrissioo. J-Bving appropriately TBJa:i at their juoction and
arrived there we gave him all the infomatioo cootinuation the "Rio Tinto". 1he SIDE narre
we could , togetJ-er \odth the rretal ...trich we is given to an "aldea" or village of sore 00
ra:eived I<ohlch we gave over to him , so that 00 hooses, distaoce about 5 loogues fran Aracena.
ccu1d arrange their excmination and analysis ." 20 l<Egue5 fran Guadalcana1 , 12 fran Sevilla
and 2 fran Zal.arra:! la Rall. This latter
Notes: t~ is a place of sore 1,0::0 houses , with
plenty of good \oSter and fertile roil, and
1. An estado is the average height of a 1IBIl. having an excellent situation and c:1irre.te.
2. An arrola is aboot II kilos . Its people are industrious and \oo'Eill-to-do ,
3. This refers to the varying coloors having a considerable bJsiness in pigs, hides,
exhibited by the jarositic silver ores . honey and _.
4. Assured to be what hecaTe koo.n as Wzva
del lBgo. '~ village of Rio Tinto is ~t
5. A.s.sun:d to be San Dionisio. contiguous to the hill referred to, wtrich
6 Assured to be Cerro Salrnm. extends sore 3,0::0 yards , at a considerable
elevation above the country heleM. '!he
sout.h--\..estern {Brt, or slope , of it has been
traversed by a read still to be seen or
identified in rart, here and there ,
undoubtedly b.dlt by the Carthaginians or
Rarans for the transport of the projocts of
t:OOse mines to the (X)rt and place of
enbarkation JHJEd San Juan dellWrto ,
sitlBted 9:lTE 9 IEGgUE!S distant fran Rio
Tinto.

"So nu:h exploration and \<oOrk ~ perfonred at


part of the ''Cordillera'' th3.t the slag
ClI"e
resulting fran the srelting furrnces forms
huge roounds , """y of than being equal in
pror:ortions to sm11 hills at and atnlt the
foot of the ''Cordillera'' and have received, or
being the subject of , the gr<Etest admiration ,
and have deeply ;.,pressed all those ..m have
visited the place and seen than.

'anus is verified and sutstantiated, apart

- 91 -
fran what is irrlicated , if not proved, by the quantity, either in nnney or in!JEtal ; but
evidence of labour, subt:erTarean aM what famdatioo or pro1:ability exists for soch
superficlal, especlally in the hills of I cannot \\ell understarrl , tmless it be that
"es:oriales" aM in the ruins of a rather because of the sudden exodus of the Saracens
coosiderable town , to which traditioo 00s after a 1008 and prosperous occupatioo of the
given the nare of "Gran Bitania", to be foond place, they nust have been canpelled to bury
widely s:attered on the lo..er slope of the arxI. leave behind, hidden, a certain quantity
north side of the hill , on which the ta..er or of treasure.
castle of Salaroo in forner tines stocd.
''For better explanatioo as to the aquedoct , or
''l-Ere and there rarains of high collJIllS of cut drain, referred to , it will be proper for rre
store of an iron conglarerate, irrlications ani to state , yem- Excellencies, that it is so
remins of foundations and other IIDtS still large as to pernrit the easy entraoce of a
reraining as they fell centuries and ages ago , per9:)O to ....ork in it and that fran its
~ly dem::nstrat e , beyood any slndCM of doobt , aperture at the foot of the hill to its
the size and imp:>rtarx:.e of the place - tOOt it carl.usion there are 22 shafts serving for
was once a large , prosperous and :irrqxlrtant light aM ventiJatioo, at regular distance
colmy. fran e3Ch ot:rer of ~ve yards , thus the
total length of the gallery is 204 yards.
'~ Saracens aloo ....orl<ed in this , the north In the nnuth of the eleventh ventilating shaft
side of the mines , and they , being skilful in there is placed the very larJle stooe already
soch labour. constru::ted an aquedu::t on the rrentiooed , which detains and arrests the free
soothern side at a rruch 1""", level than that exit and draimge of the \.o6ter fran the
of the site selected for ....orking by the interior and f r an the lcxies. By it is
aoci ents 00 the north side . By it they fornal a suiEtantlal lake of highly
....orked to..ards the ca1tre of the mine , with vitriolized \<Bter , very clear and translu:::ent ,
the object of being able to ....ork at la..er so II1.Ich so that the bottan can easily te
levels in procuring a natural drainage. distinguished , as..,u as the obstrocting
witlurt: h3ving r~ to any artificial stone.
""""; and altlnlgh to:Iay "" fiIxl large
deIX>Sits of vitriolized \<Bters in the interior "I h:ld the curiosity to rreasure the depth of
of this !lDUI1tain, I believe that , as all might the water and ascertained it to be al:xx.rt: 12
be rrede to drain cut withoot the use of estados. The highest of these ventilating
artificial rrea:ns , it can be easily and quickly sffifts , that is the last of than going up the
dme and in that 1JEflrer , at smll cost , ~ can hill , is sore 3) estadas in depth, 15 estados
discover all the old , grand and important being in water.
interior ....orkings and ride:; .
''Of v.hat Jmticular k::i.M of rretal trese or es
lilt is evident that the obstru::tioo to the are nnst aburxlant in , wtY=dEr gold or silver,
free exit of the \<Bter fran the interior of it is not easy to ag:ertain, rut all
the mine by that drain or aquedu::t - for that indications lead me to infer that gold is the
is its present conditioo - is a stme of very priocipsl iten. But ap:nt fran indications
large ProIXlrtions , which , in my opinim, has so p:ltent which I h3ve derived arxl. dedoced
been rmlicioucily placed at the roouth of the fran dOCUlB1ts of tmdoubted1y high aut:OOrity,
eleventh shaft or ventilator of the aquedoct , are the ootic.es given by a nnst an:inent
in consequence of which the exit fron the subject on the ....orking and treat:ne'lt of the
interior parts is interrupted and there is no Iretals obtained in Peru, and under 9:lre
doobt rut the S:rracens, ~ were the last to guidaoce and teoching they are to:Iay being
'-OIi< in these mines, fiIxling thamelves han! \oUrked in the boo 1dngda!E of the Irxlies.
pressed and obliged to retire fran the place ,
adoptal this IlB3!lS of preventing the Spaniards ''IE c.arTe to this Idngdan with DIU of the IIl)St
fron any easy adoptioo of the ~it of their expert assistants that could be found , under
CW1 and earlier laro.rrs and explorations. an order of King Philip the fifth , and fran
the year 1648 until 1651 they ""'" anp10yed in
'~ traditioo is cammly current in this the stufy and inspectioo of various mines.
neighbourOOo:! that in the varirus hollows and In that of Rio Tinto they were for 9:lre t:i.nl::!
caves of this ''hill'', in its subterrare9n employed , and after rrany and various
....orks, exists hiddm treasure in great experieoces , discovered the IIEtind of

- 92 -
separating the mineral. In the rrarorial the ruins of that ancient city of Gran Bitania
th:lt he wrote of wrnt re had done, he and of the old castle on the hill alre3dy
rmintained that His l1! jesty had in these ""00 referred to , wch I Mve been able to acquire
arrl in the "es:oriales" iJme1se treasure , and hand to His l1! jesty the King . One is a
having found oot littl e silver, oot a pie:e of silver , a coin distinctly sI'n.ri.ng the
coosiderable part of gold; oot as His l1!jesty rust and rare of Augustus Caesar; and yet
wished to charge all the exp'5lSE'S :in relatioo others, Iohlch fran their fonn, rmke and
to the rmtter to the TrffiSlJI"Y and rarain similitude to others I judge to be of the
interested in all prooocts, nothing resulted . Caesars Trojan and Tiberius, also of copper
partly because of the inefficient and gold. Another , again obtained fran a
administratioo arxl large costs and because stene sarcOIfBgus , is very distinctly l1E!W' , as
there aloo existed at the sane ti.rrE the war tlxxJgh rut re::entl y coi.ne:l , rut, as the
with Portugal ; the ultiJrate result and end characters impressed uJXlO it are in Arabic, I
being that this site and its abundant minerals carmot pretend to deterndne to what perio:l it
reraine1 forgotten . lIBy be as:ribed .

'~ netals IJrich are herein indicated and "Although it is not at all necessary in this
referred to are not those as given or as instance to determine or as:ertain exactly
extracted fran these mines , but are those ho,.r,...nen, or by IJlan these evidently ancient
wch had alrEBdy been suffered a first works were ~ and aOOrxloned , I JJBintain
trmtJIelt by the ancients and ~re by them that the art of extracting and 3JElting
left dep:lSit ed and hidden , with the liltentioo nri.nerals and the drainage of the mines is
of returning again to trmt and assay then at obliged no whit to the ancients; on the
a convenient ti.Ire and op{X)rtllIlity. ~y are contrary, within a certain period of galius ,
conposed of llBJ1y Jretals and differffit kinds of industry and application of the people of the
minerals , abouMing in ant.im::ny. arsenic , different kingdcms Mve been IIBterially
sulp,ur and irm; for which reasoo in order to developed and ad<anced by the ingenious
abstract the ric1"a- parts contained in then , d iocovery of so very rreny admirable na:.hanical
it will be necessary to prooecute the method appliances, inst.ruJe1ts and furnaces for the
of extractioo no doubt ascertainable in the saving of labour in mines , and \o.()rking in
archives of the year alluded to of 1651 and minerals and "",tals gerera1ly, IoIrich today
there are rmny rren of great skill able to are beyond the canprehension of very rreny
extract and seImOte pure metal fran impJre , artificers and miners ~ Mve not yet rrade
in different kingdars of the north. use of them or tad any practical acquaint:an::e
with their application .
"I an unable to specify definitely and clearly
whst are or will be pure netals to be obtained ''This Sirs, I IlBintain is all pertinent to the
fran these mines, but fran all that I h3.ve rratter and very rruch in its favoor and to your
IJHltiOl'lErl , the existence of the dep::>Sits of advantage, in which supposition I conclude ,
vitriolized water in the interior , the copirus supplicating that you will continue to be
qwntities of "vernel.lon" and "capuTosa", stinulata:i to and determined on the
Mtural and fine, that are also rruch in prosecution of this grand 'wDrk.
evidence , and of which I send samples to your Providential signs are not wanting in your
Excelleocies ; all, in my judgarent, favour, as already a mine tas been foorxl
uOOoobtedly indicate the abundaoce of and abundant in "carron de fierro" , as to the
superior value of the rretals to be fourxl quality of ...mch expert opinioo has been taken
there. at the to.m of Gu3dalCBMl. and I assert that
it does not yield in character or favoorable
"At Iohat perio:l of antiquity and history, or conditioos to any of the very fCIJDJS mines in
un:Ier what rarticular goverment, the first Fngland.
attanpts ~ IIBde to extract and assay these
minerals , I an quite unable to ascertain and "At Cazal.1a, too , a no less valuable mine of
certify , rut , undoobte:lly , operatioos Mve az<XJue [rrerrury 1 has been dis::overed , the use,
mre or less continoously been carria:i on here impJrtaoce and value of wch, in furnaces and
for very rreny centuries; for the present I in the rep:rratioo and assaying of rretals in
will simply take the evidence of pie::es of general, is so notorirus that I an e:<Cl.I9;.'!(\
rrmey and rre::lallions , casually found by fran further praising it.
"p3StOres", IErdsren and others in and about

- 93 -
''Your crnpmy is not to be at the cost or AEpendix 4
ctarge of the Govemrent nor under the charge
of the vassals ; you are neither contractors CtH'!R ffiClJ.CITOO 1829 - 1849
nor lessees of royal reverrue , nor will your
agents cause trooble or disturtence to the Year I. 2. 3. 4.
JXlPllatioo of the district affecte:l by your
operatioos ; yoo do not pretend to fonn 1829 35.00 37.~ 72.~
treasure JX310ces or castles at the cost of 183J 93.00 79.00 1n.00
otrers or of the !XJblic; finally yoo do not 1831 82.00 72.75 154. 75
prop::se to crEate certain offices tfut nay 1832 272.75 55.~ 328.25
hecare a 00rden or c:h3rge to the State 1833 1'Xl.00 39.75 229.75
revenues; on the contrary , an.i.neted by a 1834 132.25 31.00 163. 25
valour and .za:U rrost noble and profitable to 1835 155.~ 26.00 ISI.~
your ooverei.gn and his country in general , yoo 1836 177.25 :D. 25 ::lJ7 . ~
enp10y your own capital and resources in the 1837 124.00 24. 25 148.25
extractioo fran the bcJI..el.s of the earth of a 1838 136.25 39.~ 175.75
trffiSUre and canron benefit to all. 1839 SI.75 35 . ~ 117. 25
1840 128.~ 70.~ IS .OO 216 . ~
"Fran this industry toot you seek to 1841 55 . ~ 63.00 54.00 172 . ~
re-<>Stablish ""y be hoped and awaited the 1842 66.~ 7O . ~ 116.~ 253 . ~
alleviatioo of the vassal , the help and 1843 96. 25 46.75 ::lJ6. 75 349. 75
soccour of the necessitous and the cons:>latioo 1844 49 . ~ ~. ~ 244.~ 344.~
of the wid<M and the oqilan ; all with 1845 41 . 25 51.25 241.25 333. 75
coosiderations ...roch invite Spain in general 1846 13.00 ~ . OO 234.00 297.00
to contribute to and prorote the happy SIiCCess 1847 12. 25 47 . 75 327.~ 387 . ~
of it , which nay rearonably t:e anticijBted 1848 4. ~ 49 . ~ 373.~ 427.~
tID:ler the berclicence of the Almighty Po.er, 1849 12.00 7. 75 85. 00 1()\. 75
the favour and assistance of our ren<7w'f"al and
pious rrornrchs , Fhilip and Isat:ella , the Totals 1959 978 l'Xll 4838
SUPPJrt of your illustrious canp3l1y , and of
the intelligent directorate. In this Key :
coofideoce I COI1~ , desirous of other and
grEater occasion to be able to enp10y my ~r 1. Fran ore srelting - t:cI1re3
zeal and talents for the catm:Xl goo::l . 2. Fran precipitation "
3. Fran vitriols "
4. Total "
"Signed D Roberto sree
Mldrid 17 t1rrch 1nB' Copper fron vitriols probably inclmes copper
fran artificial cateltatioo .

- 94 -
Appendix 5 drooses are constantly use:l in tlY= snalting,
as fran the imperfe:t JretOOds of the ancients
()}MOO'ARIIS RFlATllC 10 TIlE RIMISA IRA they are foond to contain rruch 1.ln\\IBIlted
copper.
I. Visit by Richard Ford
''Ire village is built aboot a mile fran the
Richard Ford lival in Spain fran 18JJ to 1833 mines, and \oI8S raised by CIle Uberto \>.bIters,
and subsequently publ:iste:i "A HarxlOOd<. for a S\..€de, to \\han Rrilip V had granted a lease
Travellers in Sprin" (lrodon, JOOn l1Jrray, of the mines, which reverted to the Cro.m in
1847) fran .roch the follNing extract 1783. It is principill.y occupied by miners;
covering a trip to Rio Tinta fran Seville is tJ-ere is, to..Bver, a dec:a1t "posada"; the
taken: "empleados" and official people have a street
to t:hensel ves. The vie,..r fran above the
''Fnssing through ltalica, the high rood to church is striking; the tCMl lies belo,.; with
BOOajoz is continued to the Venta de Pajanasa, its strean and orange groves: to the left
4 leagues , and turn off to the left over a rises the ragged copper hill, WTBpt in
waste of Xaras, cistus and arooatic f1~ su1~eoos wreaths of socke: while to the
giva1 up to the bees and butterflies to right the IlBgnificent flat fir tank, wch
Algarrooo., 1 leagLE , a SlBll hamlet, where supplies fuel to the furnaces . ''La r-Esa de
bait. Heoce three l~ over similar country los Pi.oc6" is tacked by a 00undless extent of
to a nmmtain village. Castillo de las cistus-cJ..ad hills , rising one over another .
Guardas, so called fran its t1:orish "atalaya";
we sleep. 5 leagues over a lonely "clehes:!" IIA proper officer will condoct the traveller
lead next day to Rio Tinto. over the mines, and tlal follo,.; the are
throogh every stage of the process, until it
'''Ire red nake:l sides of the copper rrountain, becalEs JW€ copper . FIltering the shaft you
La Corbeza Colorado, with c10trls of sm::l<e soon deocaxi by a ~ or "~" do.m a ladder
curli.ng over dark pine 'o<O:Xis, anoounce fran to an underground gallery: the heat increases
afar these celebrated mines, The :imrEdi.ate with the depth, as there is no ventilatioo; at
apprmch to the hamlet is like that to a mioor the bottan the therm:rJEter stands at 00
infernal regl.cn; the road is nade of b.lrnt degrees Fahrenbait and the rrri.ners, wm drive
ames and ''Fscoriae'' I the \oiW.l.s are COllJX)SErl iron ~ges into the rock previously to
of lava-like droos, Wle Mggard miners, with blasting, ~rk a1.rrost naked , and what fe,..r
sallOW' faces and clarkaled dress , creep about, clades they have on are perfectly drenched
fit denizens of the place; a snaIl green with perspiration; the s:ene is gloony, the
coppery strean w:inis under the 00nk of firs, air c100e and poisonous , the twinkling
and it is the "tinged river" fran wheoce the flickers of the miners I lanps taper blue and
village takes its nare. This.stre:rn fla..'S unearthly; rere and there figures, with lamps
cut of the boI.els of the !lDltntain, is supPlS6i at their brEflSts, flit aboot like the tenants
to be conrected with s:JJE internal of the lcll of Eblis and disappear by ladders
urr:lis:overed ancient corrluit; it is fran this into deeper depths. ~Iy is the soun:l
that the p.rrest copper is obtained; iron tars of the pick of the solitary \ooOrlomn, wm alone
are pJ..ace:j in \ItQCrlal traJghs I which are in his stone mere is lmmering at his rocky
:iJmersed in the waters , ~ a "cascara". or prison like sam coo£ined dE!lll1, endeavouring
flake of netal, is deposited on it. which is to force his \.ooBy to light and liberty.
kmcked off; the tar is subjected to the .serre
process until ccmpletely eaten away. The 'tne copper is found in an iron pyrites, and
...ater is deadly lXlis:::floJs: no aniIJBl or yields aOOut 5 per cent. The sta1a:tites are
vegetable can live near it, and it stains and very beautiful; for wrenever the \ol8.ter
corro:les everything that it t~. trickles throogh the roof of the gallery, it
fOIlT5 icicles as it \oE!re of ereralds , and
'tne mines were perfe:tly wt:ill kno.m to the arethysts, but these bright colours oxidize in
aocients, Ib::::se shafts and galleries are the opel air and are 9:XXl changed to dun
coostantly being diocovered . 1re Ratans and brCMl.
r1:x:>rs appear chiefly to have \lUrked on the
North side of tlY= hill; the ffiOmws '\hen the "'Zafra", or rough are, is extracted,
accurulatioos of "escoriales" show to what an it is taken to the ''Calcinatioo'' 00 the bro,..t
extent tlY=y carried on operatioos; trese old of the hill, and is there rurnt three t:ines in

- 95 -
the open air ; the sul!Xrur is sublineted and called "JBp.rlBII.
passes off in a elcul of 9id<e ; the rough
netal , which. lcx:ks like a s:>rt of iron cd<e , Several srell srelters treated all the cascara
is next carried to be ~ted at 00u.ses ploca:l. and any high copper content pyrites , the
near the strean, by wtJose \o'3ter JX'WE!l' the latter after roasting twice. ~ blast
bellows are set .in action. The rretal is furnace; """" of the Catalan type, each 1.6
first rrri..xa1 with eqll31 parts of charcca1 and rretres high, and a typical daily charge \0135:
''Focoriales''. the ancient ones being
preferre:l , and is then fused with ''&e:zo'', a Rman slag goo kilos
sort of fuel canp:>.<:e:i of cistus and rooamry . Paru:m m "
~ iron flows 8\o13y like lava. and the copper Refinery slag 110 "
is precipitated into an iron p:m or "cope1la" llirrcrel. 740 "
bel"",. It is then refined in ovens or
"Reverberos". and looes about a third of its 1h:! ootpJt .... 245 to 270 kilos of black
~t; the scun and impJrities as they rise cop~. assaying typically 81% Cu. 17% Fe and
to the surfoce are ocraped off with a \oOCXIen 1.5% As. Paru:m might be replaced by
me. The ~ copper is then sent either to rooste::l ore ; refirery slag assayed :0 to 55%
Seville, to the canon fourxiry I or to Segovia Cu. If only cascara .... srelted the charge
to be coined." was :

1010 kilos
2. C/oservatioos by Femaroo Bemaldez ~ "
5'D "
Fernaldo Eernaldez \oUrked at Rio Tinto after
the Renisa lease .... ternrinated . Referex:e has and this yielded 225 kilos of black copper.
been JTBde in Qapter 2 to his publicatioo in
the l1!drid joornaJ., Revista Minera in 1853, of Copper obtained f ran srelting paru:m
and
olEervatioos 00 the ~ble origin of ancient ro3Sted ore tad to be rE!Jel.ted twice before it
slags. In the SEI1E article he provides an could be refine:l , 00 doubt in order to oxidize
interesting accoont of rretallurgica1 inq:mities . Refining of cascara fran natural
operations in the years iJma:Ii.ate1y preceding caJEfltatioo and black copper was carried out
his anplo)'JIffit at Rio Tinto; fran this accoont in eiili!r Genran refining hearths or
the infornation which follows has been reverberatory furnaces.
garnered.
A Gemm refining hearth could process a
The cuproous pyrites was broken to nut size . charge of 'JJJ kil os of black copper or good
slowly roasted , l eoclBl and the copper cascara in 24 OOurs. pro:hcing l{'JJ kil os of
precipitated on pig iron. An analysis of copper suitable for all oying , or 29) kilos of
precipitate , or cascara , is given as : refined copper, and requiring 400 kilos of
charccal in the first case. and 62) in the
Cu 71.45%

=
second.
Fe 5.47%
Grnfhlte l4.f:ffi In the reverberatory furnace , 100) to
S,As,etc 10.1& kilos of b)Bck copper and/or natural
CSTEIltatioo. cascara \oBS refined daily,
In canpm.soo. cascara obtained by natural pro:locing Il£O to 14(1) kilos of refined copper
cer61tatioo fran the mine drainage waters and using be"""," 675 and mkilos of logs.
analysed :
Fran his study of the relative rrerits of the
Cu 94.6at 0.0 refining rretlxxls . Bemaldez recaJIJe'rled
Fe 3.S8Z the installatioo of a larger reverberatory
Silica,As 1.51<% fwn:tCe and that was dooe in due course.

Poth cas:aras were washed before being sent to


the srelting IvJse and sludge recovered fran
the ~ contained 45 to :m Cu. Slu:lge
fran the pnripitating tanks contained 8 to
1m Cu. Both slu!ges _e very fine and

- 96 -
Apperxlix 6

<IHl'R m:w::rnN 1849-72

tames

Year Ore Mined RefiJlej w 1re slIccessful bid to acquire ~ mines was
92,8ll,ooo ptas plus 1,195,912 ptas for
1849 3,117 ))1 valuatioo of plant , b.ri.ldings, mineral stocks,
18:0 5,IIJI 373 etc; this was equivalent to E3,B:O,OOJ. ~
1851 6,558 579 <:CflOOrtiun of finaociers wro rrede the bid
1852 6,296 672 incltxled:
1853 5,373 537
1854 8,5ffi 722 Messrs !-BtIESOO & Co of loodoo
1855 8,193 785 The lleu<s;:re National Bank of llretEn
1856 8,256 743 Messrs Snith, Payne & Snith of i1nIoo
1857 8,283 650 ~rs Arthur 1Ie)"OOd Sons & Co of l.iverpool
1858 9,826 674 The Unioo Bank of Scotland of Glasgo.<
1859 12,849 953
It!'/) 15,702 817 Their offer was acceptEd 00 17 Febrwry 1873.
IBSI 17,f03 1,136 The property""" l'Jl"Chased in perpetuity and
IBS2 16,653 1,255 consiste:I of 1,659 rectare8 (4,100 acres) and
IB53 89,694 1,355 incltxled nearly all the houses in Rio Tinto
IB54 74,234 1,0\6 pueblo . The first P'JIlBlt in cash of
IBS5 66,156 1,025 £442 ,680 was nede 00 5 April 1873 and nine
IB56 62,342 1,135 furtlEr "~es'l or pranissory rotes ~ to
IBS7 53,48) 829 be redeaJEd on anniversaries of this date up
IB58 52,<r6 1, l23 t o 1892.
1M 00,5)) 974
1870 67,075 1,012 The Spsnish govermelt was, in the years
1871 55,000 t!'/) :i.n1TeJiately following the sale, in serious
1872 62,W B54 fimncial diffiaJlty and asked the Cat!>any
.nether these future P'JIlBlts could be nede
i.mre.diate1y at an appropriate dis:.oont. RIC
raised the neres<l3ry """"Y by issuing bonds
and redeered all the prani.soory notes by the
end of 1876.

The Canp:my was registered with a capital of


£2,~ , ())) 00 29 M3rch 1873 arrl a prospa:tus
was issued 00 8 July 1873 offering the J>lblic
200,000 shares of £10 each. In 1881 the
share capital was increased to £3,m,OCO by
the isSJe of a further 100,000 shares of £10
at £22 eoc.h. 'llal, in 1897. at tfr request of
the larger shareh>lders, the lla3rer shares
were split into Preferred and Ordinary shares.
The shares \oeI"e split to E5 rxmi.nal value,
after ...trich the capital consisted of 325,OOJ
Preferred and 325,000 ordinary shares. The
rate of dividenl. en the preferred shares was
set at 5%. A further issue of ~ , O)) £5
ordinary shares """ nede in Novenber I'm at
£65 each. In !-By 1929 an additional 53,000
£5 ordinary shares """ issued at £50 each.
Thus , by1m the share capital """:

- 97 -
325,axJ £5 preferred shares fl,625,axJ llBIly others, I CflI one of the original
425,axJ £5 orttinary shares fZ,125,axJ shareholders of the C'mpany, the nen .no
ha.ve rome the burden and the lEat of the
Total O,7'IJ,rm day. In the prospoctus ...,., the C'mpany
was fornal, it was stated that if pregent
Further 5% f-brtgage B::nds Ioere issued in 1&£), prospocts continued, the C'mpany might
1884 and 1892 and the earlier bonds issued to reesooably be expected to pay 18 or Xl%.
reclean the pran:i..ssory notes . ...ere reprid. This certainly "'" very tanpting and indoce:!
'Ire borx1 JX>Sition in 1895 was as foll~: llB1ly of us to becare sharetvlders. We
lm::rw very ....e1l that the Directors c.arux>t
rate of Drillinal Ortstanding centrol prices any !lOre than trey can
Ilood Value Value cootrol the \\I6ltrer [a refereoce to the
DlairnEn I S reJX>rts at ACMs that the
1800 £2, 9l) ,rm fl,!lSZ,3IoO slx>r!age of rain at Rio Tinto had hirrlered
1884 £1 ,200,(0) £l ,CnI ,m prodoctioo of coppsr! J. We have been
1892 f fIX) ,axJ f 573,5Xl exceedingly anxious to hear wmt \Ie have J'lOoo{
heard, viz that \<E ha.ve oo,.,r turned the
£4,3)),OCO O,437,(ffl comar, and I, like otiffs, ~ very pleased
to see the Canp3ny rrekiJ1g a profit. WOOt
furing July 1895, tIossrs N M Rotl=hild & Soos future rise rTllSt take place in price:;
cmverted the Canpany' s rrortgage debt and in before they reach the pJint \Johere \o{! shall
the ""'" year issued 4% First M:lrtgage Iloods be paid $I ? I an not greedy - I do not
to the value of O ,EOJ,ox>, This IOOrtgage >ant 18 or Xl% although I shoold very rruch
was SUbseqlBltly redeare::l by the praniun like it."
obtained with the iSSlE of ordinary shares :in
1'lJ5. Mr IAmdas and other shareholders ..... pranptly
rewarded; for 1879 a $I dividend was peirl,
Flnancing the large enterprise which the next year g:(, tren 14%, and the canpany
Canpmy had plBnned was difficult - the progressed arazingly for llB1ly years until the
rail...ay to Huelva had to be built, a pier 193) sltlnp. Little was earned fran the nrines
coostructed, dans and ""rlafups built and the in Sp:rin after that altlnJgh, 00ng to wise
mine developed and equipped. Finally, new fimncing, useful profits for shareOOlders
00using was needed for expatriate staff and were earn::rl fran other 0ClUt"CeS, as recorded by
the ~ \o,Qrkforce . A groop of \oQrlc:i.ng Harvey(32) .
Directors tmder Hugh M3thesJn controlle:l the
day to day affairs of the Canpany - it At the A(}1 of 189:), ...,., the first dividend
consist.ed of Helnrich !betsch, Dyes of the was declared, a Mr G Ibniltoo said:
Breren Penk and ll:Iwin Clark of M.ssrs Clark,
Punch3rd & Co, the railway constructors . "In reviewing the ~ of our C'.anp:my, I
have note::i very carefully its progrec:;s and
TIE-e was widespread oceptidsn about the develop1Blt during a period ...,., disaster
prospocts of the C'mpany fulfilling the claims was oveNJalmi..ng us on all lExis, and
nEde in the prospoctus and, although the locking bock 00 all this to the care and
Olainmn gave glMng rep::>rts of progress at attentioo rranifest for our interests by the
the annual shareIxllders rrEetings, confideoce firm of f>tIt::hes:II1 & Co , wOO , if I en rightly
8ITDIl8 shareholders declined - one shareholder infome:l , provide:1 IIOre than a millioo of
jX)inted out that IIDre rroney had gone into the rooney ..men it was wanted ..•• I think,
mines than lIBIly Gernan States pos.geSSed! A therefore, I shall only be expressing the
""ll-l<na.n Pelglan minIDg engineer, M Julian general feeling of this rreeting in
Ierby was engaged to provide an indepefKient proposing a cordial vote of thanks to our
asse5SlHlt and his rejX)rt did s:xrething to Olai.rnan and his finn . "
restore confidence.
Mr t-ht;hegJn, in replying and a::kncMledging the
At the A(11 for 1879, a Mr IAmdas said: canpl.iIrent, said:

"I and others wuuld be greatly interested if "I can only say, gentiEJl'ffi, it was a great
~ could be informed when we reaoonably my trial to us, in ccmroo with yourselves, when
expe::t .serre return for our outlay . Like year after year passed and heavy and

- 98 -
in:reasing experditure >as incurred without
any apparent satisfactory result ." A new ~y , Rio Tinto Patiro SA (RTP) """
fonred in 1966 to demop the Cerro Colorado
later . in le::6, the sharetclders wanted to dejXlSit for both gold fron the gossans and
vote £5 ,0)) in excess of the Directors' copper f ran ~f]ilyry . This canp:my f s
ordimry eroitJrelts "for the fine way in which _Idees """':
they have J1'BIl3gErl our bJsiness". Mr Keswick
was then ChriITmn and he expressed his awr 5st
gratitule rut said that the Board could not Patiro Group (Canadian) 4(Jt
see its 'tfdy clear to accept the offer . RT2 st

!AIring the period that 1m: controlled the In 1970 ClMIT IlEI"ged with the larger SIBffi.sh
mines there ""'" 6 D-einren, 12 Gel&al cooq:eny . lhim Expl osivas SA, to form Unioo
J1magers and 2 Interim J1magers. E'lqJJ.ooivos Rio Tinto SA (m) . In the late
197CS Patiro withdrew fron RTP which was
renared Rio Tinto Minora (RTM) . RTM acquired
ERrs rretal mining interests , RIZ later
H M I1ltheoon 1873-98 invested rrore JJJ:Xley in RIM and the
J J Keswick 18':6-1~ _Idem today (I ga;) are:
C WFielding 19l4-23
Vi.scrunt Milner 1923-25 00' 51%
lord Geddes 192>47 RT2 4<JZ
lord Bessborough 1947-54
and RIZ no lcnger has any interest in F.RI'.
Gel&al J1magers

MWCarr
Trew Prebbles
A Blechyrxlen
J (sborne
WRich
WAQu-Iyle
1_
1874-79
1879-<l5
IBBS-aS

1889-1!ID
1!ID.ai
N Kennedy * 1'lli-07
WJ Bro.ning Im.27
P S O:Juldrey 1927- 32
F WCooper 1932-34
GWGray * 1934-35
A Ilill 1935-41
AT G:ugh 1941-:>l
C RJulian 1951-54

• Interim J1magers
en aJ June 1954 negotiatioos ""'" canpleted
fOl" the sale of __thirds of the SIBffish
asgets of RTC to a Spmish finarria1 groop for
£7.67 millioo. The SIBffish banks JBrties to
trese negotiatioos ~ the Bancos de BilOOo,
de Viocaya , Central , Exterior and Urquijo,
together with the Baoco Fspeool de Credito and
the Baoco Hispmo M>!rlcano. A new canp3y ,
CanJmria E".sJ>loola de Minas de Rio Tinto SA
(rnRl') """ fomal with the abore as
_Idem and with 1m: OOlding one-third of

_tor
the equity. In 191i2 1m: IlEI"ged with the
Coosolidated Z:i.n: Corporation to form the Rio
Tin~ Corporatioo WI (RT2) which
held the interest in ClMIT.

- 99 -
Appendix 8 uncertainty asscciated with "srd<e farming"
am special diffiOJlties in assessi ng
lNI'IRCtMNI'AL - lAND, KR!SIRY AND FAI<Mlt{; caIlpffiSCitioo for tree damge.

The arm of land acquired by RIC was 1, 9Xl Fran 1800 to 1'XJ7, inclusive, RiC J>rld 3.7
re:tares (4, J\ll acres) but it """ nustly millioo pesetas canpensatioo. To redoce
barren and, according to the Goverrm;nt continuing liability, the canpany bought land
inventory of IBiD. contained 001y: where appropriate and in this \oay increased
its land l>olding to alnnst 13, J\ll re:tares by
Pine trees equivalent to 4.252 m:5 of \\UOd 1954. By that t.iIre, a groot proportioo of
Oak II 11 " 1,875" II II the land was forest , with oore farm and
Poplar ,elm & acacia " 134"" II grazing aroos - SCIre 2,II.JJ ta::::tares of waste
land, m rrore t:h3n the aroo p.rrclBsed in
In Rrnan t.inEs it is believed the co..m.try was 1873, """ still used by the mining d e _ t s
covered with oak forests but during Ramo for overburden, pyrites 00ap5, dnders dtJDpS
occup3tioo large arffiS were felled to provide and the rail,""y .
dmcool for SJel.ting and darestic use. In
1556, Diego 1Bgad0 observed only very thick As ffirly as 18n the canpany experiJrented with
undergrowth 00 the hills, and in 1634 Rodrigo tree plantings of Pinus narit.ina at Fraties, a
Caro oOOerved the lack of vegetation. statim on the railway to Huelva and 12 kIn
fran Rio Tinto. Focalypts, ..trich had been
\o.ren the Frarciscan brothers visited the arm introdoced to Sj>rln in 1865 by a British
in 178) they remrked on the presence of Ambessador and planted in a &rcelooa park,
evergrea-t oaks and a lack of pines and praisOO ~ intraloced to Rio Tinto in 19:8 by WG
S3nz for planting, a few yesrs arrlier . large Nash, an Australian in charge of the land
areas of pines and 00If! caks. In 1832 Ford de~t, \Jlo obtained tOOn fran Granada and
( _ Appendix 5) referred to the magnifiicent planted tOOn near Zumjo dam. 100 variety
pines on la r-esa de 100 Pinos , ..trich had intro:!oced to Parcelona was Eu::a1.yptus
_ b l y been planted by Sanz fJ) yffirS gloOOlus, kno.m. then as "Ar-tol de fiebre" as
earlier. it was t:lnJght to purify the air and prevent
fever (nalaria). _ planted lIOre
In 1839 there were 440,0:0 pines 011 the lease eocalypts near El Valle in 1914 and in Bella
area. When the Prieto process was Vista in 1921 - there they grew quickly and
intro:loced in 1841. Reni.sa did not hesitate to soon obocure:l the view across the sierras.
fell pines to provide fuel to roost ore and
this was a100 the beginning of the activities Walter Bro.ning , .00 becare generalllBllBgeI" in
creating IIBjor pollutioo. The Spaniffi 19:8, roolised the need to cultivate land and
Goverrm:!nt operatioos after Ranisa continued plant trees if the canpany was to d6T03trate
to use the Prieto Process , limited at that redoctioos in the darraging effects of
tine to roosting 6S,0Xl toones p3 of pyrites emi.ssioos and he oought advice fran Goverrnent
by mine ootp.!t and availability of water. forestry experts and they suggested thet Pinus
pinea was the best tree to plant in the
fu:e R'IC began operatioos, the tonrnge roosted particular corrlitioos of limited soil capping
9JOO increased to l,em tpd, nearby villages , and generally rid corrlitions. In their
notably Nerva , suffered badly and considerable view, eucalypts coold be grawn only in S1Bll
damge to the naturally poor agricultural land areas where there was suitable ooil. In
extended over an aral of 76,((0 hectares , lWl Bro.ning had 120 eocalypt seedlings
affecting 9:lre 1,670 farnErS a.ming 9:lle planted en "","",y land p.rrclBsed by the
ll ,CXXl separate properties. Asses9inent of canp:my the previous year 003!' lfuelva and pine
damge was extretcly difficult and an sea:Is and acorns were sown at the mines .
arbitrary s:::al.e was fixed 00 the tasis of
distance fran the burning teleras - for Sin:e 1'Xl1 the canpany had anployed a Ilme,
exaJqlie, owners of land within a radius of 6.5 Viggo Poulsoo., to nul a farm which it CMIed at
km recieved 5% annually of the value of the Huelva. Bro.ning brought trim to the mines to
land in crop, betwe::n 6.5 and 9.5 km distant advise 00 laM OJltivatioo there and Pool.senls
the caopensation """ 4% and beyond thet advice was to employ a forester, rot a farner .
distance the rate """ negotiated beb.<!en 0.5 As a result of tmt advice , Kai lhsse, a
and 3.0:. Of course there """ the graduate of the Lhlversity of Copenhagen I<IS

- 100 -
~ and arrived at the mires in 1916. were intereste::1 in getting land cultivated.
lIa intensified the planting of Pinus pines , Although the farm at Huel va supplied milk and
using a technique in ....ru.ch seeds ~e oown pnxluce to the rrri.nes, pro:loctioo nearer to the
directly into holes lIBde in lm"ren rocky site offered tenefits and, with the cessation
ground with a spiked lmmer. MIDy yoong of heap roosting, eocouragarent was given to
seedlings died rutfurther sa.1ngs >ere ande srall farms in the rrri.nes area. The rrnst
and the ultinate survi",u has prodoced i.rrqx:Irtant of these was at Zumjo rut it was
hillsides tOOay covered with IIl3ture trees . not lllltil 192) that a najor effort was rrade to
improve it . In that year a long strike
(»en air roasting of oo.ps ended in 19:17 and affa:ted the farm 1;,Qrkers on t:re lb:llva fann
pollution by sulIhtr dioxide was confined to and Kai Ibsse brought cows fran it to Zum jo
t:re stack gases of the srelter. yet claims for and C<JJlJBX€d milk proooction in a:m1eSt,
sn:J<e darrege continued to be "",de and Bro.ning 'Ilv:!n:after it supplied milk , eggs . vegetables
srught advice fran the GoverTJTETlt agricultural and fruit , although it was never a profitable
departnelt in lfuelva. 'Ire investigation by enterprise.
its entaJDlogists sln.e:i that with the
redoctioo of the sul~ dioxide content in
the a~ , nElly lmmful inse:ts had
reappeared and ~ the cause of crop darnge -
they suggested that the situation -.oul.d
corre:::t itself by natural proces.9?S and no
further OOIIpE!1S8tion I<3.S p'lid by the canpsny .

By 1925 S<IIE 3,em hectares had been planted


with trees and 3,CBS hectares were being usa:!
for pastwing geats, sheep amcattle and tree
planting was halted in that year . IntBlSive
planting of eocalypts started in 1m and nElly
varieties were intro:loced. Ccntrary to the
Em" tierdoubts expresse::l by Govenment
foresters , eucalypts have gra.m ....clJ. at the
mines and are now widely gt"CMl throughoot the
provioce, supplying logs to a cellulose
factory at San J1.EI1 del Puerto.

In 1935, as an e:m:lll}' neasure, the canp:u1Y


dispensed with the services of the forester
and did not enploy one again until 1949 and
during that period the plantations suffered,
fran three IlBin causes :

t1rh damge I<3.S done during the Civil I<rr by


fugitives leaving canp fires burning.

Cootroctors anployed to fell trees for fuel


'-"'ld cut da.n the b~ and strongest
trees i.nsteerl of thinning out the ....mk ooes .

Trees >ere trinne:I excessively by charrcel


Ixrrners.

1be lanl d e _ t """ revived in 1949 and


S<IIE I,:m hectares >ere planted with
eocalypts, chiefly &ral.yptus rostrara and
&ral.yptus globulus, betl<Bl 19~ and 1955.

AIBrt fran tree planting, Bro.ning and the RIC


chaiInm of that tina , Sir DBrles Fielding ,

- 101 -
Appendix 9 Appendix 10

F1JNllICIal MINA 1HE BElEEMER S1El.l1'll AND TIS CHRATIOO


1901- 14
Furnace Clm-ge lOOJ - 1889

In Toones Cu% Toones Cu Blast Furnaces

Calcired paJU'ha 7 ,471 ~ . 71 2. 294.3 'Ire bla& furnace feed ""terials were
lKy raw paJU'ha 215 20. 25 43.5 delivered by rail at a J.eveJ. above tre
Crude rrrinera1 4,595 7.78 357.5 clmging floor and dtJJl!l"d into stalls. 'Ire
Qude quartz 28 ,roJ 2.m 581.7 ctm-ge c.aJ1IXX1E!I1ts - ore, linestcoe, silica
Calcired rrrinera1 170,549 6.61 11 , 273. 3 flux , cd<:e. etc. - were stxwe1led into Steel
Calcired quartz ~ , 753 3.72 1, 144.0 .teel harro.s of IiJJ kg capocity . 'Ire
KerneJs rm 9.85 88.6 .teeJharro.s were weighe:l before dlJlljJing their
Precipitate 2,555 15.23 388.1 cootents in froot of the fumoce charging
Copper sIEg 3,988 5.m 200. 2 1lrJlIths; """ tha1 !>JShed tre charJle into tre
furnaces. TIe IlEthxi of charging was seen as
furden 249,825 6.55 16,372. 2 a big in:q>roVaIelt over that used at Furxiicioo
lli>3rta Rrnana , where """ carried tre charJle in
Cd<e 47,467 (= 19% 00 rurden) baskets on their t.ms and climbed a ladder to
dUJql tre charge into tre top of tre furnace.
Cut
Slag , overfl M.ng fran the ~ttlers . ran

_e
t1ltte 1.8,629 31.87 15,494 directly into smll, conical shap:rl , cast irm
Slag 11.8,779 0.1.8 714 pots , carried on _ e d buggies. ;,m,
filled , tre buggies pulled by three IlEI1
to the slag dU11p aloogside the river - !J1.rll of
t1ltte PnxIoced & Expcrted Fran Ht>31"" tJ-e slag was adventi tiously granulated and
lOOJ - 1889 carried away fron tirrJe to t:irrE when the river
\\as in SJEte . TIe ~ed OOggies were
Toones Cu% Toones Cu replaced by foor.......tleeled trucks nming on
narr"", gauge rail track - n.o <Tefl coold then
1895 IlBtte 17,945 34.5 6,191 haOOle tre hauling and dlJlljJing.
1885-88
1st cl.ass mtte 8,314 37.8 3,143
2rxI class rratte 10,942 32.7 3,578 Cawertees
188S-<l9
3rd class ""tte 10,123 22.3 2,257 Initially the converter ~1s were lined with
1885-87 a 4 in layer of firebricks after ....ru.ch '.«XXIen
4th class natte 1,051 21.6 227 forTl'ffs were fitted. A pugged mixture of
silica and clay was sOOvel.led beboeE!l the
1.8,375 31.8 15,395 bricks and fornErS and pressed into place by
IlBl using tlrir MOOs and feet - holes for the
tuyeres ~e JTBde by 1 in dia ro:ls oc.ting as
In 1881 , OOy 3,027 tcnnes of 00rden was fonrers. After lining , the top sectioos
91elted - it contained 13.75% Cu and prodoced (lmds) _e bolted on and tre linings dried
1166 toones of 33.2% Cu ""tte. In 1888, rut, first by firing with \o.OOd , t:hm with
42.<.:83 tcrules \\as srrelted - it cootaired 6.24% cd<e.
Cu and prodoced 8,070 toones of ~ . 8% Cu natte
plus 31 ,(69 toones of 0 .54% w slag . Wh.:!n relining, tre firebricks ~ oot
replaced and only occasional patching of tre
In:xis \o3S needed . The lO\oEI" sectioos of the
lining ~ badly attacked by rol ten iron
oxide and relining I<3S needed after prodocing
only 10 toores of blister copper ! This
called for relining five shells daily and IIll'3t
have been a very derrending operation . SlElls

- 102 -
""'" renvved by cmne am rapidly quen::red 2. Open-air roasting of rupreous pyrites
with water; silica was crusi'Yad and IXJgga:I with CEaSed in 1g:)7 because all mine outJllt was
clay in a Chllean mill am each relining required for the I'&' Fundicioo Pirita which
required 7,;ro kg of silica am 5JJ kg of clay care into operatim that year .
- silicecus COPJ:et ore was usa:! as far as
poosible am clay """ brooght fran the Seville 3. In about 1911 the linings for the
area. cooverters \o.ere changed fran acid silica to
rosie rmgnesi te. using bricks .
A newly lined converter ooold mId 3 tames of
natte and its ca{acity incr6'lSed to 8 toones In 1908 the low grade fum3ce natte containing
_ t e l y before relining . Omging the 16 to 18% Cu """ first srelted in canbination
45-SO% OJ ITBtte was by JTEaIlS of an 8 toone with the last of the roasted ores am the
capri.ty ladle; copper precipitate was added furnace charge .as:
after the converter had been slagged .
Roosted ore
.
6,712 tames
Cruie ore 1,212
.
In 19)2, the first full yEm" of operations, Roosted quartz 5,956
.
the blast furnaces srel ted : Cru:Ie quartz 16,696
.
No 3 precipitate 9,))2
.
Toones Cu% Tames Cu Oonverter slag 36,863
.
l..o.-; grade rratte 41,106
.
Crude pyrites 27 I 719
Roosted pyrites 63 ,071
5.54
6.02
1,400. 2
3,796.9
Flue dust
Li1Testone
16,8n
5,660 .
Rich slag 312 )).78 96.0
t-btte 46 45.07 21.0 140,379 tames
Copper precipitate 6,372
Flue dust 4ffJ
48.14
5.56
3,067.5
26.1 13,2BS .
(= 9.46% on burden)
97,'Bl 8.75 8,487. 7
The converters also nalted 1,JJ4 tames of No
13,689 (= 14,1% on burden) 1 precipitate am 74 toones of scrap copper.
prroocing a total of 14,592 toores of blister.
Slag prodoced 87,547 0.68 595.3 assaying 98.17% Cu, am 5,&>3 tames of slag.
No 1 blast furnace ""rked for 6182 hours; No 2
The converters prcdoced: for 4fJ:b hours and No 3 for 5482 hours, for an
average of 210 toones of l:urden srelted IE"
Blister copper 7,317.5 98.5 7,207.7 furnace day . 1474 cooverter shells l6'e
White !lEta! 28.2 74.2 20.9 lined , for an average of 9.9 tannes of blister
Flue dust 1,147.0 8.43 541.8 . .I
per lining

The analysis of blister copper for February of Following the success of Pierce and Smith at
tmt year was: the Ihltinvre Copper Stelting and Rolling
Qnq:any with nagnesite brick lining in 1909,
Cu 98.7% RIC began to use soch lining in 1911. For
Sb O,OIl! the efficient \ooQrking of the tBsic lined
As 0,= converters, good quality silica flux was
Bi 0.0026% required , certainly equal to that used
Au
Ag 45 .0 "
. .
7.7 gn per tonne previcusly in the silica lining. Be::ause
there was a stortage of silica, the flux was
rmde by mixing decarqx>Sed porji1yry, containing
3 to 4% Cu, with dial:Ese, in the prop::lrtions
Three significant changes affecta:l the n.o to one. The free silica arrnmted to on!y
Fessarer srelter: f:{1%, and the resultant slag was vis:oos,
probably te::ause of the alurri.na content of the
1. A third blast furnace was insta11a:i for dial:Ese rock.
pyritic srelting.

- 103 -
Appendix II

PYRITIC S>lEL1ThG

Furnace Cl1arge 1913

Toones %on turden

Cupreous pyrites 200,600 TI.73


Q.mtz )),685 9. 15
Lirrestooe 13,993 4.17
Clean IIBtte 815 0.24
Cooverter slBg fran
Besserer srelter 28,185 8.41
Flue dust 538 0 .16
No 3 precipitate 474 0.14

Burden 335 ,378

Coke 11,285 3.36

Cl1arge 346,663

OJtJl1t:

M:!.tte 45,328 21.51% Cu

Slag ))3,615 0 .42" "


Flue dust 14,079

Pyrites feed contained ber-> 3 and 4% Cu;


qtartz contained 3.63% Cu, 14.3% S.

- 104 -
Appendix 12

SUMMARY OF PRODUCTION AND MANPOWER DURING THE PERIOD OF RTC OPERATIONS 1874 - 1954

Tons Pyrites Mined Washed Tons eu Employees


Year Sales Local Total Cu % Ore Produced
Treatment at Mines

1874 900 950


1875 932 1, 132

1876 189,982 159 , 196 349,178 1.5 946 3, 169


1877 251,360 520,391 771,151 2.38 2,495 4,152
1878 218,818 652 , 289 871,107 2.78 4 , 184 4,452
1879 243,241 663 , 359 906,600 2.78 7,179 5,439
1880 277 , 590 637,567 915,157 2.87 8,559 7, 126
1881 249 , 098 743,949 993,047 2.75 9, 466 8,364
1882 259,924 688 , 307 948,231 2.89 9,740 ll,851
1883 313,291 786,682 1,099 , 973 2.96 12 , 295 9, 801
1884 312 , 028 1, 057 ,890 1,369 , 918 3.23 12,668 9,003
1885 406,771 944,694 1,351,465 3. 10 14 , 593 8 , 273
1886 336 , 548 I , Oll ,833 1,378,381 3. 05 15 ,863 9 , 017
1887 362,796 819 , 642 1,182,438 3. 05 17 ,813 9 , 986
1888 434,316 969,317 1,403,633 2.95 18,522 9 , 233
1889 389,943 824 , 380 1,214,323 2.85 18 ,807 8 , 955
1890 396 , 949 865,405 1,261 , 274 2.88 19,183 9,050
1891 464 , 027 972,060 1,436,087 2.65 21 , 327 10 , 576
1892 406,912 995,151 1,402 , 063 2. 82 20,017 10 , 260
1893 477 , 656 854,346 1,332,002 3.00 20,887 10,305
1894 498,540 888,555 1,387,095 3 . 03 20 , 606 10 , 288
1895 525,195 847,181 1,372 , 376 2.82 20,762 8 , 761
1896 591,752 845,580 1,437 , 332 2.93 20,817 8 ,71 7
1897 575,733 812,293 1, 388 , 026 2.81 20,826 8 , 697
1898 644 , 518 820 ,882 1,465,380 2.85 20,426 8,744
1899 644,271 1,005,573 1,649,844 2.72 20,230 9 , 377
1900 704,803 1, 189,701 1,894,504 2.74 21,120 10,243
- 105 -
Tons Pyr ites Mined Washed Tons Cu Employees
Year Sales Local Total Cu % Ore Produced
Treatment at Mines

1901 633 , 949 1, 294 ,827 1,928,776 2. 63 21,000 10 , 475

1902 627 , 967 1, 237 , 322 1,865 , 289 2.53 21 , 659 10 , 104

1903 688 , 919 1,229 , 619 1, 918,539 2. 39 118 , 174 21 , 565 10 , 161

1904 672 , 344 1,276,475 1, 948 ,819 2. 34 157,810 21,218 10 , 447

1905 627 , 336 1, 202 , 768 1,830 , 104 2.36 308 ,184 19 , 530 II ,486

1906 655 , 328 1, 268 , 388 1, 923 , 716 2.41 477,843 21,287 13 , 108

1907 641,959 1,265,090 1, 907 , 019 2.42 619 ,814 21 , 251 14 , 22 1

1908 604 , 275 1, 1l5 , 610 1, 719 , 885 2. 27 668 , 477 24 , 256 16 , 465

1909 604 , 799 1, 184 , 188 1, 788,987 2.35 569 , 604 24,364 16 ,873

1910 637 , 020 1, 509 , 745 2, 146,705 2.10 683 , 605 22 , 790 15,740

1911 649 , 215 1,536 , 390 2, 185 , 605 2.14 841,964 21 ,880 15 , 449

1912 698,399 1,708 , 570 2, 406 , 969 2. 18 977,812 25 , 623 15 , 399

1913 652,168 1, 207 , 403 1,859 , 571 2. 19 729 , 099 21 , 400 14 , 604

1914 606 , 252 636 , 570 1, 204 ,822 2. 13 637 , 348 17,544 13 , 709
1915 264 , 455 789 , 767 1, 054 , 222 2. 20 676,163 20,357 14 , 633

1916 279,999 1, 248 , 709 1, 528 , 708 1.98 741 , 387 21 , 385 13 ,869
1917 224,682 1, 156,436 1,381 , 1l8 2. 22 531 , 667 27 , 005 14, 054
1918 141,979 1, 481 , 030 1, 623 , 009 1.95 205,062 23,244 12 , 459
1919 72 , 464 1,343,730 1, 416 , 194 1.85 212,560 21 , 361 11,145

1920 59,464 863,384 922 ,848 1.59 182 , 182 16,294 10 , 396
1921 252 , 517 1,665 , 559 1, 918 , 076 1.37 402 , 548 18,124 7, 996
1922 560,253 1,145,198 1, 705 , 451 1.28 502,993 23 , 397 8, 108
1923 470,989 1, 54 1,092 2, 012 , 08 1 1.28 419 , 331 22 , 090 8 , 154
1924 706 , 794 1, 731 , 995 2, 438 , 789 1. 21 529,605 26 , 132 8, 676
1925 857 ,801 1, 575 ,830 2, 433,631 1. 21 445 , 250 27,370 8 ,817
1926 879 ,1 25 1, 657 , 369 2, 536,494 328 , 131 24 , 751 9, 090
1927 835 ,802 1, 673 ,863 2, 509,665 307,262 25 , 270 9 , 914

- 106 -
Tons Pyr ites Mined Washed Tons eu Employees
Year Sales Local Total Cu % Ore Produced at
Treatment Mine s

1928 857 ,850 1,549 ,878 2, 407 , 728 498 , 426 23 ,670 9,813

1929 981,268 1, 566 ,062 2, 547 , 330 1. 79 515 , 495 25 , 237 10 , 486

1930 800,822 1,446 ,993 2, 247 ,815 1. 94 515 , 203 22,742 10,994

1931 558 ,098 1,242 , 789 1,800 ,887 2.04 413 , 525 22 ,838 10,410
1932 515 ,856 697 ,014 1,212,870 1.83 387 ,673 15,726 9 ,923

1933 701 , 417 567 , 778 1, 269 , 195 1.66 431 , 765 15,695 9,739
1934 636,538 530 ,374 1,166,912 1. 74 590 , 454 11,968 9,584
1935 679, 542 454 , 733 1, 133 , 275 1. 91 480 , 291 12, 833 8,304

1936 656 ,103 247 ,352 903 , 455 1.49 379 , 089 12,192 6,757
1937 898 ,499 255 , 355 1,153,804 1.43 346 ,744 9,354 6,629
1938 951,170 167 ,357 1, 118, 527 1.45 252 ,460 8 ,721 6,490
1939 686 , 222 141,848 828,070 1.37 266 ,181 6,667 6,848
1940 451,840 277 ,344 729,184 1.31 171 ,403 4, 728 6 , 755
1941 181 ,884 165 ,049 346 , 933 1.43 111,663 4,650 5, 252
1942 191,989 219 ,381 411 ,370 1.35 121,709 6, 756 5 , II I
1943 265 , 292 248 , 186 513,478 1.12 75 , 567 7,808 5 ,579
1944 157 ,668 233 ,307 390 ,975 1.28 78, 695 7,634 5 , 587

1945 302 ,869 162 , 244 465 ,11 3 1.1 5 96,290 4,606 5,118
1946 360 ,755 175 , 697 536 ,452 1. 08 149,328 6 , 594 5, 362
1947 476 , 774 118,839 595 , 613 0. 99 89 , 359 5, 742 6,570
1948 517 ,094 132 , 200 649 , 294 0. 93 204 ,047 5, 428 6,386
1949 526 ,886 145 ,690 672 , 576 0.89 190,551 5, 720 6 , 752
1950 627 , 237 161,072 788 , 309 0. 88 172 , 223 6,107 6 ,683
1951 676 ,889 149 ,050 825 ,939 0.90 281 ,947 5,145 6,944
1952 739 ,1 71 153 , 723 892 ,894 0.86 233 , 583 6 ,008 7,358
1953 576,537 173,1 65 749,702 1. 00 142 , 669 6,1 82 7, 513
1954 648,8 16 157 , 283 806,099 0. 92 168 ,471 5 ,451 7,916

- 107 -
1. Avery D. Not on QJeen Victoria's birthday: 14. Rw Figueroo Ra.:x! . Minas de Rio Tinto:
the story of the Rio Tinto mines (Lax!oo: estu1ioo oobre la explotacion Y e1 beneficio
Coll:in.s , 1974), 464p. de rug minerales (Corum, 1958).

2. TI-e mineral ..ruth of Huelva: being an 15. Rw Figueroo Ra.:x!. Ibsayoo oobre Ia
illustrated article on the history of tbis historia de las Minas de Rio Tinto (MWid,
district fran the earliest tines. Min. J., 1859).
Lond. , vol. M, Ie:¥., 153, 171 , 193, 233, 255,
193, 311, ?1'6, 401 , 457, 478. 16. 100ms JooeIiI Lee. Note; 00 the mines of
Rio Tinto (Lax!oo: \.6rren Ihll, 1865).
3. Allan J.C. Cmsiderations on the antiquity
of mining in the Iberirul Peninsula. O:cas. 17. Allan J.F. TI-e pyrite; deposits of the
Pap. R. Anthropological Inst. no. 27, 1970, provioce of Huelva. Trans. N. Engl. Inst.
42p. Min. JJECh. Fngrs, vol. 37, 1007-<38, 2751.

4. Illi3oco A. Wzoo J .M. and Ruiz D. Excavac- 18. Pa1Jrer R.E.. Notes 00 sare aocient nrire
iooes arquelogicas en e1 Cerro SalOlIXl equiprents and systans. Trans. Instn Min.
(Riotinto, fuelva) (Sevilla: Uriversidad de ~tall. , vol 36, 1926-27, 299-336.
Sevilla, 1970) , 39 p., 22 plate;, 382 figs.
19. Bernaldez Fernando. ~talurgia del cobre
5. Blaoco A. and Wzoo J.M. Pre-llrnan silver en Rio Tinto. Revista Minera, vol. IV,
mining at Rio TInto. Antiquityu, vol. 43, r-Bdrld, 1853, 252'{>5.
June 1%9, 124-31.
20. Tylecote R.F. A history of rretallurgy
6. Coort:ney L. F. Mining and treat:nEnt of (Lax!on : TI-e ~tals Society, 1976), 29.
copper are at Tharsis, Sprin. Min. Proc.
Iffitn civ . Fngrs, vol. 12.S, 1M. 126-44. 21. Willians D. TI-e geology of the Rio Tinto
Illires , Sprin.
7. Gt:ruala y Tarin Jooquin. ~p:ioo vol. 43, m~~
fisica , geologica Y minera de Ia Provincia de
fuelva (MWid: Canisioo del roBpa GeologiCO, 22. Rickard T.A. With the geologists in
Provi.nd.a de Htelva, 1BBS), 2 vols . Spain : the Rio Tinto mines - Ronan slags and
ancient mining impl""",ts. Fngng Min. J . ,
8. Wzon J M Tartessos y Ia ria de Ib:!l va. vol. 124, July 2 1927, 16.
Seminar Argueologica Salamoca, 1%2.
23. Nash W.G. The Rio TInto mine, its
9. 2 Orronic1es, 9,13 ; 1 Kings, 10,22. history and ramoce (Lmdoo: Sirrkin. t-E.rsta1.1 ,
IBnilton, Kent & Co .. lW1).
10. Mgado Diego. Letter to King Fhilip II,
1557. (Held in Spanish Archives ; reproduced in 24. Percy J. ~tallurgy: the art of
reference IS, page 118). extracting rretals fran t1E.r ores - Si1 ver and
gold-Part I (lnndon : JOOn M=ay, 1880), 561.
11. Cara Rcrlrigo Caro was a farnJS JXlet and
archaeologist 1iving in Seville in the first 25. G:malez. Registro de minas de 1a cOr(na
half of the 17th century; the source of tbis de Castilla (r-Bdrld, 1832).
qootation in his rrany p.!blicaticrn has not
been establi.sred - I'd. 26 . de 1a E'.s::osura Luis ~ Ia f1.D1dicion de
las m:inerales de las minas de Rio Tinto.
12. Strabo The geograIiIy of Strabo with an Anales de Minas, vol. 3, 1844/45 .
English transIatioo by l-brace Leooard Jeres
(Canbridge , r-Bss . : Harvard Uriversity, 27 . de Prado Casi.aoo Minas de Rio Tinto:
1%1-1%9). r-Boorias (r-Bdrld, 1856).

13. AocioIa Antonio and de Cassia Eloy. 28. Checkland S.G. TI-e Mines of 1lErsis:
M:nnria sobre las minas de Rio 1'into (t1ldrid Ronan , Freoch and British enterprise in
1856). ~(Lax!oo: George Allen & lhwin, 1%7),
2ffi p.

- 108 -
29. Parten D.B. The Cornish bEan engine
(Truro: D BrOOford Parten, 1965), 2B5 p.

JJ. Jullim C.R. tmderground minillg at Rio


Tinto, Splln. Trnns. Instn MID. Matall . ,
<01 49, 1939-40, 237-312 .

3!. Collins J .H. Co tre geology of tre Rio


Tinto mines, with SCflE groeral remrks 00 the
pyritic regioo of the Sierra t-brena. Q. Jl.
goo!. Soc. Lml. , vo!. 41, IffiS , 245-65.

32. Ibrvey C. E. The Rio Tinto Canpmy: an


e::::oo:::mic history of a leading internatiCflBl
mining cax:em 1873-1954 (Penzance: Alison
Iblge , I~I) , 39J p.

33 • Taylor J. H. and Whel1m P. F• The leaching


of cupreous pyrites and the precipitation of
cop~ at Rio Tinto , S~. Trans. Instn
MID. Matall . , vo!. 52, 1942-43, 35-96.

34. fbtts H.R. Prese!lt-<lay srelting proctice


at Rio Tinto, SJlrin. Trans. Instn Min.
Matall. , vol. 38, 1928-29, 421- JJ .

35. fbtts H.R. Notes on converting l~e


rratte at Rio Tinto. Trans . Instn Min .
Matall. , vol. 38, 1928-29, 431-49

.:6. Fbtts H.R. Further notes on converter


practice at Rio Tinto Trans. Instn Min .
Matall. , vo!. 57 , 1947-48, 337 75 .

37 . Ibtts H.R . and lawford E.G. Recovery of


sulIfur f ran srelter gases by the Orkla

_rk
process at Rio Tinto. Trans. Instn Min .
Matall. , vo!' 58, 1948-49, 4'lJ-462.

38. Pryor R.N. Mining of cupreous


ores at Rio Tinto, SJlrin. Trans. Instn Min.
Matall. , <01. ffi , 19s9..((), 661-a5.

39. Collins J.H. Co tre ecooonic trealJIBlt


of law-grade copper ores . Trans. Instn Min .
Matall. , vol. 2, 100:>-94, t.-57;59-75 .

- 109 -
acid~ 1, 27 bullring 48
II waters 1),40,41 ,48 burden , pyritic SJel.ting 74
adits Furxlicicn Pirita 75
<loatro fblims /I)
Sonta Perbara 22 Caddick, Arthur J 73
Son Illis 38,/1) calcines
Son Pe:!ro /I) " IE>lChing/~ ]),34 ,44
Son Roque 22 ,/1) Calle Palos 7
Sonta Perbara 22 Canpofrio 48, 49
mire 34 Caro, ROOrigo 9
Raren 1, 10 , 11 Cartagena 15
Administrator 22 Carthaginians 1,8
"Alamnes" 28 Cassio, Eloy de 10,33,37 ,3S
Aljustrel Tablets ffi cassiterite 8
Allan J C 6 Cazella 20
Allan J F 11 ,14 CEJTeltatioo , also precipitation 18,21 ,24 ,26
A1reria 5 33,34 ,67
aml.gooatioo 18 II artificial 25 ,211 ,35
anphora 7 II natural 36,63-67
Aociola, Antooio 10,33 II tanks 34
Andevallo 1,59 Central E1ectrica 49,:>1
Angulo, Francis:<> 24 , 25 Cerda . Fabrica de 33
antinmy 19, n " heap leaching groonds 65
Arabs 15 Cerda, M3riano de la 32
Aracena 20,50 Cerro Colorado 2, 10
" Sierra de 2.7 " Retarer 2
Araraque 8 " Salamon 2,6,23
arsenic 37 /I San Dicnisio 2
in carent copper 29 chalcocite 22,57
in Orkla process sulJllur 79,!JJ Chaperrales see snelters
oxidatioo of 29 clmcool 14,33,36,43
artificial cerentation 29 Chackland S G 45
II "disadvantages 35 chlorine 61
Atalaya 3,48 eWers 3)
/I opencast 54-55,57 Civil I<lr !JJ
Augustus 9 classificatioo of mineral 59
Avery D 2,20 Ciarl<, FImchatd & Co /I)
azurite 10 Claus reacticn 79
ccke W, n ,73 , 74
bock filling 42,53 Colaeus of Saros 8
bacterial leaching 66 Collins J H 59,61 ,77
Perbasco heaps ]),43 Collins H F 63
''batea'' S) Colunbus , Ou-istop,er 48
Pella Vista 48,:>1 coocentratioo , p,ysica1 fA
bell~ 5,14 , 22 ,27 ,68 converters 71,77.102
" water--p:?o.ered 35 ,68 Sisbees 71
I'ermldez, FernaOOo 31 ,96 Great Falls 73
Betulia 20 converting, selective n
blast fumace(s) 10 Pierce & Snith 103
" " primitive 14 copper
blowers 69.70 ,72 arsenic content 29
bl C>Opipe 5 black 22
Blun, Thexior 39 refining of 35
Boetis 9 blister I gold & siver contffit n
briquet~ 75-76 detailed analyses 78
bro.n liqoor 44 carbooates 5
Bruce G 39 CE!JBlt 21 ,29,34
Ihltron 10,37 cost of prodoctioo 1869 38

- 110 -
native 5 flotation 74,75
",q;,yry 3, B5 " ccocentrator, copper 74 ,85
pro:hx:tion , RIC SJelters 78 Forbes D 2 ,39
refined , CJ)St Iff/) 38 Ford , Richerd 31 ,95
rosettes 'z:J French trOO!" 25
stcx:k\.ork ore 85 flEl for roasting 27
sulptate, pro::loction 86 " dearness of 33
copperas 18, 20 ,86 furmce{s)
Comi,., boilers ff} Alemnes 28
II engine 40,41 blast 10, 14,27,68,102
II punp 49 circular , water- jacket if)
Cortes 2,3) re:tangu1ar, " " 71
Correlejos 65 ix>;l 5, 13
Cotinas 9 Ibm> de Capel 21
Courtney L F 7 refining 21
cupelling 6 reverberatory 27
OJt-end-fill 42,53 Roman 14
"spleiss" 28 ,35,70

ean",frio 49 Galarosa 20
Mmlsnilla 49 ,71 galleries , R(JTEI1l 11,12,15,33
Raihay 48 Gibraltar 8
South 48 Gcroalo y Tarin, Jaoquin 7,10
Zmajo 49 gossan 10, I3 , I3 ,84
dating, carbon 9 as gold ore 2.),83
" tbmrollrnines::.ent 7 as ircn ore 83
~ 3,9,10,48 Gran Bitania 10,20 ,93
" l..OOe 55 ,56 Guadalcaral 18, 19,20
" opencast 54 ,57 Guadalquivir 8 ,9
Lhlgado , Diego 9,10,18, 20 ,89 GuadiNe 8 ,9
desanbarcadero 7 G~e I-I!tal \.brks 68
~ see srelters "gui jareo" 7
ll:Jetsth , !Enrich 2,39,44 ,61-<>3
" Processes 61-62 Harvey, C E 63
" royalties 62 heBp rcasting see roasting
drainage , acid 1,27 halp leaching 43,61 ,&HJ7
drilling, hand 55 halps , Berbaoco :rJ
Hendersm process 40
earths. coloured 5 !l;,rbert, lady fBria 21
Edrronds, Willian ff) J-erodotus 8
B:lquist process 84 Hill , Alexamer 68
ele:tricity supply 49 Iblortus 1,9
ele:trochenical process 32 roopi tal I<J
ele:trostatic precipitators 79 musing 46
ele:trun 6 !belva 7,37
el Valle 48 rail\009y to 45
env:irome"tt, damge to 31 , 100 RIC p::>rt and pier 45
Esc~ , luis de la 27 Ib>rta de la Cana 15,48
Fspeleta, Alejardro Viviente 27
Esquerra, JooqlriJn 26 IOOrolia 26
Ferdinan:I am Isabella 18 ilneUte 8
ferric chloride 61 ioclined plane 1<J,66
ferric iron redoctioo infrastru:ture 8,45
..;.th sulj:l1ur dioxide 67 iron
..;.th pyrites 67 fran Viscaya 21
ferric liquor 61 are mining 83
ferric sul~te process 63 pig, arsenic content 34
ferroos sulJi1ate 18,86 ocrap for c.erentation 26
Figueroo, Roo see Rua Figueroa srelting 83
firesetting 16 by Arx:ients 84

- III -
.Jaramr , river 49 Moors 1,18
jarosite 5,6,10, 11,15, 18,84 ''troITCl'lgOO'' 63
amlyses 14 TTOrtars, and pestles 6
RIC exploration for 14 fuelle de San Antatio '31
toonage 13
argento-jarosjte 5 Nash WG 20,86,100
plll1l00-jarosite 15 Naya 50
Jillrinez, Molchor 24 Cffiefltation tanks 70
Jdmoon F 63 crushing plant 59,60
Joly M 61 hoop leaching ~
Neolithic 5
Kemedy , Neil 11,56 Nerva , F.hp:ror 22
kernels 35,43 ,68 Nerva , village 25 ,lJ,4s ,ro
rmtte fran 36 Niebla 7,8 , 75 ,£0
North L:xle 39,41 ,54,55--57
Lago 3 ,6
cave 5 ,8 ook 14
Cueva del lago 15 , 26 , ~ , 32 , 48, 56 Q:tiel , river 8
L:xle 55--56 ihIte 10
lagunazo 10 opencasts , ancient 10
las Mill.as 45 ,46 opencast mining 33 , 38 , ~ , 54
I.aurioo 15 at North L:xle 56
lavadora 74 ,84 ,85 at Sooth L:xle 39
lwd overOOrden 12,41,48
anchors 6 Orkla furrnces 76
tllilioo 6 rmtte 76
deficieocy of at R'T 15 process 79
srelting slags 15
lease, mine 25 ,26 ,27 Pa.IJrer R E 11,51
infriIlgaTelt of concli tims 3),31 "papucha" 34,96
survey 25 Patio process 18
Letona , Vicente 24 ,25 ,26 Pen:insular \>ku-s 25,26
line 75 pestles , and ITDrtars 6
kiln 75 Ihllip II 18
milk of 80 Fh:lenicians 1,6.7,8
linEstone 75 ,83 shards 7
l ocarvtives 45 ,55 pier , Huelva 40
WzooJM 8 pigrents 6
pillar and stall mining 33,40,41 ,51
M>::kayJS 46 " robbing 42
nelachite 10 Planes 22
rranganese oxide , ore 61 ,62 CanjEnia de los ~ , 32
Mmsfeld 22,28 Fabrica de l os 32
Marasrrilla dan 49 , 71 L:xle and mine 11,57
Martinez M:trcos , Jose 24 ,26 srelting furnaces 22 , 26
Matheson, Hugh 2,39,55 poI]i1yry 6,10,40 ,85
rratte Pozuelo 37
fran kernels 36 Potts H R 73,74,80
cooverting 71 PrOOo , Casiano de 32
roasting 36 precipitation see CE!Te1tatioo
.rul"""t 68,71 Prieto , Felipe 29,3) ,32 ,33
srelting 36,68 process 29 ,3),33 ,43
Modina , Bartol"'" 18 prospectus (RIC) 39
Mosa de los Pinos 46,48 ,83 proustite 18
''netal blanquillo" 19 pueblo la Mina 23 , 24 , 27 , ~
Miaja y Plngarroo, Ja;e 26 Rio Tinto ~ , 42
mining, Raran 10, 11 , 15 Puerto Rubio 2
in North L:xle 56 PIJJl>3
in Planes 57 brooze tIJ,66
_ p = 76 centrifugal 66

- 112 -
stainless steel 67 Arnments factory 21 , 29,37
CDnlliIl 49 transport of copper to 37
shafts
pyrites Albertc 51
classification 59 Alfooso 51
cupreous 22 Alfredo 53
oxidation 8 &!uardo 51
for acid prexloctioo 37 lliillerno 49 ,53
pyritic smelting 72-76 I.re Inocentes 38
Mrin (M3estro) 41
quartz 73 Robertc 53,55
mineral (fJ, 69 Raoon 12,15,16
Q.Jebranta Huesoo 49,58,85 San Dionisio 51
Santa Am 27,38
rail...ay 3,37 ,40,45 Santa Barbera 22
ballast 13 Victoria 41
Carmission to stu:1y 37 No 6 51
rninfall 108,49 9Jee, Robert 20,24,91
reafforestation 23 shovels, stean 54-55
regenerated liquor 61 silver 5,6 ,12.18,19
Rerrisa, Morquis de 24 ,27-32 Ims 8
Rich, Willian 53,63 ore 5
Rio Agrio 26 smelting, Raoon 14,15
Rio Tinto Fstac.ioo 46 sintering 74-75
hanlet 20,23 Sjohjelm see Wolters
l'l"blo :u slag
roods 14,;0 arcient heafS 9,10
roosters , pyrites for acid plant 8S tonnage 13,14
roosting bun 5
cuprecus ore 22 ,69 copper STElting, discs 12
heap 27,43 ,44 ,61 ,63 lead " 12
fuel required 27 silver" 12
IlBtte 22 smelters
opetHdr, prohibitioo 3) Bessemer 70,71
Raoon adits 10 ChararraJes 25,32
furnaces 14 o..m Avon (Port Talbot) 62,68,69,Tl ,f'h
galleries 11 ,12 ,15, 33 ~os 22,33,36
mi.n:ing operatioos 15 Fundicioo JhJerta Raoono 68,69,71 ,85
see alro Raoon miniIlg Fl.I1dicion Mina 68,69
occuIlltion 9 Fundicion Pirita 72-76
shafts 16 smelting
slags 9 aocient slag 28
lead content 15 calcined ore 24
Rarer, Dr 2,39 carlxnate & oxide ore 13,14
Roo Figueroa 10,11,14, 34,39 C6lalt copper 21
Salitre cave 19 cupreous pyrites 33.38.68, 73
Salaron Lode 55-56,85 flotation con:entrates 7lr76
salt 61 ,62 hearth 6
S:m Antooio I..a:le 58 precipitate 70, 74, n
S:m Dionisio 3,10,39,41,51-54 ,85 roasted matte 37
San lbrringoo 63 silver 14
San Juan del !\Jerto 37,:fl Sol"""" King 2
Santa Barbera church 24,108 SfBlt liquor 61
Santana , Juan 26 speiss 19
Sanz, Francisco Toms 21 "spleiss" furnace 28. 35 ,70
scoria! 7 stalactites 26 ,29
secondary enriclm2nt II stEBll ro--er 1,48,49 ,68
selectivity, in mining 40,53 Strabo 9
Seville sulI*rlde precipitation PJ1
Mint 21 sulJirur

- 113 -
elerental 62 ,79
labile 62 , 79
loss in heap roosting 35,61
sulphur dioxide
reduction of leach liquor 67
sulJiluric acid 39,85--ffi
su1Ifrurcus gases or srd<e
anti-srd<e league 44
beneficial effa:ts 43
danage fran ))
objections to 27
srd<e indemities 64
supeqrosrmte 86
Syrroo, Brenton 62 ,63

tanks,lix:i.viation 33
carentation 34
Tarshish 8
Tartessos 1,8
Tejonera 65
"telerasll 27,33,43,44
"terreros" )),44 ,65,(;6
Tharsis 10,37 ,42 ,46,63,65
Thams , Lee 10, 11 ,33,37
lltierras vitriolicasll 29
Tinto river 8
tin-stooe (cassiterite) 8
Tiquet Sjohjelm , Sa.ruel :D, 21
Trigueros 37
t~ Central 57
Chico 45
rmn 40 ,41,53
Salaoon ffJ
South Lode 46
llth 1100r 4O,53 ,ffJ
16th 1100r ffJ
turOO-altemators 49
II bla..ers 72
Tylecote R F 13
Tyre 8
Uri", 10

Valverde 37
Ventooa .:J)
vitriol 24 , 26 ,29
vitriolas '5f}

oashing tanks 43
\ll8.ter supply 15,48 ,66
welfare 25
loheels , water-lifting I1 ,S7
Willians D 13
IIillies , Lynn 15
\\bIters L 1, A), 22,39
\oUCld consunptioo 3)

Zalamea 18,19,25,30,44
Zarnndas Naya ffJ
fumjo dan 49

- 114 -

You might also like