Professional Documents
Culture Documents
Presented by:
Richard Cooper, AM.AIRAH – Air Con Serve
Alek Wcislo – A G O’Connor
LESSONS LEARNT FROM
COMMISSIONING CONTROLS
Richard Cooper
What Affects Commissioning
• Preparation for commissioning should start from the moment you receive a
purchase order.
– You must have this philosophy.
– If you install what is specified and just let everyone do their own thing, the job
will not commission well.
– If you do the above, and you cut costs, you will be lucky to ever get out of the
project.
If you coordinated the trades and make sure what you are installing is engineered
to work, the project will commission faster.
Commissioning time is Money.
Achieving completion on time is good.
So what are the most common problems ACS are finding
with systems that we go to commission?
• DX A/C systems are oversized and cannot control evenly and effectively.
• Pumping equipment is sized so marginally that motors fall of their curves.
• Fans are already at 100% speed and have no room to speed up as HEPA filters get dirty
and PC2 Rooms are not sealed.
• Light load chillers are selected with compressors larger than the smallest compressor on
the duty chiller.
• Buffer Tanks are not installed or are too small on chilled water systems
So what are the most common problems ACS are finding
with systems that we go to commission? Cont’d
• Fans like pumps need to be sized with spare capacity, so be proactive and
size with some spare.
• Be astute get on the builders early, and warn them that they need to seal
the space, door frames, GPOs and light fittings.
• Too much time is being lost during commissioning because people just are
not aware how these areas react.
• This adds cost to everyone involved.
Light load chillers are selected with compressors larger
than the smallest compressor on the Duty Chiller.
• On Primary / Secondary Chilled water systems, the buffer tank must be located in
the decoupling line to work correctly.
• It is normally installed to ride out staging times between chillers starting and
stopping.
Sizing Buffer Tanks on Chilled Water Systems
• The CHW is going in and out too close together, and field supply
is not being taken from the cold bottom of the tank.
• This system did not deliver all of the cold water to the field.
• The final modifications were at great cost, and ensured that
cold went IN and OUT at the bottom, and warm went back to
the tank and back to the chiller from the TOP.
• Please don’t get it wrong.
Primary / Secondary Headers Piped Incorrectly
• Primary Secondary CHW Systems with instruments, are good to commission and will
provide ongoing energy savings.
• Often these days we like to couple the towers together and take advantage of low fan
speed with natural adiabatic cooling to save energy.
• When cooling tower nozzles are not sized correctly for low flow we get dry patches on
the tower fill material and the air bypasses the wet fill and the water does not get
cooled.
• Nozzle selection should be designed to cope with low to maximum flow to allow full
tower optimization and commissioning.
Cooling Towers have an incorrectly sized balancing line
• Although system balance valves may be fitted to multiple tower returns, these rarely are so
precise that water returns are evenly balanced to all towers under all operating conditions.
• The result is excessive water may return to one tower, leading to that tower’s basin
overflowing, while the other tower basin may be depleted and start to draw in air to its
pump suction.
• Because the towers rely on gravity and have little head, the balance lines need to be large
or oversized.
• We are often told to put isolation valves on the tower discharge lines, but this limits the
ability to even out basin temperatures, group operate the towers and adds another point of
failure.
• Why use the controls to fix hydraulic issues that can be corrected by good design.
Cooling/Heating Coils are too close to each other in de-
humidification applications
• Too often we are finding that incorrect selections are being made for
dehumidification applications.
• I have been involved in several jobs now, and when we go to commission the
dehumidification control, we find the cooling coil is often too close to the
heating coil.
• If the heating coil is going to warm the cooling coil by either conduction or
radiated heat, you limit the ability to reach dew point and dehumidify.
• You need distance between the coils for any such system to work.
• The coil arrangement needs the room for the condensate to settle and for heat
not to be transmitted back into the cooling coil.
• Check what arrangement you are getting before you install?
Air distribution is not even, in particular areas with ceiling-
based return air, are over heating, stratification is occurring,
and they are not warming up
• If you deliver air at 8 to 10°C hotter than space temperature, to a room with
a ceiling return air path, even with the best diffusion, the air will tend to
stratify, and you will loose a good percentage of the heat back out the
return air.
• Whenever the room is colder than the supply air, the supply air will be
buoyant and will rise after delivery.
• Cooler warm supply air will have more room penetration and heat the space
better and faster.
• Typically 28°C to 30°C air will work better for a 22.5°C Setpoint.
• Leaving Air sensors following any heating coil are essential for better
control.
ANALYTICS / COMMISSIONING
• Analytics is the hot topic at the moment in regard to BMS systems and Fine Tuning
Mechanical Plant.
• Basically as we see it Analytic Rules are applied to a BMS system to try and find
problems that could be causing plant to run incorrectly or could be wasting energy.
• Analytics come in two forms.
– Part of a BMS system either built in, or an add on to the main BMS software.
– Independent to the BMS operated by a 3rd party and the reads information from a
BMS system using BACnet High Level Interface protocol, or from trend information
written to a separate Windows SQL Server.
– There are a lot of people getting into this you would have heard or seen the term,
BIG DATA.
When coupled with Cloud Storage this can be a powerful tool.
ANALYTICS / COMMISSIONING
We feel analytics in some form will keep moving forward with BMS systems.
Clients may choose to enter into long term analytics contracts with either there trusted
incumbent BMS contractors or select an Independent analytics contractor.
The more Data that is brought into a BMS system the more benefit analytics will be to
the client.
You can’t analyse what is not measured.
Some essential items to be measured for analytics are proving to be.
Leaving Air Sensors.
Even Humidity
ANALYTICS AS A COMMISSIONING TOOL
• When BMS systems are installed on a budget you only get what you pay for.
• The same with Mechanical systems.
• We know of at least 3 significant buildings, in Adelaide, where we have been asked to
review an oppositions BMS, that has been deemed uncommissioned.
• How does this happen, I think we know?
– They were screwed to a ridiculous price,
– The project was design and construct with impossible deadlines.
– The building was occupied before the commissioning was fully finished, access
became difficult
– The list goes on.
• The fact is we were smashed price wise, on all of these building at tender, and I truly
believe this is because we allowed more hours to commission.
• The industry has tried to prevent this from happening by adding the independent
commissioning agent, and in some cases this has been very successful.
ANALYTICS AS A COMMISSIONING TOOL
If you coordinated the trades and make sure what you are installing is
engineered to work, the project will commission quicker.
• Take more time to review plant that is selected that is application specific and
think about the ongoing operation and commissioning.
• Data Analytics is the way of the future and we believe if applied during
construction will improve the whole industry to a level where projects are
commissioned correctly.
MECHANICAL SERVICES COMMISSIONING
PROCESS
CHALLENGES
Alek Wcislo
PRESENTATION OVERVIEW
• COMMISSIONING STAGES
• CHALLENGES
• LESSONS LEARNT
WHAT IS MECHANICAL SERVICES COMMISSIONING
The process focuses upon verifying and documenting that the facility and all of its
systems and assemblies are planned, designed, installed, tested, operated, and
maintained to meet the Owner's Project Requirements.
• Networking
COMMISSIONING PROCESS
• COMMISSIONING PRELIMINARIES
• PRECOMMISSIONING
• ELEMANTAL COMMISSIONING
• SYSTEM COMMISSIONING
• PROJECT HANDOVER
COMMISSIONING PROCESS
PRELIMINARIES
RESOURCES
• Mechanical Specification
• Standards and Regulations
• For Construction Drawings, Schematics
• BMS Functional Description
• Commissioning Procedures - Project Specific
• Commissioning SWMSs – Project Specific
• Equipment Technical Data, fan/pump curves etc
• Fire Matrix
• Commissioning Report Proformas
• COMMISSIONING PLAN !!!
COMMISSIONING PROCESS
PRECOMMISSIONING
• EQUIPMENT PRE-COMMISSIONING
• CONDITIONS PRECEDENT
• Builders Works Complete – zone safe to work in
• MSSBs Commissioned and COC-ed
• Mechanical Works (ductwork, air diffusion installed, piping, equipment installed
• Control Valves, Dampers Point to Point Tested
COMMISSIONING PROCESS
DALT
• Duct Leakage impacts on:
• energy efficiency
• greenhouse gas emission
• system performance
• commissioning progress
• AS 4254.2:2012 Testing of
systems >3000 L/s is mandatory
ELEMENTAL COMMISSIONING
• AHUs, FCUs, Fans, Evap. Coolers etc…
Initial Set-up and Start-up
• DX Systems
• Trendlogs
COMMISSIONING PROCESS
PROJECT HANDOVER
• Final Witnessing
• Handover Training
• O&M manuals
COMMISSIONING PROCESS
COMMISSIONING FLOW DIAGRAM - sample
CHALLENGES
• Fire Matrix
• Fire-Mechanical Services-BMS Interface Testing
• Functional Testing (Fire Matrix)
• Operation of non-HVAC plant and equipment (e.g. Smoke Curtins, gas shutdown etc…)
• Performance Testing
• Stair Press Systems,
• Smoke Exhaust Systems,
• Operation of AHUs/Fans etc…
MANAGEMENT ISSUES
• For Construction documentation not followed by subcontractors
• Working of superseded drawings, equipment schedules…
• Electrician installed wrong size O/Ls, VSDs…
• BMS contractor selected wrong control valves…
• ITPs not followed
• Duct contractor poorly managed e.g. balancing to start now and no registers fitted
INSTALLATION ISSUS
• Poor Workmanship
• Duct joints leaking
• Plastic foil left in ductwork
• Crossovers….Most Notorious
• Pipes
• Ducts
• Control and/or Balancing Valves installed back to front
• Temperature Sensors
• VRF Systems – Piping and Controls Wiring
• CTRL/Balancing Valves
• not enough straight pipe up/downflow
• no ID Tags, poor access to binders
CHALLENGES
DESIGN/ENGINEERING ISSUES
CHW-HHW-CW SYSTEMS
CHW-HHW-CW SYSTEMS
• No branch dampers
DESIGN/ENGINEERING ISSUES
• Commissioning Crew to start on site Not Too Early Not Too Late
• Fire Mode Test Coordination needs to start early and involve ALL participants