You are on page 1of 8

SPE 30343

Design, Preparation, and Operational Aspects of the Society of Petroleum Engineers


First Horizontal Subsea Trees Installed from a Jack-Up
R A Ferguson, SPE and D R Stewart, SPE, BHP Petroleum Ltd, B Holland, SPE, Holland OCS
and A Thompson, Cooper Oil Tool
Copyright 1995. Society of Petroleum Engineers. Inc.
fourth slot, production and methanol injection manifolds,

Downloaded from http://onepetro.org/SPEOE/proceedings-pdf/95OE/All-95OE/SPE-30343-MS/1967023/spe-30343-ms.pdf/1 by Total SE user on 17 June 2021


This paper was prepared tor presentallon at the Offshore Europe Conference in Aberdeen,
5-8 September 1995. and the subsea control equipment. The template and
This paper was selecied for presentation by an SPE Program Comm~neefollowing review of
protection frame were designed to be installed either
information contained in an abstract submined by the author@).Contents of the paper, as sequentially or in one piece, the choice of which was to be
presented, have not been reviewed by the Soc~etyof Petroleum Engineers and are subject to
correction by theauthor@). The material, as presented, does not necessardy reflect any position
determined by delivery constraints.
of the Society of Petroleum Engineers, its officers or members. Papers presented at SPE
meetings are subjed to publicat~onreview by Editorla1Comminees of the Soc~etyof Petroleum
Engineers. Permtssion to copy IS restricted to an abstract of not more than 300 words.
The Johnston field development was 'fast-track', first
Illustrations may not be copied. The abstract should contain conspicuous acknowledgment of gas was produced ahead of schedule and under budget,
where and by whom the paper IS presented. Wrlte Librarian, SPE, P. 0.Box 833836, R~chardson,
TX 75083-3836, U.S.A.,fax 01-214-952-9435.
some 14 months after project sanction. The procurement of
the trees was also 'fast-track', the wellhead equipment was
tendered, design finalised, manufactured, tested and
Introduction installed w i t h 12 months.
The Johnston Gas Field lies in blocks 43126a and 43/27 of
the UK sector of the Southern North Sea, 11 km to the Prior to placing the order for the trees, the operator in
Northeast of the Ravenspurn North production platform conjunction with the tree manufacturer, carried out a
(Figure 1). The water depth at this location is detailed technical review and HAZOP of the horizontal tree
approximately 145 feet. The field was discovered in April concept. Both parties were fully satified that the spooltree
1990 by the 43127-1 well and successfully appraised in July design was the preferred option for the Johnston
1991, by the 43126a-8 well. development.

The field (Figure 2) is formed by a structural trap These advantages of horizontal trees are discussed
bounded to the Southwest by a NW-SE trending fault and throughout this paper, however, the primary advantages
by structural dip to the north and east. The reservoir itself were considered to be :
comprises Permian Lower Leman sandstone exhibiting
excellent porosity and permeability characteristics. Reduced capital and installation costs
Recoverable reserves are estimated to be in the range of 155 Reduced delivery times
to 195 BCF. The gas sales contract requires a DCQ of 53 Reduced size allowing easier handling
MMSCFD for a six year plateau, with a peak rate of 90
MMSCFD. Two wells located near the crest of the Horizontal 'Spooltree'
structure satisfy the production contract requirements, The Johnston mudline spooltree is shown in Figures 3 and
however a third well may be required in the thrd year of 4. The 5000 psi spooltree comprises the main spool body
production. The overall field life is expected to be 13 years. with an integral hydraulic 5-118" production master valve
(HMV), and an integral manual 2" annulus master valve
This paper describes the selection, design and (MAV). The 5-118" hydraulic production wing valve
installation, in this field, of the first horizontal subsea trees (PWV), the 2" hydraulic service wing valve (SWV), the 2"
to be installed from a jack-up. hydraulic annulus cross-over valve and the 2" hydraulic
annulus drilling valve are in separate valve blocks bolted to
Development Plan the main spool body. The tubing hanger is landed within
Two primary development options were considered for the spool body and is ported horizontally to allow flow into
developing the Johnston Field; a "not-normally manned" the production valvcs.
satellite platform or a subsea installation, both of which
would be tied back to the Ravenspurn North processing The production master and the production wing valves
facilities. Evaluation of both these options concluded that provide the main well control barriers in the production
the subsea installation was preferred, due to shorter lead flow path. The well barriers in the vertical bore are
time for fabrication and lower initial capital expendture. provided by two independent, positively sealing plugs. The
lower plug is set in the tubing hanger, the upper plug is set
The Johnston subsea structure contains a three slot within a high pressure cap set inside the spool body above
drilling template, a protection frame incorporating a spare
11
2 DESIGN, PREPARATION, & OPERATIONAL ASPECTS OF THE SPE 30343
FIRST HORIZONTAL SUBSEA XMAS TREES INSTALLED FROM A JACK-UP

the tubing hanger. The service wing valve allows for


injection of methanol between the master and wing valves. In order to deploy the work-over controls system and to
allow changing over the stab plates to production, a work-
Conventional subsea trees are termed "concentric" or over running tool, WORT, was designed. The design was a
"dual" depending on the arrangement of the annular access combined effort between the tree, ROV and control system
through the tubing hanger. During work-over the spooltree contractors. The WORT was deployed on the tree with the
design provides annular access around the hanger. The work-over controls made-up to the tree. The WORT
annulus flow path from surface runs between the included ROV docking points for the ROV to changeout the

Downloaded from http://onepetro.org/SPEOE/proceedings-pdf/95OE/All-95OE/SPE-30343-MS/1967023/spe-30343-ms.pdf/1 by Total SE user on 17 June 2021


completion landing string and the riser down to the tubing stab plates. The WORT was retrieved on the riser.
hanger, communication is then via the annulus drilling
valve and the manual annulus valve. During production the electrical and hydraulic functions on
the tree and on the template are controlled from the
A cross-over line from the annulus is tied into the flowline Ravenspurn North control room using an electro-hydraulic
downstream of the choke, this enables venting of annulus system. Dual subsea control modules are located on the
pressure into the flowline. The actuated cross-over valve template. During work-over the functions are controlled
and a check valve are installed on the line to prevent from a control panel on the rig. At the end of completion
production pressure reaching the annulus. operations control is transferred to production by changing
over stab plates using the ROV.
Wellhead temperature and pressure are monitored between
the production master and wing valves. Annulus pressure is Compared to a conventional subsea tree, the spool tree is
monitored between the annulus master and the cross-over significantly smaller. The height from the wellhead hub to
valves. Pressure monitoring ports are isolated by double the top of the tree is 53.6" and it weighs only 14.75 tons.
block and bleed valves. The size of the tree results in reduced cost, easier handling
offshore and would allow the use of a smaller protective
The tubing hanger lands in the spool body with the main structure. The design of the spooltree as one main,
metal to metal seals above and below the production outlet relatively small, spool and a number of bolt-on valve blocks
being energised by a tapered bore. The tubing hanger is allowed for manufacturing of several components to
precisely oriented in the spool by a key-on helix proceed in parallel thereby reducing delivery time.
mechanism, the orientation aligns the production port in
the hanger with the spool valves but the precision is Running a subsea completion from a jack-up is
required to accommodate the tolerances of a dowhole gauge operationally much simpler than from a floater. No rig
instrument penetrator. Communication to the DHSV is heave offers the advantage of greater control on the
through a pressurised gallery on the outside of the hanger application of weight and torque allowing the use of simple
body. The tubing hanger OD is 12", suitable for running running and pulling tools. No heave also eliminates
through the 13 518" BOP stack. swabbing of the equipment through the stack and riser,
allowing for simple seals to be used.
The tree to wellhead connector is hydraulic, with a manual
over-ride. The riser to tree connector is a 13-518" hydraulic ROV Intervention
collet type. It was recognised at an early stage that diver intervention
during the drilling and completion operations would not be
A high pressure cap seals the bore of the spool body above viable. Although air dwing would have been possible "on
the tubing hanger providing a secondary barrier. A wireline bottom" times were very limited. Installation of a saturation
plug is set within the high pressure cap to provide wireline diving spread on the jack-up rig was impossible due to
access without recovering the cap. space limitations and mobilisation of a dwing support
vessel would have been commercially restrictive. The
A debris cap is installed on top of the tree to protect the re- elimination of diver operations also provided additional
entry hub and the high pressure cap. The debris cap was safety advantages.
specifically designed to be ROV retrievable.
All subsea work required during the drilling and
All manual valves on the tree, including all test and bleed completion phases was therefore designed to be carried out
valves, can be functioned by an ROV. The hydraulic valves using a work-class ROV. The main functions to be carried
have ROV over-rides. All ROV functions are performed by out by the ROV were :
docking a work-class ROV on the ROV interface plate.
Figure 5 shows the multiple docking stations and the tool Observation of subsea operations
interfaces, all locations are clearly identified . Installation/removal of the guidelines
12
SF% 30343 R A FERGUSON, B HOLLAND, A THOMPSON 3

Operating manual valves Three of the tendered rigs were considered suitable for the
Engaging downhole gauge penetrator work, with minor modifications. On the selected rig the
Instalationlremoval of stab plates only modifications required were the upgrading of the
Debris cap installation conductorlriser tensioning system and installation of the
guidelineltugger system.
The ROV to tree interface was recognised as being critical.
The ROV contractor was selected at the same time as the
tree supplier, the two companies then worked in close c+ OVERVIEW OF OPERATIONS
operation to design a ROV-friendly system.

Downloaded from http://onepetro.org/SPEOE/proceedings-pdf/95OE/All-95OE/SPE-30343-MS/1967023/spe-30343-ms.pdf/1 by Total SE user on 17 June 2021


Drilling Operations
A specifk ROV with an X-Y-Z tool deployment unit was The casing programme consisted of 30", 20", 13-318" and
selected, the ROV panel on the tree was then designed with 9-518" strings and a 7" liner. The 30" was supported on the
docktng points and tool interfaces to suit. The hydraulic template, subsequent casings were supported on positive
stab plates were designed by the control system contractor landing shoulders in the wellhead. The wellhead used was a
to suit the ROV. drill through mudline system which incorporated a 13-518"
high pressure housing allowing direct installation of the
Prior to shipping equipment offshore a dry integration test subsea tree.
between the ROV and the tree was caried out. The tool
deployment unit was installed onto the ROV interface panel Drilling operations were carried out using two diagonally
and all ROV functions were performed. opposite guidelines. No surface wellhead was used, the
surface BOP'S being installed drectly onto the drilling
A dummy ROV was built and used to ensure that the access risers.
in and around the template and protective structure was
suitable. The two wells 43/27-51 and 43/27-52 were drilled
consecutively prior to commencement of completion
Rig Selection operations. The operator is very experienced in this area of
Prior to selecting the jack-up rig to drill and complete the the southern North Sea and as expected drilling operations
Johnston wells the additional operational requirements for were completed successfully and on target.
installing a subsea tree were considered. The following list
of specific requirements was generated : Completion Operations
The completion design is shown in figure 6. This is very
Space for a work class ROV system in an similar to the operators conventional platform completion
accessible location. for a Southern North Sea high rate gas well. One change
Minimum height of 13 ft below the cantilever was required as a consequence of selecting the spool tree
deck to facilitate handling of the Xmas tree, test system. The restricted ID of 4.65" through the tubing
base and lifting cap. hanger led to the selection of a 5-112" downhole safety
Space for three 5 ton air tuggers under the valve, DHSV, in a 7" completion. The tubing above the
DHSV was maintained at 5-112" to the tubing hanger. A
rotary, to provide guidelines.
permanent downhole temperature and pressure gauge was
Facility to skid the rig floor and have access,
installed to enable monitoring of the reservoir from the
through the rotary, to the main deck, to permit
Ravenspurn North Platform.
handling of the Xmas tree.
A tensioning system to support a 16"
Setting operational targets for the first completion using a
completion/workover riser with 60 tons surface
mudline spool tree was very uncertain. However,
tension, and a lateral restraint to support the 30"
considering the potential operational advantages of the
conductor.
spool tree an aggressive target of 14 days was set to
Accommodation for 38 personnel in adhtion to complete the well. The completion phase is defined as :
the rig's normal drilling and catering
complement.
Running, cementing and cleaning out the liner
Space for the hydraulic control line control
Running CBL over liner
panel and umbilical(s).
Pulling tieback strings
Large deck area to accommodate the additional
Running the subsea tree on the riser
drilling and completion risers and well test
equipment. Nippling up the BOP
Craneage, both under the cantilever deck and for Running the completion clw TCP guns
working boats, capable of handling the Xmas Perforating and flow testing the well
tree system. Suspending the well
4 DESIGN, PREPARATION, & OPERATIONAL.ASPECTS OF THE SPE 30343
FIRST HORlZONTAL SUBSEA XMAS TREFiS INSTALLED FROM A JACK-UP

In order to achieve such a target it was realised that first carried out in just 11.92 days. As a result of some minor
class performance of equipment and personnel would be problems on J1 completion time was 14.29 days, missing
required. Prior to the start of completion operations, the the target by just 7 hours. However the overall target of 28
operator, in conjunction with all of the major suppliers and days for the two wells was beaten by 1.79 days.
service companies, carried out a series of design reviews,
operational training and teambuilding exercises. Every
detail of contractor interfaces was discussed and agreed. All CONCLUSIONS
contractors shared in the objective of achieving the targets

Downloaded from http://onepetro.org/SPEOE/proceedings-pdf/95OE/All-95OE/SPE-30343-MS/1967023/spe-30343-ms.pdf/1 by Total SE user on 17 June 2021


set and all contractors participated in an incentive payment The design, preparation and installation of two subsea
scheme for target achievement. spooltree systems in the Johnston field was highly
successful.
Completion operations on each well commenced with the
installation of the spool tree. The tree was skidded under The design is innovative and fit for purpose. The lack of
the cantilever and picked by the rig. The tree was then run, significant installation problems reflects on the high
with the WORT installed, on the 16" riser using a three standard of design engineering. The engineering
guidewire system. The tree was oriented on the template by involvement continued with key design personnel workmg
engagmg the guideposts. The work-over control lines were offshore throughout the tree installation period.
made up to the work-over stab plate on the tree prior to
running. Detailed preparation for the offshore operations including,
design reviews, training and teambuilding, contributed to
The TCP guns, completion assemblies and production the successful installation programme.
tubing were made-up and run into the well. The tubing
hanger was installed with an isolation sleeve over the The time from award of the contract to the delivery of the
production port to maintain well control while running. first tree was only 9 months. This short delivery time
The gauge instrument line and the DHSV control line were contributed to the overall success of the Johnston project.
terminated into the hanger. The hanger was run with the
DHSV locked open, communication to the gauge and The spool tree system was highly cost effective, not only in
DHSV was not maintained while landing the hanger. As the capital cost of the trees but in the rig time saving
the tubing hanger entered the seal bore surface control of provided by the systems operational advantages. The total
the DHSV was immediately resumed. cost to drill and complete one of the Johnston wells was
approximately £5 Million.
After landing the hanger a number of pressure tests were
carried out, the ROV was used extensively for opening and Acknowledgements
closing manual valves and monitoring pressure. The ROV The authors wish to thank the management of BHP
was then used to make-up the instrument connection by Petroleum and Cooper 011 Tool for permission to publish
driving forward the electrical penetrator to engage the this paper, as well as to the Johnston Field partners; British
connector in the tubing hanger. Real time monitoring of the Gas E & P Ltd, Brasoil UK Ltd, Lasmo (ULX) Ltd, Hardy
downhole gauge was then possible through the ROV Oil and Gas (UK) Ltd, OD & G Dev Co Ltd, Enterprise Oil
umbilical, via a penetrator on the ROV panel. plc, and Monument Oil and Gas.

The well was then perforated, cleaned-up and a full well The authors also wish to thank all of the Subsea
test performed. Well J1 was tested at a rate of 140 mmscfld, Offshore and Rowan Drilling personnel who contributed to
this confirmed that the 5-112" tubing down to the DHSV the success of the project.
would not cause a significant flow restriction.

The well was suspended with three tested barriers, the


DHSV, the plug in the tubing hanger and the high pressure
cap with plug installed.

The ROV was then used to disengage the work-over stab


plates and make-up the production control stab plates.

The performance of these completion operations was


monitored very closely using the charts shown in Figures 7
and 8. On the 'first well, J2, completion operations were
Downloaded from http://onepetro.org/SPEOE/proceedings-pdf/95OE/All-95OE/SPE-30343-MS/1967023/spe-30343-ms.pdf/1 by Total SE user on 17 June 2021
Downloaded from http://onepetro.org/SPEOE/proceedings-pdf/95OE/All-95OE/SPE-30343-MS/1967023/spe-30343-ms.pdf/1 by Total SE user on 17 June 2021
ACV

FIGURE 4 - SPOOL TREE HYDRAULIC SCHEMATIC


FIGURE 3 - SCHEMATIC OF JOHNSTON SPOOL TREE
Tubing Hanger

Downloaded from http://onepetro.org/SPEOE/proceedings-pdf/95OE/All-95OE/SPE-30343-MS/1967023/spe-30343-ms.pdf/1 by Total SE user on 17 June 2021


5.5" tubing

5.5" TRSV

7" Tubing

Wireline Nipple

Downhole Gauge

PBR

Packer

4.5" Tubing

b
Wireline Nipple

FIGURE 5 - ROV INTERFACE PANEL Perforated Joint


Wireline Nipple
Re-Entry Guide
Perforations

TCP Fish

FIGURE 6 - COMPLETION SCHEMATIC


FIGURE 7 - WELL 43127-502 COMPLETION PERFORMANCE

CBL
PULL TIEBACX STIUNCB
RUN& TLBT TREE co-OR
NIPPLE UP BOP'S
RUN GYP0
RUNTCP GUNS& SWMSZXBLlEB
RUN TUBING& PDHG LINE
RUN & S E I WlRELmE PLUG

Downloaded from http://onepetro.org/SPEOE/proceedings-pdf/95OE/All-95OE/SPE-30343-MS/1967023/spe-30343-ms.pdf/1 by Total SE user on 17 June 2021


SEX PA-
PULL WlRELmE PLUG
SHEAR PBR & PULL BACX
DJSPLACCTUBINGTO D m E L
STAB m O PBX& M - O W
TLBT TUBING & HANG=
PEWORATE& --UP W
FLOW TLBT WEW.
LEAK OF? TEST DKBV
RUN& TLBT TBGHGR PLUG

.,
PULL LANDING IITIUNG
IION,SEI & TLBT HI CAP & PLUG
NrnBOP'S & PULL 16" mm
m s u u DEBI(UI c o r n
PECOvrR G W n v I m x 1
PI(FPdllET0 MOVETO JO1 1

30 25 20 15 10 5 0 0 1 2 3 4 5 6 7 8 9101112131415
OPERATION TlME (HOURS1 CUMULATIVE DAYS

FIGURE 8 - WELL 43127-501 COMPLETION PERFORMANCE

TIMEACCRWEWLOCCING& LLNm
SKDkROM JM,RUN G W E W R F S
PULL D E m m CAP
RUN&TESTTREE
NIPPLE UP BOP'S
PULL H I G H P ~ S U P ECAP
RUN TCP GUNS & SUB MSZXBLlEB

-
RUN TUBING & PDHG LINE
RUN & 8 E I WlRELmE PLUG
S E I PA-
PULL PLUG
SHEAR PBR & PULL BACX
DJSPLACETUBING TO D ~ E L
STAB EJIO PBR& LbM)-OF?
TLBT TUBING & HANGEX
P r a F O I U I L & CLEmJ-m WEW.
SmWEW.INIORBOILDUP
INTIUL FLOW PFRIOD
s m waL (RUN STATIC PLT)
FLOW WLZL (RUN DYNAMIC PIT)
smwm.LINmALsmLom)
P O 0 4 RIG DOWN PLT
LEAK OF? TLBT DHSV
RUN& TEST TBG HGR PLUG
PULL LANDING IITRmG
RUN.8EI & TLBT HI CAP & PLUG
Nrn BOP'S & PULL 1VllI901
INSTALL DE
Bm COvrR
PECOvrRGmDnvImx
PI(FPAIIET0 MOVE OF? LOCATION
30 25 20 15 10 5 0 0 1 2 3 4 5 6 7 8 9101112131415
OPERATION TlME (HOURS) CUMULATIVE DAYS

You might also like