Professional Documents
Culture Documents
1. Office layout: Positions workers, their equipment, and spaces/offices to provide for movement of information.
2. Retail layout: Allocates display space and responds to customer behavior.
3. Warehouse layout: Addresses trade-offs between space and material handling.
4. Production Facility or Plant Layout: Addresses plant, machinery, and equipment’s optimum arrangement.
PLANT LAYOUT
Plant layout refers to the physical arrangement of production facilities. It is the configuration of departments, work centers, and
equipment in the conversion process. It is a floor plan of the physical facilities, which are used in production.
According to Moore “Plant layout is a plan of an optimum arrangement of facilities including personnel, operating equipment,
storage space, material handling equipment and all other supporting services along with the design of the best structure to contain
all these facilities”.
Product Layout is useful if you have a dedicated product to be produced on large scale and the layout applies to both
manufacturing and non-manufacturing operations.
Advantages Disadvantages
◼ High volume ◼ Lacks flexibility in Volume, design, mix
◼ Low unit cost ◼ Boring for labor: Low motivation & Low worker
◼ Low labor skill needed enrichment
◼ Low material handling ◼ Cannot accommodate partial
◼ Low WIP shutdowns/breakdowns
◼ High efficiency and utilization ◼ Individual incentive plans are not possible
◼ Simple routing and scheduling ◼ Large Investment
◼ Simple to track and control
PROCESS LAYOUT
Essentially, a process layout is that in
which there are different departments
equipped with similar equipment
performing the same function within the
department but all different departments
perform different tasks & Material moves
from department to department to
change into the finished product.
A major problem in process layout is that a lot of processed/unprocessed material moves here & there from department to
department creating lots of confusion resulting longer production cycle.
CHARACTERISTICS-PROCESS LAYOUT
Better utilization of machines & equipment, hence fewer equipment & machines required.
Used for intermittent operations.
Comparatively low investment in machines required.
A high degree of flexibility concerning equipment or manpower allocation for a specified job.
Greater job satisfaction for supervisor
Applicable to both manufacturing and non-manufacturing operations.
Specialized supervision is possible.
ADVANTAGES DISADVANTAGES
Flexibility: equipment and personnel can be used where they Lack of process efficiency: backtracking and long movements
are needed & a variety of products can be handheld. may occur in the handling of materials.
Smaller investment in equipment: duplication is not necessary Lack of efficiency in timing: workers must wait between tasks.
unless the volume is large. Complication: of production planning and control.
Expertise: supervisors for each department become an expert Cost: workers must have broad skills and must be paid higher
in their functions wages than assembly-line workers.
Diversity of tasks: changing work assignments makes work Lowered productivity: because each job is different it requires
more satisfying for people who prefer variety. different setups and operator training.
ADVANTAGES DISADVANTAGES
1. Reduces movement of work items; minimizes 1. Skilled and versatile workers are required.
damage or cost of moving. 2. The movement of people and equipment to and from
2. More continuity of the assigned workforce (since the the work site may be expensive.
item does not go from one department to another). 3. Equipment utilization may be low because the
This reduces the problems of re-planning and equipment may be left at a location where it will be
instructing people each time a new type of activity is needed again in a few days rather than moved to
to begin. another location where it would be productive.
CELLULAR LAYOUTS
A cellular layout is a combination of process and product layouts, in which machines and personnel are grouped into cells
containing all the tools and operations required to produce a particular product or predictable family of products.
In cellular layout, we can identify machines that are grouped into a cell that can process items that have similar processing
requirements. A product layout is visible inside each cell. Each cell is designed to produce a part family. A part family is a set of
parts that require similar machinery, tooling, machine operations, and/or jigs and fixtures. The parts within the family normally
go from raw material to finished parts within a single cell.
ADVANTAGES DISADVANTAGES
1. Reduced machine setup times 1. Volumes too low to justify highly efficient high
2. increased capacity volume equipment
3. economical to produce in smaller batch sizes 2. Vulnerable to equipment breakdowns
4. smaller batch sizes result in less WIP 3. Balancing work across cells
5. less WIP leads to shorter lead times
4. Does not offer the same high degree of customization
6. shorter lead times increase forecast accuracy and
provide a competitive advantage as the job shop
7. Parts produced in one cell
8. Capitalize on benefits of using worker teams
9. Minimal cost to move from job shop to cellular
production (e.g. EHC)
10. Can move from cellular production to “mini-plants”
The simplest way for layout decisions would be to compare the total cost of the layouts at various levels of output.
Based on the above information, let us calculate the total cost for all three layouts at the desired volume level of
10000,20000 and 30000 units
(I) At a volume level of 10000 units job shop is the best option as its total cost is a minimum of the three
options.
(II) At a volume level of 20000 units job shop is the best option as its total cost is minimum the three option.
(III) At a volume level of 30000 units, cellular Manufacturing is the best option as its total cost is the
minimum of the three options.
The weekly total material handling cost of the layout will be given by
𝐷 𝐷
where
Cij= Cost per unit per meter of moving material from ith to jth work area
Xij=Weekly number of units material moved from ith to jth work area
In our given case note that Cij=$1 per unit per meter, the Dijs and Xijs can be obtained from the given two grids, rest
of the calculation for weekly total material handling cost is worked out below:
LINE BALANCING
Write the steps of Line Balancing. From the table below, draw the 5 stations facility layout chart. If desired output rate is 3600
units/week then calculate the Cycle time, Idle time, and Theoretical minimum (# of stations) and Efficiency.
Work Stations Predecessor Time (sec)
A - 40
B A 30
C A 50
D B 40
E B 6
F C 25
G C 15
H D, E 20
I F, G 18
Solution:
STEPS FOR LINE BALANCING
Step 1: Specify the sequential relationship among the tasks using a precedence diagram by denoting tasks on nodes and using
arrow to denotes order of tasks
For given case the diagram is below:
D/40
B/30 H/20
E/6
A/40
F/25
C/50 I/18
G/15
Step 4: Decide a primary rule for assigning tasks to work station and secondary rule for breaking time.
Your priority rule may be: Longest Work Elements, Most Followers Work Elements, Shortest Work Elements, fewest Followers
Work Elements
In current case, I am taking “longest task time first” as primary rule and highest number of following tasks as secondary rule for
allocation of tasks to work station.
Step 5: Assigning task to work stations one by one as per rule of step 4 sequentially from station 1 to the last station.
A task goes to the next station if it cannot be accommodated at the current station due longer task time than the time left to
reach the cycle time at current station. Every time a task is assigned, recreate the list of feasible tasks that can be started now.
Repeat the process for all workstations until finished.
The same is shown in the table below for the given case:
Station Task (Allocate Task Time left at Available to Start Tasks (Refer
longest first from Time Station=CT- precedence Chart: Note that a task will
Available to Start ∑Allocated Tasks to be available to start its all predecessors
Tasks in case of Station have been finished)
tie, choose with
highest number
of successor)
CT=56 A
1 A 40 56-40=16 B, C( But Time Left< Task time for all
Tasks Available to Start hence start new
station)
2 C 50 56-50=6 B, F, and G ( But Time Left< Task time for
all Tasks Available to Start hence start new
station)
3 B 30 56-30=26 D, E, F, G ( D can not be accommodated
here so we try to accommodate next
longest task F)
3 F 25 56-30-26=1 D, E, G ( But Time Left< Task time for all
Tasks Available to Start hence start new
station)
4 D 40 56-40=16 E, G
4 G 15 56-40-15=1 E, I ( But Time Left< Task time of E hence
start new station)
5 I 18 56-18=38 E
5 E 6 56-18-6=32 H
5 H 20 56-18-6-20=12
Step 6: Minimize the idle time for stations and decrease the cycle time and compute the output level based on new cycle time
further compute the efficiency of the assembly line
Now, as we can see the minimum of time left at stations is 1 for station 3 and 4 hence, we can reduce our cycle time to 56-1=55
seconds without increasing the number of stations and in that case time left at every station will get reduced by 1 second and
these will be as follows:
Station Task (Allocate longest first from Available to Task Time left at Station=CT-∑Allocated
Start Tasks in case of tie choose with Time Tasks to Station
highest number of successor)
CT=55
1 A 40 55-40=16
2 C 50 55-50=5
3 B 30 55-30=25
3 F 25 55-30-26=0
4 D 40 55-40=15
4 G 15 55-40-15=0
5 H 20 55-20=35
5 I 18 55-20-18=17
5 E 6 55-20-18-6=11
So the alocation of tasks to stations are as below:
Station 4
Station 3 Station 5
D/40
H/20
B/30
Station 1
F/25 E/6
A/40
I/18
Station 2
C/50 G/15
Illustration: Prior to launching a new model, a manufacturing company needs to set up a new flow line which will
produce 1100 products per day. The manufacturer operates 24 hours per day. The assembly information for the new
product is outlined in the table
d) Produce the line design which achieves the required cycle time.
e) Calculate the idle time/cycle and the output level based upon the new cycle time produced in (d)
Solution:
(a)
1
𝐶𝑦𝑐𝑙𝑒 𝑇𝑖𝑚𝑒 =
𝐷𝑒𝑠𝑖𝑟𝑒𝑑 𝑂𝑢𝑡𝑝𝑢𝑡 𝑅𝑎𝑡𝑒
Since our desired output is 1100 products a day and a day consist of 24 Hours =24*60*60=86400 Seconds hence desired
output rate=1100/86400=(11/864) products per second hence
1 1
𝐶𝑦𝑐𝑙𝑒 𝑇𝑖𝑚𝑒 = = = 78. 5̇4̇ 𝑠𝑒𝑐𝑜𝑛𝑑𝑠
𝐷𝑒𝑠𝑖𝑟𝑒𝑑 𝑂𝑢𝑡𝑝𝑢𝑡 𝑅𝑎𝑡𝑒 11/864
(b)
Hence,
(c)Precedence Diagram
B
19
A C G K
42 20 20 30
M
F J 58
19 65
D L
35 46
E H I
17 30 25
(d)Designing Line to achieves the required cycle time: The line can be designed with six stations based on LPT
Now, as we can see the minimum of time left at stations is 0.54545 for station 2 hence we can reduce our cycle time to
78.54545-0.54545=78 seconds without increasing the number of stations and in that case time left at every station will
get reduced by 0.54545 seconds and these will be as follows:
Thus, Tasks A and Task D are allocated to station 1. Tasks, C, B, G, and F are allocated to station 2, Tasks E, H, and I are
allocated to station 3, Task J alone to station 4, Tasks L & K are allocated to station 5, and Task M to station 6.
Station 2
B
19
Station Station 5
1
A C G K
42 20 20 30
Station
Station 6
4
M
F J 58
19 65
D L
35 Station 3 46
E H I
17 30 25