Inspection Report Final SALINTUBIG 2019

The inspection report details an inspection of an expansion of a water system project in Aborlan, Palawan. The report notes the project name, location, contract price, contractor, and date of inspection. It recommends the contractor has completed all works and is subject to a 1 year defects liability period before final project acceptance.

Uploaded by

Anthony Delarosa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
43 views1 page

Inspection Report Final SALINTUBIG 2019

The inspection report details an inspection of an expansion of a water system project in Aborlan, Palawan. The report notes the project name, location, contract price, contractor, and date of inspection. It recommends the contractor has completed all works and is subject to a 1 year defects liability period before final project acceptance.

Uploaded by

Anthony Delarosa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

Annex M-1

Inspection Report
2019 SALINTUBIG
Republic of the Philippines
Province of Palawan
Municipality of Aborlan
December 27, 2021
INSPECTION REPORT NO.001
PROJECT NAME : EXPANSION OF ABORLAN LEVEL III WATER SYSTEM IN BRGY. APOC-
APOC, MABINI AND MAGSAYSAY
LOCATION : BRGY. APOC-APOC/ MABINI/ MAGSAYSAY, ABORLAN, PALAWAN
CONTRACT PRICE : Php 11,681,726.87
CONTRACTOR : CHAD LOURENCE TRADING & CONSTRUCTION SERVICES
DATE OF INSPECTION : DECEMBER 22, 2021
Findings : SEE ATTACHED INSPECTION REPORT.

If there are no defects/deficiencies observed by the Inspectorate Team during the First Inspection, this
will serve as the basis of the issuance of the Certificate of Completion.

If there are defects/deficiencies observed, indicate rectifications needed to be done by the Contractor,
and attach this to the succeeding Inspection Reports until there are no defects/deficiencies observed
that would warrant the issuance of the Certificate of Completion.

Attach Inspection Report(s), indicating defects/deficiencies, if any, observed by the Inspectorate Team
and repair works done by the Contractor. If this Inspection Report shows no defects/failures, this will
serve as the basis of the issuance of the Certificate of Completion.
Recommendations:
CONTRACTOR HAS COMPLETED 100% ALL THE WORKS AS STIPULATED IN THE
PROGRAM OF WORKS AND IS SUBJECT FOR 1 YEAR DEFECTS LIABILITY PERIOD
BEFORE THE PROJECT FINAL ACCEPTANCE.

ENGR. ELBEN S. PATEÑO


MLGU INSPECTORATE TEAM CHAIRMAN

MS. JEANETTE SAYANG, CPA MS. VENUS PHOEBE DELA CRUZ, NURSE
INSPECTORATE TEAM MEMBER INSPECTORATE TEAM MEMBER

MR. RONNEL S. AMBAY, AO4, GSO MR. JONATHAN DANIEL C. PIZAÑA,


MDRRMO
INSPECTORATE TEAM MEMBER INSPECTORATE TEAM MEMBER