You are on page 1of 1

DPWH FORM NO.

77-004-B
REPUBLIC OF THE PHILIPPINES Revision No. 00
CITY OF MANILA
OFFICE OF THE BUILDING OFFICIAL

CERTIFICATE OF COMPLETION

THIS IS TO CERTIFY THAT THE CONSTRUCTION OF THE BUILDING COVERED BY BUILDING PERMIT NO.
ISSUED ON HAS BEEN COMPLETED IN ACCORDANCE WITH THE
APPROVED PLANS AND SPECIFICATIONS ON FILE WITH THIS OFFICE OF THE BUILDING OFFICIAL AND THE
“NATIONAL BUILDING CODE (P.D. 1096).”

THAT THE SAID BUILDING AND/OR STRUCTURE IS READY FOR FINAL INSPECTION FOR THE ISSUANCE OF
THE “CERTIFICATE OF OCCUPANCY.”

NAME OF OWNER
LOCATION OF CONSTRUCTION
USE OR TYPE OF OCCUPANCY
DATE OF START OF CONSTRUCTION:
PROPOSED ACTUAL
DATE OF COMPLETION:
EXPECTED ACTUAL
TOTAL FLOOR AREA (sq. meter)
ESTIMATED ACTUAL
NO. OF STOREYS ACTUAL HEIGHT _
ESTIMATED COST P
ACTUAL COST P (FOR STATISTICAL PURPOSE ONLY)

A. Materials (total cost) P _


1. Cement (bags)
2. Lumber
3. Reinforcing bars (kg.)
4. No. of G.I. sheets
5. Pre-fab structural steel (kg.)
B. Direct Labor (total cost) P
This include compensation whether by salary on contract
Architect/Engineer down to laborers.
C. Rental Equipment if any P _
D. Other cost P _
This includes professional service fee, permits and other fees.

IF CONSTRUCTION IS UNDERTAKEN BY CONTRACT

ARCHITECT/CIVIL ENGINEER SANITARY ENGINEER


IN-CHARGE OF CONSTRUCTION IN-CHARGE OF INSTALLATION CONTRACTOR

PRC REG. NO. CONFORME:


CLASS
TIN
RES. CERT.
ADDRESS OWNER/APPLICANT

http://www.manila.gov.ph