ABSTRACT ESTIMATE
Quantities G + 5 + Tower
S.
N Description NO. L B H Qty Unit Rate Amount
O
SITE CLEARING
1
Surface dressing of the ground including
removing vegetation and in-
equalities not exceeding 15 cm deep and
disposal of rubbish, lead upto 50 m and lift
upto 1.5 m.
All kinds of soil. 80 70 5600.00
EXCAVATION
( 60% lead to shifting & 30 Lift for refilling ) 13036.2 1 13036.2006 Cum 100 1303620.06
0
Volume
PCC FOUNDATION
6
Providing and laying in position cement concrete
of specified grade excluding the cost of centering
and shuttering - All work up to plinth
level :
RCC SUBSTRUCTURE
RCC SUPERSTRUCTURE
8
Reinforced cement concrete
work (with 20 mm nominal size
graded stone aggregate) in
walls (any thickness), including
attached pilasters, buttresses,
plinth and string courses,
fillets, columns, pillars, posts
and struts etc. above plinth
level and upto floor two level
excluding cost of centering,
shuttering, finishing and
574
TOTAL 6991.
VOLUME 70
S.NO
REINFORCEMENT
10 Reinforcement for R.C.C. work including
straightering, cutting, bending, placing in position
and binding including cost of binding wire up to
floor two level including all wastage etc. complete.
699170.00
11 Binding steel
6991.70 Kg 90 629253
BRICKWORK
12 Brick work with well
burnt chimney bricks in
bulls pattern trench kiln,
crushing strength not
less than 25kg /cm2
and water absorption
not more than 20% in
superstructure above plinth level and
up to floor two level i/c
curing etc complete
Cement mortar 1:6 (1 cement : 6 sand) Volume
S.
N Description NO. L B H Qty Unit Rate Amount
O
Total 124295178.084
S.
N Description NO. L B H Qty Unit Rate Amount
O
350 12180350
34801.00 Sqm
400 403600
1009.00 Sqm
PLASTER
15 6 mm cement plaster of mix : Ceiling Plaster
Area
19 Extra for Sand face Plaster 2692.20 2692.20 Sqm 200 538440
GRAND 153856948.084
TOTAL
SAY. 15.38 crores
GST 18%