You are on page 1of 2

FABRICATION/SITE MODIFICATION FOR 11 & 33KV LINE PROJE

Cross arm Danger Borad


Anticlimbing
Sl.No. No.Of Poles Cross arm Per Pole Clamps
Device Clamps
03 modification
1 SW#01 11KV Line 51 51 153 51 51
2 33KV OH Line 172 162 486 172 172
3 11KV Line Phase-II 258 258 774 258 258
VD#02 11KV
4
Line(Additional) 53 53 159 53 53
Total
534 524 1572 534 534

Complated till date


25.12.20 199 199 597 30 30

Balance to be Fabricate
335 325 975 504 504
ON FOR 11 & 33KV LINE PROJECT

Name Plate Circuit Plate


Team for
Clamps Clamps Remarks
Fabrication
Modifiction modification
51 51 Supervisor :01 Need below line tools on basis
172 172 Welder:01 1.Megnetic drill machine -01no
258 258 Skilled people:02

53 53 Labour:03
Present
534 534 Mapower:07

30 30
Every day 20 Pcs of Each clamps will be
fabricated and target completion date
504 504 is 25.01.2021

You might also like