Perform the exercise in Microsoft Project. Do not forget to save your work in laboratory files. A new
product will be launched for JCM Company. JCM is preparing a budget for possible bank loans. The
following table provides the associated activities and their durations. Construct the Project network
Questions: 1. If you will start tomorrow, when will the project be accomplished?
Yes, there is a critical patch in the project network of JCM Company. The critical activities listed are A, C,
D, E, F, G.
The activities that have free slacks are equal to the critical activities of JCM Company. The free slack
activities listed are A, C, D, E, F, G.