EXERCISE WORK MEASUREMENT

OBSERVATION IN MINUTES

ELEMENT 1 2 3 4 5 PR IN %

Check Minibar 1.5 1.6 1.4 1.5 1.5 100

Make bed 2.3 2.5 2.2 90

Vacuum Floor 1.7 1.9 1.9 1.4 1.6 120

Clean Bath 3.5 5.6* 3.6 3.6 3.2 100

Compute the OT, NT, and ST, given an allowance job time of 0.20

OBSERVED NORMAL STANDARD


ELEMENT PR TIME TIME AFJOB TIME

Check Minibar 100% 1.50 1.50 120% 1.80

Make bed 90% 2.35 2.12 120%

Vacuum Floor 120% 1.70 2.04 120% 2.45

Clean Bath 100% 3.48 120% 4.18

TOTAL 9.03 9.14 10.97

SOLUTIONS:

Check Minibar 1.5+1.6+1.4+1.5+1.5= 7.5/5= 1.5

Make bed 2.3+2.5+2.2+2.4 = 9.4/4= 2.35

Vacuum Floor 1.7+1.9+1.9+1.4+1.6= 8.5/5= 1.7

Clean Bath 3.5+3.6+3.6+3.2= 13.9/4= 3.48

Check Minibar 1.50*100%= 1.50


Make bed 2.35*90%= 2.12

Vacuum Floor 1.70*120%= 2.04

Clean Bath 3.48*100%= 3.48

Check Minibar 1.50*120%= 1.80

Make bed 2.12*120%= 2.54

Vacuum Floor 2.04*120%= 2.45

Clean Bath 3.48*120%= 4.18