1omton Tomasetti
Project
Kiwanis Riverview Terrace
400 College Avenue, Adrian MI
TT Project No. C22150.00
Structural Investigation Report
Prepared For
Scott Beltz
ceo
‘Medallion Management, Inc.
834 King Highway Suite 100
Kalamazoo, Mi 49001
Propared By
Kevin Jackson, P.E.
Associate Principal
‘Thornton Tomasetti
330 N. Wabash Avenue, Suite 1500
Chicago, IL 60611
Phone: 312.598.2000
Fax: 312.596.2001
‘August 18, 2022N
iornton Tomasetti
0 EXE
UTIVE SUMMARY
At the request of the Client (Medallion Management, Inc.), Thornton Tomasetti, Inc. (TT) has
‘completed an assessment on whether the Kiwanis Riverview Terrace structure can be
reoccupied. Based on TT's preliminary review and site observations, the existing structure has a
discontinuous lateral load path and should not be reoccupied until repairs can be implemented. In
addition, significant distress exists at the connection of the facade to the floor system.
Possible repair approaches are discussed; however a full building analysis willbe required to
determine the extent and specific detalling of required repairs.
ROUN
‘Thomton Tomasett, Inc. was previously engaged by the Client to provide an assessment of the
building structure and make recommendations as to the possibilty of occupancy prior to andior
during repair of the structure.
TT visited the site on August 1, 2022 to observe visible and accessible portions of the building to
understand the nature of the observed cracking in the precast plank. TT algo reviewed the
following relevant documents as part of cur review, in addition to other documentation provided
by the Client:
* Original Architectural Design Drawings prepared by Francis A. Faulhaber & Associates,
Architects dated February 18, 1972, Sheets 1 through 15.
+ Original Structural Design Drawings prepared by Samborn, Steketee, Otis, & Evans Inc.,
dated February 18, 1972, Sheets S1 through $5.
CUSSION
1 BUILDING OVERVIEW
The Kiwanis Riverview Terrace is a twelve-story senior living facility lacated in Adrian Michigan.
The building i 'L’ shaped in plan with the legs of the 'L’ being approximately 120 feet and 120
feet long respectively. Bath legs are 56 feet wide. The primary superstructure consists of 8-inch
hollow core precast piank floors supported on load bearing masonry walls. Figure 1 below shows
the typical overall floor plan and arrangement of the precast planks. Some of these walls are
transferred to columns at the second floor to create larger open areas atthe ground floor.
Conerete grade beams support the walls and transfer gravity loads to belled caissons,
Page 2of 8
Kiwanis Riverview Terrace ‘August 18, 2022 | Project # €22160.00Tomasetti
—
Figure 1 — Typical Floor Plan
Lateral loads are resisted by both interior and perimeter masonry shear walls. Interior walls
consist of 6" concrete masonry units, and perimeter walls consist of 8" concrete block composite
with 4” brick masonry at the exterior. The design drawings indicate that connections transferring
lateral loads between the floor planks and the walls are made with dowels embedded in the
{grouted joints at the ends of the plank and to the outer most cell of the edge plank where the wall,
's parallel to the wall (Figure 3). No topping slab over the precast is specified, except at the
balcony.
Exterior walls are designed to span vertically between floors for out-of-plane loading due to wind,
Page 9018
Kiwanis Riverview Terrace ‘August 18,2022 | Project # 22150.0032
Tomasetti
Figure 2 - Connections between precast planks and masonry walls.
‘SITE OBSERVATIONS
‘TT visited the site on August 1, 2022. On site TT observed cracks parallel to the span of the
planks of various widths. The observed cracks were primarily observed adjacent to the exterior
Walls, adjacent to the interior walls along the side of the stairs, and in the main corridors. At some
locations the cracks were observed through the plank, and in other locations cracks were
observed at the joints between planks,
Cracks were typically observed from the underside of the planks as they are generally exposed
within the units. At some locations, the carpet was removed, and cracks were observed from
above. in addition to the horizontal nature of the cracks, vertical displacement was also
‘commonly observed.
Cracks were observed at al floors that were visited, however no significant cracks were observed
at the roof level
TT observed the exterior fagade from the ground level. No widespread cracking or distress such
{as bowing of the walls was observed. Localized cracks were observed at various locations,
including the narrow masonry piers located between sets of windows, and around various wall
penetrations near the base of the walls.
Page 4 of 8
Kiwanis Riverview Terrace ‘August 18,2022 | Project #0221800hornton Tomasetti
ieee
Photo 2 Cracks observed at underside of Level 4 plank acjacent to interor stairwell
Page 5 of 8
Kiwanis Rveniew Terrace ‘August 18,2022 | Project # €22150.00on Tomasetti
3.3 DISCUSSION
{In addition to supporting the gravity loads at each floor, the precast plank system serves two
other functions. First it connects the fagade to the building and collects loads applied to the face
of the building from the wind. Second, it takes that load and distributes it to the building's shear
walls that resist the wind loads.
‘Two general phenomena appear to be associated with the observed cracks. The fist is related to
the transfer of horizontal loads that are parallel to the span of the plank. Lateral loads due to wind
‘acting parallel to the plank span are applied to the ends of the planks by the fagade. The loads
then must travel through the planks to the walls that are also parallel to the planks. Since there is
‘no topping slab to serve as a diaphragm, the load must pass through the grouted joints between
planks. The load collected by the planks accumulates to its highest levels at the walls, and the
stiffest walls attract the load in proportion to their stiffness. Its at the floor connections to the
stitfest walls where the most severe cracks have been observed.
‘The second effect is that once a crack forms atthe perimeter wall, it greatly reduces the capacity
Cf the connection ofthe fagade tothe flor system for wind loads applied in the perpendicular
direction, It also reduces the capacity ofthe wall for gravity and flexural loading as the wall is no
longer braced by those fore.
‘Where cracks occur on multiple floors in the same plan location, the walls must span a larger
distance vertically for out-of-plane loads, or rely on the horizontal joint reinforcement and span
horizontally between perpendicular walls at either end. TT evaluated the ability of the wall to span
horizontally based on an assumed area of reinforcement, however, there is insufficient capacity to
resist code required loads in the horizontal span configuration.
‘As described above, the damage to the floor system has reduced or removed the ability to
reliably transfer lateral loads to the shear walls in the portion of the building on which relies on the
damaged plank. Further, the capacities of those walls are reduced by lack of out of plane bracing
the floor would ordinarily provide. Despite the observed distress, the damage is confined to the
diaphragm portion of the lateral system and therefore does not comply with the definition of
‘Substantial Structural Damage in the Intemational Existing Building Code (IEBC). Therefore,
upgrading the remainder of the building's lateral system to current code is not required.
While no distress was observed at the building exterior, the exterior facades remain at risk of
possible failure in a wind event due to the damaged connections to the base building structure.
4.0 NEXT STEPS & RECOMMENDATIONS
‘TT recommends that the building remain unoccupied until repairs can be implemented, TT further
recommends that the previously established perimeter around the building remain in place due to
the potential for failure of the fagadk
Repairs are required to establish a reliable diaphragm capable of transferring loads the planks
into the shear walls, and to reestablish the connection of the fagade back to the floors at each
level. itis anticipated thet tis connection will need to be retrofit throughout the building,
regardless of whether damage has occurred at that location or not.
A full assessment of the building willbe required to establish the full extent of the damage.
‘Access to all rooms and floors will be required to document the full extent of distress. It is
anticipated that the majority of the observation can be made from the underside of the planks,
Page 6 of 8
Kiwanis Riveriow Terace ‘August 18, 2022 | Project # 022150,00iton Tomasetti
however localized removal of carpet or other finishes may also be required. Materials sampling
and testing may also be necessary to establish the existing capacity of various components, such
as the precast plank.
TT reviewed the possibility of adding a topping slab to establish a diaphragm. TT reviewed the
existing caissons to determine what reserve capacity may exist. The available capacity varies,
nificantly and is further affected by the overturning due to wind. At some locations no additional
capacity exists. Therefore, the extent of the topping would need to be limited and likely
‘supplemented with additional chord and collector elements. Another consideration is to avoid
‘adding topping adjacent to existing stair landings and elevators in order to avoid modifications
there. Finally further study is required to evaluate the existing precast for the additional load,
however itis common to add topping to precast plank and achieve composite action and
increased capacity.
‘Stee! strapping can be considered; however it may decrease headroom. Similarly, carbon fiber
bars, plates, of fabric could be utlized to reinforce the diaphragm, Careful detailing for both
systems willbe required atthe interface with the shear walls, and existing offsets and
discontinuities between adjacent planks may create installation challenges.
Yet another option would be to create a series of slots, perpendicular to the span from the top
such that reinforcing could be placed perpendicular to the span and doweled into the walls for
direct transfer of load to the walls. Cutting the slot would require shoring of the precast, and
possible ballast above the planks.
‘Attachment of the exterior walls for out-of-plane loading can be achieved with carbon fiber fabric
anchored into the solid grouted course of concrete masonry located just below the floor line and
adhered to the underside of the planks.
In all approaches, or combinations thereof, further analysis is required to identify the full extent
and feasibilty of repairs.
QUALIFICATIONS
This report shall not be construed to warrant or guarantee the building and/or any of its components
under any circumstances,
Thorton Tomasetti, Inc. (T7) shall not be responsible for latent or hidden defects that may exis, nor
shall it be inferred that all defects have been ether observed or recorded. TT's visual observations
include no specific knowledge of concealed construction or subsurface conditions at the subject
property. Comments pertaining to concealed construction or subsurface conditions are professional
opinion of TT based on relevant experiance, judgment and current standards of practice, however the
actual concealed conditions at the subject property may vary from TT's observations.
This report is based upon information obtained from visual observations of representative items made
atthe time of TT's site visi(s) and from TT's review of the information available atthe time, TT's findings
{and conclusions are subject to change based upon the receipt of additional or updated information.
4, TT's professional services have been performed in accordance with the standards of skill and care
generally exercised by other professional consultants acting under similar circumstances and
Conditions at the time the services were performed. TT's findings, conclusions and opinions are based
Page 7 of 8
Kiwanis Riverview Terrace ‘August 18, 2022 | Project #€22160.00Thornton Tomasetti
on TT's visual observations, review of the available documents, professional experience, interviews
with those knowledgeable with the conditions pertinent to the subject investigation, and sound
investigation practices. No warranty or future performance of the subject property is expressed or
implied findings and conclusions in this report
5. This report has been prepared by TT at the request of the Client strictly under the terms and coneiitions
of our agreement, and is exclusively for the Client's use in TT's evaluation of the subject property. This
report is not intended for use by any third parties and no third party has any right to rely on any of the
‘analysis or conclusion set forth herein. TT has no responsibilty or liability to any third party for any loss
or damage whatsoever arising out of the use of or reliance on this report by any third party.
6. Without limiting any of the above, TT's liability, whether under the law of contract, tor, statute, equity
or otherwise, is limited as set out inthe terms of TT's engagement with the Client.
7. Budget estimates, if included inthis report, are opinions of probable cost based on our experience with
similar buildings and systems, industry-standard cost data, local cost data, and/or discussions with local
Contractors. Our opinions of costs are to be used for budgeting purposes only and to ilustate the
Felative magnitude of the work involved. Actual costs may vary due to weather and time of season,
contractor schedules, unusual owner requirements, phasing, contractor or material availablity and
other factors beyond our control. These budget estimates, unless otherwise noted, do not include
Provisions for"soft costs” such as professional fees, permits, contingencies, ete. or costs for unforeseen
elements involving demotion, asbestos abatement, overtime labor, escalation, ete.
8. To the extent this report includes observations regarding construction means and methods, unsafe
conditions, or safety precautions, they are intended solely to advise the Client of potential deviations
by the Contractor from their obligations under the Contract Documents, and must not be construed as
an assumption by TT of any duty towards the Contractor or any third party, or as an assumption by TT
of any of the Contractor's obligations.
Page 8 of8
Kiwanis Riverdew Terrace ‘August 18,2022 | Project #22180.00