You are on page 1of 2

JASCH INDUSTRIES LTD. Doc No.

JIL/19
Registered Office & Works : Rev. 00, 05.05.2008
43/5, Bahalgarh Road, P.O. Bahalgarh,
Distt. Sonepat (Haryana) INDIA 131021.
Tel.: (0130) 6451517, 6451518, 2232694 Fax: 2230693
Website : www.jasch.biz email : vivek@jasch.biz
Customer Name and Address Engineer Name Vivek Srivastava
M/s Meenu Paper Mills (P) Ltd. Dated : 22-09-2020
Muzaffer Nagar (UP) Visit type (Service/commissioning/AMC): Commissioning
Customer Contact person: Mr. Bhupender Total man days worked: 11 Days
Date of Complaint: 10-09-2020 Attend date 11-09-2020
FIELD SERVICE REPORT
Customer Complaint-
Commissioning of QCS (BW and Moisture) at PM#2
WORK DONE AND OBSERVATION
1 INSTALLED QCS ON POPE REEL AND CONTROL PANEL IN CONTROL ROOM.
2 CONNECTED SCANNER AND CONTROL PANEL TO PC AND SWITCHED ON THE POWER
FOR PANELS AND PC.
3 ESTABLISHED COMMUNICATION THROUGH LAN.
4 INSTALLED ENGINEERING AND OPERATING SYSTEMS.
5 ALL THE SETTINGS DONE TO COMMUNICATE WITH SCANNER AND TO RUN THE SYSTEM
6 AIR CONNECTION FOR AIR HEATER CONNECTED TO SYSTEM. AIR TEMP IS SET AT 60 ºC
7 LED TV DISPLAY IS MOUNTED AND CONNECTED TO QCS .TOWER LIGHT AND ACTUATOR
VALVE ARE MOUNTED ON SCANNER. PRINTER IS CONNECTED WITH QCS .
8 LOCAL SCANNER START/STOP COMMAND BUTTONS, REEL CHANGE SIGNAL, DRY AND
WET END PAPER BREAK SENSOR AND BOTH LAYER BW VALVE A/M STATUS SIGNAL
INSTALLED AND WORKING PROPERLY.
9 MACHINE SPEED, REEL SPEED, STEAM FLOW, WATER FLOW, CONSISTENCY, BOTH LAYER
BW VALVE POSITION, 3RD AND 5TH GROUP DRYER STEAM PRESSURE SIGNALS ARE
CONNECTED TO QCS
10 SCANNER STARTED WITHOUT ANY PROBLEM. ALL MEASUREMENTS ARE MATCHING
WITH LABORATORY REPORTS AND CONTROLS ARE OK.
11 BRIEF TRAINING ABOUT O&M OF QCS IS GIVEN TO M/s MEENU PAPER MILL STAFF.
12 SYSTEM IS RUNNING WITHOUT ANY PROBLEM AND UNDER OBSERVATION.
13 COMMISSIONING OF QCS IS COMPLETED AND SYSTEM IS HANDED OVER TO M/s MEENU
PAPER MILL.
14 AFTER BREAK FREE RUNNING ( FOR ATLEAST 4-5 DAYS) OF PAPER MACHINE M/s MEENU
PAPER MILL WILL INFORM TO M/s JASCH IND. LTD. FOR AUTO CONTROL TRIAL OF GSM
AND MOISTURE.
SUGGESTIONS AND RECOMMENDATIONS
1 MAINTAIN AIR PRESSURE AROUND 3.5 Kg/Cm².
2 MAINTAIN POWER SUPPLY EARTH BELOW 2.5 Volts.
3 ENSURE FLUTTERPROOF AND STABLE RUN OF PAPER BETWEEN DRYER AND POPEREEL.
4 MAINTAIN CONSISTENCY OF PULP ENTERING TO PAPER MACHINE.

Members Present
M/s MEENU PAPER MILLS (P) LTD. M/s JASCH IND. LTD.

Mr. Manish Kapoor ( MD ) Mr. Vivek Srivastava

Mr.Bhupender

Customer Remarks:

DELHI OFFICE: JASCH IND. LTD. 502, BLOCK C, NDM-2, PITAMPURA, NEW DELHI – 110 034
PHONE: 91-11-27356629, 31/ Fax: 91-11-41557311 Email: manish@jaschgauging.com, amardeep@jasch.biz
JASCH INDUSTRIES LTD. Doc No. JIL/19
Registered Office & Works : Rev. 00, 05.05.2008
43/5, Bahalgarh Road, P.O. Bahalgarh,
Distt. Sonepat (Haryana) INDIA 131021.
Tel.: (0130) 6451517, 6451518, 2232694 Fax: 2230693
Website : www.jasch.biz email : vivek@jasch.biz

DELHI OFFICE: JASCH IND. LTD. 502, BLOCK C, NDM-2, PITAMPURA, NEW DELHI – 110 034
PHONE: 91-11-27356629, 31/ Fax: 91-11-41557311 Email: manish@jaschgauging.com, amardeep@jasch.biz

You might also like