Sl Description YES NO NA
1 Are the latest drawing is available?
6 Have the marking pillars been constructed and ready for reference?
Cement - is it approved grade and less than one month old? & Sand - Medium
9
gritty, clean
13 Has the procedure of not constructing more than 5 courses a day been followed?
17 Has waterproofing plaster in case of retaining walls done for external surface?
18 Has a nail been driven to test the strength of joint after 7days of curing?
Signature Signature
Name Name
Client/ Consultant Contractor