Professional Documents
Culture Documents
060-26 _ C Page 1 of 43
1. Introduction
060-26 _ C Page 2 of 43
2. Technical Details
Detail Comment
Std. Horizontal Adjustability ±5mm per rail seat, (±10mm Total Gauge
Adjustment)
060-26 _ C Page 3 of 43
3. Components
Each resilient baseplate assembly consists of the following components:
Part Spec
# Item Description Qty. Comments
No. No.
1 13146 Cast Iron Baseplate 1 EC-K
2 14613 Rubber Baseplate Pad 1 DC-E
3 14614 EVA Rail Pad 1 DC-D
4 2759 e2007 Pandrol e-Clip 2 A-A
5 5720 8mm HVN Insulator 2 BC-H
Only used for lateral
5a 8605 6mm HVN Insulator A/R BC-H
adjustment
Only used for lateral
5b 8604 10mm HVN Insulator A/R BC-H
adjustment
6 12683 Eccentric Nylon Bush 2/4 GC-C
7 10108 Compression Spring 2/4 KC-G
8 12740 Plastic Collared Washer 2/4 GC-C
9 12791 M27 Nyloc Nut 2/4 LC-B
10 12717 M27 Anchor Stud 2/4 LC-B
15385
11 Conforming Shim 1 DC-AB
/IND
Table 2 - Component List
The quantity of these components is dependent on the track radius for curved and
tangent track, but should not be less than four each on curves less than 500m
radius, and for tangents two each. This however will be guided by the instruction of
the client / contract document.
All of these components are easily maintainable, with spare parts being readily
available direct from Pandrol.
4. Installation Methods
4.1. Introduction
This proposed methodology is for the use of a dummy plate assembly to accurately
position the rail alignment and ensure a good quality finish of concrete beneath the
assembly as shown in Figure 2.
060-26 _ C Page 4 of 43
The designs of the dummy plates have the following features:
The base of the dummy plate shall be perforated to prevent water and air from
becoming trapped and causing voids.
The dummy plate is designed such that it accurately positions the anchor
bolts and ensures their verticality and height above the concrete. The
verticality is achieved by mating the external threads of the threaded spacer
bushes with the internal threads of the dummy plate when the threaded
spacer bushes are located through the cast baseplate holes. A rubber O-ring
is fitted to the anchor bolt to seal the gap between the anchor stud and
dummy plate hole to prohibit the ingress of liquid concrete, during concreting
stage. The spacer bush also has an internal thread which mates with the
Anchor Stud thread for centralising and maintaining the correct anchor bolt
height.
The dummy plate assembly simulates the thickness of the final assembly to
ensure correct vertical alignment of the rail.
Note:
A quality assurance check is necessary to inspect all important dimensions. Failure
to check the threaded dummy plates and threaded spacer bush can result in
inaccuracies of the final assembly construction.
Figure 2
060-26 _ C Page 5 of 43
4.2. Surface Preparation (Coating) of Anchor Bolts:
Before installing the anchor studs in the dummy plate for concreting, the followings
are important:
To ensure good cohesion between the anchor studs and the concrete, the lower
part of the anchor studs should be prepared using either of the following
methods. Note that these are recommendations and local environmental
conditions may influence results.
Method A: Slurry
1. Create a slurry mix with crushed stone, water and cement with proper ratio.
Crushed stone aggregate should be clean and of particle size 2-4mm.
3. Dip the anchor bolt for 2-3 seconds into the slurry mix to a depth between 140
– 145mm.
060-26 _ C Page 6 of 43
Method B: Resin
1. Dip the bolt for 2-3 seconds into a polymer resin to a depth between 140 –
145mm. Pandrol recommends polymer resins ‘Sikatop 77’ or ‘Kuna Latex’
water resistant bonding agent. Mix cement to the polymer resins as required
for better cohesion.
A rubber O-ring is made to roll in from the top of the anchor stud till an approximate
length of 121 mm from the top. See Figures 5 and 6. In each case, after dipping in
the cement slurry or resin mixed with cement (as shown in Fig. 4 to 8), the anchor
stud should be allowed to fully cure before use. Failure to follow the above shall
result in loose bolts.
Figure 5 Figure 6
060-26 _ C Page 7 of 43
Figure 7 Figure 8
1. Hole position
2. Hole size
3. Overall dummy plate thickness
4. Plate flatness
Failure to check these positions could result in misalignment of the final assembly
construction.
It is recommended that in straight track, the remaining unused holes in the 4-hole
dummy plate should be sealed in the bottom with plugs and/or strong adhesive tape
to prevent ingress of concrete and avoid uneven concrete surface.
It is also recommended that Gauges be used to check the dummy plate to ensure
the coordinate dimensions of the anchor stud before casting. Figure 9
060-26 _ C Page 8 of 43
Figure9: Typical Gauge for Checking of Dummy Plate
Installation Sequence:
For ease of installation and speed, it is recommended that two men are used to
install the dummy plate assembly; one man on the fieldside of the rail and one man
on the gauge side.
Place the railpad into the railseat of the cast baseplate and offer up the cast
baseplate/railpad to the underside of the rail foot. One man on each side. Ensure
the field and gauge side cast baseplate orientation is correct. Figure10.
Figure 10
Insert the sidepost insulators to field and gauge side. Figure 11.
060-26 _ C Page 9 of 43
Figure 11
Attach the shoulder retention clamps to field and gauge side. They should be
firmly hand tight so the baseplate cannot move side to side. Figure12. During this
procedure ensure that the baseplate is pushed firmly in the direction of the gauge
side. This ensures that there is no gap between the insulator and rail foot on the
field side. This is required to compensate for any manufacturing tolerances of
components and allows the track gauge to be correctly set after casting. For
added security a spacer may be added between the gauge side clip housing and
the insulator.
Spacer
Figure 12
Offer up the dummy plate to the underside of the cast baseplate. The dummy
plate is not specific to field or gauge side; however the flat side should be face
down to the concrete. Figure13.
060-26 _ C Page 10 of 43
Figure 13
Apply machine grease to the threaded portion of the spacer bush and machine oil
to the dummy plate hole and the anchor stud top few threads (4 to 5) for easy
removal of dummy components post concreting. Figure 14 & 15.
Note: ensure no grease/ oil contaminates the portion of anchor stud that is cast
below concrete level. This could prevent the stud from adhering to the concrete
resulting in loose bolts.
Figure14 Figure 15
Align the dummy plate holes with the holes in the cast baseplate and hold it from
both ends. The dummy plate will need a more precise alignment during the
following stage. Figure16
060-26 _ C Page 11 of 43
Figure 16
Push the spacer bush through the cast baseplate and screw it to the threaded
dummy plate holes. It should be mated such that the largest diameter of the
spacer bush should sit flush with the top surface of the cast baseplate. Figure17&
18.
Figure 17
Insert the anchor bolt from underneath the dummy plate and mate the threaded
portion to the internal thread present in the spacer bush till it is completely tight
and secured. This is only necessary by hand. This will set the anchor bolt to the
060-26 _ C Page 12 of 43
correct height desired from top of anchor to surface of concrete after casting.
After the anchor stud is secured push the rubber O-ring such that it touches the
bottom of the dummy plate and covers the dummy plate hole to prevent
ingression of concrete through the dummy plate holes. If using a 2 anchor system
then the opposing anchor studs should be offset and also use plugs on the
unused holes to prevent ingression of concrete. Figure18 to 21.
Figure 18
Figure 19
060-26 _ C Page 13 of 43
Anchor Stud
tightened
completely up to
the top of the
Spacer Bush
ensures desired
Height of Stud
from TOC
Figure 20
Figure 21
Place a protective plastic cover over the anchor studs, shoulder retention clamps
and spacer bushes to protect the components from concrete during pour. See
examples in Figure22.
Figure 22
060-26 _ C Page 14 of 43
Carry out the following checks before casting:
1. Inspect if the external threads of the spacer bush mates properly with the
internal threads of the dummy plate holes and also the thread of the
anchor stud matches with the internal thread of spacer bush to ensure the
Anchor stud is vertical and maintains the appropriate height.
2. Ensure the anchor stud is not contacting any reinforcing bars. If so,
manipulate the reinforcing to avoid stud contact. If the reinforcing contacts
the anchor it will cause a) The anchor to be non-vertical and b) Affect the
electrical conductivity. Figure23.
Figure 23
3. Ensure the anchor stud feels firm and cannot be moved from side to side.
4. Pour concrete up to the bottom of the dummy plate, vibrating as
necessary. Note that experimentation will be required with the concrete
mix to ensure the correct workability, flow and surface finish etc. Figure24.
060-26 _ C Page 15 of 43
Figure 24
After the concrete achieves sufficient strength, loosen the shoulder retention
clamps on field and gauge side to allow for any thermal expansion or
contraction of rail. Figure 25.
Figure 25
When the concrete has reached sufficient strength, unscrew the spacer bushes
using a wrench/ spanner. As an aid to increase productivity during the casting of
anchor studs 12717, Pandrol recommend that the spacer bush can be removed from
the concrete slab surface 3 days after casting. At which time the anchor bolt integrity
within the concrete should be sufficient to allow removal.
Due to the variation in concrete mix and environments, it is strongly
recommended that initial trials be carried out to assure the process. If loose
bolts are found during the normal course of activities then the contractor
060-26 _ C Page 16 of 43
should consider increasing the dummy plate and Spacer bush removal time.
See the below Figure 26 and 27.
Figure 26
Figure 27
Lift the rail to clear over the top of the anchor studs. Detach the cast
baseplate and dummy plate from rails. Timing of dummy plate removal is
subject to the local environment, the concrete mix, and any additives, etc. but
practice adopted successfully to date suggests curing the concrete to
approximately 85% of full strength. Strength of concrete can be determined by
on site tests.
060-26 _ C Page 17 of 43
Ensure dummy plate is thoroughly cleaned and checked with a receiving gauge prior
to re-use.
4.4. Requirements
The following requirements should be fulfilled.
2. The anchor studs shall be placed at the centre position corresponding to the
slotted holes provided in the baseplate, or the zero setting corresponding to
the eccentric bushes in the baseplate.
3. After the concrete has cured the studs must not be loose in the concrete.
4. The top of the anchor stud thread shall be nominally 121 ± 4mm from the
concrete surface. This will allow full vertical height adjustment of the
assembly.
5. The anchor stud shall be able to withstand a vertical load of 60kN for 3
minutes without showing any signs of cracking or spalling.
6. The support area above which the baseplates shall be installed including the
area under which any lateral adjustment may cause the baseplate to be
located shall conform to:
The concrete finish under the baseplate assembly shall give at least
85% bearing surface to the assembly and shall not contain individual
voids greater than 25mm diameter.
The surface finish of the concrete shall be flat across the top of the
bearing area with no discernible gap under a straight edge across any
part greater than 1.5mm.
The surface shall not contain total voids in excess of 15% of the total
area, evenly distributed. Voids with a diameter <2mm can be ignored.
060-26 _ C Page 18 of 43
The difference in height elevation between one railseat bearing area to
the corresponding rail seat bearing area across the track gauge shall be
not more than 2mm from the design position.
The top of slab / plinth shall be parallel to design position of the plane of
the rails to within +/-1 degree unless otherwise stated in the design
criteria for track work, in which case that document will take priority.
7. The top surface shall be clean of any grout/concrete material, foreign or other
material before final installation of the fastening assembly with anchorage at
the final installed position.
8. There shall be no gaps deeper than 1.5mm between the underside of the
fastening assembly and the grout/concrete surface extending for more than
25mm under the assembly at any position around the assembly.
9. The rail shall be installed in the baseplate assembly with no gap between the
rail edge and the fieldside insulator in the railseat, with the insulator hard up
against the baseplate shoulder.
10. The highest level of grout/concrete under the baseplate assembly shall be
used as a reference for any finishing work required.
1. The concrete must have had sufficient curing time before installation is
started. Figure 30.
060-26 _ C Page 19 of 43
Figure 30
2. A 3mm 15385 LLDPE Conforming shim can be used under the assembly to
improve the surface and compensate for any minor irregularities in the
concrete finish. Figure 31.
Figure 31
3. The 14613 baseplate pad is then placed over the anchors, followed by the
13146 baseplate. Figure 32 and 33.
060-26 _ C Page 20 of 43
Figure 32 Figure 33
4. Next, the 12683 eccentric bushes are placed over the anchors into the correct
setting on the baseplate, ensuring the notches on the bush are fully located in the
locators. On initial installation, try to set the eccentric bush at the ‘0’ - Zero
position against the triangular mark as shown below. Figure 34 and 35.
Figure 34 Figure 35
5. A 10108 compression spring is placed over each stud, followed by a 12740
plastic collared washer, and finally a 12791 M27 Nyloc nut. See below Figure
36 to 43.
Figure 36 Figure 37
060-26 _ C Page 21 of 43
Figure 38
50mm 38.5mm
m
Figure 39 Figure 40
The clearance of the internal diameter of the bush allows it to sit on the top face of
the eccentric bush, and also allows its removal post tightening of the compression
spring.
060-26 _ C Page 22 of 43
Figure 41 Figure 42
The nyloc nut is tightened until the bottom of long series socket sits on the top face
of the “plastic height gauge”, when the said top surface of the plastic bush will be at
the same level as the top surface of 12740 collared washer. The length of the bush
assures the spring is compressed to 34.5 ± 0.5mm.Figure 43, showing correct
tightening of the nut.
Figure 43
Note: It is not possible to provide a torque setting due to the variability of the nyloc
nut frictional forces and low compression spring stiffness. The torque required to
overcome the nylon is initially greater than the torque after the thread has been cut in
the nylon. The spring stiffness is so low that a sensible value cannot be determined.
6. Insert the 14614 rail pad in the rail seat then the rail can be placed back in
the rail seat. Figure 44.
060-26 _ C Page 23 of 43
Figure 44
7. The appropriate insulators are then installed on either side of the rail.
Upon initial installation, two 8mm thick green 5720 insulators are used. If
lateral adjustment is needed, these insulators may be changed to
insulators 8604 and 8605 as discussed in Section 6, Gauge Adjustment.
See below Figure 45.
Figure 45
060-26 _ C Page 24 of 43
Figure 46
Figure 47
9. In order to prevent water collecting in the unused holes of the two anchor
system, a plastic baseplate plug as in Figure48can be inserted into the
unused holes.
Figure 48
060-26 _ C Page 25 of 43
5. Clip Installation, Extraction and Insulator Setting with
Hand Tools
The installation of the Pandrol e2007 clip is undertaken using a Pandrol Type D
Panpuller (Part number AE18068), which are available directly from Pandrol / PRT.
Same to be manufactured by Pandrol approved manufacturer. The hook on the
Panpuller should be checked for wear every 6 months, using a Pandrol Panpuller
Hook Wear gauge (Part number AE17170) available separately. Worn hooks have
an increased tendency to slip off clips during installation and extraction and should
be replaced immediately.
1. Insert the clip into the shoulder on the baseplate, with the toe of the clip over
the insulator.
3. Place the hook over the top of the main arch of the clip, as shown in Figure
49, with the foot of the Panpuller on the baseplate, against the shoulder.
4. Take up a stable standing position behind the Panpuller with both hands on
the T-shaped handle.
5. Pull firmly towards the chest until the whole of the straight stem of the clip is
inside the shoulder.
060-26 _ C Page 26 of 43
5.2. Clip Extraction
Clip extraction uses the same tool, but in the opposite direction
2. Place the hook over the main arch of the clip, with the small notch on the
bottom of the Panpuller on the shoulder as shown
3. Take up a stable standing position behind the Panpuller with both hands on
the T-shaped handle
4. Ensuring nobody is immediately behind you, pull firmly into your chest until
the clip is removed
060-26 _ C Page 27 of 43
6. Gauge and Vertical Height Adjustment
6.1. Gauge Adjustment
As standard, the 13145 assembly allows for up to ±3mm per rail seat, using the
adjustability of the eccentric bush. Additional ±2mm lateral adjustment is available
through differential sidepost insulators.
The 12683 eccentric bush has seven settings from -3 to +3. Initially this bush should
be set at 0-zero as shown in Figure 51. The bush setting is indicated by the position
of the triangular mark circled in red.
Note; clips are to be removed to allow for baseplate movement during adjustment via
the eccentric bush. Additionally the same setting should be applied on all the bushes
on a single assembly. If the sidepost insulators have to be changed, remove the clips
as detailed in 5.2 above, replace the insulators as detailed below and then reinstall
the clips as detailed in 5.1 above.
060-26 _ C Page 28 of 43
The gauge adjustment table is found on the 13145 assembly drawing, but is
summarised below for reference.
Pandrol VIPA DRS assembly 13145 allows for up to +12mm vertical adjustment
during the track construction stage or for maintenance of the track. Any height
adjustment used during the construction stage will reduce the amount of height
adjustment for track maintenance.
060-26 _ C Page 29 of 43
Height Adjustment Procedure(Construction)
1. Identify any rail seat requiring height adjustment correction, refer to Section 4.4
requirements. This can be carried out either by:
b) Checking between baseplate 13146 and baseplate pad 14613 for any
visual gaps following assembly build. Identified assemblies should be
unclipped and clearance measured between underside of rail foot and
top side of rail pad 14614. Noted clearance will be approximate shim
thickness to add between baseplate pad and conforming shim. After
noting the clearance, replace the rail clips.
2. Release nyloc nuts 12791, such that rail and baseplate can be lifted sufficiently
to insert shim beneath baseplate pad 14613. Note – prior to lifting the rail
ensure a sufficient quantity of nyloc nuts are released on a number of
baseplates either side of the section to be adjusted.
3. Lift rail.
4. Insert height adjustment shim between baseplate pad 14613 and conforming
shim 15385. Where two part split shim is used ensure correct engagement of
the two parts.
5. Lower rail.
6. Tighten nyloc nuts until compression spring 10108 has a vertical dimension of
34.5+/- 0.5mm.
060-26 _ C Page 30 of 43
Height Adjustment Procedure (Maintenance)
The operation below is a post installation maintenance procedure and assumes all
track is clipped up and fully assembled.
2. Release nyloc nuts 12791, such that rail and baseplate can be lifted
sufficiently to insert shim beneath baseplate pad 14613. Note – prior to lifting
the rail ensure a sufficient quantity of nyloc nuts are released on a number of
baseplates either side of the section to be adjusted.
3. Lift rail.
4. Insert height adjustment shim between baseplate pad 14613 and conforming
shim 15385. Where two part split shim is used ensure correct engagement of
the two parts.
5. Lower rail.
6. Tighten nyloc nuts until compression spring 10108 has a vertical dimension
34.5 +/- 0.5mm.
060-26 _ C Page 31 of 43
7. Inspection and Maintenance
It is recommended that a visual inspection is carried out every 3 months, or as part
of the standard maintenance regime of the maintaining organisation. This inspection
can easily be undertaken while inspecting other components such as rail or concrete
slab.
The visual assessment should include the inspection of all the components of the
assembly. The modular construction of the Pandrol resilient baseplate assembly
allows simple dismantling, replacement of components and reassembly should the
need arise. All spare parts are available direct from Pandrol.
The Pandrol resilient baseplate assembly is designed for long life, and under normal
operating conditions should not require serious maintenance for many years. Should
any parts need to be replaced; the assembly can easily be dismantled using basic
hand tools, allowing easy replacement of parts within short engineering access
hours.
At times of major work, such as a rail change, it is possible to fully dismantle the
assembly for a thorough inspection, and if required, the replacement of any/all
components. There is normally no need to remove the assembly from track to
undertake this operation.
The standard inspection criteria for each component and associated actions are
shown in Table 4 below.
Damaged clip housing If the rail is still restrained laterally and vertically,
then monitor until the next inspection. If rail is free
to move, replace the baseplate.
060-26 _ C Page 32 of 43
Component and Action to be taken
Observation
Clip not fully installed Pull clip fully in position. See section 5 for details.
Rail Pad
060-26 _ C Page 33 of 43
Component and Action to be taken
Observation
Baseplate Pad
Anchor Stud
Eccentric Bush
Washer
Compression Spring
Nyloc Nut
060-26 _ C Page 34 of 43
8. Methodology for Repair of Loose Anchor Studs
Checking of Anchors
Using a 14mm drill bit the hole should be drilled approximately 75-100mm
from the bolt/concrete interface at 30-45 degrees into the concrete.
Continue drilling until the drill bit hits the anchor stud.
After drilling, the hole should be cleaned with compressed air or brush
060-26 _ C Page 35 of 43
Injection Material and Pressure Gun
Injection – Sikadur 52
Make sure that ~15ml is pumped through the nozzle before application
begins. This will ensure the two components are mixed.
Sikadur 52 epoxy grout is applied by using a pressure gun until the grout
appears on the surface. At this point the gun becomes stiff to pump which
indicates the void is filled. Grout comes out of periphery of the bolt or
through cracks in the concrete.
060-26 _ C Page 36 of 43
Figure 56 - Repair of Anchor
Refer to product data sheets for recommended cure times, after cure the
components can be assembled and the nuts tightened to the correct
position achieving the spring compression of 34.5mm.
060-26 _ C Page 37 of 43
9. Methodology for Repair of Non-Vertical Anchor Studs
Equipment required
Or
Procedure
This methodology describes the process to replace anchor studs that are either non-
vertical or cast too high or low in the concrete.
1. Prior to assembling the fastening system: Identify the anchor stud which is
outside the verticality tolerance of +/-1 deg or has been cast either too high or
too low in the concrete. Figure 57.
Figure 57
060-26 _ C Page 38 of 43
2. Select suitable coredrilling equipment fitted with either 54mm or 72mm core
drill bit. The Coredrill should allow the removal of a complete anchor stud.
Ensure the drilling fixture is secure and lined up perpendicular to the concrete
surface in the x and y plane. Figure 58.
In the event the anchor stud is inclined to an extent that the above core
drill bit cannot reach the plinth for drilling, then the anchor stud should be
cut off above the plinth using an angle grinder as shown in Figure 59.
Note: Prior to coredrilling the correct center co-ordinate of the non-vertical anchor
should be established with respect to the location of the remaining vertical anchors,
such that the replaced anchor is positioned correctly as per drawing tolerance in the
railseat.
Figure 58
060-26 _ C Page 39 of 43
Figure 59
3. Drill the hole to an approximate depth of 150mm. If the anchor has been cast
into the concrete greater than 150mm then calculate the depth from the
remaining length above concrete level. The total length of the Pandrol anchor
stud is 270mm +/-6mm. Figure 60.
Figure 60
060-26 _ C Page 40 of 43
4. When the hole is sufficiently deep enough, withdraw the drill and break off the
core in the concrete. A tap with a hammer to the anchor stud top will break off
the concrete core quite easily. Figure 61.
Figure 61
5. Thoroughly clean out the hole and surrounding area with rags and
compressed air to remove debris and moisture. Figure 62 and 63.
Figure 62 Figure 63
060-26 _ C Page 41 of 43
6. For a 54mm coredrill bit, inject Hilti RE 500 epoxy adhesive into the hole.
Figure 64. For a 72mm Coredrill bit, prepare the hole first with FosrocNito-
Bond following manufacturers guidelines then pour Fosroc GP2 into the hole.
Figure 65. Estimate the quantities required to avoid overspill.
Figure 64 Figure 65
7. Insert the replacement anchor stud into the hole centrally and clean off any
excess sealing material or top up if necessary, which should be level with
concrete surface. Figure 66.
Figure 66
8. Re-install all the components except compression spring and use the
eccentric bushes at zero position to align the bolt vertically and in the correct
geometric position. In place of the compression spring insert a 56mm long
tube with internal diameter of 32mm over the replacement anchor stud to sit
on the eccentric bush. Install the nyloc nut hand tight until it clamps the tube.
This will set the height of the repair stud to 121mm above the concrete
surface. Figure 67.
060-26 _ C Page 42 of 43
Figure 67
After curing, the tube can be removed and components reassembled as per
guidelines.
Note:
This method has been tested and approved by DMRC in India and tested and
approved by Pandrol Ltd in the UK.
Using either Hilti 500 or Fosroc GP2 to the above procedure, the anchor stud
is capable of withstanding the 60kN minimum load requirement for 3 minutes
as specified in EN13481-2.
060-26 _ C Page 43 of 43