You are on page 1of 3

ID Name Start Date End Date

1 Identify the topic Jan 03, 2022 Jan 28, 2022


2 Literature Review Jan 31, 2022 Dec 16, 2022
3 Submission of proposal Feb 18, 2022 Mar 11, 2022
4 Interim Presentation Mar 14, 2022 Mar 31, 2022
5 Material Selection Apr 01, 2022 Apr 29, 2022
6 Concrete Mix Preparation May 02, 2022 May 19, 2022
7 Casting Concrete Samples May 20, 2022 May 20, 2022
8 Curing and Sample Testing May 23, 2022 Jun 29, 2022
9 Obtaining the results Jun 30, 2022 Aug 17, 2022
10 Analysis of results Aug 18, 2022 Sep 28, 2022
11 Finalise the report Sep 29, 2022 Dec 21, 2022
Duration Progress % Dependency
20 days 0
230 days 0 1FS
16 days 0 2SS+14 days
14 days 0 3FS
21 days 0 4FS
14 days 0 5FS
1 day 0 6FS
28 days 0 7FS
35 days 0 8FS
30 days 0 9FS
60 days 0 10FS
Resources