DETAILED UNIT PRICE ANALYSIS (DUPA)

Project Name: Construction of Perimeter Fence


Location: Digos City, Davao del Sur

Scope of Work: FENCE Quantity: 12.00 m


Unit of Measurement: meters

A. MATERIALS
Item Materials Unit Quantity Unit Price Amount
1. CHB set 158 10.00 PHP 8,000.00
2. Cement bags 13 207 PHP 2,691.00
3. Sand cu.m 0.65 700 PHP 453.94
3. Gravel set 0.60 900.00 PHP 540.00
4. Tie Wire #16 kls 2 70.00 PHP 140.00
5. DRB # 8 set 20 110.00 PHP 2,200.00
6. 2x2x1.5 Tubular Pipe pc 1 800.00 PHP 800.00
7. 2x2x3/16 Angle Bar pc 1 633.00 PHP 633.00
8. Cyclone 4x4' mtrs 13 310.00 PHP 4,030.00

Materials Subtotal: PHP 19,487.94

B. EQUIPMENTS
Item Description Unit Quantity Rental Cost Amount

Equipment Subtotal: PHP 0.00

C. LABOR
Item Designation days No. of Persons Rate Amount
1. Foreman 2 1 600 PHP 1,200.00
2. Skilled Laborer 2 1 500 PHP 1,000.00
3. Unskilled Laborer 2 1 350 PHP 700.00
4.
Labor Subtotal: PHP 2,900.00

Total Direct Cost: PHP 22,387.94

Tax (5%): PHP 1,119.40


Contingencies (10%): PHP 2,238.79
Others:

Total Indirect Cost: PHP 3,358.19

TOTAL COST: PHP 25,746.13