Payment Schedule as per sft basis for 4280 sft @ 898.7 per sft = 4280*898.

7/SI NO

DISCRIPTION

AMOUNT

75% ON R.C.C@3846436/ =

2884827

15% ON BLOCK WORK

576965.4

10% ON PLASTERING

384643.6

TOTAL

3,846,436.00

RCC

FOOTING 10%
PLINTH 15%
1ST SLAB 15%
2ND SLAB 15%
3RD SLAB [1] 10%
3RD SLAB [2] 10%
TOTAL
B

576965.4
576965.4
384643.6
384643.6
2884827

BLOCK WORK
G FLOOR 4%
F FLOOR 4%
S FLOOR 4%
T FLOOR 3%
TOTAL

384643.6
576965.4

153857.44
153857.44
153857.44
115393.08
576965.4

PLASTERING [INT]
G FLOOR 1.25%
F FLOOR 1.25%
S FLOOR 1.25%
T FLOOR 1.25%
TOTAL

48080.45
48080.45
48080.45
48080.45
192321.8

PLASTERING [EXT]
5% ON COMPLITION
G TOTAL

192321.8
3846436

3846436