week 1 2 3 4 5 6
Gross Requirement (Dt) 150 120 150
Scheduled Receipts (SR) 230
On-hand (It) 37 117 117 117 0 0 0
Planned Receipts (Qt) 3 150
Planned Order Releases (Q't) 3 150 120
week 1 2 3 4 5 6
Gross Requirement (Dt) 150 120 150
Scheduled Receipts (SR) 230
On-hand (It) 37 117 117 117 227 277 77
Planned Receipts (Qt) 230
Planned Order Releases (Q't) 230 230
week 1 2 3 4 5 6
Gross Requirement (Dt) 150 120 150
Scheduled Receipts (SR) 230
On-hand (It) 37 117 117 117 150 150 0
Planned Receipts (Qt) 153 120
Planned Order Releases (Q't) 153 120
7 8
120 L 2 weeks
0 0
120
7 8
120
187 187
230
7 8
120