You are on page 1of 3

Document No.

: FM-SO-29-00
PROJECT PROPOSAL OUTLINE FORM (PPOF)
Effective Date: July 18, 2018

PROJECT PROPOSAL OUTLINE

I. GENERAL INFORMATION

1.0 Project Title: “Serbisyong Kalinisan Para Sa Kalikasan”

2.0 Nature: Environment

3.0 Project Duration: 8:00 - 12:00

4.0 Project Location: Brgy. XXX, Zone XX Pandacan, manila

5.0 Beneficiaries: 30 Teenagers (ages 12 - 19)

6.0 Initiating Section: CWTS01 -A51

8.0 Facilitator: Prof. Melissa Ann Crisostomo

9.0 MAPÚA-CWTS Project Cost Counterpart: Php3537.00

10.0 Community Project Cost Counterpart:

11.0 Total Project Cost: Php 3537.00


Document No.: FM-SO-29-00
PROJECT PROPOSAL OUTLINE FORM (PPOF)
Effective Date: July 18, 2018

II. PROJECT DESCRIPTION

Every city needs to be safe, clean, and healthy. Each of us wants and needs to breathe fresh air. This
project will help the community to be responsible when it comes to cleanliness and prevent the different
kinds of pollution that may harm both humans and animals. Also, it will help build connections and
friendship to everyone in the community that helps clean with.

III. PROJECT RATIONALE

If there’s a healthy environment, there’s a healthy people. The project will help the community to be
aware of how important is the environment and how important is cleaning. People in the community
should learn the benefits and consequences of having a well-organized and well-cleaned environment.

learn the teenagers to learn how to value the environment by cleaning.

IV. PROJECT BENEFICIARIES

Since, the teenagers are mostly on social media, playing games, and not exercising. In this project, the
beneficiaries of this project are the teenagers ages 12 - 19 and there will be 30 participants. This will help
them learn to clean and value the environment.

V. PROJECT OBJECTIVES

This project aims to:

● Educate people in the community


● Give importance to the environment
● Reduce pollution in the environment

VI. PROJECT ACTIVITIES AND TIME TABLE

Time Frame
Activities
Start End
Assembly at Mapua 8:00 8:30
Travel 8:30 9:00
Opening Remarks 9:00 9:10
Orientation 9:10 9:40
Project Implementation 9:40 11:00
Snack time 11:00 11:20
Clean-up/Pack-up time 11:20 11:40
Closing remarks 11:40 12:00
Document No.: FM-SO-29-00
PROJECT PROPOSAL OUTLINE FORM (PPOF)
Effective Date: July 18, 2018

VII. PROJECT MANAGEMENT

Person/s in charge Roles/Tasks


Group 1 (2 persons) Documentation Committee
Group 2 (4 persons) Food Committee
Group 3 (5 persons) Materials distributor
Group 4 (5 persons) leader instructors per team

VIII. PROJECT FINANCIAL REQUIREMENTS

Qty Unit Materials Purpose Cost Per Mat. Total


15 pcs broomstick (walis tingting) cleaning 35 525
20 pcs dust pan cleaning 43 860
5 pcs shovel cleaning 99 495
10 pcs trash grabber tool cleaning 82 820
5 packs garbage bag cleaning 50 250
2 box disposable gloves (100 pcs protection 179 358
each)
2 kit first aid kit medicine 78 156
1 box face mask protection 73 73
Total 3537.00

You might also like