Professional Documents
Culture Documents
Ch10-Monitoring and Information Systems
Ch10-Monitoring and Information Systems
Chapter 10
Monitoring and
Information
Systems
Planning activities
Monitoring activities
6-2
1
7/9/2018
Terms
10-3
The Planning–Monitoring–Controlling
Cycle
10-4
2
7/9/2018
10-6
3
7/9/2018
10-7
Data Collection
10-8
4
7/9/2018
Frequency counts
Raw numbers: Hours, dollars, dates…
Subjective numeric ratings
Indicators: Indirect measures
Verbal measures: quality, moral…
10-9
5
7/9/2018
10-11
6
7/9/2018
Report Types
10-13
Meetings
7
7/9/2018
Meeting Rules
Use meetings to make group decisions
Start and end on time and have an
agenda
Do your homework before the meeting
Take minutes
Avoid attributing remarks to individuals in
minutes
Avoid overly formal rules of procedure
Call meeting for serious problems
10-15
10-16
8
7/9/2018
9
7/9/2018
50-50 rule
0-100 percent rule
Critical input use rule
Proportionality rule
10-19
CV
SV
TV
10
7/9/2018
Variances
10-21
Glossary of Terms
EV (Earned Value)
The percent of the original budget that has been earned by actual
work completed.
(BCWP—Budgeted Cost of the Work Performed)
PV (Planned Value)
The cost of work we scheduled to be performed to date
(BCWS—Budgeted Cost of the Work Scheduled).
AC (Actual Cost)
The actual cost of the work completed.
(ACWP—Actual Cost of the Work Performed).
11
7/9/2018
Variance Analysis
CV (Cost Variance)
The difference between the earned value EV and the actual costs
for the work completed to date, CV = EV-AC.
CV = BCWP – ACWP (CV <0: Cost overrun)
SV (Schedule Variance)
The difference between the earned value EV and the cost of work
we scheduled to be perform to date, SV = EV-PV.
SV = BCWP – BCWS (SV<0: behind schedule)
TV (Time Variance)
The difference in the time scheduled for the work that has been
performed ST and the actual time used to perform it AT, TV=ST-AT
TV <0: delay/ behind schedule
Glossary of Terms
BAC
– Budgeted cost at completion. The total budgeted cost of the
baseline or project cost accounts.
EAC
– Estimated cost at completion. Includes costs to-date plus
revised estimated costs for the work remaining.
ETC
– Estimate cost to complete.
12
7/9/2018
13
7/9/2018
Indices
14
7/9/2018
15
7/9/2018
Milestone Reporting
10-31
Milestone Reporting
MILESTONE REPORT
16
7/9/2018
PMIS Errors
10-34
17
7/9/2018
Friendliness Graphics
Schedules Charts
Calendars Migration
Budgets Consolidation
Reports Access
10-35
Questions?
8-36
18