MASTER PLANT TURN AROUND TAHUN 2023
ID Task Task Name Duration Start
Mode 2021 2022 2023
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
29 Penyiapan JSA 2 mons Wed 30/11/22 0%
30 Planning &Scheduling Complete 2 mons Wed 30/11/22 0%
31 Final Scheduling Approval 7 days Tue 31/01/23 0%
32 Mayor Material at Site 0 mons Wed 15/03/23 15/03
33 Release Buku Panduan TA 1 mon Thu 09/02/23 0%
34 Sub Contractor Ready 1 mon Fri 30/12/22 0%
35 Tim Building TA 1 wk Fri 30/12/22 0%
36 Planning & scheduling complete 0 days Thu 05/01/23 05/01
37 Pelaksanaan Pra TA, TA & Post TA 5,55 mons Thu 16/03/23 0%
38 Pra TA 1,45 mons Thu 16/03/23 0%
39 -Mulai Pemasangan Fasilitas 22 days Thu 16/03/23 0%
40 -Mulai Pemasangan Scafolding 2 wks Mon 17/04/23 0%
41 Shut Down 2 days Mon 01/05/23 0%
42 Safety Comittment 2 hrs Mon 01/05/23 0%
43 kick of meeting 1 hr Mon 01/05/23 0%
44 TA Execution 20 days Mon 01/05/23 0%
45 Start Up 4 days Mon 29/05/23 0%
46 Pabrik on spec 0 wks Thu 01/06/23 01/06
47 Pasca TA 3 mons Fri 02/06/23 0%
48 TA Evaluation & Recommendation. 3 mons Fri 02/06/23 0%
Page 2