MASTER PLANT TURN AROUND TAHUN 2023

ID Task Task Name Duration Start


Mode 2021 2022 2023
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
1 MASTER PLAN TURNAROUND 2023 23,77 mons Wed 01/09/21 42%
2 Persiapan TA 18,23 mons Wed 01/09/21 47%
3 Difinision Phase 5 mons Wed 01/09/21 72%
4 Penyusunan master plan TA 2023 1 mon Wed 01/09/21 100%
5 TA Structure Organisasi dan TA Team 2 mons Fri 01/10/21 95%
6 Konsinyering ke-1 2 days Mon 18/10/21 100%
7 TA Goal (difinisi dan target) 2 mons Fri 01/10/21 100%
8 Management Risiko TA 1 mon Thu 02/12/21 70%
9 SHE Plan 2 mons Thu 02/12/21 60%
10 Strategi kontraktor 2 mons Thu 02/12/21 20%
11 Difinision Phase complete 0 days Tue 01/02/22 01/02
12 Scooping Phase 13,55 mons Wed 20/10/21 68%
13 Usulan item TA 6 mons Wed 20/10/21 100%
14 Konsinyering Ke-2 2 days Fri 22/04/22 0%
15 Scooping TA WR 3 mons Tue 26/04/22 95%
16 Konsinyering ke-3 2 days Wed 27/07/22 0%
17 Freeze Date Work Request 0 mons Thu 28/07/22 28/07
18 Issue TA List 2 mons Fri 29/07/22 10%
19 Rapat evaluasi item final 2 mons Thu 29/09/22 10%
20 Usulan material TA 6 mons Fri 08/04/22 80%
21 C Estimate ready 2 mons Tue 11/10/22 20%
22 Scooping phase complete 0 days Tue 29/11/22 29/11
23 Planning &Scheduling 12 mons Fri 11/03/22 12%
24 Issue Long Delivery Item 12 mons Fri 11/03/22 20%
25 Work Preparation 50% Complete 1,77 mons Wed 30/11/22 0%
26 Production SD/SU Detail Schedule 2 wks Tue 10/01/23 0%
27 Preliminary Manpower 1 mon Wed 30/11/22 0%
28 Work Preparation 100% Complete 2 mons Wed 30/11/22 0%

Page 1
MASTER PLANT TURN AROUND TAHUN 2023
ID Task Task Name Duration Start
Mode 2021 2022 2023
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
29 Penyiapan JSA 2 mons Wed 30/11/22 0%
30 Planning &Scheduling Complete 2 mons Wed 30/11/22 0%
31 Final Scheduling Approval 7 days Tue 31/01/23 0%
32 Mayor Material at Site 0 mons Wed 15/03/23 15/03
33 Release Buku Panduan TA 1 mon Thu 09/02/23 0%
34 Sub Contractor Ready 1 mon Fri 30/12/22 0%
35 Tim Building TA 1 wk Fri 30/12/22 0%
36 Planning & scheduling complete 0 days Thu 05/01/23 05/01
37 Pelaksanaan Pra TA, TA & Post TA 5,55 mons Thu 16/03/23 0%
38 Pra TA 1,45 mons Thu 16/03/23 0%
39 -Mulai Pemasangan Fasilitas 22 days Thu 16/03/23 0%
40 -Mulai Pemasangan Scafolding 2 wks Mon 17/04/23 0%
41 Shut Down 2 days Mon 01/05/23 0%
42 Safety Comittment 2 hrs Mon 01/05/23 0%
43 kick of meeting 1 hr Mon 01/05/23 0%
44 TA Execution 20 days Mon 01/05/23 0%
45 Start Up 4 days Mon 29/05/23 0%
46 Pabrik on spec 0 wks Thu 01/06/23 01/06
47 Pasca TA 3 mons Fri 02/06/23 0%
48 TA Evaluation & Recommendation. 3 mons Fri 02/06/23 0%

Page 2