Professional Documents
Culture Documents
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
1
9
Project Engineer 1
Materials Engineer 1
Foreman 1
Safety and Health officer 1
First Aider 1
Carpenter 4
Mason 4
Welder 1
Steelman 2
Laborers 8
45 CALENDAR DAYS
Item Equipment Used No.
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
1
9
Welding Machine 1
Concrete Mixer 1
Bar Cutter 1
Bar Bender 1
Hand Tools
Prepared by:
ABDULCARIM M. TABAYAG
Owner/Manager
A.M. TABAYAG BUILDERS
A.M TABAYAG BUILDERS
Labangan, Zamboanga del Sur
Project Title: REPAIR & UPGRADING OF BOKONG BHS
Location: LABANGAN, ZAMBOANGA DEL SUR
PERT/CPM
15 30 45
I SPECIAL ITEM
II EXCAVATION WORKS VII
F G
III EMBANKMENT WORKS
IV STRUCTURAL CONCRETE WORKS
V MASONRY WORKS
VI DOORS & WINDOWS
V
VII REINFORCE STEEL WORKS Move-IN A H I VI
III
VIII ROOFING WORKS I
IX PLUMBING WORKS Move-Out
II IV VIII
B C D E
IX
J K
ABDULCARIM M. TABAYAG
Owner/Manager
CONSTRUCTION OF SAFETY & HEALTH
A.M TABAYAG BUILDERS
SUPERVISION/DELIVERY OF MATERIAL
A.M TABAYAG BUILDERS
Labangan Zamboanga del Sur
Project Title: REPAIR & UPGRADING OF BOKONG BHS
Location: LABANGAN, ZAMBOANGA DEL SUR
ABDULCARIM M. TABAYAG
Owner/Manager
A.M TABAYAG BUILDERS
A.M TABAYAG BUILDERS
Labangan, Zamboanga del Sur
SUMMARY
NAME/LOCATION OF PROJECT :
REPAIR & UPGRADING OF BOKONG BHS
LABANGAN, ZAMBOANGA DEL SUR
ITEM DESCRIPTION
403 Metal Structure (Roof Framing)
REINFORCE STEEL
404 ( a ) R.S for Column and Wall Footing
404 ( b ) R.S for Columns
404 ( c ) R.S for Tie Beam and Roof Beam
404 ( d ) R.S for Slab on Grade,Stair & Septic Tank
506(a-b) MASONRY UNIT
803 STRUCTURES EXCAVATION
804 EMBANKMENT
900 STRUCTURAL CONCRETE
900 ( a ) R.C for Column and Wall Footings
900 ( b ) R.C for Columns
900 ( c ) R.C for Tie Beam and Roof Beam
900 ( d ) R.C for Slab on Fill and Ramp
PLUMBING WORKS
1002 ( a ) Sanitary Pipe Lines & Fittings
1002 ( b ) Water Pipe Lines & Fittings
1002 ( c ) Plumbing Fixtures
DOOR & WINDOW
1009 GLASS JALOUSIE WINDOWS
1010 ( a ) Panel & Flush Type Doors(Wooden)
1010 ( b ) Door Jamb and Window Jamb(Wooden)
1014 PRE-PAINTED METAL ROOFING
FE A.1.1 Construction Safety & Health Facilities
Project Title: REPAIR & UPGRADING OF BOKONG BHS
Location: LABANGAN, ZAMBOANGA DEL SUR
DETAILED ESTIMATES
ESTIMATED COST
A. DIRECT COST
B. INDIRECT COST
DETAILED ESTIMATE
Project Title: REPAIR & UPGRADING OF BOKONG BHS
Location: LABANGAN, ZAMBOANGA DEL SUR
PAY ITEM NO. : 403
Metal Structure (Roof Framing)
A. Material Quantity Unit Unit Cost Total Cost
C. LABOR COST
C. LABOR COST
OCM % 666.90
10%
PROFIT % 666.90
10%
VAT % 333.45
5%
C. LABOR COST
OCM % 1,200.50
10%
PROFIT % 1,200.50
10%
VAT % 600.25
5%
16mm Dia. x 6mm Def. Main Bar 56.00 pcs 260.00 14,560.00
10mm Dia. x 6mm Def. Bar 97.00 pcs 110.00 10,670.00
# 16 G.I Tie wire 25.00 kgs 70.00 1,750.00
Sub - Total 26,980.00
Quantity
No. of Total
Equip./Labor days Rate
EQUIPMENT
B.
Bar Cutter 1 1 300.00 300.00
Bar Bender 1 1 350.00 350.00
Sub - Total 650.00
C. LABOR COST
OCM % 3,083.00
10%
PROFIT % 3,083.00
10%
VAT % 1,541.50
5%
C. LABOR COST
OCM % 2,874.00
10%
PROFIT % 2,874.00
10%
VAT % 1,437.00
5%
Sub - Total -
C. LABOR COST
OCM % 9,251.40
10%
PROFIT % 9,251.40
10%
VAT % 4,625.70
5%
-
Sub - Total -
Quantity
No. of Total
Equip./Labor days Rate
EQUIPMENT
B.
-
-
Sub - Total -
C. LABOR COST
-
Laborer 2 5 200.00 2,000.00
Sub - Total 2,000.00
D. TOTAL DIRECT COST ( A + B + C ) 2,000.00
OCM % 200.00
10%
PROFIT % 200.00
10%
VAT % 100.00
5%
C. LABOR COST
-
Laborer 2 2 200.00 800.00
Sub - Total 800.00
D. TOTAL DIRECT COST ( A + B + C ) 4,800.00
OCM % 480.00
10%
PROFIT % 480.00
10%
VAT % 240.00
5%
C. LABOR COST
OCM % 840.40
10%
PROFIT % 840.40
10%
VAT % 420.20
5%
C. LABOR COST
OCM % 2,334.96
10%
PROFIT % 2,334.96
10%
VAT % 1,167.48
5%
C. LABOR COST
OCM % 4,295.40
10%
PROFIT % 4,295.40
10%
VAT % 2,147.70
5%
C. LABOR COST
-
Mason 2 3 300.00 1,800.00
Laborer 4 3 200.00 2,400.00
Sub - Total 4,200.00
D. TOTAL DIRECT COST ( A + B + C ) 33,522.00
OCM % 3,352.20
10%
PROFIT % 3,352.20
10%
VAT % 1,676.10
5%
C. LABOR COST
OCM % 1,319.10
10%
PROFIT % 1,319.10
10%
VAT % 659.55
5%
C. LABOR COST
OCM % 500.60
10%
PROFIT % 500.60
10%
VAT % 250.30
5%
Stainless Floor Drain 4"x 4" with 1.00 pcs 160.00 160.00
Strainer
C. LABOR COST
OCM % 1,253.00
10%
PROFIT % 1,253.00
10%
VAT % 626.50
5%
-
W-1 7 sets-Jalousie window w/ clear blades on -
standard aluminum casing -
w/ complete hardware and acc. 11.55 sq.m 650.00 7,507.50
-
W-2 1 sets-Jalousie window w/ clear blades -
standard aluminum casing 0.40 sq.m 650.00 260.00
w/ complete hardware and acc.
C. LABOR COST
OCM % 992.35
10%
PROFIT % 992.35
10%
VAT % 496.18
5%
C. LABOR COST
OCM % 1,880.00
10%
PROFIT % 1,880.00
10%
VAT % 940.00
5%
C. LABOR COST
OCM % 2,687.80
10%
PROFIT % 2,687.80
10%
VAT % 1,343.90
5%
C. LABOR COST
OCM % 2,871.75
10%
PROFIT % 2,871.75
10%
VAT % 1,435.88
5%
C. LABOR COST
-
-
Sub - Total -
D. TOTAL DIRECT COST ( A + B + C ) 10,000.00
PROFIT % 1,000.00
10%
VAT % 500.00
5%