Professional Documents
Culture Documents
Draft - Traffic - Report - Ramban - Banihal PSC2 (ED-PKS) - DS
Draft - Traffic - Report - Ramban - Banihal PSC2 (ED-PKS) - DS
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
1
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
movement pattern in the project area on the basis of field visits and in
consultation with NHAI officials. A complete analysis of the data collected and
future projections of traffic based on necessary traffic analysis has been made
and are presented in this chapter. This chapter presents the details about
estimation of traffic on the project road in the following sections:
Section 5.1 : Traffic Study Background
Section 5.2 : Traffic Surveys
Section 5.3 : Traffic Data and Analysis
Section 5.4 : Traffic Forecast
Section 5.5 : ESTIMATION OF TRAFFIC FOR RAMBAN BANIHAL ROAD
SECTION
Section 5.6 : Capacity and Level of Service Analysis
Section 5.7 : CONCLUSIONS AND RECOMMENDATIONS
The traffic survey analysis along with the study of past trend of the economic
parameters was carried out and the traffic growth was estimated. Using the
growth rate, the future traffic projections have been carried out, which form a part
of this chapter. Impact of implementation of any competing facility in near future
along with all other development impacts, and also the impact of toll charges on
the traffic estimates have been taken into consideration.
5.2 TRAFFIC SURVEYS
5.2.1 Planning of the Surveys
The planning for conducting of traffic surveys started after signing of the
agreement. A reconnaissance survey was taken up for the project road in the
month of November 2020 and possibility of traffic diversion to or from the project
road, if there was any, were duly examined while identifying the traffic survey
locations. The survey locations were identified in conjunction with the surrounding
road network of the project road. The network was also verified by visiting all the
associated road junctions and links so as to assess the traffic level and logistic
requirements for the surveys.
To capture the traffic flow characteristics and travel pattern of users passing
through the project road and other characteristics related to miscellaneous
requirements of the ToR, the following primary traffic surveys were planned and
conducted.
Automated Traffic Count and Classifier (ATCC) based Classified Traffic
Volume Count Survey
Intersection Turning Movement Count Survey (TMC)
Origin-Destination and Commodity Movement Survey (O-D)
Axle Load Survey
Pedestrian Count Survey
Traffic survey stations for carrying out traffic volume count survey, O-D survey,
and axle load survey were selected considering the following parameters:
The station should represent homogeneous traffic section
The station should lie outside an urban area and away from local traffic
influence
2
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
The station should be located in a reasonably level road section with good
visibility (preferably a straight section)
Further, the O-D and axle load survey stations should preferably be located near
police stations on the road, if any, in addition to other criteria listed above for the
convenience and safety of stopping vehicles for roadside interview survey.
The details of survey locations identified for the project road are also given in
Table 5 -1. The finalized survey locations are schematically shown in Figure 5
-2. It can be observed that the project road and its surrounding network have
been covered extensively and appropriately in terms of capturing of the traffic
flows and characteristics of travel pattern. The traffic survey locations and
methodology were given in the Inception Report and in turn were discussed with
client officials.
Table 5-1: Traffic Survey Locations
No. of
Sl. Location / Road
Type of Survey Code Location
No. Reference Name
s
Automated Traffic Km 165+000 at
Count and ATCC-1
Khooni Nalah
Classifier based
1 NH-44 2
Classified Traffic
Volume Count (14 Km 172+500 at
ATCC-2
days, 24 hours) Rashtriya Rifle
Km 166+700 at
TMC-1
Makarkote
Intersection Turning
Movement Count Km 172+000 at
2 TMC-2 NH-44 3
Survey (24 hours / Rashtriya Rifle
12 hours)
Km 177+800 at
TMC-3
Chamalwas
Origin-Destination
and Commodity Km 165+000 at
3 OD-1 NH-44 1
Movement Survey Khooni Nalah
(24 hours)
Axle Load Survey Km 165+000 at
4 AL-1 NH-44 1
(48 hours) Khooni Nalah
PC-1 Km 168+200
Pedestrian Count
5 NH-44 2
Survey (16 hours)
PC-2 Km 171+800
3
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
4
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
As the surveys were conducted simultaneously in more than one location, and
more than one type of survey was conducted simultaneously in certain locations,
strict supervision was imposed, and for this purpose necessary supervisory staffs
were deployed by the consultants.
5.2.2 Schedule of Primary Surveys
A schedule of the surveys was prepared so as to cover all types of surveys
(some of them simultaneously) for collecting data. Traffic movement on the
project road is allowed alternately in one direction i.e. from Jammu to Srinagar
and then from Srinagar to Jammu, based on movements of army convoys. In
order to capture a complete week of temporal variation in traffic, the consultant
conducted traffic surveys for 14 days for the traffic volume counts Similarly two
days of survey were scheduled for turning movement counts and three days of
axle load survey to arrive at the 24 hours of counts. The traffic survey schedule
for the project road is presented in Table 5 -2.
Table 5-2: Schedule of Traffic Surveys
Sl. Location / Survey Survey End
Type of Survey Code
No. Reference Start Date Date
5
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
Videography was used for automatic counting of traffic. The count was conducted
by fixing video camera at a strategic point on the survey location in order to
capture traffic flow passing through the selected point clearly and without
obstructions in view. This data was converted to excel data sheet format by
means of computer software. Traffic flows in both directions are recorded in video
camera for 24 hours a day for a period of 14 days. Battery back-up arrangements
were put in place for uninterrupted power supply to the cameras and one camera
operator and a reliever were assigned at the counting station.. Recorded data are
extracted and direction wise classified traffic volume count data are recorded
using appropriate software and manual support for successive 15 minute periods,
24 hours a day. Survey proforma for recording the data is presented in Annexure
5.1.
Figure 5 -3 shows photographs of enumerators carrying out traffic volume count
surveys and ATCC cameras and computer monitor display unit at site.
6
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
7
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
8
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
Figure 5-5: Enumerators Carrying out Axle Load Survey on the Project
Road
5.2.4 Secondary Data
5.2.4.1 Socio-Economic Data
Secondary data on socio-economic development of areas along the project road
section are required for assessment of economic vibrancy of the region for
identifying future prospects of road development. Thus, data from various
sources were collected to estimate the trend in growth of traffic along the project
corridor. Various socio-economic parameters like population; Net State Domestic
Product (NSDP), Gross State Domestic Project (GSDP), Per Capita Income
(PCI), etc. were used to estimate traffic growth rates on the project road.
9
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
10
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
11
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal Section of
NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations to Provide
Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc., to Make Such
Locations All Weather Traffic Worthy and Safe for Operations
From the above table, it can be observed that the share of passenger traffic
(including cars / taxis, buses, mini buses, 2-wheelers, and 3-wheelers) along the
project road section varies between 0% and 47% of the total traffic, whereas the
share of goods traffic (including 2-axle trucks, 3-axle trucks, LGVs, and 4-6 axle
trucks) varies between 0% and 52%.
12
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal Section of
NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations to Provide
Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc., to Make Such
Locations All Weather Traffic Worthy and Safe for Operations
The ratio of average yearly petrol and diesel sales data with the sale during
November and December 2020 (the survey months) has been used to determine the
seasonal variation factor. The diesel sales data has been used to find the seasonality
factor for freight vehicles, whereas the petrol sales data has been used to calculate
the seasonality factor for passenger vehicles. This is based on the fuel used by
vehicles in the two categories. The seasonality factors presented above are used to
convert Average Daily Traffic (ADT) to Annual Average Daily Traffic (AADT) at the
survey locations. Table 5 -9 gives the mode-wise AADT obtained for all survey
locations. The same has also been presented in Annexure 5.2.
13
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal Section of
NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations to Provide
Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc., to Make Such
Locations All Weather Traffic Worthy and Safe for Operations
Table 5-9: Annual Average Daily Traffic (AADT) at the Survey Locations
ATCC-1 at Km 165+000 at ATCC-2 at Km 172+500 at
Vehicle Category Khooni Nalah on NH-44 Rashtriya Rifle on NH-44
Veh. PCUs Veh. PCUs
Car / Taxi 3216 3216 3052 3052
Mini Bus 163 244 143 215
Bus 35 104 34 102
LGV 4-Wheeler 581 872 667 1000
2-axle Truck 2488 7465 2721 8162
3-axle Truck 1130 3391 1061 3183
4-6 axle Truck 659 2966 668 3005
Total Tollable Traffic 8272 18258 8348 18730
Toll Exempt Vehicles 43 109 42 115
LGV 3-Wheeler 4 6 19 28
3-Wheeler (Passenger) 4 4 3 3
2-Wheeler 77 38 92 46
Tractor 3 4 5 7
Tractor With Trailer 6 26 4 17
Bicycle 0 0 0 0
Cycle Rickshaw 0 0 0 0
Hand Cart 0 0 0 0
Animal Drawn Cart 0 0 0 0
Total
137 188 165 216
Non-Tollable Traffic
Total Traffic 8409 18445 8513 18946
1
https://www.ncbi.nlm.nih.gov/pmc/articles/PMC7289746/
14
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal Section of
NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations to Provide
Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc., to Make Such
Locations All Weather Traffic Worthy and Safe for Operations
24 March 2020 and just gone one day (March 25, 2020) of the beginning of
lockdown, there have a decreased in percentage (−70.51% in retail and recreation
mobility), (−64.26% in grocery and pharmacy mobility), (−46.17% in parks mobility),
(−65.6% in transit stations mobility), (−60.03% in workplaces mobility) from baseline
in compared to the pre-lockdown period and residential mobility has been increased
in percentage (26.32%) from baseline due to people stayed home during the
lockdown for COVID-19 pandemic in India. Average change in community mobility for
the pre-lockdown and after lockdown period of COVID-19 pandemic is shown in
Figure 5 -7.
15
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal Section of
NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations to Provide
Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc., to Make Such
Locations All Weather Traffic Worthy and Safe for Operations
Mode Factors
LGV 1.10
For the COVID-19 scenario, the AADTs as estimated from primary survey can be
multiplied by the mode-wise COVID-19 factors as enlisted above to get AADT for a
realistic normal traffic scenario, overcoming any impact of Covid-19.
Table 5-11: Annual Average Daily Traffic (AADT) at the Survey Location
(With COVID-19 corrections)
ATCC-1 ATCC-2
Vehicle Category (Km 165+000 of (Km 165+000 of
Project Road Section) Project Road Section)
Veh. PCUs Veh. PCUs
Car 3537 3537 3358 3358
Mini Bus 179 268 157 236
Bus 38 115 37 112
LGV (4-Wheeler) 639 959 733 1100
2 Axle Truck 2737 8211 2993 8979
3 Axle Truck 1243 3730 1167 3501
MAV 725 3262 735 3306
Total Tollable Traffic 9099 20083 9183 20603
Toll Exempt Vehicles 43 109 42 115
LGV 3WH 5 7 21 31
3-Wheeler (Passenger) 5 5 3 3
2-WH 84 42 101 51
Tractor 3 4 5 8
Tractor With Trailer 6 29 4 18
Bicycle 0 0 0 0
Cycle 0 0 0 0
Hand Cart 0 0 0 0
Animal Drawn Vehicle 0 0 0 0
Total
146 196 177 226
Non-Tollable Traffic
Total Traffic 9245 20279 9360 20829
16
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal Section of
NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations to Provide
Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc., to Make Such
Locations All Weather Traffic Worthy and Safe for Operations
surveyed junctions, are presented in Table 5 -12, and detailed daily and peak hour
flow diagrams are given in Annexure 5.4.
The daily total approach volumes vary from 8432 PCUs (5245 vehicles) to 17,483
PCUs (8306 vehicles). The highest total approach volume in terms of PCUs has
been observed at Makarkote Junction (Km 166+700). The lowest total approach
volume is found at Rashtriya Rifles (Km 172+000).
Table 5-12: Daily Traffic Flows at Major Intersections
Count Total
Chainage Total Traffic
Sl. No. Name of Intersection Station Traffic
(Km) (in Vehicles)
No. (in PCUs)
The peak hour is the most important time period for any intersection. The ability of
the intersection to accommodate the traffic during peak hours is the measure of its
level of service. The junction turning flows during the daily and the peak hour will be
useful in planning for interchanges. The peak hour traffic details on these major
junctions are presented in Table 5 -13. It is observed that the total approach
volumes during peak hour vary from 1168 PCUs at Chamalwas (Km 177+900) to a
volume of 3797 PCUs at Makarkote Junction (Km 166+700). The peak hour
proportion at the three surveyed intersections varies from 9.0% to 21.65%.These
higher proportions are due to the irregular flow of vehicle as per the direction from
traffic police and convoy movement. Traffic is generally allowed to move in one
direction at a time. Hence, when the traffic is allowed to move, it result in peak hour
period for that day.
Table 5-13: Peak Hour Traffic Flows at Major Intersections
Peak Hour
Peak Hour Peak Hour Proportion
Sl. Name of Count Chainage
Traffic (in Traffic (in (As % of
No Intersection Station No. (Km)
Vehicles) PCUs) Daily
Traffic)
1 Makarkote TMC 1 166+700 1538 3797 21.65
Rashtriya
TMC 2 172+000 401 1226 14.45
2 Rifles
3 Chamalwas TMC 3 177+900 612 1168 9.00
17
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal Section of
NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations to Provide
Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc., to Make Such
Locations All Weather Traffic Worthy and Safe for Operations
system and compiled for base year (i.e., 2020) using the zoning system adopted for
the study. Modewise O-D matrices were prepared from the collected data in order
that the travel characteristics of traffic plying on the project road be found.
5.3.5.1 Data Checking
The data fed to the computer system were checked manually for inconsistencies.
The checking included:
Matching vehicle type with commodity carried
Vehicle type with their corresponding lead / load / occupancy for any
inconsistencies
Any other inconsistency in data
The checked and corrected data were used for final analysis
5.3.5.2 Zoning System
In order that the movement pattern of vehicles on the project influence area is
assessed, a scientifically developed zoning system was adopted keeping in view of
the major trip generation and attraction points in the area. The zones so developed
and made use of in the analysis are as shown in Table 5 -14 and subsequently in
Figure 5 -8 and Figure 5 -9.
Table 5-14: Adopted Zoning System for the Project Influence Area
Zone No. Particular
Internal Zones
1 Ladakh, Leh
2 Kargil
3 Bandipora
4 Kupwara, Gulgam, Handwara, Tangdhar
5 Baramullah, Pattan, Sopore, Uri
6 Ganderbal
7 Badgam, Srinagar Airport
8 Shopian
9 Pulwama, Awantipora, Pampore, Lethipora
10 Srinagar, Batmaloo
Anantnag, Kokernag, Bijbehara, Khanabal, Pahalgam, Achabal, Qazigund,
11
Verinag, Mir Bazaar
12 Kulgam
13 Poonch and Rajouri
14 Banihal West, Banihal town
15 Banihal East, Chamalwas
16 Ramsoo West, Digdol
17 Ramsoo East, Neel, Ramsoo, Makarkote
18 Khari
19 Gool
20 Ramban North
21 Ramban South, Ramban town, Seri
22 Batote
23 Rajgarh
24 Ukhral, Khurd, Senabati
25 Doda, Bhaderwah, Bhari
26 Kishtwar
27 Kathua, Lakhenpora
28 Samba
29 Udhampur
30 Jammu, Seri Panditian
18
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal Section of
NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations to Provide
Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc., to Make Such
Locations All Weather Traffic Worthy and Safe for Operations
19
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal Section of
NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations to Provide
Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc., to Make Such
Locations All Weather Traffic Worthy and Safe for Operations
20
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal Section of
NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations to Provide
Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc., to Make Such
Locations All Weather Traffic Worthy and Safe for Operations
Commodity
Commodity Type Description
Code
1 Minerals Coal, etc.
2 Food Grains Wheat, Rice, etc.
3 Cash Crops Cotton, Jute, Tea, etc.
Vegetables, Fruits, Fish, Meat, Milk and Milk
4 Perishables Items
Products, etc.
5 Wood and Forest Products Timber, Furniture, etc.
6 Building Materials Brick, Cement, Sand, Lime, Stone, Iron, etc.
7 Oil and Natural Gas Petrol, Diesel, Oil, Lubricant, etc.
8 Grocery Items Soap, Salt, Sugar, Pulses, Spices, etc.
Electronic items, Vehicles, Medicine, Leather,
9 Manufacturing Items Wine, Tobacco, Rubber/ Tyre, Plastics, Cloth,
Paper, etc.
10 Others Fertilizer, Rubbish, Animals, etc.
11 Empty ---
21
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal Section of
NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations to Provide
Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc., to Make Such
Locations All Weather Traffic Worthy and Safe for Operations
grains. Manufacturing items from these are observed to be transported along the
project stretch as NH-44 is the only supply route through which manufacturing items
from other states are transported to Srinagar and nearby zones.
Similarly, foods grains are third highest category in commodity which is transported in
significant number from the neighboring high agricultural productivity state of Punjab.
A large number of vehicles are also found to travel on the project road empty loaded.
This is due to the reason that commodities are unloaded and distributed in the region
and return empty.
5.3.5.6 Load Analysis
Average load carried by goods vehicles (LGVs, 2-axle trucks, 3-axle trucks, and 4-6
axle trucks) at the surveyed location varies between 6 and 22 tons.
The load analysis for various types of goods vehicles at the surveyed location is
given in Table 5 -17.
Table 5-17: Vehicle Wise Distribution of Trips by Various Load Ranges at the
Survey Location (in Percentage)
OD-1 at Km 165+000 at Khooni Nalah on NH-44
Vehicle Average
Type 0.1- 2.6- 5.1- 10.1- 20.1- 30.1- >
Empty Load
2.5 5.0 10.0 20.0 30.0 40.0 40.0
(Tonnes)
LGV 5.56 16.67 16.67 33.33 27.78 0.00 0.00 0.00 6.8
2-axle
12.70 1.39 1.39 30.72 50.12 1.85 0.46 1.39 9.8
Truck
3-axle
9.66 0.28 0.85 9.94 56.53 21.88 0.00 0.85 14.5
Truck
4-6 axle
3.88 2.91 0.00 4.85 19.42 62.14 4.85 1.94 21.1
Truck
From the above table it can be clearly observed that the average load carried by
goods vehicles at the survey location doesn’t exceed the standards for overloading
as laid out for the respective vehicle classes. This is an expected scenario for a
mountainous terrain due to the difficulty experienced in maneuvering of such heavily
loaded vehicles.
5.3.5.7 Lead Analysis
O-D survey data has been analysed for lead ranges / trip length ranges for various
vehicle categories. The trip length frequency distribution in terms of proportion of
vehicles in each range is as presented in Table 5 -18 and subsequently in Figure 5
-10.
Table 5-18: Vehicle Wise Distribution of Trips by Various Trip Length Ranges
at the Survey Location (in Percentage)
OD-1 at Km 165+000 at Khooni Nalah on NH-44
Vehicle Average
Type 50- 100- 250- 500- 1000- Trip
0-20 20-50 >1500
100 250 500 1000 1500 Length
(km)
Car /
0.0 6.1 1.2 29.2 57.7 4.2 1.4 0.1 279.5
Taxi
22
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal Section of
NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations to Provide
Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc., to Make Such
Locations All Weather Traffic Worthy and Safe for Operations
From the above table it can be observed that the average trip length amongst goods
vehicles is higher for the heavier vehicles. This is so, since the heavier goods
vehicles are used for transporting goods to longer distances while smaller goods
vehicles like LGVs and 2-axle trucks are commonly used for distribution of
commodities to nearer locations.
23
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal Section of
NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations to Provide
Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc., to Make Such
Locations All Weather Traffic Worthy and Safe for Operations
various trip purposes for passenger vehicles at the survey location is as represented
in Table 5 -19.
Table 5-19: Vehicle Wise Distribution of Trips by Various Trip Purposes at the
Survey Location (in Percentage)
OD-1 at Km 165+000 at Khooni Nalah on NH-44
Vehicle Social /
Type Work / Business Recreation / Education Others
Shopping
Car / Taxi 79.13 4.66 0.44 15.76
Bus 14.29 0.00 0.00 85.71
Mini Bus 50.00 0.00 0.00 50.00
Analysis on distribution of trips by trip purpose at the survey location shows that there
exists a large share of work / business oriented trips through the project corridor. The
project road offers direct connectivity to Srinagar, the administrative capital of Jammu
and Kashmir. A large number of administrative offices exist in Srinagar and most of
the work / business oriented travellers traverse through NH-44.
5.3.5.9 Travel Time Analysis
O-D survey data has been analysed for distribution of trips for various vehicle
categories based on travel time ranges. The distribution in terms of proportion of
vehicles in each range is as presented in Table 5 -20.
Table 5-20: Vehicle Wise Distribution of Trips by Various Travel Time Ranges
at the Survey Location (in Percentage)
OD-1 at Km 165+000 at Khooni Nalah on NH-44
Vehicle Type Average
0-2 hr 2-5 hr 5-10 hr >10 hr Travel Time
(hr)
Car / Taxi 2.55 5.88 80.91 10.65 8.0
Bus 14.29 0.00 57.14 28.57 7.3
Mini Bus 10.00 20.00 60.00 10.00 6.3
LGV 0.00 11.11 38.89 50.00 11.3
2-axle Truck 1.15 1.62 46.65 50.58 13.8
3-axle Truck 0.00 1.70 30.40 67.90 19.0
4-6 axle Truck 0.00 0.00 31.07 68.93 20.0
Analysis of travel time at the survey location indicates longer travel times for the
heavier freight vehicles as compared to the lighter ones. This is since heavier freight
vehicles are used for distribution of commodities to longer distances and hence have
a longer travel time associated with them. Also, the movement of traffic on NH-44 is
not normal, movement to northbound and southbound is allowed on alternated day.
This movement further varies based on the movement of convoy and weather
conditions. Hence, vehicles in each direction have to wait in queue for longer period
of time depending on the traffic movement allowed on the road.
5.3.5.10 Occupancy Survey
Passenger occupancy survey was carried out for passenger vehicles at the O-D
survey location. Table 5 -21 gives mode-wise average occupancy at the survey
locations.
24
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal Section of
NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations to Provide
Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc., to Make Such
Locations All Weather Traffic Worthy and Safe for Operations
25
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal Section of
NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations to Provide
Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc., to Make Such
Locations All Weather Traffic Worthy and Safe for Operations
by equivalency factor (EF) of that axle. All EFs per axle of the vehicle is then
summed up to obtain the cumulative value of the EF of all vehicles in a category,
which is finally divided by the number of vehicles in that class of vehicle for obtaining
the average value of the VDF (vehicle damage factor) of that class of vehicle.
Cumulative value of the Equivalency Factor
VDF=¿
No . of Vehicles Weighed
The values of VDF were calculated by dividing the sum of all the Equivalency Factors
by the number of samples. But, it was observed that the Equivalency Factor of empty
vehicle had got substantial influence on the VDF values. Therefore, an attempt was
made to give weightage to the empty and loaded vehicle based on their presence on
the highway according to their proportion.
To calculate the cumulative number of standard axles to be catered for in the design
in terms of msa, vehicle category-wise VDF is required. In order to arrive at category
wise VDF values for various types of vehicles, a weighted average of different axle
configuration for a particular category has been calculated. Both, average and
weighted average values of VDF for all commercial vehicles of different axle
configuration at the survey location are given in Table 5 -23. The survey data are
furnished in Annexure 5.6.
Table 5-23: Vehicle Damage Factor (VDF) for Observed Commercial Vehicles
on Project Road
Vehicle Damage Factor (VDF)
Vehicle Type
Up Down
LCV 0.03 0.02
2-axle Truck 3.90 2.54
3-axle Truck 5.85 4.68
MAV 6.96 4.94
26
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal Section of NH44 (Km 151 to Km 187) Under Implementation and
Prepare Revised DPR for Critical Locations to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc., to Make Such
Locations All Weather Traffic Worthy and Safe for Operations
Table 5-24: Axle Load Spectrum from Axle Load Survey at Km 165+000 at Khooni Nalah on NH-44
Day Time Night Time
Single Axle Tandem Axle Tridem Axle Single Axle Tandem Axle Tridem Axle
Axle Load No of Axle Load No of Axle Load No of Axle Load No of Axle Load No of Axle Load No of
Axle Axle Axle Axle Axle Axle
Class. KN s Class. KN s Class. KN s Class. KN s Class. KN s Class. KN s
205 215 0 420 440 0 530 560 0 205 215 0 420 440 0 530 560 0
195 205 0 400 420 0 500 530 0 195 205 0 400 420 0 500 530 0
185 195 0 380 400 0 470 500 0 185 195 0 380 400 0 470 500 0
175 185 0 360 380 0 440 470 0 175 185 0 360 380 0 440 470 0
165 175 2 340 360 0 410 440 0 165 175 0 340 360 0 410 440 0
155 165 1 320 340 1 380 410 0 155 165 0 320 340 0 380 410 0
145 155 1 300 320 2 350 380 0 145 155 0 300 320 4 350 380 0
135 145 7 280 300 5 320 350 1 135 145 2 280 300 1 320 350 0
125 135 25 260 280 20 290 320 0 125 135 6 260 280 3 290 320 2
115 125 28 240 260 38 260 290 2 115 125 15 240 260 8 260 290 0
105 115 74 220 240 81 230 260 2 105 115 27 220 240 16 230 260 0
27
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
Daily Flow
Daily
Chainage Ramban to Banihal Banihal to Ramban
Flow
Across Along Across Along
Peak
Chainage Peak Hour Flow
Flow
166+200 5 13 2 35 55
171+800 0 4 2 2 14
At the location where a pedestrian count was conducted and where vehicular
volumes were available from survey, data has been analyzed to assess the need
of providing controlled crossing, if there any. For the same, Guidelines for
Pedestrian Facilities as per IRC-103-1988 has been referred. According to IRC-
103-1988 a controlled crossing is desirable in case of those locations where the
conflicting peak hour pedestrian volume (P) and vehicle volume (V) are such that
PV2 ≥ 108 for undivided carriageways. Values of PV2 for the intersection are
shown in Table 5 -29.
Table 5-26: PV2 value at Intersections
Location P V V
2
PV
2
The value of PV2 is not exceeding 108 at any of the locations. Therefore, there is
no requirement of a foot over bridge. However zebra crossings need to be
provided at all the arms in each intersection.
5.3.8 Accident data analysis
Accident data was collected from the traffic police stations of Ramsoo and
Ramban for the locations along NH-44 for the years 2016-20. The data gives
information about the number of accidents during these years however, the
details about type of vehicles involved in the accident and exact location of
accident was not provided, instead the accidents have been classified as minor
28
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
injury, major injury and fatal accidents according to IPC 337, IPC 338 and IPC
304A respectively. The details have been furnished in Table 5 -27 for project
stretch. However, as the exact locations of these accidents are not available, the
design will attend to overall safety requirements, rather than the specific
locations.
Table 5-27: Accident data along project road
Number of Number of Number of Number of
Accidents Minor Injuries Major Injuries Fatalities
Year
under under under under
(IPC-279) (IPC-337) (IPC-338) (IPC-304A/304)
Ramsoo
2016-
2 21 - 8
17
2017-
7 17 1 2
18
2018-
11 14 - 6
19
2019-
11 15 1 5
20
2020-
4 12 - -
21
Ramban
2016-
12 36 12
17
2017-
9 26 5
18
2018-
11 34 15
19
2019-
17 26 15
20
2020-
6 27 14
21
5.4 TRAFFIC FORECAST
5.4.1 Introduction
Financial resources available are always scarce and have competing demands,
and therefore, the investments in a highway and related project has to be
carefully planned, keeping in view not only the present demand but also the
requirements for a reasonable period in future. This underlines the need for
estimating the future traffic accurately, whether the plan is for the construction of
a new facility or the improvement of existing facilities. Accurate estimate of future
traffic will not only have a significant impact on the engineering design of the
facility, but also influence the financial viability of the project.
Traffic forecasting is at best an approximation, which is based on analysis of
available data. Traffic is generated as a result of the interplay of a number of
contributory factors. Forecasts of traffic have, therefore, to be dependent on the
forecasts of factors such as population, gross domestic product, vehicle
ownership, agricultural output, fuel consumption and other related variables.
Future pattern of change in these factors can be estimated with only a limited
degree of accuracy and hence the forecasting of future traffic levels cannot be
precise.
29
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
2
IRC:108-2015 Guidelines for Traffic Forecast on Highways, published by IRC, New Delhi
30
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
31
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
Table 5-30: Population of PIA States from Year 2011 to Year 2020 3
Himachal
Year J&K Punjab Haryana Delhi UP
Pradesh
2011-
12393000 27743338 6865000 25772000 16788000 201600000
2012
2012-
12519000 28023000 6923000 26193000 17166000 204700000
2013
2013-
12645000 28302000 6982000 26614000 17544000 207800000
2014
2014-
12771000 28581000 7041000 27034000 17921000 211000000
2015
2015-
12897000 28861000 7100000 27455000 18299000 214200000
2016
2016-
12999000 29140000 7158000 27861000 18677000 217500000
2017
2017-
13101000 29380000 7206000 28266000 19056000 220800000
2018
2018-
13203000 29619000 7253000 28672000 19435000 224200000
2019
2019-
13305000 29858000 7300000 29077000 19814000 227700000
2020
CAGR 0.91% 0.94% 0.79% 1.53% 2.09% 1.53%
3
https://nhm.gov.in/New_Updates_2018/Report_Population_Projection_2019.pdf
4
Digest of Statistics, 2017-18 by Directorate of Economics & Statistics
32
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
13.28
CAGR % 10.39% 8.62% 3.13% 9.77% 5.22% 8.57% 5.41%
Table 5-32: Registered Motor Vehicles in Himachal Pradesh 5
5
Road Transport Year Book, MoRTH
33
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
6
Economic & Statistical Organization, Govt. of Punjab
7
Road Transport Year Book, MoRTH
6
Road Transport Year Book, MoRTH
7
Road Transport Year Book, MoRTH
34
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
2018 1 4 7
2018- 315522 659839 14503
2019 1 9 7 53890 254055 94947 6010
2019- 336843 701267 16503
2020 7 7 0 55562 278715 96166 6108
13.78
CAGR 6.76% 6.28% % 3.10% 9.71% 1.28% 1.64%
35
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
86
Economic & Statistical Organization of Himachal Pradesh, Punjab, Haryana, Delhi, UP, & India
36
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
37
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
38
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
Trucks
Pop 0.98 y=1.99x+-21.78 1.99 2.4% 4.70%
GSDP 0.89 y=0.8x+1.82 0.80 5.2% 4.17%
5.0%
NSDP 0.821 y=0.82x+1.7 0.82 4.4% 3.64%
PCI 0.707 y=1.04x+-0.44 1.04 2.9% 2.97%
39
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
40
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
economic on
parameter trend
Pop 1.00 y=6.09x+-88.82 6.09 1.53% 9.35%
GSDP 0.99 y=1.09x+1.44 1.09 8.6% 9.39% 10.6%
PCI 0.990 y=1.32x+-0.17 1.32 6.9% 9.16%
Taxi
Growth Growth
Mode Vs rate of Growth Rate
paramete R2 Equation Elasticity socio- rate based
r coefficient economic obtained on
parameter trend
Pop 0.99 y=14.59x+-238.97 14.59 1.53% 22.40%
GSDP 1.00 y=2.63x+-23.04 2.63 8.63% 22.65% 15.7%
PCI 0.997 y=3.21x+-27.02 3.21 6.92% 22.17%
Two Wheeler
Growth Growth
Mode Vs rate of Growth Rate
paramete R2 Equation Elasticity socio- rate based
r coefficient economic obtained on
parameter trend
Pop 1.00 y=7.72x+-120.19 7.72 1.5% 11.85%
GSDP 1.00 y=1.38x+-5.86 1.38 8.6% 11.92% 13.3%
PCI 0.994 y=1.68x+-7.92 1.68 6.9% 11.64%
Bus
Growth Growth
Mode Vs rate of Growth Rate
paramete R2 Equation Elasticity socio- rate based
r coefficient economic obtained on
parameter trend
Pop 1.00 y=5.29x+-79.66 5.29 1.5% 8.12%
GSDP 0.99 y=0.94x+-1.31 0.94 8.6% 8.15% 10.1%
PCI 0.986 y=1.15x+-2.71 1.15 6.9% 7.95%
LGV
Growth Growth
Mode Vs rate of Growth Rate
paramete R2 Equation Elasticity socio- rate based
r coefficient economic obtained on
parameter trend
Pop 1.00 y=5.79x+-87.03 5.79 1.5% 8.88%
GSDP 0.99 y=1.03x+-1.23 1.03 8.6% 8.90% 8.9%
PCI 0.98 y=1.25x+-2.75 1.25 6.9% 8.68%
Trucks
Growth Growth
Mode Vs rate of Growth Rate
paramete R2 Equation Elasticity socio- rate based
r coefficient economic obtained on
parameter trend
Pop 1.00 y=3.94x+-54.58 3.94 1.5% 6.04%
GSDP 0.99 y=0.7x+3.72 0.70 8.6% 6.07% 6.9%
PCI 0.992 y=0.86x+2.68 0.86 6.9% 5.93%
Table 5-44: Regression Results Delhi
Regression Analysis Results
Cars
Mode Vs R2 Equation Growth Growth Growth
parameter Elasticity rate of rate Rate
coefficient socio- obtained based
41
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
42
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
economic
on
t paramete
trend
r
Pop 1.00 y=6.76x+-115.33 6.76 1.53% 10.36%
GSDP 0.97 y=1.44x+-5.42 1.44 7.0% 10.08% 11.8%
PCI 0.993 y=1.02x+3.29 1.02 10.4% 10.59%
Taxi
Growth
Growth
rate of
Mode Vs Growth Rate
Elasticity socio-
paramete R2 Equation rate based
coefficien economic
r obtained on
t paramete
trend
r
Pop 0.99 y=10.14x+-182.69 10.14 1.53% 15.55%
GSDP 0.94 y=2.1x+-16.98 2.10 6.99% 14.70% 21.0%
PCI 0.982 y=1.53x+-4.73 1.53 10.36% 15.89%
Two-Wheeler
Growth
Growth
rate of
Mode Vs Growth Rate
Elasticity socio-
paramete R2 Equation rate based
coefficien economic
r obtained on
t paramete
trend
r
Pop 1.00 y=7.19x+-121.2 7.19 1.5% 11.02%
GSDP 0.97 y=1.55x+-4.48 1.55 7.0% 10.81% 11.6%
PCI 0.994 y=1.09x+4.96 1.09 10.4% 11.26%
Bus
Growth
Growth
rate of
Mode Vs Growth Rate
Elasticity socio-
paramete R2 Equation rate based
coefficien economic
r obtained on
t paramete
trend
r
Pop 1.00 y=7.84x+-139.31 7.84 1.5% 12.02%
GSDP 0.98 y=1.68x+-11.83 1.68 7.0% 11.71% 12.8%
PCI 0.996 y=1.19x+-1.69 1.19 10.4% 12.30%
LGV
Growth
Growth
rate of
Mode Vs Growth Rate
Elasticity socio-
paramete R2 Equation rate based
coefficien economic
r obtained on
t paramete
trend
r
Pop 0.99 y=9.15x+-162.87 9.15 1.5% 14.03%
GSDP 0.94 y=1.94x+-13.85 1.94 7.0% 13.57% 17.1%
PCI 0.98 y=1.38x+-2.19 1.38 10.4% 14.31%
Trucks
Growth
Growth
rate of
Mode Vs Growth Rate
Elasticity socio-
paramete R2 Equation rate based
coefficien economic
r obtained on
t paramete
trend
r
Pop 1.00 y=6.1x+-104.5 6.10 1.5% 9.35%
GSDP 0.97 y=1.29x+-5.22 1.29 7.0% 9.02% 10.8%
PCI 0.995 y=0.92x+2.47 0.92 10.4% 9.57%
Elasticity values obtained from log-normal regression model were further refined
to simulate the actual observed growths in economic parameters. Traffic growth
43
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
rates obtained from significant socio-economic parameters are compared with the
traffic growth rates from vehicle registration data. Thus, the adopted elasticity
values for different modes of traffic are given in Table 5 -46.
Table 5-46: Adopted Elasticity Values
Influence Zone Car Taxi 2-Wheeler Buses LGV Trucks MAV
Jammu and Kashmir 1.1 1.1 1.1 0.6 0.9 0.9 0.8
Punjab 1.0 1.0 1.0 0.6 0.8 0.8 0.8
Uttar Pradesh 0.9 0.8 0.9 0.5 0.8 0.8 0.8
Delhi 0.9 0.8 0.9 0.5 0.8 0.8 0.8
Haryana 1.0 1.0 0.9 0.6 0.9 0.9 0.9
Himachal 1.0 1.0 1.0 0.7 0.9 0.9 0.9
Rest of India 0.8 0.7 0.8 0.5 0.8 0.8 0.8
Different zones have different proportion of traffic originating and destined to it .It
is evident from Table 5 -28 and Table 5 -29 that the traffic originating and
destined to Jammu and Kashmir, Himachal Pradesh, Punjab, Haryana, Delhi and
U.P have higher share of traffic on the project road. Thus, growth rates for all the
identified zones (influence region) were worked out separately. The proportion of
traffic coming from an influence zone was found from the O-D data, and the
growth rate of that particular zone was applied to this proportion of total traffic.
This exercise was carried out for long distance (through) traffic observed on the
project at all survey locations. For the local traffic, one growth rate was adopted
as they originate and are found to be destined within the same state or the district
along the existing road only. The modes that formed the pool of through traffic
are cars, jeeps, buses, LGV, 2-Axle Truck, 3-Axle Truck and MAV.
The average proportion of the contribution of traffic identified from the data
collected from O-D, from major traffic contributing zones in project influence area,
is given in Table 5 -47 for passenger and goods vehicles respectively. The
proportion of traffic coming from an influence zone was found from the O-D data.
Table 5-47: Share of Traffic from Influence Zones at the Location of
O-D Survey (in %)
MAV
Mini 2-Axle 3-Axle
Zones Car Taxi Buses LGV (4-6
Bus Trucks Trucks
Axle)
100.0 100.0
J&K 96.4% 97.7% 77.8% 75.6% 66.2% 65.5%
% %
Delhi 1.9% 0.3% 0.0% 0.0% 5.6% 7.0% 4.1% 2.4%
Punjab 0.7% 1.1% 0.0% 0.0% 13.9% 7.5% 10.9% 15.1%
UP 0.6% 0.6% 0.0% 0.0% 0.0% 1.7% 6.1% 1.5%
Haryana 0.3% 0.0% 0.0% 0.0% 2.8% 1.9% 1.1% 0.5%
Himachal
0.1% 0.3% 0.0% 0.0% 0.0% 0.1% 0.4% 0.0%
Pradesh
All India 0.1% 0.0% 0.0% 0.0% 0.0% 6.1% 11.1% 15.1%
Total % 100% 100% 100% 100% 100% 100% 100% 100%
To assess the future elasticity of transport demand upto 2050, the forecast of
GDP values for the various influence zones, as given by Niti Aayog in the
publication “Transforming India -2032”, and “India 2020 Economy Outlook by Dun
& Bradstreet” were referred. Statistical Books of J&K, Himachal Pradesh, Punjab,
44
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
Haryana, Delhi and U.P were also considered for using the data to arrive at the
forecast values.
Effect of COVID-19 on Economy
According to India Ratings and Research (A Fitch Group Company), Gross state
domestic products (GSDP) of all states are expected to contract 1.4-14.3 per cent
in the current financial year 2020-21, with Goa, Gujarat, Sikkim and Assam
expected to record a double-digit contraction in GSDP rate. Refer Slide 1 from
the India Ratings and Research website.
45
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
India Ratings and Research (Ind-Ra) expects the gross state domestic product (GSDP) of all states in India to
contract in FY21. The contraction will be range in be in the range of 1.4%-14.3%. According to the agency's estimate,
the states that will witness a double-digit contraction in GSDP growth in FY21 are Assam, Goa, Gujarat and Sikkim.
Using the insight gained in terms of the proportion of the state economy that was dysfunctional during the lockdown,
the agency has estimated the GSDP for various states.
Despite the nation-wide lockdown enforced on 25 March 2020, several economic activities defined as essentials
remained operational, while the lockdown impacted different sectors namely agriculture, industry and services
differently. Since agricultural activities were less impacted, the states having a higher share of agriculture are
expected to have suffered less compared to the one where the share of agriculture is low. Also, some sub-sectors
especially in the services such as banking and financial services, IT and IT enabled services were less impacted,
because they were able to readjust their operations remotely owing to the high penetration of digital platform in their
business operations. The states in which the share of these services is high are expected to have suffered less during
the lockdown compared to the one where share of these services is low.
For example, the proportion of agriculture in gross value added was 14.6% for Haryana and 25.0% for Punjab in
FY19. Similarly, the proportion of industry and services was 31.1% and 54.3% respectively in Haryana and 25.2%
and 49.8% in Punjab. This means the overall growth performance of Haryana is more susceptible to the performance
of the industrial and services sectors. As a result, our estimate suggests that the proportion of Haryana economy that
became dysfunctional during the lockdown is 64.3%, higher than 47.9% of Punjab. The top five major states where
impact of lockdown was the most pronounced are Karnataka, Jharkhand, Tamil Nadu, Kerala and Odisha. Similarly,
the five major states where impact of lockdown was the least pronounced are Madhya Pradesh, Punjab, Bihar,
Andhra Pradesh and Uttar Pradesh.
State’s own tax revenue (SOTR) is a function of the nominal GSDP of the state. Although the lockdown is going to
adversely impact the revenue performance of all the states, the states that are likely to be impacted more in FY21 are
the states whose share of SOTR in the total revenue is higher and are also expected to witness a higher deviation in
their nominal GSDP from the budgeted GSDP. The most vulnerable states in this respect are Maharashtra, Gujarat,
Tamil Nadu, Kerala, Telangana and Haryana. The share of SOTR in the total revenue of these states has been
budgeted in the range of 57%-64% in FY21 and their FY21 nominal GSDP is expected to deviate from the budged
nominal GSDP in the range of 15%-24%.
46
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
47
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
Once the proportion of traffic coming from each zone was established in Table 5
-47 he next step was to find the growth rates for the project road stretch. A
weighted average growth rate was worked out for the project road stretch and
influence area, depending upon the share of traffic contributed by each influence
zone (obtained from O-D), GDP growth of the influence zone and its respective
mode-wise elasticity values obtained through regression analysis.
The weighted average elasticity values, arrived for the project road stretch are
shown in Table 5 -49 and influence area, and corresponding traffic growth rates
obtained are given in Table 5 -50.
Table 5-49: Weighted Elasticity Values Adopted for the Project Road
2 2 Axle 3-Axle
Year Car Taxi Buses LGV MAV
Wheeler Truck Truck
Table 5-50: Traffic Growth Rates obtained for the Project Road
Growth Rates % (Most Likely Scenario)
GR 2020- 2025- 2030- 2035- 2040- Beyond
2025 2030 2035 2040 2045 2045
Car / Jeep / Van 5.23 5.76 5.76 4.93 3.94 3.94
Taxi 5.19 5.72 5.72 4.89 3.91 3.91
Two Wheelers 5.23 5.76 5.76 4.93 3.94 3.94
Three Wheelers 5.20 5.50 4.50 3.00 3.00 3.00
Bus / Mini bus 2.83 3.12 3.12 2.67 2.13 2.13
Light Commercial
4.41 4.86 4.86 4.15 3.32 3.32
Vehicles
2 Axle Trucks 4.51 4.97 4.97 4.25 3.40 3.40
9
*IMF, Niti Aayog Transorming India 2032 and India 2020 Economy Outlook by Dun & Bradstreet
48
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
49
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
50
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
Hence actual diversion to the railway link will be 33.4% of the total AADT of the
project road.
Further to this, Table 5 -52 gives a summary of the historical trend in traffic
volumes and modal shares of the rail and road modes of transport (Planning
Commission, 1988, 2001; Ministry of Surface Transport, 1996, 1999, 2001; and
the Annual Statistical Statements of the Indian Railways for various years). India
became a decidedly road-dominant economy in the beginning of the eighties with
the railways losing out in respect of freight traffic in addition to its already
declining share in passenger traffic. The dominance of road over rail has since
continued unabated till the present and is almost certain to continue into the
future. The share of rail in the total freight traffic carried by both rail and road
declined from 61 per cent in 1970- 71 to 47 per cent in 1980-81, 30 per cent in
51
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
1990-91, and 26 per cent in 2000-01. The decline in the share of rail passenger
traffic is almost equally dramatic: the rail mode had a much reduced share of 31
per cent in 1970- 71 which declined to 24 per cent in 1980-81, 15 per cent in
1990-91, and seems to have risen slightly to 18 per cent in 2000-01.
Table 5-52: Rail and Road Traffic Volumes and Modal Shares
Rail Rail
Modal Modal
Rail Rail Road Rail Total Total
Share in Share in
Year Freight Pass. Freight Pass. Freight Pass.
Freight Pass
Traffic Traffic Traffic Traffic Traffic Traffic
Transpor Transpor
t t
(BTKM) (BPKM) (BTKM) (BTKM) (BPKM) (BTKM) (%) (%)
1950-51 44 67 12.09 44.80 56.09 111.80 78.45 59.93
1960-61 88 78 32.53 105.04 120.53 183.04 73.01 42.61
1963-64 107 89 41.05 139.7 148.05 228.70 72.27 38.92
1964-65 107 93 45.46 162.13 152.46 255.13 70.18 36.45
1970-71 127 118 82.36 263.09 209.36 381.09 60.66 30.96
1977-78 163 177 114.97 484.98 277.97 661.98 58.64 26.74
1980-81 159 209 178.36 664.83 337.36 873.83 47.13 23.92
1985-86 206 241 307.03 1038.56 513.03 1279.56 40.15 18.83
1990-91 243 296 566.66 1615.20 809.66 1911.20 30.01 15.49
1995-96 274 342 762.00 2238.00 1036.00 2580 26.45 13.26
2000-01 312 457 899.26 2127.96 1211.26 2584.96 25.76 17.68
Note: Pass.–Passenger, BTKM–billion tonne kilometres, BPKM- billion passenger kilometres.
Citing all these information, consultant is suggesting that potential diversion will
be in the range of 25.76%-33% for the goods and 17.68% to 30% for the
passengers.
For this study, consultant has assumed a negative diversion of 20 % for vehicles
in passenger category and 20% for the vehicles in goods category. This diverted
traffic will also be added in three phases after opening of railway link, i.e. 30% in
year 2022, 30% in year 2023 and remaining 40% in year 2025. Railway Link is
going to be open in the year 2022.
5.5.3 Induced and Development Traffic
When a new road is built, new traffic will divert onto it. Many people may make
new trips they would otherwise not make, and will travel longer distances just
because of the presence of the new road. This well-known and long-established
effect is known as ‘induced traffic’ . Estimation of actual induced traffic will result
in reaping of benefits of a new road, as this will be the new traffic other than
diverted traffic which will be using the road.
Hence, induced and developmental traffic would also be added to account for the
extra traffic which may start using the proposed road once it is constructed and
opened to the normal traffic.
Estimation of induced traffic is a challenging task. Adequate investigations have
not been carried out in Indian context to provide readily usable models or charts
for the estimation of induced traffic. 10 There are some research studies from UK
and USA. Among those studies, SACTRA Report 1994 on Truck Road and the
10
IRC:108-2015 Guidelines for Traffic Forecast on Highways, published by IRC, New Delhi
52
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
53
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
54
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
'B' 'C'
Plain 10000
40000 60000
Rolling 8500
Mountainous and
Steep
6000 20000 30000
As per standard IRC: SP:73-2018 IRC:SP:84-2019
Unless otherwise specified in the concession agreement, 6
laning shall be done when total traffic (including traffic on service
Notes:
road, if any) reaches design service volume to LOS 'C' for 4 lane
highway.
The project road lies in the mountainous region of J&K. The lane configuration
proposals based on the IRC: SP: 73-2018 and IRC: SP: 84-2019 are given in
Table 5 -55.
Table 5-55: Year-wise Improvement Proposal Based on IRC Codes
Recommendations
Project Road 2–lane with paved 4–lane with paved 6–lane with paved
shoulder shoulder shoulder
Ramban -
Banihal Section - 2020 2031
(NH-44)
Analysis of the observed traffic and the traffic forecast show the need of four
laning from the year of opening, i.e. 2023. Traffic on the project road section will
exceed the design service volume at LOS C for a 4-lane with paved shoulder
road in the year 2031, and therefore, warranting the project road to be developed
to six lanes with paved shoulder.
Since the requirement of six laning of project road is becoming necessary from
the year 2031 which is just 10 years after year of opening, the consultants
recommend that construction of the project road should be planned as a six lane
facility from the year of opening itself.
5.7 CONCLUSIONS AND RECOMMENDATIONS
A comprehensive set of traffic surveys were conducted on the surrounding
network. The traffic surveys included the Traffic Volume Counts, Turning
Movement Counts, O-D Surveys and Axle Load surveys. List of surveys have
been presented in Section 5.2.
The traffic data analysis shows that the AADT at survey station ATCC-1 near
Khooni Nalah is of the order of 18,445 PCUs (8,409 vehicles), while the AADT at
station ATCC-2 (Rashtriya Rifle) is of the order of 18,946 PCUs (8,513 vehicles).
The Consultant has also studied the effect of COVID 19 on the traffic and
accordingly COVID 19 correction have been used after comparing the present
traffic with the pre-COVID traffic data obtained from recently conducted traffic
studies in Himachal Pradesh. Finalized AADT after taking into account COVID-19
has been used for analysis of proposed road up-gradation as given in Section
Error: Reference source not found.
Traffic projections have been done to identify the growth rate in project influence
area. J&K, Himachal Pradesh, Haryana, Punjab, Delhi, U.P are the major
influencing states which contributes maximum to traffic. The consultants have
used the elasticity approach for determining the growth rates of future traffic. This
involved establishing a quantitative relationship between traffic growth as the
55
Consultancy Services to Study the existing DPR / Contract Provisions for 4-Laning of Ramban-Banihal
Section of NH44 (Km 151 to Km 187) Under Implementation and Prepare Revised DPR for Critical Locations
to Provide Realignments / Alternate Solutions to the Extent Required in the form of Tunnels / Viaducts etc.,
to Make Such Locations All Weather Traffic Worthy and Safe for Operations
dependent variable and growth in GSDP, PCI, and population as the independent
variables. The methodology involved fitting of a log-log regression equation to the
time series data. Negative diverted traffic from road to Jammu-Baramulla Rail link
has been analyzed from the potential trips from the OD survey conducted on the
road. A diversion of 20% for all modes has been assumed based results arrived
from the analysis. This have been added in three stages i.e. 30% in Year 2022,
30% in Year 2023 and 40% in Year 2025 (refer Section 5.4).
Induced and Generated traffic of 5% have been suitably assumed from the
secondary research from the studies happed in western countries and also from
the experience of consultant in previous project of similar nature. This have been
added in three stages i.e. 30% in Year 2022, 30% in Year 2023 and 40% in Year
2025.
Traffic on project road section will exceed the design service volume at LOS C in
the year 2031, and therefore, warranting the project road to be developed to six
lanes in the year 2032. It will be unrealistic to predict the economic growth in the
region and the development patterns surrounding the proposed road for such a
long period of 30 years from the base year (2020). It is, therefore, suggested that
the trend of growth of the economy in the region, development patterns
surrounding the project road (NH-44) and traffic movement on the project road be
re-assessed in the year 2030 or so before taking a decision on six-laning of the
project road.
56