Breakup of Quotation

Sl No Surveys Quotation  (Million  Taka)

1 Traffic Survey 8.0


2 Topography 4.35
3 Geology/Geotechnical 118.0
4 Materials Availability Survey 1.0
5 Utility Survey 50.0
6 Hydrology 2.0
7 Infrastructure Survey 2.0
8 Social Survey, Land Acquisition and Resettlement 2.5
9 Environment Survey  & Climate Risk and Vulnerability 2.0

1. Traffic survey (including traffic modelling which may be required):


16 survey points @Tk 500,000 per point = Tk 8,000,000
2. Topography:
17.4 km @Tk 250,000 = Tk 4,350,000
3. Geology/Geotechnical
For UG section 12.8 km @1 borehole (BH) per 100 m = 128 BH + 1 – 16 stations = 113 BH
For Viaduct section (4.6 km) 1 BH per pier (about 30 m span) = 4.6/30 m = 153 + 1 = 154 BH
For stations 7 BH for each station = 16*7 =112 BH
40 BH for depot = 40 BH
Total = 113 + 154 + 112 + 40 = 419 BH + taken 1 additional = 120 BH
420 BH @ 50 m per BH @ Tk 5,000 per m = 105,600,000
CPTU 42 nos. @ Tk 3,00,000 = 12,600,000
Geophysics + Georadar test = 42 nos. @ 8,500 = 357,000
Total = 117,957,000
(Unit prices have been taken from ongoing Dhaka Subway project)
4 Materials Availability Survey = 1,000,000 Lump sum
5. Utility survey = 50,000,000 (Lump sum)
6. Hydrology = 2,000,000 (Lump sum)
7. Infrastructure survey = 2,000,000 (Lump sum)
8. Social Survey and Land Acquisition and Resettlement Planning = 2,500,000 (Lump sum)
9. Environment Survey & Climate Risk and Vulnerability = 2,000,000 (Lump sum)