Professional Documents
Culture Documents
CHAPTER 10
STANDARD COSTING
OBJECTIVE
• Describe the use of standard cost for control and performance measurement
purposes.
• Elaborate the variance analysis of direct materials, direct labour and factory
overhead ;
1
Chapter 10: Standard Costing & Variance Analysis
Direct labour Standard usage of direct labour x Standard cost of direct labour
2
Chapter 10: Standard Costing & Variance Analysis
3
Chapter 10: Standard Costing & Variance Analysis
4
Chapter 10: Standard Costing & Variance Analysis
Purchasing manager
Direct materials price variance Production manager
Store manager
Production manager
Supervisor
Direct materials quantity variance
Human resource manager
Equipment maintenance department
Production manager
Direct labour efficiency variance Supervisor
Human resource manager
5
Chapter 10: Standard Costing & Variance Analysis
Sample Question :
Direct Materials 3 kg @ RM 1
Direct Labour 2 hours @ RM 2.50
Manufacturing Overhead :
Variable 2 hours @ RM 1
Fixed 2 hours @ RM 1.50*
Required :
Solution :
6
Chapter 10: Standard Costing & Variance Analysis
b.
i. Direct materials price variance = (AP x AQ) – (SP x AQ)
= (AP – SP) x AQ
= (RM 1.10 – RM 1.00) x 20,000 kg
= RM 2,000 (U)
vii. Fixed overhead spending variance = Actual fixed overhead – Budgeted fixed overhead
= (AR x AH) – (SR x Normal Hour)
= RM 19,000 – (RM 1.50 x 12,000 hours)
= RM 19,000 – RM 18,000
= RM 1,000 (U)
viii. Fixed overhead volume variance = Budgeted fixed overhead – Absorbed fixed overhead
= (SR x Normal Hour) – (SR x Absorbed Hour)
= (RM 1.50 x 12,000 hours) – (RM 1.50 x [2 hours x 5,000 units
= RM 18,000 – RM 15,000
= RM 3,000 (U)
7
Chapter 10: Standard Costing & Variance Analysis
TUTORIAL QUESTIONS
QUESTION 1
Required :
1. Calculate the following variances. For each variance, label F for favourable variance and
UF for unfavourable variance.
8
Chapter 10: Standard Costing & Variance Analysis
QUESTION 2
Lagenda Limited provides the following standard cost data for one of its products :
Required :
Calculate the following variances. For each variance, label F for favourable variance and UF for
unfavourable variance.
9
Chapter 10: Standard Costing & Variance Analysis
QUESTION 3
Jappy Company manufactures kitchen appliances. The company uses standard costing
system. One of its best-seller products is bread toaster.
The activities below are related to the production of the bread toaster for the year 2021 :
Required :
1. Calculate the following variances. For each variance, label F for favourable variance and
UF for unfavourable variance.
i. Direct material usage variance [RM45,000 (UF)]
ii. Direct material price variance [RM75,000 (F)]
iii. Direct labour efficiency variance [RM19,000 (UF)]
iv. Direct labour rate variance [RM8,000 (UF)]
v. Variable overhead efficiency variance [RM12,000 (UF)]
vi. Variable overhead spending variance [RM80,000 (F)]
vii. Fixed overhead volume variance [RM9,000 (F)]
viii. Fixed overhead spending variance [RM2,400 (UF)]
10
Chapter 10: Standard Costing & Variance Analysis
QUESTION 4
Comtab Company manufactures computer tables. Below is the standard cost for each
computer table :
Overhead absorbed :
Variable 40 hours @ RM 3.00 = RM 120
Fixed 40 hours @ RM 2.00 = RM 80 RM 200
Standard cost is based on the normal activity of 24,000 direct labour hours. Actual activities for
the month of March are as follows :
Required :
Calculate the following variances. For each variance, label F for favourable variance and UF for
unfavourable variance.
11
Chapter 10: Standard Costing & Variance Analysis
QUESTION 5
Orange Limited manufactures metal screen door for commercial buildings. Standard cost for a
unit of metal screen door are as follows :
Direct material : RM
Aluminium 4 pieces at RM3 per piece 12
Copper 3 pieces at RM5 per piece 15
Overhead rate is based on the normal capacity of 6,000 machine hours monthly.
In August 2021, 850 units of metal screen doors have been manufactured. The following
activities occurred in August 2021 :
Direct material :
Aluminium 4,000 pieces purchased at RM3 per piece ;
3,500 pieces used
Copper 3,000 pieces purchased at RM5.20 per piece ;
2,600 pieces used
Required :
Calculate the following variances. For each variance, label F for favourable variance and UF for
unfavourable variance.
12
Chapter 10: Standard Costing & Variance Analysis
QUESTION 6
Bowl Company manufactures a product called “Superbowl”. The company uses standard
costing system in recording operations.
Standard established that 1.5 kg of direct material and 90 minutes of direct labour hour are
needed to produce one unit of finished goods. Standard costs are RM15.00/unit for direct
material and RM12.00/unit for direct labour.
Variable overhead is calculated on the basis of direct material input (in kg) at a rate of
RM4.00/kg, whereas the fixed overhead is calculated on the basis of direct labour hours.
Total annual budgeted overhead is RM100,000. Normal annual production is 10,000 units.
During 2021, a total of 12,000 units of finished goods were produced. 18,000 kg of direct
material were purchased at a price RM8.20/kg and 17,200 kg were used. A total of 18,800
hours of direct labour were used and paid at RM9.50/hour. The amount of overhead incurred
was RM90,000, of which 40% was fixed component.
Required :
3. Calculate the following variances. For each variance, label F for favourable variance and
UF for unfavourable variance.
i. Direct material usage variance
ii. Direct material price variance
iii. Direct labour efficiency variance
iv. Direct labour rate variance
v. Variable overhead efficiency variance
vi. Variable overhead spending variance
vii. Fixed overhead volume variance
viii Fixed overhead spending variance
13
Chapter 10: Standard Costing & Variance Analysis
QUESTION 7
Below are the details relating to the budget that Rasilla Company has prepared for toys
products and the actual results for the year 2021 :
Budgeted Actual
Production volume 30,000 units 33,000 units
Direct labour hours 18,000 hours 15,800 hours
Direct materials used 60,000 kg 61,000 kg
Direct materials cost RM 30,000 RM 28,300
Direct labour cost RM 21,600 RM 18,900
Variable overhead cost RM 23,400 RM 22,320
Fixed overhead cost RM 25,200 RM 24,000
Required:
ii. Direct materials quantity variance and price variance. [RM2,500(F), RM2,200(F)]
iii. Direct labour efficiency variance and rate variance. [RM4,800(F), RM60(F)]
iv. Variable overhead efficiency variance and spending variance. [RM5,200(F), RM1,780(UF)]
14
Chapter 10: Standard Costing & Variance Analysis
QUESTION 8
Mooi Limited produces a product and uses standard costing system. Below is the standard cost
per unit of the product :
The following information is the actual activity and cost incurred during 2021 :
3. Mooi Limited has used 41,000 hours of direct labour at a total cost of RM533,000.
4. A total of 130,000 kilograms of direct material were purchased at a price of RM3.70 per
kg.
5. Opening inventory of direct material is 25,000 kg. No closing inventory of direct material.
Normal production is 45,000 units per year. The standard overhead rate is calculated based on
normal activities on the basis of direct labour hours.
Required :
Calculate the following variances. For each variance, label F for favourable variance and UF for
unfavourable variance.
15