AFC COMMERCIAL BANK ZEEPAY FULL INTEGRATION TASK LIST
Task Target Date By Whom Status
Setting up of virtual test 30/04/2022 AFC Done server Setup of VPN network to 07/05/2022 All parties Done ZIMSWITCH End to End VPN tests 18/05/2022 AFC Done Detailed documentation on 20/05/2022 Zimswitch Done API settings to be shared between parties Provision of API by AFC 25/05/2022 AFC Ongoing according to ISO20022 specifications given Setting up of Gateway 3/06/2022 Zimswitch WIP Development and 13/06/2022 Zimswitch TBA Implementation of integration solution by Zimswitch Systems integration testing 15/07/2022 Project Team TBA Operations workshop 18/07/2022 Zimswitch TBA Carry out User Acceptance 19/07/2022 AFC TBA test and document results Zimswitch Certification 22/07/2022 Zimswitch TBA Production deployment 25/07/2022 Zimswitch TBA Go Live 26/07/2022 AFC