AFC COMMERCIAL BANK ZEEPAY FULL INTEGRATION TASK LIST

Task Target Date By Whom Status


Setting up of virtual test 30/04/2022 AFC Done
server
Setup of VPN network to 07/05/2022 All parties Done
ZIMSWITCH
End to End VPN tests 18/05/2022 AFC Done
Detailed documentation on 20/05/2022 Zimswitch Done
API settings to be shared
between parties
Provision of API by AFC 25/05/2022 AFC Ongoing
according to ISO20022
specifications given
Setting up of Gateway 3/06/2022 Zimswitch WIP
Development and 13/06/2022 Zimswitch TBA
Implementation of
integration solution by
Zimswitch
Systems integration testing 15/07/2022 Project Team TBA
Operations workshop 18/07/2022 Zimswitch TBA
Carry out User Acceptance 19/07/2022 AFC TBA
test and document results
Zimswitch Certification 22/07/2022 Zimswitch TBA
Production deployment 25/07/2022 Zimswitch TBA
Go Live 26/07/2022 AFC