BOBOT PRESTASI

Proyek Renovasi Façade 29/09/2022


No Item Pekerjaan Spesifikasi qty satuan bobot progress actual bobot actual
I Persiapan Mob - Demob
a Perapihan area pemindahan barang customer 1 ls 1.2% 75.0% 0.9%
b Mobilisasi pekerja dan material 1 ls 1.2% 75.0% 0.9%
c Sampah proyek 1 ls 1.2% 75.0% 0.9%

II Pekerjaan Carport
a Chipping keramik existing marking and sloping 19.8 m2 0.6% 100.0% 0.6%
b Bongkar rolling door existing 1 ls 0.9% 100.0% 0.9%
c Balok sabuk besi 8 - 6/120 3.3 m1 1.8% 100.0% 1.8%
d Keramik carport 50 x 50, KW 1 19.8 m2 9.4% 0.0% 0.0%
e Pengecatan vinilex 55.8 m2 6.9% 0.0% 0.0%
f Plafon Gypsum 8 mm 19.8 m2 9.7% 100.0% 9.7%
g Pintu Henderson sliding 7.92 m2 24.6% 20.0% 4.9%
h Perapihan jalur kabel dan titik lampu 1 ls 1.9% 100.0% 1.9%
i Service area perapihan dinding dan cor yang kropos 1 ls 1.9% 100.0% 1.9%

III Relokasi Warung


a Bobok tembok existing 1 ls 1.4% 100.0% 1.4%
b Balok sabuk besi 8 - 6/120 2.1 m1 1.2% 100.0% 1.2%
c kolom support besi 8 - 6/120 5 m1 2.8% 100.0% 2.8%
d Pasang rolling door 1 ls 1.9% 100.0% 1.9%
e Pengecatan vinilex 9 m2 1.1% 0.0% 0.0%
f Service area 1 ls 1.9% 0.0% 0.0%

IV Pintu Utama
a Pembongkaran pintu existing 1 ls 1.4% 100.0% 1.4%
b kusen alumunium + pintu alexindo 1 ls 8.7% 0.0% 0.0%
c jendela alumunium alexindo + kaca riben 3 mm 2 unit 5.2% 0.0% 0.0%
d Balok sabuk besi 8 - 6/120 3 m1 1.7% 0.0% 0.0%
e kolom praktis besi 8 - 6/120 5 m1 2.8% 75.0% 2.1%
f Pengecatan vinilex 9 m2 1.1% 0.0% 0.0%

V TERAS
a plafon GRC 4 mm + finish cat 15 m2 6.5% 0.0% 0.0%
b titik lampu - 2 ttk 0.9% 0.0% 0.0%

TOTAL 100.0% 35.1% 35.1%