Variation Order Final
Variation Order Final
A.1 Masonry Works (from 1.8m high to ceiling line) sqm 19.62 3,345.12 65,618.76
1.3.1 MANPOWER
Mason md 8.00 650.00 5,200.00 5,200.00
Helper md 6.50 450.00 2,925.00 2,925.00
1.4.2 MANPOWER
Mason md 11.00 650.00 7,150.00 7,150.00
Helper md 8.00 450.00 3,600.00 3,600.00
2.4.1 MANPOWER
Electrician md 35.00 650.00 22,750.00 22,750.00
Labor md 25.00 450.00 11,250.00 11,250.00
2.5.1 MANPOWER
Plumber md 2.50 650.00 1,625.00 1,625.00
Labor md 2.00 450.00 900.00 900.00
1.10 MANPOWER
Installer md 2.00 650.00 1,300.00 1,300.00
Labor md 1.00 450.00 450.00 450.00