COMMISSION ON AUDIT
LGS C-Leyte II and Biliran Province – Team R8-01
Ormoc City, Leyte
We have audited the funds transferred from National Government Agencies for
various projects to be implemented by the Municipality and observed the following:
1.1 The Municipal Government of Kananga has been a recipient of funds from
various National Government Agencies (NGAs) in CY 2020 and previous years.
The funds transferred were accompanied with a Memorandum of Agreement
(MOA) between the Municipality and the source agency. Perusal of the MOAs
revealed that the completion period of the PPAs ranges from one year to two years
from the date of signing of the MOA.
AOM No. 2021-08 LGU Kananga- Due to NGAs - Fund Transfers Page 1 of 6
amount of P9,254,000.00 and P4,000,000.00 were received by the Municipality
for the Local Government Support Fund – Assistance to Municipalities (LGSF-
AM) program and Yolanda Recovery and Rehabilitation Program (YRRP),
respectively.
1.4 In the review of the utilization of the available funds, the Audit Team noted that
P72,874,289.86 or 79% were utilized during the year as shown in Table 1.
AOM No. 2021-08 LGU Kananga- Due to NGAs - Fund Transfers Page 2 of 6
Agency/Department Balance PY Received CY Utilization Returned BALANCE
2019 2020 CY 2020 CY 2020
1.6. Although the Municipality prioritized the needs of its constituents during the
pandemic, it was also able to implement other projects which were already
programmed and funded from prior years. However, eight (8) PPAs were not
implemented and funds amounting P19,722,394.84 were not utilized as of
December 31, 2020. Details are shown in Table 2.
AOM No. 2021-08 LGU Kananga- Due to NGAs - Fund Transfers Page 3 of 6
Source PPA Amount Amount Balance
Agency Received Utilized
Rapid
Composting
Program
(BSWM)
DA - Construction of 6,932,619.45 140,000.00 6,792,619.45
YRRP Lonoy Dam
DA RO8 Implementation 500,000.00 0.00 500,000.00
of Scion Grove
Project
DOLE Bahay Ko 2,684,500.00 2,684,500.00 0.00
Barangay Ko
TUPAD Project
422,500.00 422,500.00 0.00
325,000.00 318,500.00 6,500.00
LGSF - Upgrading of 4,804,000.00 0.00 4,804,000.00
Assistance to Barangay Road
Municipalities in Brgy.
Libertad,
Kananga, Leyte
Upgrading of 4,450,000.00 0.00 4,450,000.00
Barangay Road
in Brgy. Lonoy,
Kananga, Leyte
DENR Implementation 171,000.00 0.00 171,000.00
of Ecological
Solid Waste
Management
System in the
Public Market
DOH - HFEP Construction/ 743,626.99 0.00 743,626.99
Renovation of
Kananga
Municipal
Hospital
TOTAL P23,287,894.80 P3,565,500.0 P19,722,394.84
1.7. The Audit Team obtained from the implementing offices the causes which
contributed to the delay and non-implementation of the PPAs. Among the reasons
given were the following:
b. Department of Agriculture
Construction of the Lonoy Dam - The project was still not implemented
due to the relocation of the project site. Interview with the personnel
from the Engineering Department disclosed that a new site has been
approved by the DA RO8 and they are going to schedule the
implementation of the project in CY 2021.
Scion Grove Project - The audit team requested for the MOA of the
project but were told by the Municipal Agriculturist that it is not
available and he will request from DA RO8 for this. When asked why
this was not implemented, the Municipal Agriculturist replied that due to
the pandemic, he was not able to implement said project.
c. Department of Health
AOM No. 2021-08 LGU Kananga- Due to NGAs - Fund Transfers Page 5 of 6
e. Local Government Support Fund – Assistance to Municipalities
1.8 The delay in the completion of the above stated PPAs deprived the intended
beneficiaries of the benefits that could have been derived therefrom, which could
provide for an additional source of livelihood and improve their living conditions.
1.9 We recommend that the Mayor issue a directive to all the Department Heads,
who are in-charge in the implementation of programs/projects of National
Government Agencies, to:
May we have your comments on the audit observations noted within three (3)
calendar days from receipt hereof.
WEMIA P. SENO
State Auditor IV
OIC - Supervising Auditor
AOM No. 2021-08 LGU Kananga- Due to NGAs - Fund Transfers Page 6 of 6