Quiz No.

3 13-12-2021
Computer Engg Project Management
Marks (15) CLO 3 Time: 30 min

Question # 1 (10+5)
Using the information from the following table, create an AON network activity
diagram:
a. Calculate each activity TE (rounding to the nearest integer), the total duration
of the project, its early start, early finish, late start, and late finish times, and
the slack for each activity. Finally, show the project’s critical path.
b. Now, assume that activity E has taken 10 days past its anticipated duration to
complete. What happens to the project’s schedule? Has the duration changed? Is
there a new critical path? Show your conclusions.
Quiz No. 3 13-12-2021
Computer Engg Project Management
Marks (15) CLO 3 Time: 30 min

c. Because Activity E has 10 days of slack associated with it, delaying the completion of E by 10 days uses up
all the slack; therefore, Activity E is now part of the project’s critical path. The overall project’s schedule
remains unchanged except there is a new critical path: A – E – G – I – K.