Professional Documents
Culture Documents
Email *
zhangyujiao2004@gmail.com
A Quality rating
C Cash Bow
A Number of complaints
D Staff turnover
A customer perspective
A Mnance perspective
All of them
1 and 2 only
2 only
2 and 4 only
:
( 20 ) In the last year a division's controllable return investment was 25% 0/2
and its controllable profit was $8000 . The cost of finance appropriate to
the division was 18% per annum . What was the division's controllable
residual income in the last year?
$5600
$22400
$74400
$76400
Correct answer
$22400
Economy
Effectiveness
EVciency
Externality
Correct answer
EVciency
:
( 28 ) The direct labour capacity ratio for a period was 104% . What could 2/2
have caused this?
Standard time for actual output beeing greater than budgeted hours
Standard time for actual output being less than budgeted hours
Financial
Customer
Internal
:
( 41 ) A company wants to encourage an investment centre to make new 2/2
investments. Performance measurement using which of the following KPIs
would achieve this?
ROI
ROCE
RI
IRR
Correct answer
86%
90%
105%
116%
~ Questio 6 ~ 0/2
A $1,000
B $3,500
C $7,500
D $11,000
Correct answer
B $3,500
:
~ Questio 8 ~ 2/2
A $10,000 Adverse
B $10,000 Favourable
C $25,000 Adverse
D $25,000 Favourable
~ Questio 9 ~ 2/2
A 800 kg
B 1,000 kg
C 1,200 kg
D None of these
Correct answer
A 800 kg
~ Questio 12 ~ 2/2
$384,000
$405,000
$432,000
$459,000
:
~ Questio 14 ~ 2/2
~ Questio 15 ~ 0/2
$4,250 favourable
$4,250 adverse
$5,250 favourable
$5,250 adverse
Correct answer
$5,250 adverse
:
~ Question 16 ~ Last month Zed Co purchased 750kg of raw materials for 2/2
$13,500. The material price variance was $1,125 favourable. What was the
standard price per kg of the raw materials?
$15.00
$16.50
$17.00
$19.50
Correct answer
The budgeted cost ascribed to the level of activity achieved in a budget centre in
a control period
~ Question 24 ~ 2/2
30000
40000
50000
60000
:
~ Question 26 ~ 2/2
Bulk discounts on purchases – the discount being given on all units purchased
Correct answer
$137,000
$103,000
$110,000
$130,000
Correct answer
$130,000
~Question 31 ~ A company's operating costs are 60% variable and 40% 2/2
fixed. Which of the following variances' values would change if the
company switched from standard marginal costing to standard absorption
costing?
~Question 35 ~ 2/2
$41,500
$40,800
$38,500
$39,200
:
~Question 36 ~ ( 10 mark ) - Task 1 2/2
20
30
40
50
1550
1650
1750
1850
:
Task 2 During June 450 tables were produced, which used 950 mand 2/2
5,000 labour hours at a total cost of $113,400. Actual fixed overheads for
the month were $21,000. Calculate the following variances: Labour
Efficiency Variance [ no need to answer ( Favourable , Adverse ) Just only
amount ]
8000
7000
6000
5000
Task 2 During June 450 tables were produced, which used 950 mand 2/2
5,000 labour hours at a total cost of $113,400. Actual fixed overheads for
the month were $21,000. Calculate the following variances: Labour Rate
Variance [ no need to answer ( Favourable , Adverse ) Just only amount ]
11400
12400
13400
14400
:
Task 2 During June 450 tables were produced, which used 950 mand 2/2
5,000 labour hours at a total cost of $113,400. Actual fixed overheads for
the month were $21,000. Calculate the following variances: FPOH
Expenditure Variance [ no need to answer ( Favourable , Adverse ) Just
only amount ]
500
1000
1500
2000
Time
: AM
:
Task 1 - Calculate the direct labour rate variance for June [ no need to 0/2
answer ( Favourable , Adverse ) Just only amount ]
432000
442000
452000
400000
Correct answer
432000
Calculate the variable overhead efficiency variance for June [ no need to 0/2
answer ( Favourable , Adverse ) Just only amount ]
170000
175000
180000
185000
Correct answer
180000
:
Task 2 The sales volume profit variance reported for June was $24,000 0/2
(A). Seashell Co is considering using standard marginal costing as the
basis for variance reporting in the future. Calculate the sales volume
variance to be shown in a marginal costing operating statement for June. [
no need to answer ( Favourable , Adverse ) Just only amount ]
23600
33600
34600
35600
Correct answer
33600
Task 3 (i) In July, Seashell Co's management accountant thinks that the 2/2
direct material price and direct material usage variances could be
interrelated. Which of the following could explain their interrelationship?
Materiality
Controllability
Personnel involved
Option 1
Task 1 Select the appropriate words, phrases or numbers to correctly complete the
commentary on the last month’s results.
Option 1
absorption
marginal
:
In the last month actual selling price was ____________ standard. 1/1
higher than
lower than
equal to
$1,210,000
$1,310,000
Correct answer
$1,310,000
:
Production was ____________ than budgeted. 1/1
Materials caused the biggest cost variance, where a decision to pay 1/1
____________.
less than
more than
Correct answer
This content is neither created nor endorsed by Google. - Terms of Service - Privacy Policy
: