Professional Documents
Culture Documents
Explanation:
- Purchase requisition is the principal form required in purchasing. It is like a
voucher, designed according to its demand.
- Purchase department issues purchase order. Purchase order is also a principal
form which gives the vendor a description of the goods and services desired as
well as terms, prices, and shipping instructions. Nowadays, purchase department
is also named as procurement department
- Accounting department finalizes the amounts that need to be paid but they are
not authorized to pay. Treasurer signs for the payment and they are not included
in the accounting department.
1
Quantitative Models
Planning Materials
Requirements
Planning deals with two Fundamental Factors
1. The Quantity 2. The Time to purchase
Explanation:
2
Economic Order Quantity (EOQ)
The order size where cost of material is
minimum
Carrying Cost = Ordering Cost
Total Cost
Low Point Annual Carrying Cost
Costs
Economic Order
Quantity (EOQ)
Explanation:
Economic order quantity (EOQ) is the amount of economic inventory ordered at one
time that minimizes annual inventory cost. If a company buys materials infrequently
and in large quantities, the cost of carrying the inventory is high because of the
sizeable average investment in inventory. If purchase is made in small quantities in
frequent orders correspondingly high ordering cost can result. Thus the optimum
quantity to order when carrying cost = ordering costs. We must also note that
carrying cost is inversely related to ordering cost. Economic order quantity is a
widely used traditional approach. Meanwhile, Enterprise Resource Planning (ERP) is
the advanced approach.
3
Mathematical Formulation of EOQ
Economic Order Quantity = 2 RU CO
CU CC
4
Derivation of the Equation
RU
1. Number of Orders Placed Annually: EOQ
RU CO
2. Annual Ordering Costs: EOQ
EOQ
3. Average Inventory: 2
RU CO CU CC EOQ
AC
EOQ 2
CU CC EOQ
AC RU CO EOQ 1
2
dAC CU CC
RU CO EOQ 2
dEOQ 2
dAC RU CO CU CC
dEOQ EOQ 2 2
Assuming, dAC (Here marginal cost is minimum).
0
dEOQ
2 RU CO
EOQ 2
CU CC
RU CO CU CC
EOQ 2 2
EOQ 2 CU CC 2 RU CO
2 RU CO
EOQ
CU CC
2 RU CO
EOQ
CU CC
5
Determining the Time to Order
Factors:
1. Time Needed for Delivery (Lead Time)
2. Rate of Inventory Usage (LT * Daily Usage)
3. Safety Stock – to minimize the possible stock out
Safety Stock will be maintained where total stock out cost and carrying
cost will be minimum.
Materials Control Method
Order Cycling Method or Cycle Review Method
Min-Max Method
Two-bin Method
Selective Control – ABC Plan
Explanation: While determining the time to order, the following three factors should
be taken into consideration:
1. Time needed for delivery: Lead time is the interval between the time an order is
placed and the time when the materials arrive on the factory floor, ready for
production.
2. Rate of inventory usage: Lead time * daily usage. If lead time or usage is below
expectation during an order period, the new materials arrive before the existing
stock is consumed thereby adding to the cost of carrying inventory. If lead time
or usage is greater than expected, a stock out will occur with its many forms of
cost, including lost customers. If average or normal lead time and usage are used
to determine an order point, a stock out can be expected on every other order.
3. Safety stock: to minimize the possible stock out an inventory cushion or safety
stock is often the least costly protection. Stock outs will occur only in times of
lead time. The basic problem is to determine the safety stock quantity. Time to
order depends on whether we need safety stocks or not. The optimum safety
stock is that quantity that results in the smallest total cost of stock outs plus safety
stock carrying costs.
6
- Method of Calculation of the Reorder point when the firm is:
Initially at every level of units we will conduct the trial and error method.
Thus, safety stock will be maintained where total stock out cost and carrying
cost will be at minimum.
7
1. Order Cycling Method or Cycle Review Method
Goods are examined at the end of each cycle, say, 30, 60, 90 days
Cycle time varies over the products
Costly items have lower cycle time and low-cost items have higher cycle time.
Explanation:
Order Cycling Method or Cycle Review Method : Goods
are examined at the end of each cycle, say, 30, 60, 90 days.
Cycle time varies over the types of material. High value
critical items usually require a short review cycle. For low-
cost, non-critical items a longer review cycle is common
because order quantities are large and a stock out is not as
costly. This is a rough and simple process.
Min-Max method: Quantities of most items are subject to
definable limits. Maximum quantity is established for each
item. Minimum level provides the margin of safety,
necessary to prevent stock outs during a reorder cycle.
Minimum level sets the order point and the order quantity
usually brings inventory up to the maximum level but not
more than that.
8
Two-Bin Method: Each stock item is stored in two bins,
piles, or bundles. First bin contains enough stock required
from receipt of an order to the placing of the next order.
Second bin contains normal lead time usage plus the safety
stock. When the first bin is empty and the second bin is
tapped a purchase requisition for a new supply is prepared.
Explanation:
So far this is the best method. It is also known as ABC plan. The term ABC is related to
material control method. Here inventories are classified into 3 types.
a. A – Type: High value, critical items are under the tightest
Control.
b. B – Type: Middle value items require moderate Control.
c. C – Type: Non-critical items are under simple physical controls
such as the two – bin method.
9
Problems
Requirement 1
2 RU CO
EOQ
CU CC
= √ (2 *24000*1.20)
10 * 0.10
= 240 packages
Requirement 2
Requirement 3
=24000*1.20 +10*0.10*240
240 2
=120+120
=$240
Requirement 4
10
Extra inventory = 400-200
= 200 packages
Days can be used = 200
66.67
= 3 days
After 3 days, the next order should be placed.
Requirement 5
The assumption that EOQ formula holds are always wrong, it is not fixed. So every time
the manufacturers will face problems. EOQ formula just gives a guideline for the
manufacturer.
Requirement 1
Order point = (Lead Time*Daily usage) + (maximum usage - normal usage)* Lead
Time
= (10*200) + (230-200)*10
=2000+300
=2300 units
Requirement 2
Normal maximum inventory = EOQ + safety stock
= 4000+300
= 4300 units
Requirement 3
Absolute maximum inventory =EOQ + safety stock + (Normal usage -Minimum usage)
*Lead time
= 4000+300+ (200-150)*10
= 4000+300+500
= 4800 units
Requirement 4
2 RU CO
EOQ
CU CC
Let, CU*CC = X
EOQ = √ (2 *RU*CO)
X
Or, 4000 = √ (2 *(200*250)*80)
X
Or, (4000)² = (√ 2 *(200*250)*80)²
X
11
Or, 2*(200*250)*80 = (4000)²
X
12
13