Professional Documents
Culture Documents
Civil Engineers
Geotechnical Engineering 161
February 2008 Issue GE1
Pages 49–57
doi: 10.1680/geng.2008.161.1.49
Paper 14800
Received 30/05/2006
Accepted 26/04/2007
Eric R. Farrell Myles L. Lawler
Keywords: geotechnical Senior Lecturer, Trinity Research Fellow, Trinity
engineering/piles & piling College Dublin, Ireland College Dublin, Ireland
The design of CFA piles in the stiff/hard lodgement till high undrained shear strength. The behaviour of structures
that underlies most of Dublin is usually based on founded in this deposit is of interest in many of the large
published experience from similar piles in other soils building and infrastructural projects that are currently under
that lack the high density and stiffness of this till. The construction in the city. Structures are frequently required to
results of load tests on two instrumented test piles are be founded on piles in this stratum, either because of overlying
presented, one 450 mm in diameter and 12.3 m long and made ground of doubtful quality or because its weathered
the other 600 mm in diameter and 11 m long, which upper zone, normally described as the Dublin brown boulder
were loaded to 3.15 MN and 4.5 MN respectively. A 1 m clay, has insufficient bearing capacity. The behaviour of piles
long instrumented dummy pile was formed at the same driven into this lodgement till has been previously researched
time as the prototype and was tested in the laboratory at the Croke Park site in Dublin; 1 however, such piles are less
to confirm the calibrations for use in interpreting the frequently used in recent projects because of noise and
instrumentation. The instrumented piles showed that vibration issues.
high average shaft resistances of 230 kPa and 270 kPa
were mobilised, which were of similar magnitude to This paper presents the results of load tests on two
those recorded on an instrumented driven pile in this instrumented CFA piles, one 450 mm in diameter and the other
lodgement till that was reported previously. The pile 600 mm in diameter, constructed in the Dublin black
load tests indicate an estimated Nc value of about 7 for lodgement till. The load–strain response of the piles was
the bearing capacity factor in ultimate end resistance, verified by forming a short dummy pile on site, which was
which is less than the value of 9 normally used and subsequently tested in the laboratory. The behaviour of these
considerably less than a value of about 55 estimated piles is compared with that expected from the measured
from the tests on the driven pile. The results also parameters and with that of a driven pile at Croke Park. The
indicate a change in the load–pile-head deflection curves results show the high shearing resistance that is developed
with time, which could be related to disturbance of the along the pile shaft, and that the end bearing capacity is less
ground caused by the construction process. than that obtained in the driven pile.
NOTATION
cu undrained cohesion
E secant soil Young’s modulus 2. INSTRUMENTED TEST PILES
Ep pile stiffness
K0 coefficient of earth pressure at rest 2.1. Description of piles
N standard penetration test N Two CFA test piles were constructed, one 450 mm in diameter
Nc end bearing capacity factor and 12.3 m long (pile 450) and one 600 mm in diameter and
P pile head load 11 m long (pile 600), using a CFA rig of 15–20 t m torque
Pu ultimate pile capacity capacity. The specification required the piles to have less than
Qu ultimate end bearing capacity 10 mm settlement at 1.5 times the design verification load
wl liquid limit (DVL), and to have an ultimate load capacity in excess of
wn natural water content 2.5 3 DVL. The DVLs of pile 450 and pile 600 were 1400 kN
wp plastic limit and 1800 kN respectively. The augers were bored to the
Æ shaft friction coefficient required depth, and 35 N concrete, with a maximum water–
Æmob mobilised shaft friction coefficient cement ratio of 0.5, a target slump of 175 mm and a maximum
r pile head settlement aggregate size of 20 mm, was pumped under pressure as the
mob mobilised shaft friction auger was withdrawn. Full-length reinforcement cages with
spacers, and with instrumentation attached to the
INTRODUCTION reinforcement bars, were then inserted into the fluid concrete.
Much of Dublin city is underlain by Dublin black boulder clay, The instrumented piles were reinforced with six T20 bars and
which is a lodgement till known for its very stiff behaviour and with R8 helical reinforcement at 300 mm centres.
Geotechnical Engineering 161 Issue GE1 CFA pile behaviour in very stiff lodgement till Farrell • Lawler 49
Downloaded by [ UNIVERSIDADE CRUZEIRO DO SUL] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
2.2. Dummy pile
A 1 m long dummy pile was formed within a 450 mm diameter
steel tube at the same time and with the same concrete,
reinforcement and instrumentation as used in the 450 mm
instrumented test pile. This dummy pile was cast to enable the
pile instrumentation and calibration to be tested in the
laboratories of Trinity College, Dublin.
6·1 m 5·9 m
The general properties of the brown and black lodgement till
have been presented in the literature. 2 The moisture contents
7·6 m and Atterberg limits on this site were similar to those
7·4 m T T
recorded on the Croke Park site, which was the location of
8·6 m
9·1 m the instrumented driven pile, 1 as can be seen from Fig. 4,
and are consistent with values expected for a heavily
10·1 m overconsolidated low-plasticity till. The plasticity index of
10·25 m
10·6 m 10·95 m
this till varied from 8% to 14% with an average of 10.8%.
The particle size distribution analyses on samples from the St
11 m
James’s Hospital recorded about 35–40% fines, which is
typical of these soils.
12·3 m
The high undrained shear strength and the presence of stones
Fig. 1. Diagrams of instrumented piles prevented successful recovery of undisturbed samples of the
lodgement till, a typical problem when investigating these
50 Geotechnical Engineering 161 Issue GE1 CFA pile behaviour in very stiff lodgement till Farrell • Lawler
Downloaded by [ UNIVERSIDADE CRUZEIRO DO SUL] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
1 km Undrained shear strength, cu: kPa
M50 Pile
0 250 500 750 1000
M1 450 600
Dublin Port 0
Fill
10
fit to the data shown, and this would agree with the
relationship between N and cu determined by Stroud and
4
Butler 4 for a soil with a plasticity index of 11. The SPT data
at St James’s Hospital, are similar to those reported1 for the
6 Croke Park site, and cu values of 350 kPa (N 60) and
450 kPa (N 75) are considered appropriate for the average
over the shaft and at the toe, respectively. The average
8 undrained shear strength over the shaft was less than the
Pile 450: w value of 450 kPa used to assess the shaft friction at the
Pile 600: w Croke Park site,1 as the N values above the base were
10 wp-wl: Saint James’s
slightly lower on the St James’s Hospital site. From previous
Croke Park: w
wp-wl: Croke Park research, the St James’s lodgement till would be expected to
have a high angle of shearing resistance of about 378.
Lawler5 inferred an apparent vertical yield stress of the order
Fig. 4. Moisture content (w), liquid (wl ) and plastic (wp ) limits
of Saint James’s and Croke Park sites of 1200–1500 kPa for the lodgement till at the Dublin Port
Tunnel site from the change in behaviour of the till in one-
dimensional compression.
Geotechnical Engineering 161 Issue GE1 CFA pile behaviour in very stiff lodgement till Farrell • Lawler 51
Downloaded by [ UNIVERSIDADE CRUZEIRO DO SUL] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
testing in the laboratory to determine the modulus of
deformation and strength of the concrete. The load–strain
Reaction frame characteristics of the dummy pile determined up to failure at
1500 kN are shown in Fig. 8.
5000
The proof load tests on the working piles were carried out in
the same manner as the instrumented piles and to the same
criteria; however, the load tests on the 450 mm diameter piles 4000
were at 22–28 days following construction and those on the
Pile head load: kN
600 mm piles were at 13–15 days, rather than the 3 and 5 days
allowed for the instrumented piles. The 450 mm and 600 mm 3000
1·8 m depth
3·9 m depth
150 5·9 m depth
Contractive strain
8·6 m depth
10·25 m depth
100
Microstrain
50
0
0 1 2 3
Expansive strain
⫺100
Fig. 7. Photograph of dummy pile test Fig. 9. Curing strains against time (Pile 450)
52 Geotechnical Engineering 161 Issue GE1 CFA pile behaviour in very stiff lodgement till Farrell • Lawler
Downloaded by [ UNIVERSIDADE CRUZEIRO DO SUL] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
VWSGs by applying the temperature readings taken at the time day pile stiffness (Ep ) of 35N concrete would be about 32 GPa,
in accordance with Pennington. 7 The graph generally compares with 3-day and 5-day stiffnesses of 85% and 90% of this value.
favourably with expected curing behaviour: thermal expansion Increasing the pile stiffness Ep for a 450 mm diameter pile in a
(up to about 1 day), followed by thermal contraction (up to finite element analysis—which assumes that the soil behaves as
about 2 days), followed by equilibrium. Furthermore, the top of a linear elastic isotropic material with a secant modulus, E, of
the pile, which is less constrained, deflected about twice as 150 MPa9 —from the measured value of Ep ¼ 23.5 GPa at 3
much as the pile centre. The overall contraction of the pile at days to Ep ¼ 50 GPa, which is greater than the estimated pile
the curing stage was about 1 mm at 2 days. These initial stiffness of 32 GPa at 28 days, did not fully account for the
deflections would cause initial shaft friction stresses to be higher stiffness of the proof piles at small strain, as can be seen
mobilised. from Fig. 11. It is therefore considered that some of the
difference in the performance between the instrumented and
proof piles is due to installation effects that decrease with time.
7. PILE TEST RESULTS
These installation effects could arise from pore pressures set up
Pile head load P against pile head deflection r of the
by the construction process, as was experienced in the tests on
instrumented piles is plotted along with the piles that were
driven piles on the Croke Park site, and could result in lower-
proof-tested to 1.5 times working load in Figs 10(a) and 10(b).
than-expected pile capacity.
These figures show that the proof pile tests, which were carried
out to the same loading specification as the instrumented pile,
The load distribution along the length of the piles is shown in
possessed an initial stiffer response than the instrumented piles.
Fig. 12 and in the form of shaft friction distribution in Fig.
The concrete of the proof piles would be stiffer than the
13. In the case of the 450 mm pile, included in Fig. 13(a) is
instrumented piles, as these were tested typically following 22–
the shaft friction mobilised prior to loading in the curing
28 days (450 mm diameter piles) and 13–15 days (600 mm
stage.
diameter piles), whereas the instrumented piles were tested
after 3 to 5 days. Published information 8 indicates that the 28-
The average shaft shear stresses generated by an applied load
are plotted against pile head displacement in Fig. 14(a) and as
Æmob against pile head displacement in Fig. 14(b). The shaft
shear stress is the difference in the load between instrument
4000
levels divided by the shaft area, measured within the
lodgement till. In the latter graph, the mobilised shaft friction
mob was divided by the average cu value along the shaft
3000
(¼ 350 kPa), giving Æmob ¼ mob /cu .
Pile head load: kN
Proof piles
The approximate end bearing response of pile 600 is
2000
demonstrated in Fig. 15 as a graph of end bearing mobilised
against pile head displacement and against pile toe
displacement. These plots are based on the assumption that
1000
the base readings, which were 0.4 m from the toe, represent
the actual pile toe response. In the case of the 450 mm pile
the base level gauges were 1.35 m from the toe, and the
0
0 4 8 12 errors in extrapolating the results to the base would be
Pile head deflection: mm excessive.
(a)
5000
Ep (GPa)
2500
4000 50 32 23·5
2000
Pile head load: kN
1500
2000
1000
0
0 10 20 30
0
Pile head deflection: mm 0 2 4 6 8
(b) Pile head deflection: mm
Fig. 10. Pile head load against pile head deflection: (a) 450 mm Fig. 11. Comparison of finite element analysis with measured
diameter piles; (b) 600 mm diameter piles pile head deflection
Geotechnical Engineering 161 Issue GE1 CFA pile behaviour in very stiff lodgement till Farrell • Lawler 53
Downloaded by [ UNIVERSIDADE CRUZEIRO DO SUL] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
Load: kN Shaft friction: kPa
0 500 1000 1500 2000 2500 3000 3500 ⫺150 0 150 300 450 600
0 0
Initial shaft friction
2 Maximum load
Depth below ground level: m
Initial ⫹ maximum
2
4
6
8 6
10
8
12 (a)
Load: kN 10
0 1000 2000 3000 4000 5000
0
Depth below ground level: m
12
2 (a)
4
Shaft friction: kPa
6 ⫺100 0 100 200 300 400
0
8
P ⫽ 450 kN
10
2 P ⫽ 1350 kN
12
(b) Depth below ground level: m P ⫽ 2250 kN
4 P ⫽ 3150 kN
Fig. 12. Load distribution against depth: (a) pile 450; (b) pile
600 P ⫽ 3607 kN
6 P ⫽ 4050 kN
P ⫽ 4481 kN
8. DISCUSSION
10
8.1. Pile settlement
The apparent soil stiffness E, based on the recorded settlements
12
of the piles, was highly non-linear. A modulus of E ¼ 150 MPa (b)
was, however, shown to produce a reasonable estimate of the
settlement of the proof-loaded piles at working load, when Fig. 13. Shaft friction distribution against depth: (a) pile 450;
applied in a finite element analysis (Fig. 11). This modulus (b) pile 600
value was the same as the soil modulus determined 9 for precast
concrete piles in Dublin till. Weltman and Healy’s formula for
the apparent modulus of piles in glacial till 10 could not be
applied in this case, as the value of cu for the Dublin
lodgement till exceeded the range of values cited. Using this
soil stiffness value, the ratio of E mobilised, Esoilmob , to cu in the Dublin till may be explained by the additional shaft
(¼ 350 kPa) would be about 430. friction capacity.
8.2. Ultimate pile capacity A hyperbolic extrapolation of the end bearing load against
A prediction of ultimate capacity Pu assuming a hyperbolic deflection for pile 600, shown in Fig. 16, gives an
extrapolation 11 is given in Fig. 16 for pile 600. (The Chin approximate ultimate end bearing Qu (end bearing not
extrapolation has been found to be applicable in cases where measured directly) of 900 kN. Assuming cu ¼ 450 kN/m2 at
sharing of the load is low. 12 ) Pu of about 7.25 MN for pile the pile base—in keeping with Fig. 5 (N 75) and Croke
600 was estimated. The ultimate capacity of pile 450 could Park 1 —the end bearing factor Nc is about 7 for pile 600. This
not be interpreted by the hyperbolic extrapolation, but the is in contrast to a value of Nc ¼ 55 for driven piles,1
measured maximum load was 3.15 MN. These were reflecting the differences in the effective mean stresses set up
considerably greater than the estimate of Pu for similar bored at the pile base in the pile construction phase. Nc is, however,
piles in Edmonton till, 13 which is also a stiff, limestone closer to but less than the value of Nc ¼ 9 generally assumed
based well-graded lodgement till, similar to the Dublin for stiff glacial till. 10,13 However, as the cu values were
lodgement till. For example, an ultimate capacity of 2350 kN estimated from N values, and as the pile was not actually
was measured for a pile 610 mm in diameter and 14.3 m taken to failure, there is a significant amount of uncertainty
long in Edmonton. The additional capacity of the CFA piles in this assessment.
54 Geotechnical Engineering 161 Issue GE1 CFA pile behaviour in very stiff lodgement till Farrell • Lawler
Downloaded by [ UNIVERSIDADE CRUZEIRO DO SUL] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
400 Est. ultimate Pu of 7250 kN
8000
7000
300
Average shaft friction: kPa
6000
600 pile Qu
5000
200 600 pile Pu
Load: kN
4000
Hyperbolic
extrapolation
100 3000
Pile 450
Pile 600
2000
Driven pile1
0 1000
0 10 20 30
Pile head deflection: mm
(a) 0
0 50 100 150 200 250 300 350 400 450 500
Pile deflection: mm
1·00
Fig. 16. Hyperbolic extrapolation of load–deflection curves to
ultimate load, Pu and Qu
Mobilised shaft friction coefficient
0·75 3150 kN
4500 kN
0·50 1750 kN
2700 kN 8.3. Shaft friction
Pile 450
The values of shaft friction shown in Fig. 13 are greater than
1800 kN the values normally quoted for auger-cast piles in glacial
0·25 Pile 600
till. 10,12 For example, assuming Æ ¼ 0.45 from these references
and cu ¼ 350 kN/m2 , an average shaft friction of 160 kN/m2
350 kN
0
would be expected over the length. This compares to an
0 10 20 30 average shaft friction mobilised, mob , over the entire length of
Pile head deflection: mm
the pile in the till (at maximum load) of 230 kN/m2 in the
(b)
450 mm pile, whereas the 600 mm pile mobilised an average of
270 kN/m2 . Furthermore, it is noted that some further shaft
Fig. 14. (a) Average shaft friction from gauges in till against pile
head deflection; (b) shaft friction coefficient Æmob from gauges friction could develop at higher loads. Estimates of the
in till against pile head deflection mobilised Æ for the piles are therefore in the region of 0.65–
0.75. Mobilised shaft shear stresses were about equal to that of
driven piles in Dublin lodgement till,1 where mob ¼ 200 kPa at
maximum load.
Geotechnical Engineering 161 Issue GE1 CFA pile behaviour in very stiff lodgement till Farrell • Lawler 55
Downloaded by [ UNIVERSIDADE CRUZEIRO DO SUL] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
increasing linearly to a point at about 8 m and then analysis for CFA piles in the very hard Dublin black boulder
reducing linearly to the pile toe. The difference in the clay is 7, which is considerably less than the value of about 55
response of the piles may be due to the very high stiffness interpreted for the driven pile on the Croke Park site. However,
of the till round pile 450, reflected in N values of 175 and as the cu values were estimated from N values, and as the pile
285 recorded at about 6 m depth. The relatively stiff ground was not actually taken to failure, there is a significant amount
may have resulted in the increased ground restraint on the of uncertainty in this assessment.
pile recorded at the same depth. Despite the 450 mm
instrumented pile mobilising less consistent shaft friction, The shear stress mobilised along the shafts of the instrumented
the overall deflection of the pile, r, was less than that of piles was non-linear with respect to depth. The average shear
the 600 mm pile. This was because very high shaft friction stresses mobilised along the shaft in the lodgement till were
was generated to compensate for those areas of the pile 230 kPa and 270 kPa in the 450 mm and 600 mm piles
where positive shaft friction was not mobilised. The respectively, which are higher than normally used in this soil
downdrag in the fill at the top of the 600 mm pile (Fig. but similar to those recorded on the driven pile at the Croke
13(b)) results from the unloading–reloading of the pile in Park site. These shaft shear stresses corresponded to Æmob of
the maintained load test (MLT). 0.65 and 0.75 respectively.
56 Geotechnical Engineering 161 Issue GE1 CFA pile behaviour in very stiff lodgement till Farrell • Lawler
Downloaded by [ UNIVERSIDADE CRUZEIRO DO SUL] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.
Information Association, London, 1978, CIRIA publication 12. FLEMING W. G. K. A new method for single pile settlement
PG5. prediction and analysis. Géotechnique, 1992, 42, No. 3,
11. CHIN F. The inverse slope as a prediction of [the] ultimate 411–425.
bearing capacity of piles. Proceedings of the 3rd South East 13. THOMSON S. Evaluation of pile load tests in the Edmonton
Asian Conference Soil Engineering, Hong Kong, 1972, area. Canadian Geotechnical Journal, 1981, 18, No. 2,
83–91. 313–316.
Geotechnical Engineering 161 Issue GE1 CFA pile behaviour in very stiff lodgement till Farrell • Lawler 57
Downloaded by [ UNIVERSIDADE CRUZEIRO DO SUL] on [12/09/16]. Copyright © ICE Publishing, all rights reserved.