You are on page 1of 22

PROJECT:G+2 DORMITORY BUILDINGLOCATION:DMUOWNER:DMUCONTRACTOR:HMGDF

TAKOFFSHEET FOR G+2 DORMITORY BUILDING

group 2 quntity surving


project

Timisi Dimen Squaring Description


A.SUB-STRUCTURE
1.EARTHWORK& EXCAVATION
1.1 Site clearance
Excavate to removal of top soil to an average depth of
20cm starting from natural ground level by taking 1m
working space for both sides.

34.07
10.62
l=32.07+2=34.07
w=8.62+2=10.62
361.82M2.Total area of site clearance
1.2 Bulk excavation
excavate to remove poor strength of soil to an average
depth of 60cm in ordinary soil by taking 50cm working
space in each side.
33.07 l=32.07+1=33.07m
9.62 w=8.62+1=9.62m
0.6 d=0.6m
190.88m3 Total volume of bulk excavation for structural
1.2.1 Excavation for pavement
excavating for diches and pavement area arround the
building with 100mm thickeness of stone pavement and
red ash with 2% slope and up to 400mm compacted earth
35.49 L=34.49+1=35.49m
2.61 W=1.61+1=2.61m
0.6 D=0.60m
55.58m3 total volume of pavement excavation and dich
1.3 pit excavation
excavation for isolated footing pads by taking 25cm
working space in each side
1.3.1 footing 1
l=1.9+0.5=2.4
2.4 w=1.9+0.5=2.4
6/ 2.4 d=2
2
69.12m3
add
1.3.2 footing 2
12/ l=2
2 w=2
2 d=2
2
96m3
add
1.3.3 footing 3
l=1.8
6/ 1.8 w=1.8
1.8 d=2
2
38.88 m3
add
1.3.4 footing 4
2/ 1.3 l=1.3
1.3 w=1.3
2 d=2
6.76 m3
add
210.76 m3 Total volume of pit excavation

22
PROJECT:G+2 DORMITORY BUILDINGLOCATION:DMUOWNER:DMUCONTRACTOR:HMGDF
TAKOFFSHEET FOR G+2 DORMITORY BUILDING

1.4 Trench excavation


excavate for masonry work with depth of 100cm from
reduced ground level by taking 50cm width.
76.61 l=76.61
0.5 w=0.5
1 d=1
38.30 m3 Total volume of trench excavation
1.5 Backfill
filling selecting material arroung footing pads
concrete work
for footings
footing 1
1.9 l=1.9
6/ 1.9 w=1.9
0.5 d=0.5
10.83 m3
add footing 2
1.5 l=1.5
12/ 1.5 w=1.5
0.4 d=0.4
10.80 m3
add
footing 3
6/ 1.3 l=1.3
1.3 w=1.3
0.3 d=0.3
3.04 m3
add
footing 4
0.8 l=0.8
2/ 0.8 w=0.8
0.2 d=0.2
0.26 m3
add
for foundation column
column 1
0.2 l=0.2
8/ 0.4 w=0.4
1.5 d=1.5
0.96 m3
add
column 2
0.2 l=0.2
12/ 0.4 w=0.4
1.6 d=1.6
1.54 m3
add
column 3
0.2 l=0.2
4/ 0.4 w=0.4
1.7 d=1.7
0.54 m3
add
column 4
0.25 l=0.25
2/ 0.25 w=0.25
1.8 d=1.8
0.23 m3
add
28.20 m3 total volume of concrete
210.76 m3
ddt
28.20 m3
182.56 m3 Total volume of back fill for pit excavation
back fill for bulk excavation
filling of bulk excavation with selected material by
deducting thickness of hardcore,RC-slab thickness and
thickness of cement screed
31.67 L=31.67m
11.22 W=11.22m
0.22 D=0.22m
78.17m3 back fill for bulk excavation
260.73m3 Total volume of backfill for earth work excavation

22
PROJECT:G+2 DORMITORY BUILDINGLOCATION:DMUOWNER:DMUCONTRACTOR:HMGDF
TAKOFFSHEET FOR G+2 DORMITORY BUILDING

1.6 CART AWAY


disposal of surplus and unwanted materials away from
the site
72.36m3 site clearance=361.82*0.2=72.36m3
add
190.88m3 bulk volume
a add
57.58m3 pavement
add
210.76m3 pit volume
add
38.30m3 trench volume
add
569.88m3
ddt
182.56m3 backfill volume
387.32m3 Total volume of backfill
1.7 hardcore
25cm crushed stone for ground floor slab
on axis 1-2 from AB-CD-DE-EF-FG-GH
6/ 4.61 l=4.61
2.81 W=2.81
77.72M2
add
4.61 on axis 2-3 from AB-CD-DE-EF-FG-GH
4.81 l=4.61
6/ 133.04m2 W=4.81
ADD
on axis 1-2 from B-C
1/ 2.81 L=2.81
2.81 W=2.81
7.89M2
ADD
ON AXIS 2-3 from B-C
1/ 2.81 L=2.81
4.81 W=4.81
13.51M2
add
232.16M2 TOTAL AREA OF HARD CORE
2.CONCRETE WORK
2.1 Lean concrete
2.1.1under footing pad
5cm thick of c-5 concrete for leveling and preventing
the reinforcement bar from resting
pad 1
6/ 1.9 l=1.9
1.9 w=1.9
21.66m2
add
pad2
12/ 1.5 l=1.5
1.5 w=1.5
27.00m2
add
pad3
6/ 1.3 l=1.3
1.3 w=1.3
10.14m2
add
0.8 pad4
2/ 0.8 l=0.8
1.28m2 w=0.8
add
60.08m 2
total area of lean concrete under pads

22
PROJECT:G+2 DORMITORY BUILDINGLOCATION:DMUOWNER:DMUCONTRACTOR:HMGDF
TAKOFFSHEET FOR G+2 DORMITORY BUILDING

2.1.2lean concrete for grade beam


for internal grade beam on axis B,C,D,E,F&G
7.62 l=7.62
6/ 0.2 w=0.20
9.13m2
add
on axis 2
30.47 l=30.47
0.2 w=0.2
6.09m2
add
15.22m2 total lean concrete for internal grade beam
2.1.3under massonary
76.61 l=76.61m
0.5 w=0.5m
38.31m2 total lean concrete under massonary work.
2.2 c-25 RC concrete
2.2.1 RC concrete for footing pad
for F1
6/ 1.9 L=1.9m
1.9 w=1.9m
0.5 d=0.5m
10.83m3
add
for F2
12/ 1.5 L=1.5m
1.5 w=1.5
0.4 d=0.4m
10.80m3
add
for F3
6/ 1.3 l=1.3
1.3 w=1.3
0.3 d=0.3
3.04m3
add
for F4
2/ 0.8 l=0.8
0.8 w=0.8
0.2 d=0.2
0.26m3
add
24.93m3 Total volume of footing pad RC concrete
2.2.2 Foundation Colomuns
for C1
8/ 0.2 l=0.2
0.4 w=0.4
1.5 d=1.5
0.96m3
add
for C2
12/ 0.2 l=0.2
0.4 w=0.4
1.6 d=1.6
1.54m3
add
for C3
4/ 0.2 l=0.2
0.4 w=0.4
1.7 d=1.7
0.54m3
add
for C4
2/ 0.25 l=0.25
0.25 w=0.25
1.8 d=1.8
0.23m3
add
3.27m3 Total valome of RC concrete for foundation columns work

22
PROJECT:G+2 DORMITORY BUILDINGLOCATION:DMUOWNER:DMUCONTRACTOR:HMGDF
TAKOFFSHEET FOR G+2 DORMITORY BUILDING

2.2.3 RC concrete for Grade beam


for GFB 1
2/ 8.62 l=8.62
0.2 w=0.2
0.5 d=0.5
1.72m3
add
for GFB 2
6/ 8.62 l=8.62
0.2 w=0.2
0.5 d=0.5
5.17m3
add
for GEB 3&4
2/ 30.47 l=30.47
0.2 w=0.2
0.5 d=0.5
6.09m3
add
for GFB 5
4.61 l=4.61
0.2 w=0.2
0.5 d=0.5
0.46m3
add
for GEB 6
23.05 l=23.05
0.2 w=0.2
0.5 d=0.5
2.30m3
add
for GEB 7
2.81 l=2.81
0.2 w=0.2
0.5 d=0.5
0.28m3
add
15.06m3 Total RC concrete for grade beam
2.2.4 RC concrete for ground floor slab
on axis 1-2 from DE,EF,FG,GH
4/ 4.62 l=4.62
2.71 w=2.71
50.08m2
add
on axis 2-3 from DE,EF,FG,GH
4/ 4.62 l=4.62
5.11 w=5.11
94.43m2
add
on axis 1-2 from AB,CD,
2/ 4.61 l=4.61
2.71 w=2.71
24.99m2
add
on axis 2-3 from AB,CD
2/ 4.61 l=4.61
5.11 w=5.11
47.11m2
add
on axis 1-2 from DC
2.81 l=2.81
2.71 w=2.71
7.62m2
add
on axis 2-3 form BC
2.81 l=2.81
5.11 w=5.11
14.36m2
add
239.31m2 Total volume of RC concrete for ground slab

22
PROJECT:G+2 DORMITORY BUILDINGLOCATION:DMUOWNER:DMUCONTRACTOR:HMGDF
TAKOFFSHEET FOR G+2 DORMITORY BUILDING

2.3 FORMWORK
2.3.1 formwork for foundation footing pads
for F1
6/ 7.7 l=7.7
0.5 d=0.5
23.10m2
add
for F2
12/ 6.1 l=6.1
0.4 d=0.4
29.28m2
add
for F3
6/ 5.3 l=5.3
0.3 d=0.3
9.54m2
add
for F4
2/ 3.3 l=3.3
0.2 d=0.2
1.32m2
add
63.24m2 Total area of for formwork footing pads
2.3.2 for foundation columns
for C1
8/ 1.3 l=1.3
1.5 d=1.5
15.60m2
add
fo2r C2
12/ 1.3 l=1.3
1.6 d=1.6
24.96m2
add
for C3
4/ 1.3 l=1.3
1.7 d=1.7
8.84m2
add
for C4
2/ 1.1 l=1.1
1.8 d=1.8
3.96m2
add
53.36m2 Total area of formwork for foundation column.
2.3.3 Formwork for grade beam
for GFB1
2/ 16.69 l=16.69
0.5 d=0.5
16.69m2
add
for GFB 2
6/ 16.04 l=16.04
0.5 d=0.5
48.12m2
add
for GFB 3
62.54 l=62.54
0.5 d=0.5
31.27m2
add
for GFB 4
60.94 l=60.94
0.5 d=0.5
30.47m2
add
for GFB5
9.22 l=9.22
0.5 d=0.5
4.61m2
add
for GFB 6
47.33 l=47.33
0.5 d=0.5
23.66m2
add
for GFB 7
5.62 l=5.62
0.5 d=0.5
2.81m2
add
157.63m2 Total area of formwork for grade beam
3.MASONRY WORK
50 cm basaltic stone with 1:4 cement mortar for trench
excavation part below natural ground level for the
construction of foundation wall
76.61 l=76.61m
0.5 w=0.5m
1 D=1m
38.30m3 total summary of masonry work for foundation wall

22
PROJECT:G+2 DORMITORY BUILDINGOWNER:DMUCONTRACTOR:HMGDFLOCATION DMU REINFORCEMENT BAR SCHEDULE

REINFORCEMENT BAR SCHEDULE FOR SUB-STRUCTURE

reinforcement bar schedule for footing pad

No. of Total length of reinforcement bar (m)


No.of Elemen
STRUCTURE LOCATION Shape Dia. (mm) bar (m) t (m) Length 6 8 10 12 14 16 18 20 24

FOOTING P footing 1 12 6 20 2.6 312

FOOTING P footing 2 10 12 22 2 528

FOOTING P footing 3 10 6 14 1.6 134.4

FOOTING P footing 4 10 2 10 0.9 18

Total length (m) 680.4 312

Unit weight (kg/m) 0.62 0.88

Weight (kg) 421.848 274.56

reinforcement bar schedule for column

No. of Total length of reinforcement bar (m)


Dia. No.of Elemen
STRUCTURE location Shape (mm) bar (m) t (m) Length 6 8 10 12 14 16 18 20 24

foundation column C-1 on pad -1 16 8 8 3.7 236.8

foundation column C-2 on pad -2 16 8 8 4 256

foundation column C-3 on pad-3 16 8 8 4 256

foundation column C-4 on pad-4 16 4 8 3 96

Total length (m) 844.8

Unit weight (k.g/m) 1.56

Weight (kg) 1321.64


PROJECT:G+2 DORMITORY BUILDINGOWNER:DMUCONTRACTOR:HMGDFLOCATION DMU REINFORCEMENT BAR SCHEDULE

REINFORCEMENT BAR SCHEDULE FOR GROUND SLAB

No.of Total length of reinforcement bar(m)


Elemen No. of
STRUCTURE LOCATION Shape Dia. (mm) t (m) bar (m) Length 6 8 10 12 14 16 18 20 24

GFS1 horizintal 8 1 192 4.3 825.6

vertical 8 1 122 4.76 580.72

GFS2 horizintal 8 1 192 4.3 825.6

vertical 8 1 120 2.76 331.2

GFS7 horizintal 8 1 21 2.7 56.7

vertical 8 1 120 2.76 331.2

Total length (m) 2951.02

Unit weight (kg/m) 0.39

Weight (kg) 1150.9

reinforcement barschedule for beam

No.of No. of Total length of reinforcement bar (m)


bar Eleme Lengt
STRUCTU LOCATION Shape Dia. (mm) (m) nt (m) h 6 8 10 12 14 16 18 20 24
Grade bea 14 3 2 9.3 55.8
GFB1 14 3 2 9.3 55.8
Grade bea 14 2 6 9.3 111.6
GEB2 14 2 6 9.3 111.6
Grade bea 14 3 1 12 36
GEB3
14 3 1 10.4 31.2
14 3 1 12 36
14 3 1 8.5 25.5
14 6 1 10 60
14 3 1 5.5 16.5
14 3 1 12 36
14 3 1 10.4 31.2
Grade bea 14 3 1 12 36
14 3 1 8.5 25.5
14 3 1 10 30
14 3 1 10 30
14 3 1 5.5 16.5
GFB4 14 3 1 5.7 17.1
Grade bea 14 3 1 5.7 17.1
GFB5 14 3 1 12 36
Grade bea 14 3 1 6 18
14 3 1 8.6 25.8
14 3 1 10.3 30.9
14 3 1 10 30
14 3 1 5.5 16.5
GFB6 14 3 1 4.1 12.3
Grade bea 14 3 1 4.1 12.3
GFB7
Total length(m) 961.2
Unit weight(kg/m) 1.19
weight(kg) 1144
PROJECT:G+2 DORMITORY BUILDINGOWNER:DMUCONTRACTOR:HMGDFLOCATION DMU REINFORCEMENT BAR SCHEDULE

REINFORCEMENT BAR SCHEDULE FOR STIRRUP

No.of Total length of reinforcement bar stirups (m)


Elemen No. of
structure Shape Dia. (mm) t (m) bar (m) Length 6 8 10 12 14 16 18 20 24

Foundation Column 1 6 6 9 0.9 48.6

Foundation Column 2 6 12 9 1.2 129.6

Foundation Column 3 6 6 10 0.9 54

Foundation Column 4 6 2

GFB -1 8 2 42 1.4 117.6

GFB -2 8 6 42 1.4 352.8

GFB -3 8 2 159 1.4 445.2

GFB -4 8 2 159 1.4 445.2

GFB -5 8 1 24 1.4 33.6

GFB -6 8 1 120 1.4 168

GFB -7 8 1 15 1.4 21

total length(m) 232.2 1113

unitweight(kg/m) 0.22 0.39

weight(kg) 51.08 434.07

BAR SCHEDULE FOR SUPER STRUCTURE

structure shape diameter length no.bar no.ele t.bar Æ6 Æ8 Æ10 Æ12 Æ14 Æ16 Æ18 Æ20

elevation column G+0

C1 16 4 8 8 256

C2 16 4 6 12 288

C3 16 4 4 4 64

Total length(m) 608


Unit weight(kg/m) 1.56
weight(kg) 948.5
Elevation column G+1

C1 16 4 6 8 192

C2 16 4 4 12 192

C3 16 4 4 4 64

Total length(m) 448


Unit weight(kg/m) 1.56
weight(kg) 698.9

Elevation column G+2

C1 16 3.2 4 8 102.4

C2 16 3 4 12 144

C3 16 3 4 4 48

Total length(m) 294.4


Unit weight(kg/m) 1.56
weight(kg) 459.3
PROJECT:G+2 DORMITORY BUILDINGOWNER:DMUCONTRACTOR:HMGDFLOCATION DMU REINFORCEMENT BAR SCHEDULE

First&Second floor beam

FB-1 14 9.3 2 4 74.4

14 9.3 2 4 74.4

FB-2 14 2.4 2 12 37.6

20 7.7 2 12 184.8

20 2.8 2 12 67.2

20 2.2 2 12 52.8

14 4.6 2 12 110.4

20 5.9 3 12 212.4

FB-3 14 12 2 4 96

14 6 2 4 24

14 8.6 2 4 68.8

14 10.3 2 4 82.4

14 10 2 4 80

14 5.5 2 4 44

FB-4 16 5.7 3 4 68.4

16 5.7 4 4 91.2

FB-5 14 3.9 2 2 15.6

14 3.9 2 2 15.6

FB-6 16 2.4 2 2 9.6

20 7.7 4 2 61.6

20 2.8 1 2 5.6

14 3.9 2 2 15.6

20 5.9 4 2 47.2

Total length(m) 738.8 169.2 631.6


Unit weight(kg/m) 1.19 1.56 2.4
weight(kg) 879.2 264 1516
PROJECT:G+2 DORMITORY BUILDINGOWNER:DMUCONTRACTOR:HMGDFLOCATION DMU REINFORCEMENT BAR SCHEDULE

Slab for toilet

b/n axis 1&2 12 8.5 22 2 374

b/n axis A&B 10 3 33 2 108.2

b/n axis 2&3 12 8.5 37 2 629

b/n axis A&B 10 3 36 2 216

b/n axis A&B 10 12 39 2 936

b/n axis 2&3 12 6.8 36 2 489.6

b/n axis A&B 12 2.6 59 2 306.8

Ribbed slab

b/n axis C&H 6 8.6 29 2 499.96

b/n axis C&H 6 24.5 81 2 392.8

b/n axis B&C 6 3.01 10 2 60.4

Total length(m) 953.16 1260 1799


Unit weight(kg/m) 0.22 0.61 0.88
weight(kg) 209.7 768.7 1583
Striup for ELC

ELC-1 6 1.2 40 6 288

ELC-2 6 1.2 40 12 576

ELC-3 6 1.2 40 6 288

Total length(m) 1152


Unit weight(kg/m) 0.22
weight(kg) 253.44
Striup for Beam

FB-1 10 1.36 41 4 223.04

FB-2 10 1.36 68 12 110.9

FB-3 8 1.36 68 4 369.9

FB-4 8 1.36 68 4 369.9

FB-5 8 1.36 68 2 184.9

FB-6 10 1.36 65 2 176.8

Total length(m) 924.7 333.9


Unit weight(kg/m) 0.39 0.61
weight(kg) 360.6 203.7
Top tie beam

TB-1 8 1.36 56 2 152.32

TB-2 8 0.5 160 3 240

Total length(m) 392.32

unitweight(kg/m) 0.22

weight(kg) 86.3104
TIMISINDimensionSquaring Description
B.SUPER STRUCTURE
1.CONCRETE WORK
Reinforced concrete in class C-25 (with a 28-day 15cm cube crushing strength of 25MPa), cast
into formworks and vibrated around rod reinforcement bars.( formwork & reinforcement bars are
measured separately.) in: "Type of cement to be ordinary portland cement (OPC)"
for elevation columns
0.4 l=0.4
24/ 0.2 w=0.2
2.61 h=2.61
5.02m3 for ground floor
add
0.4 l=0.4
24/ 0.2 w=0.2
2.61 h=2.61
5.02m3 for first floor
add
0.4 l=0.4
24/ 0.2 w=0.2
2.61 h=2.61
5.02m3 for second floor
add
15.06m3 total volume of elevation column concrete
Beam concrete
for firstfoor
FB-1
7.82 L=7.82
4/ 0.2 w=0.2
0.48 D=0.48
3.00M3
add
FB-2
7.82 L=7.82
12/ 0.2 w=0.2
0.48 D=0.48
9.00M3
add
FB-3
4/ 23.05 L=23.05
0.2 w=0.2
0.48 D=0.48
8.86M3
add
FB-4
4.61 L=4.61
4/ 0.2 w=0.2
0.48 D=0.48
1.78M3
add
FB-5
2/ 2.81 L=2.81
0.2 w=0.2
0.48 D=0.48
0.54M3
add
FB-6
2/ 7.82 L=7.82
0.2 w=0.2
0.48 D=0.48
1.50M3
add
24.68M3 TOTAL VOLUME OF CONCRETE FOR FIRST & SECOND FLOOR BEAM
add FOR TOP TIE BEAM
162.57 L=162.57
0.2 w=0.2
0.3 D=0.3
9.75M3
add
Slab Concrete for toilet room
7.62 l=7.62
2/ 4.61 w=4.61
0.28 d=0.28
19.67m3
add
54.10m3 total volume of concrete for first,second &top tie beams
2.FORM WORK
for elevation columns( G+0,G+1&G+2)
24/ 1.3 L=1.3 1.3*7.83=10.179m
7.83 H=7.83
244.29M2 Total area of formwork for columns
formwork for beams
for first and second floor beams
FB-1
4/ 23.91 L=23.91
0.48 W=0.48
45.9M2
add FB-2
12/ 22.86 L=22.86
0.48 D=0.48
131.67M2
add FB-3
4/ 69.17 L=69.17
0.48 D=0.48
132.81M2
add FB-4
4/ 13.83 L=13.83
0.48 D=0.48
26.55M2
add FB-5
6/ 8.43 L=8.43
0.48 D=0.48
24.27M2
add FB-6
22.86 L=22.86
2/ 0.48 D=0.48
21.94M2
add
ROOF BEAM FORM WORK
RB-1
22.86 L=22.86
8/ 0.3 D=0.3
54.86M2
add RB-2
2/ 93.06 L=93.06
0.3 D=0.3
55.83M2
110.69 m2 total summury of formwork for roof beam
FORM WORK FOR TOILET ROOM CONCRETE SLAB
2/ 4.61 L=4.61
7.62 W=7.62
70.25M2
add
564.08m2 total form work for beams & toilet concrete slab
3.BLOCK WORK
Supply and construct class 'A' 200x200x400mm HCB wall with cement mortar 1:4 mix ratio
External block work
Block work for all elevation(Front,Rear,Right,Left,)
3/ 70.16 l=70.16
2.61 h=2.61
549.35m2
ddt
31/ 1.21
1.57
58.90m2 window 1
ddt
6/ 0.61
0.57
2.08m2 window TW1
ddt
6/ 2.01
0.57
6.87M2
ddt
2/ 1.61
2.1
6.76m2 Door 1
ddt
3/ 0.81
2.1
5.10m2 Door 5
ddt
469.64m2 Total area of External block work
Partition wall block work
3/ 77.2 l=77.2
2.61 h=2.61
604.8m2
ddt
30/ 0.81
2.1
51.03m2 Door 5
ddt
553.45m2 partion block work for dormitory
partition wall block work for toilet room
3/ 26.34 l=26.34
2.61 h=2.61
206.24m2 partion block work for toilet
parafit wall block work area

A=1/2*5.21*1.7=4.42M2

h=1.7
B=5.21

b=5.21 H=0.15

A=5.21*0.15=0.78M2

H=1.1
A=1/2*3.21*1.1=1.76M2

B=3.21
H=0.17

B=3.21 A=3.21*0.17=0.55M2
A=(4.42+1.76+0.78+0.55)*2=15M2
15M2 TOTAL BLOCK WORK AREA FOR PARAFIT WALL FOR LEFT AND RIGHT SIDE
Ribbed slab
precast beam (PB)
L=8.22m
L=8.22m
5 14 number of precast beam =14pcs
70 pcs total number of PB1
2 70
140 pcs total number of PB1 for first & second floor
Hollow concrete block (HCB)
L=4.61m
5 312 number of HCB = 312pcs
1560 pcs total number of HCB
2 1560
3120 pcs total number of HCB for first & second floor
add
L=4.12m
number of PB2 = 7 pcs
total number of PB2 =14pcs
number of HCB in one pcs = 15pcs
2 90 total HCB in one pcs = 90pcs
180 pcs of HCB for first & second floor on axis BC
add
3300 pcs of HCB required for first & second floor
140 pcs of PB1 for first & second floor
14 pcs of PB2 for first & second floor

4.FINISHING WORK
4.1 plastering
External wall for front ,rear,right &left side elevation (G+0,G+1&G+2)
3/ 70.56 l=70.56
2.61 h=2.61
552.48M2
ADD Internal plastering wall
3/ 70.56 l=70.56
2.61 h=2.61
552.48m2
ddt opening areas
1.21
1.57
56.99m2 W1
ddt
0.61
6/ 0.57
2.08m2 TW1
ddt
6/ 2.01
0.57
6.87m2 TW2
ddt
1039.02M2 Total area of plastering for external and internal wall
partition wall
30/ 14.84 l=14.84
2.61 h=2.61
1161.97m2
ddt
30/ 1.21
1.57
56.99m2
ddt
30/ 0.81
2.61
63.42m2
ddt
1041.56m2
3/ 26.34 ADD
2.61
206.24m2
ADD
1247.8m2 partition wall plastering

26.34
2.61
206.24m2 plastering for toilet room
Column plastering
24/ 3.6 l=3.6
7.83 h=7.83
676.51m2 plaster for elevation column (G+0,G+1,G+2)
Beam plastering
2/ 161.79 l=161.79
0.68 w=0.68
220.03m2 beam plastering for first and second floor
279.67 l=279.67
0.5 w=0.5
139.83m2 plastering for top tie beam
platering for slab
plastering of slab is equals to hard core area
hardcore area=239.31m2
2/ 239.31
478.62m2 plastering of slab
4.2PAINTING
wall Painting
1041.56m2 wall Painting is equals to wall plastering area =1041.56m2
676.51m2 column painting is equals to plastering area of column
Beam plastwring
359.86m2 beam painting is equals to plastering area of beam
2077.93m2 total area of painting for wall,column and beams
239.31m2 8mm chipwood ceiling finishing area
478.62m2 plastering of slab
4.3FLOOR FINISH
Cement screed of floor finish 30mm for crack protection is equals to hard core area
3/ 239.31 hardcore area=239.31m2
0.3
215.37m2 area of cement sceed for floor finish
4.4CEILING FINISHING
Plastering &painting of ceiling is equals to hardcore area
239.31m2 8mm chipwood ceiling finishing area
4.5WINDOW SILL
to prevent water entrance in side the wall
W1
1.21+0.05=1.26M
30/ 1.26
37.8m
TW1
6/ 0.66 0.61+0.05=0.66m
3.96m
TW2
6/ 2.06 L=2.01+0.05=2.06m
12.36m
54.12m Total summary of window sill
4.6PAVMENT FINISHING&DITHES
area of pavment L=32.07*2+((8.62+2*1.21)2)=86.22m
w=1.21m
86.22
1.21
104.33m2 area of pavment concrete
area of ditch =Πr2l/2
π 86.22 L=86.22m
0.2 R=0.2m
5.42m2 area of ditch concrete
109.75m2 Total area of pavment finish and ditchs concrete
4.7 Lean concrete for stair case
for tredes(steps)
L=1.25
W=0.3
Area of lean concrete for one step=1.25*0.3=0.375*9=3.375
Total no.of tredes up to 2nd floor is 36
13.5m2 Total area of lean concrete for trerdes =0.375*36=13.5m2
add
for landing
L=2.81
W=0.83
4.66m2 Area=(2.81*0.83)2=4.66m2
add
18.16m2 total summery of lean concrete for stair case
5.ROOFING
5.1ROOF COVER
Roof cover in percolated or galvanized EGA - 300, 0.3mm thick fixed to zigba purlins. Price
shall include G-28 flat sheet metal ridge cap with dev. length of 330 mm and UV resistant
washers. (Purlins measured separately and roof measured in horizontal projections)

33.05 L=33.05m
10.01 W=10.01m
330.83m2 Total summery of roof cover
5.2GUTTER
Supply and fix G-28 galvanized flat metal sheet gutter in accordance with the Architectural detail
drawing with development length of 720mm
2/ 33.05
66.1m Total summery
5.3DOMN PIPE
Supply and fix 100mm Galvanized dawn pipe at the required height of 10m
2/ 4 8pcs
5.4FACIABOARD
supply and fix 25mm thick face board
2/ 33.05 66.1m
5.5BATTEN
supply and fix40*50cm
4/ 33.05 132.2m
5.6Chipwood cielling
231.17m2 area of hard core
6.METAL WORK
6.1.WINDOW DOOR SCHEDULE
METAL FRAME FOR WINDOWS
WINDOW 1(1.21*1.57M)
LT=1.21*3+1.57*3=8.3m
30/ 8.3
250.2m TW1(0.61*0.57)
LT=0.61*2+0.57*2=2.36m
6/ 2.36
14.16m TW2(0.57*2.01)
6/ 5.16 LT=0.57*2+2.01*2=5.16m
30.96m METAL FRAME FOR DOOR
DOOR1(1.61*2.1)
LT=1.61*3+2.1*2=9.03m
4/ 9.03
36.12m DOOR 6(0.61*1.8)
LT=0.61*2+1.8*2=4.82M
30/ 4.82
144.6m MD1(2.83*2.285)
LT=19.6m
19.6m GLAZING WORK
WINDOW 1(1.21*1.57M)
30/ 1.21
1.57
56.99M2 TW1(0.61*0.57)
6/ 0.61
0.57
2.08M2 TW2(0.57*2.01)
6/ 2.01
0.57
6.87M2 DOOR GLAZING
DOOR1(1.61*2.1)
4/ 1.61
2.1
13.52M2 MD1(2.83*2.285)
4/ 2.83
2.285
25.92m2 6.2 STAIR CASE WORK
TREDE 4mm sheet metal
L=1.25m
w=0.3
36/ 1.25 D=0.004
0.3 1.25*0.3*0.004=0.0015m3
0.004 0.054m3 0.054m3*7850kg/m3=423.9kg
LANDING
L=2.81
2/ 2.81 W=0.83
0.83 D=0.004
0.004 0.0186M3*7850kg/m3=146.01kg
0.0186M3 Hand rail
FOR 50*40*2.5mm thick
2.934*0.05*2+0.04*2*0.0025+3.64*2*0.05*2+0.04*2*0.0025
0.728m3
m=0.728m3*7850kg/m3=371.8kg
for 25*25*2.5mm
2.934*0.025*2+0.025*2+3.64*0.025*2+0.025*2*0.0025=0.00164m3
m=0.00164*7850=12.9kg
BUALSTRAIDE
40*40*2.5mmthick
TL=1.235*4=4.94
(0.04*2+0.04*2)*0.0025*4.94=0.081M3
M=0.081m3*7850kg/m3=635.75kg
PLATE(2*400*250*5mmthick)
LT=1.46m
o.25*0.005*1m=0.00125m3
M=0.00125m3*7850kg/m3=15.7kg
6.2 spiral stair
for one steps(isoclus triangle)
L=1.237m
W=0.364m
D=0.03m

V=1/3*1.237*0.364*0.03=0.0045m3 but 18 steps up to one floor


TV=0.0045*36=0.1621m3
M=0.1621m3*7850kg/m3=1272.46kg
1272.46kg for landing
add L=3.11m
W=1.3m
D=0.03
V=(3.11*1.3*0.03)2=0.243m3
M=0.243m3*7850kg/m3=1904.3kg
1904.3kg
add plate
(2*300*300*8) at4 dia.20 hole fpr J bolt connection
pcs at detail A
2pcs 2*300*300*5mm at 4 dia. 14 hole for J - bolt connection

2*200*200*5m Connection plate


8pcs pcs at C
1pcs 150*408*4m
pcs at detail D
1pcs

7.TRUSS

dia 100mm eucalyptus truss

To find the vertical members we use symilarity triangle


1.1/3.81=v1/0.6
v1=0.17m
tan ɵ =opp/adj=v1/0.6=0.17/0.6 =16°
to find v2,we use sinɵ=opp/hyp=v2/1.2
v2=sinɵ*1.2=0.32m
v3=0.277*2.4=0.64m
v4=3.6*0.277=1.1m
diagonal members
we use pythagorus theorem
d1=0.62+v2
d1=Ö0.62+0.322=0.68m
d2=1.22+v3
d2=Ö1.22+0.642=1.78m
d3=Ö1.22+1.12=2.41m

vertical members
v1'=0.59*1.5/5.8=0.15m
tan ɵ=0.15/0.59=14.26°
sinɵ=opp/hyp=0.246°
v2'=0.246*1.2=0.295m
v3'=0.246*2.4=0.59m
v4'=0.246*3.6=0.88m
v5'=0.246*4.8=1.18
v6'=1.5m
diagonal members
d1'=Ö0.2952+0.62=0.66m
d2'=Ö0.592+1.22=1.33m
d3'=Ö0.882+1.22=1.48m
d4'=Ö1.182+1.22=1.68m
d5'=Ö1.0912+1.52=1.85m
6.83m vertical members=v1+v2+v3+v4+v1'+v2'+v3'+v4'+v5'+v6'
9.61m horizontal members=8.42+0.59+0.6=9.61
11.5m diagonal members=d1+d2+d3+d1'+d2'+d3'+d4'+d5'=11.5m
9.69m rafter=3.6+4.8+0.201+1.091=9.69m
purlins

50x70mm zigba purlin

1m
d1=√(0.35m)²+(0.25)²
d1=√0.185m²
d1=0.43m
d2=0.43m
Lt=0.1+(0.35M)*2+(0.84)*3+0.85+0.54+0.1+(0.43)*2
Lt=0.1+0.7+2.52+1.39+0.1+0.86
Lt=5.37M+(0.25*6)
where M=0.84+0.85+0.84+0.84+0.54
M=3.91m
Lt=6*11.03m
L=66.18m
10 66.18
661.8 m
8.ELECTRICAL INSTALLATION WORK

SURFACE MOUNTED
single mounted flourecent lighting (ggpc)
33pcs*3=99pcs

CONDUCTOR OR WIRE
LT=3m*43=129m*3=387m with 15% allowance for wastage

CONDUIT
LT=3m*43=129m*3=387m with15%allowance for wastage

SOCKET
Ressedent mounted single socket outlet
10pcs*3=30pcs
Ressedent mounted double socket outlet
10pcs*3=30pcs
SWITCH
single switch
1pcs*3=3pcs
doubleswitch
11pcs*3=33pcs
two way switch
2pcs*3=6pcs
distribution board
1pcs*3=3pcs
MANHOLE
18PCS*3=54pcs
Going up cable E conductor
1pcs*3=3pcs

9.SANITARY INSTALLATION
water riser diagram GSP from water source of water closet
L=10.29+1.05m

Dia. 15 GSP shower (18pcs)


(0.8+2.5)=2.9m
52.2m 2.9*18=52.2
Dia.15 hand wash(18pcs)
L=0.8+1.2=2m
36m 2*18=36m
Dia. 15 foot wash (6pcs
L=0.8+0.6=1.4m
8.4m 1.4*6=8.4m
Dia. 15 Urine (6pcs)
L=0.8+0.6=1.4m
8.4m 1.4*6=8.4m
hand wash value=18pcs
Supply and fix Turkish type water closets made of
enameled cast iron ,complete with cast iron cistern and all
the necessary flushing systems and accessories including
water closet value=18pcs
get value=1pcs
fiting=24pcs

You might also like