ID Name Duration Predecessors Outline Level

1 PROPOSED G+0 COMMERTIAL BUILD 36.778d 1


2 SITE WORKS 6d 2
3 site clearing 2d 3
4 layout and staking out 1d 3 3
5 excavation 5d 4FS-2 d 3
6 CONCRET WORK 14.778d 2
7 set rebars 7d 5 3
8 forms and scafolding 4d 5SS+3 d 3
9 pouring of concrete for column 1.778d 7,8 3
10 pouring of concrete for wall 1d 3
11 pouring of elev column and beam 3d 3 3
12 MASONRY WORKS 6d 2
13 HCB wall instalation 6d 9,10 3
14 STRUCTURAL STEEL WORKS 8d 2
15 steel trusses and framings 8d 11FS+7 d 3
16 ROOFING 3d 2
17 roof cover 3d 15 3
18 FINISHING WORKS 16d 2
19 plastering 5d 13SF+1 d 3
20 painting works 4d 19FS+7 d 3
21 ELECTRICAL WORKS 4d 2
22 electrical works instalation 4d 13SS+2 d 3
23 WEEKLY MEETING 23.125d 2
24 WEEKLY MEETING 1 1d 3
25 WEEKLY MEETING 2 1d 3
26 WEEKLY MEETING 3 1d 3
27 WEEKLY MEETING 4 1d 3
ID Name Type Material Label Max Units Standard Rate Cost Per Use
1 CLAB Work 1,700% ETB10.00/hr ETB0.00
2 CARPENTER Work 400% ETB12.00/hr ETB0.00
3 STEELMAN Work 200% ETB12.00/hr ETB0.00
4 ASST STL MAN Work 200% ETB10.00/hr ETB0.00
5 ASST CARPENTER Work 200% ETB10.00/hr ETB0.00
6 MASON Work 200% ETB12.00/hr ETB0.00
7 WELDER Work 200% ETB15.00/hr ETB0.00
8 TINSMITH Work 200% ETB15.00/hr ETB0.00
9 PAINTER Work 400% ETB15.00/hr ETB0.00
10 ELECTRICIAN Work 300% ETB15.00/hr ETB0.00
11 GRADER Work 100% ETB200.00/hr ETB0.00
12 EXCAVATOR Work 100% ETB300.00/hr ETB0.00
13 BARBENDER Work 200% ETB20.00/hr ETB0.00
14 CONC.MIXER Work 100% ETB70.00/hr ETB0.00
15 WELDING MACHINE Work 100% ETB50.00/hr ETB0.00
16 ELECTRIC DRILL Work 200% ETB15.00/hr ETB0.00
17 POWER SPRAY Work 100% ETB50.00/hr ETB0.00
18 SANDER Work 100% ETB25.00/hr ETB0.00
19 CEMENT Material Bags ETB250.00 ETB0.00
20 LUMBER Material PCS ETB50.00 ETB0.00
21 REBARS Material KGS ETB35.00 ETB0.00
22 PLYWOOD Material PCS ETB200.00 ETB0.00
23 AGGREGATES Material M3 ETB500.00 ETB0.00
24 FINE SAND Material M3 ETB600.00 ETB0.00
25 STRUCTURAL METAL Material KGS ETB20.00 ETB0.00
26 PAINT Material GAL ETB300.00 ETB0.00
27 FUEL Cost ETB0.00
28 PROJ SUPV Cost ETB0.00
29 SNACK Cost ETB0.00
30 ELECTRIC Cost ETB0.00
31 ELECTL MATRIS Material ETB0.00 ETB0.00
Notes
Task Name Resource Name Work Units
site clearing CLAB 48 hrs 300%
site clearing GRADER 16 hrs 100%
site clearing FUEL
layout and staking out CARPENTER 32 hrs 400%
layout and staking out LUMBER 50 PCS 50 PCS
excavation CLAB 160 hrs 400%
excavation EXCAVATOR 40 hrs 100%
set rebars STEELMAN 112 hrs 200%
set rebars ASST STL MAN 112 hrs 200%
set rebars REBARS 500 KGS 500 KGS
forms and scafolding CARPENTER 64 hrs 200%
forms and scafolding ASST CARPENTER 64 hrs 200%
forms and scafolding PLYWOOD 200 PCS 200 PCS
pouring of concrete for column CLAB 85.33 hrs 600%
pouring of concrete for column MASON 28.45 hrs 200%
pouring of concrete for column CONC.MIXER 14.22 hrs 100%
pouring of concrete for column CEMENT 50 Bags 50 Bags
pouring of concrete for column AGGREGATES 12 M3 12 M3
pouring of concrete for column FUEL
pouring of concrete for wall CLAB 48 hrs 600%
pouring of concrete for wall MASON 16 hrs 200%
pouring of concrete for wall CONC.MIXER 8 hrs 100%
pouring of concrete for wall CEMENT 50 Bags 50 Bags
pouring of concrete for wall AGGREGATES 12 M3 12 M3
pouring of concrete for wall FUEL
pouring of elev column and beam CLAB 144 hrs 600%
pouring of elev column and beam MASON 48 hrs 200%
pouring of elev column and beam CONC.MIXER 24 hrs 100%
pouring of elev column and beam CEMENT 50 Bags 50 Bags
pouring of elev column and beam AGGREGATES 12 M3 12 M3
pouring of elev column and beam FUEL
HCB wall instalation CLAB 96 hrs 200%
HCB wall instalation MASON 96 hrs 200%
HCB wall instalation CEMENT 30 Bags 30 Bags
HCB wall instalation FINE SAND 6 M3 6 M3
steel trusses and framings STRUCTURAL METAL 1,000 KGS 1,000 KGS
steel trusses and framings ELECTRIC
roof cover CLAB 48 hrs 200%
roof cover TINSMITH 48 hrs 200%
roof cover ELECTRIC DRILL 24 hrs 100%
plastering MASON 80 hrs 200%
plastering CLAB 80 hrs 200%
plastering CEMENT 20 Bags 20 Bags
plastering FINE SAND 5 M3 5 M3
painting works PAINTER 96 hrs 300%
painting works CLAB 64 hrs 200%
painting works PAINT 30 GAL 30 GAL
electrical works instalation ELECTRICIAN 96 hrs 300%
electrical works instalation ELECTRIC DRILL 32 hrs 100%
WEEKLY MEETING 1 SNACK
WEEKLY MEETING 2 SNACK
WEEKLY MEETING 3 SNACK
WEEKLY MEETING 4 SNACK
Microsoft Office Project Template ID: 9876543210

Microsoft Office Project is a project management program designed to


help you plan and manage your projects and communicate project
information.

Whether you have a simple list of tasks or want to coordinate activities


across multiple projects, Project makes it easy to get started and learn as
you go.

With this template you can export data to Excel to perform more advanced
numerical analysis. Then you can import project data back into Project to
perform standard project tasks, such as:
* Seeing your tasks linked in a Gantt Chart
* Seeing how much work each person on the team has assigned to them
You can easily import this information back into Project and keep working
without reentering data.