Expanditure of Pent house and head room

SNO ITEMS Unite QUANTITY PER RATE TOTAL RATE


A-1 BRICK Nos 5400 8 43200
2 SAND Ton 12 2000 24000
3 CEMENT Nos 30 285 8550
4 MASON Lum 30000 30000
5 FLOORING Sft 150 75 11,250
ELECTRICAL LABOUR AND
6 MATERIALS Lus 7,500 7,500
7 ROOF Sheets BLUE Lus 14000 14,000
8 FRAMES BELOW SHEETS 5,000 5,000
9 WINDOW 5000 5,000
10 DOOR WITH FRAME 6500 6,500
11 PAINTING WITH LABOUR 12,000 12,000
12 TOILET PIPE & FIXTURES 6500 6,500
Total RS 173500

B-1 Head room all includings 120 600 72000


A+B Rs 245,500.00
Interior Expanditure as on day -16-03-2020
S.NO. Description Cost
1 As on day 27/02/2020 ply wood and 287000
internal Laminate and channels ect 93300

2 3 times delevery 3500


3 Lifting unload 3000
4 60 Falce ceiling light 30000
5 Car penter charge
15/02/2020 15000
25/02/2020 20000
2/3/2020 20000
9/3/2020 20000
16/03/2020 20000
6 Lifting Charges 1000
7 Tape and Misc 3200
8 Profiles 32000
9 Drawer Channels Baskets 14000
10 Table Top Granite 6000
11 Handle profile 19/03/2020 10666
12 Drawer Channels Baskets 19/03/2020 14000
13 Glass
14 Granite for Cracory Fitting labour charge
14 Ply and laminate

As on day 20/03/2020 Rs 592666


Advance from owner 550000
42666