PERHITUNGAN VOLUME BAJA

PROYEK : PT. INDOJAYA AGRINUSA


PEKERJAAN : PONDASI SILO
LOKASI : KIM MEDAN - SUMATRA UTARA

Jml/ttk Jml.
NO. URAIAN PEKERJAAN SAT. P L T W /plong Yg sama VOLUME TOTAL
(m) (m) (m) (Kg/m) @ (N) VOLUME

A. PEKERJAAN TOWER SUPPORT


Pekerjaan Pasang 1
1 Tower Support B1
- Angker Bolt 4M25 A325 p=70 cm bh 24,00
6,00 4,00 24,00

Pekerjaan Pasang 2
1 Tower Support B1
- Angker Bolt 4M25 A325 p=70 cm bh 32,00
8,00 4,00 32,00
2 Tower Support C
- Angker Bolt 4M25 A325 p=70 cm bh 16,00
4,00 4,00 16,00

B. PEKERJAAN PONDASI SILO


1 Siku 60x60x6 + cat ex. Jotun (1x primer 1x finish) kg 852,67
Aerasi
El. +2.10 11,00 5,42 2,00 2,00 238,48
0,52 5,42 2,00 2,00 11,27
El. +2.30 2,00 5,42 6,00 2,00 130,08
0,52 5,42 6,00 2,00 33,82
3,00 5,42 10,00 2,00 325,20
0,52 5,42 10,00 2,00 56,37
Void
El. 2,10 ( uk. 60x40cm ) 0,60 5,42 2,00 4,00 0,00
0,40 5,42 2,00 4,00 17,34
Arah Axs X
uk. 65x65cm 0,65 5,42 4,00 1,00 14,09
uk. 30x30cm 0,30 5,42 4,00 4,00 26,02

2 Pipa fumigasi Galvanish dia. 6" h=50cm tbl. 3mm + tutup plat 3mm ttk 20,00
1,00 20,00 20,00

TOTAL PEKERJAAN

Medan,
PT. OMETRACO ARYA SAMANTA

( )