Big M Company Distribution Problem

Objective: Minimize Cost

Shipping Cost
(per Lathe) Customer 1 Customer 2 Customer 3
Factory 1 $ 700 $ 900 $ 800
Factory 2 $ 800 $ 900 $ 700

Units Shipped Customer 1 Customer 2 Customer 3 Total Shipped Out


Factory 1 10 2 0 12 =
Factory 2 0 6 9 15 =
Total to Customer 10 8 9
= = =
Order Size 10 8 9
Output
12
15

Total Cost
$ 20,500.00