You are on page 1of 9

Geotechnical Engineering Proceedings of the Institution of Civil Engineers

Volume 166 Issue GE6 Geotechnical Engineering 166 December 2013 Issue GE6
Pages 540–548 http://dx.doi.org/10.1680/geng.11.00100
The base resistance of non-displacement Paper 1100100
piles in sand. Part I: field tests Received 30/10/2011 Accepted 24/09/2012
Published online 09/04/2013
Gavin, Cadogan, Tolooiyan and Casey Keywords: field testing & monitoring/geotechnical engineering/piles &
piling
ICE Publishing: All rights reserved

The base resistance of non-


displacement piles in sand.
Part I: field tests
j
1 Kenneth Gavin PhD j
3 Ali Tolooiyan MSc, PhD
Lecturer, School of Civil, Structural and Environmental Engineering, Research Fellow, School of Civil, Structural and Environmental
University College Dublin, Ireland Engineering, University College Dublin, Ireland
j
2 David Cadogan BE j
4 Patrick Casey BE
Lecturer, School of Civil, Structural and Environmental Engineering, Senior Geotechnical Engineer, Arup Consulting Engineers, Dublin,
University College Dublin and Cork Institute of Technology, Ireland Ireland

j
1 j
2 j
3 j
4

This paper presents the results of full-scale load tests performed to investigate the end bearing pressure mobilised by
continuous flight auger piles installed in sand. In particular, the tests considered the effects of the footing width and,
by varying the load test procedure (from maintained load test to constant rate of penetration), allowed quantification
of creep effects. By comparing the load test results with in situ test results from cone penetration tests, correlations
between the end bearing pressure mobilised at normalised settlement levels of 10% of the footing width and the
cone penetration test qc value were studied. For the maintained load tests, these correlations were found to be similar
to those used in routine design practice. When creep effects were reduced using constant rate of penetration load
testing, the end bearing pressure mobilised was significantly higher than that assumed in normal practice, and it was
in keeping with the results of finite-element analyses performed using a soil model that ignored creep. In the final
section, the field test results are compared to database pile load tests performed on non-displacement piles in sand.

Notation cone penetration test (CPT) end resistance (qc ) have been shown
B footing width to have a relatively high reliability (Lehane et al., 2005) and have
Dr relative density been widely accepted in industry. These techniques generally
D50 mean grain size estimate the base resistance at relatively large pile base settlement
L pile embedment depth (sb ), typically at 10% of the pile diameter, qb0:1 , using an
qb pile end bearing pressure empirical reduction factor Æ
qb0:10 pile bearing resistances mobilised at normalised
settlement of 10% 1: qb0:1 ¼ Æqc
qc cone penetration test end resistance value
qc(1:5B), qc(3:5B) cone penetration test end resistance value
average over 1.5 pile diameters or 3.5 pile Based on a database study, Jardine et al. (2005) suggest that a
diameters above and below the pile base diameter-dependent Æ value reduced from 0.63 to 0.43 as the pile
s, sb , sc , screep pile head, base and creep settlement diameter increased from 200 mm to 500 mm. Randolph (2003)
respectively and White and Bolton (2005) argued that once appropriate
v poissons ratio averaging techniques are adopted to derive design qc values and
z depth the effects of residual loads are accounted for, a constant Æ factor
Æ empirical constant linking qb0:1 and qc can be adopted which is independent of pile diameter. Lehane et
9v vertical effective stress al. (2005) found that an Æ value of 0.6 gave the best fit to a
database of instrumented pile load tests with diameters ranging
1. Introduction from 0.2 m to 0.68 m. For partial displacement (open-ended) pipe
Recent design methods linking the ultimate base resistance of piles, model and full-scale pile tests reported by Lehane and
driven, closed-ended or full-displacement piles in sand and the Gavin (2001) and Foye et al. (2009) show that direct correlations

540
Geotechnical Engineering The base resistance of non-displacement
Volume 166 Issue GE6 piles in sand. Part I: field tests
Gavin, Cadogan, Tolooiyan and Casey

0·5
between Æ (based on the average pressure mobilised over the
entire pile base area) and qc which are independent of pile
diameter or sand state can be determined once the effects of sand 0·4
displacement at the pile base during pile installation are included.

α ⫽ qb0·1/qc
Sand displacement is best quantified through the incremental 0·3
filling ration (IFR), which compares the rate of soil intrusion
during pile installation with IFR ¼ 1 for a fully coring pile 0·2 Hokksund (Dr ⫽ 50%)
(which causes minimal disruption) and IFR ¼ 0 for a pile with a Blessington (Dr ⫽ 100%)
fully formed plug, which prevents soil intrusion and results in
0·1 Tanta (Dr ⫽ 75%)
what is effectively a closed-ended pile. Minimum Æ factors in the
Monterey (Dr ⫽ 65%)
range 0.15–0.2 have been suggested by Lehane and Randolph
0
(2002) and Gavin and Lehane (2003) for fully coring piles. 3 4 5 6 7 8 9
Pile length: m
The Laboratoire Central des Ponts et Chaussées or French method
(Bustamante and Gianeselli, 1982) is widely used in practice to Figure 1. Results of numerical analyses by Tolooiyan and Gavin
estimate pile end bearing. The approach is based on a database of (2013)
197 pile tests on driven and bored piles in a range of soil
conditions. An Æ value of 0.2 is recommended for bored piles in
sand and gravel. The design qc(1:5B) value is given by cone tip 2. Field tests: site conditions
resistance around the pile tip averaged in the area ranging from The field tests were performed in Killarney in south-west Ireland.
1.5B under the pile tip to 1.5B above the pile tip, having excluded The town of Killarney is underlain by thick glacial sand and
values that are in excess of 30% of the average. De Cock et al. gravel deposits, the geological formation of which is described by
(2003) compiled a review of pile design practice in Europe and Wright (1927) and Warren (1991). The in situ investigation at the
found that Æ commonly ranged between 0.15 and 0.2 and site comprised ten shell and auger boreholes and six CPT profiles.
typically did not depend on the diameter or the length of the pile. The boreholes indicated that the ground conditions consisted of a
Eurocode 7, Part 1/EN 1997-1 (BSI, 2004), suggests that Æ 2 m layer of mixed deposits (sand/silt and clay) overlying sand
values, which although independent of footing width and depth, extending to at least 20 m below ground level. The water table
reduce from 0.2 for qc values up to 15 MPa, to 0.16 for level was at the top of the sand layer. Particle size analyses tests
qc ¼ 20 MPa. Numerical analyses reported by Lee and Salgado performed on disturbed samples revealed that the mean particle
(1999) suggest that Æ varies with pile length (or stress level), size (D50 ) of the sand reduced slightly with depth, from 0.35 mm
coefficient of earth pressure and relative density. Lehane (2009) at 2 m below ground level to 0.31 mm for samples recovered
reported a database study of continuous flight auger (CFA) piles from 10 m below ground level.
where the pile length varied from 4 m to 10.5 m. The database
contained both straight and expanded base piles and recorded Æ Two CPT qc profiles taken within 3 m of the test piles are shown in
values that increased from approximately 0.15 for 4 m long piles, Figure 2. The CPT tests were performed after the pile load tests
to approximately 0.4 for a 10.5 m long pile. It should be noted were complete. The qc profiles suggested that the sand consisted of
that Æ values at a given site could also be affected by other three sub-units: an upper dense layer extending between 2 and 4 m
effects, including geological variability and workmanship. below ground level, an overlay of loose to medium-dense sand to
approximately 14–15 m below ground level at the test pile
In a companion paper Tolooiyan and Gavin (2013) used finite- locations, which in turn overlay dense sand. Moving north when on
element analyses (FEAs) to investigate the effect of pile diameter, the site, it was clear from the CPT resistance and pile installation
length and sand relative density on the Æ factor mobilised in records that the loose sand layer became much thinner (and was
sand. They found that once the design qc(3:5B) value used to not evident in some profiles), whereas the depth to the lower dense
derive Æ accounted for soil variability within the zone of applied sand layer decreased. The torque reading measured during pile
stress (which required averaging up to 3.5B in highly variable installation indicated that the test piles penetrated the lower dense
soil) a constant Æ value was obtained that was independent of pile sand where the CPT qc resistance was in the range 10–15 MPa.
diameter, and in situ density (see Figure 1). Although a small
length effect was evident, with Æ reducing slightly as the pile 3. Test piles
length (or stress level) increased, they suggested that a constant Æ Two instrumented piles were installed at the test site. The first
factor of 0.31 could be adopted that was substantially higher than test pile was an 800 mm diameter pile (designated C800) and the
the value proposed in most design approaches. The field tests second was a 450 mm diameter pile (C450). Both piles were
described in this paper were designed to investigate possible installed using a Soilmec CM-48 piling rig, and the torque
causes for these apparently high Æ values. In the final section of required to install the piles increased significantly when the auger
the paper, the results of the maintained load tests described in reached the lower dense sand; installation stopped when the
this paper are compared to a database of field tests. maximum torque (84 kN m) was applied. The final pile length

541
Geotechnical Engineering The base resistance of non-displacement
Volume 166 Issue GE6 piles in sand. Part I: field tests
Gavin, Cadogan, Tolooiyan and Casey

CPT end resistance, qc: MPa


rapid load test was performed on each pile. The maintained load
0 5 10 15 20
0 periods were initially creep controlled, with a requirement for the
pile settlement rate to be less than 0.1 mm/h before the applica-
tion of the next load increment. However, in order to determine
2
the ultimate resistance of the piles at displacements in excess of
10% of the pile diameter, this creep criterion was ignored for
4 loads above the safe working load (SWL) of the piles (1000 kN
and 1800 kN for the 450 mm and 800 mm piles respectively).
The amended test procedure is set out in the next section. Further
6
details of the test piles, site conditions and consideration of the
shaft capacity developed by the piles are presented in Gavin et al.
8 (2009).

4. Load test results


Depth, z: m

10
Reaction to the test piles was measured using four tension piles
connected to a stiffened load transfer beam. The axial load was
12 controlled by a hydraulic pump system and the pile head
displacement was monitored using four linear variable displace-
ment transducers located around the pile head.
14

The load test on the 450 mm diameter pile (see Figure 3) was
16 performed in four stages.

(a) In stage 1, the SWL of 1000 kN was applied and the total
18 pile settlement, s, recorded was 15.2 mm, which was
CPT1
significantly below the specification level of 25 mm. The
20 CPT2 strain gauge data revealed that only 15% of the pile
resistance at SWL was generated by base resistance.
Average
(b) During stage 2, the load increments were applied to 150% of
22 the SWL. When the applied load reached 1250 kN (125% of
SWL), additional creep settlement of 5 mm developed over a
Figure 2. Cone penetration test qc profiles at test site
period of 20 min. When the load was increased to 1500 kN
(150% of SWL), large creep settlements of up to 20 mm were

was 14 m for pile C800 and 15 m for pile C450. Both piles were 2000
reinforced over their entire length, with seven T32 bars and five
T25 bars used in piles C800 and C450 respectively. Vibrating 1800
Stage 3 Stage 4
wire strain gauges were attached to the reinforcement cages (in 1600 Stage 2
groups of four) at depths of 0 m, 3.1 m, 6.05 m, 8.9 m and
11.85 m below ground level. The load distribution in the pile was 1400
Stage
calculated using a pile modulus calibrated using the strain gauges 1
1200 Shaft
positioned at ground level, assuming a pile diameter equal to the
Load: kN

auger and accounting for the effects of strain as well as creep 1000
level effects (see Fellenius, 2001; Gavin et al., 2009; Lehane et
800
al., 2003). In order to allow the reinforcement cage to be pushed
into the fluid concrete, the lowest section of the reinforcement 600
cage (below 11.85 m) was crimped. The shaft resistance over the Base
lower section of the pile was estimated using the CPT qc value 400
using a site-specific correlation determined by Gavin et al.
200
(2009). The base resistance was calculated by subtracting the
total shaft resistance from the applied load. Both piles were 0
0 50 100 150 200 250
subjected to static compression maintained load tests (within 1 Displacement: mm
week of installation), which were performed in accordance with
the UK Institution of Civil Engineers specification (ICE, 1996). Figure 3. Load–settlement response of pile C450
Immediately following the last stage of the maintained load test a

542
Geotechnical Engineering The base resistance of non-displacement
Volume 166 Issue GE6 piles in sand. Part I: field tests
Gavin, Cadogan, Tolooiyan and Casey

4500
recorded during the first 5 min of the load holding period.
The creep settlement reduced to specified limits between 30 4000
to 50 min after the application of the load, by which time the Stage 3
total pile head settlement had reached 58 mm (13% of the 3500 Stage 2
pile diameter). The strain gauge data revealed that the
mobilised base resistance provided 18% of the pile resistance 3000
at 1.5 SWL.
Shaft

Load: kN
(c) In stage 3, the pile was initially loaded to 100% of the SWL 2500 Stage
and no appreciable creep settlements developed. When the 1
load was increased to 150% of the SWL creep, settlements 2000
Base
were again initiated, with the overall pile head settlement
1500
reaching 82.23 mm (18% of the pile diameter), before the
creep rates reduced below the specified limits. Comparison of
1000
the load distribution in the pile when the applied load was
1500 kN in stage 2 and stage 3 shows that the shaft resistance 500
mobilised in the third stage was lower than that recorded in
stage 2. This suggests the occurrence of friction fatigue (see 0
Lehane et al., 1993; White and Lehane, 2004) whereby the 0 20 40 60 80 100 120 140
Displacement: mm
application of cyclic loading to the pile can reduce the
available shaft resistance. As a consequence, in order to Figure 4. Load–settlement response of pile C800
support the same applied load, the pile mobilised a higher
proportion of the available base resistance in stage 3. When
the applied pile load was increased to 1650 kN (165% SWL)
the additional resistance was provided exclusively by the Stage Applied load: % of SWL
mobilisation of additional base resistance, with approximately
29% of total pile resistance. Significant creep settlements C450 C800
were recorded (over 50 mm in 5 min) and the load test stage
was terminated. Stage 1 25 25
(d ) In stage 4, a rapid load test was performed in which the 50 50
applied load was increased steadily (with no pause periods) in 75 75
an attempt to establish the ultimate resistance of the pile. A 90 90
peak pile capacity of 1720 kN was mobilised when the pile 100 100
head settlement reached 240 mm (53% of the pile diameter). Stage 2 33 33
The available shaft resistance again reduced, suggesting 66 66
further effects of friction fatigue, which tend to be 100 100
concentrated during the initial cycles of loading at or near the 125 125
pile maximum shaft resistance (Gavin and O’Kelly, 2007). 150 150
— 175
The load test on the 800 mm diameter pile (see Figure 4) was — 200
performed in three load stages. Stage 3 50 50
100 100
(a) In stage 1 the pile load was increased to the SWL using the 150 150
loading sequence outlined in Table 1. The pile head 165 200
settlement at the SWL was 9 mm (i.e. just over 1% of the Stage 4 — 227
pile diameter). The strain gauges showed that 28% of this 125 —
resistance was mobilised by the pile base. 150 —
(b) In stage 2 the pile was loaded to 3600 kN (200% of SWL). 172 —
Total creep settlements during loading increments up to
Table 1. Static load test procedure
2700 kN (150%) were generally small and reduced to rates
below the specified creep rate during the 50 min holding
periods adopted. When the applied load was increased to
3150 kN, the creep criterion was not achieved during a holding period. As the creep rate remained high and the load
50 min holding period (a total creep settlement of 4 mm was was difficult to maintain, the load stage was terminated.
measured). When the applied load was increased to 3600 kN, (c) In stage 3 a rapid load test was performed to establish the
the creep settlement reached almost 6 mm in a 20 min ultimate capacity of the pile. A peak resistance of 4080 kN

543
Geotechnical Engineering The base resistance of non-displacement
Volume 166 Issue GE6 piles in sand. Part I: field tests
Gavin, Cadogan, Tolooiyan and Casey

6
was mobilised at a pile head settlement of 124 mm (16% of
2208 kPa (Stage 2 – 200% SWL)
the pile diameter). At this load level, the base resistance
accounted for 40% of the applied load.
5

The normalised base pressure pile base settlement response


measured during the maintained load portion of the static load 1900 kPa (Stage 2 – 175% SWL)
4

Creep settlement: mm
test is shown in Figure 5. In keeping with observations by Briaud
(2007) and Gavin and Lehane (2007), the mobilised base pressure
(qb ) was similar for both piles up to 2200 kPa. At this stage, the
3
test on C800 was halted because of the large pile head loads
required to maintain the applied base pressure. The base pressure
response was highly non-linear, with qb in the range 1800–
2
1900 kPa when sb /B ¼ 5%, which increased to only 2400 kPa 1537 kPa (Stage 2 – 150% SWL)
when s/B reached 10%. In this dense sand deposit (with qc3,5B
10 600 kPa), Æ values of 0.23 for pile C450 and 0.22 for pile
C800 are inferred. These values are in keeping with many of the 1
empirical correlations from the literature. However, it is evident
that the response of the piles was strongly affected by creep, a
time-dependent phenomenon, the extent of which is obviously 0
0 10 20 30 40 50 60
determined by the test procedures. Time: min
(a)
65
The creep settlement (screep ) response measured during three load
holding stages on pile C800 is shown in Figure 6(a). The relevant 60
stage of loading (see Table 1) and the percentage of the total load 55 2986 kPa (Stage 3 – 165%)
applied are included in the figure. It is apparent that for base
50
pressures up to approximately 2200 kPa, the rate of creep
settlement reduced significantly between 10 min and 20 min after 45
Creep settlement: mm

application of the load, while the creep settlement rate measured


40
at the maximum applied pressure was still significant 20 min after
35

30

25 2392 kPa (Stage 2 – 150%)


4500
20
4000 450 mm 15

3500 10

5 1794 kPa (Stage 2 – 125% SWL)


Base pressure, qb: kPa

3000
0
800 mm 0 10 20 30 40 50 60
2500
Time: min
(b)
2000
Figure 6. Creep measured during maintained load tests: (a) pile
1500 C800; (b) pile C450

1000

500

0 loading. The creep settlement rates measured on pile C450 (see


0 5 10 15 20 25 30 35
Normalised base displacement, sb /B: % Figure 6(b)) appeared to be much higher than those measured on
pile C800, and yet for applied pressures less than 2400 kPa,
Figure 5. Normalised base-pressure response of test piles during reduced to within specification limits (, 0.1 mm/h) within 3 min.
maintained load tests Small increases in settlement that were evident during some
maintained load periods were the result of the automated pressure

544
Geotechnical Engineering The base resistance of non-displacement
Volume 166 Issue GE6 piles in sand. Part I: field tests
Gavin, Cadogan, Tolooiyan and Casey

5000
controller attempting to maintain the specified pile head load. For
the maximum applied pressure qb of approximately 3000 kPa, 4500
creep settlements approached 55 mm within 5 min of loading and
the test was stopped. 4000

The pressure-base settlement response measured during the 3500


constant rate of penetration tests (final load stage of the static

Base pressure: kPa


3000
load tests) is shown in Figure 7. Although the response
(including the initial stiffness and total settlement) was affected
2500 800 mm
by previous maintained load cycles, the absence of creep in the
450 mm
test clearly allowed a more rapid mobilisation of the available 2000
base resistance. The test on pile C800 terminated at a normal-
ised displacement of about 9%, but the measured pressure qb0:1 1500
of 3150 kPa was 31% higher than the value measured at a
comparable settlement in the maintained load test. The mobi- 1000
lised Æ value of 0.30 (derived using qc3:5B ) is in keeping with
500
the FEAs of Tolooiyan and Gavin (2013), which were performed
using a constitutive model that did not consider the effects of 0
creep. 0 5 10 15 20 25
Normalised base displacement, sb /B: %
The test results presented here suggest that the mobilised pressure
settlement response of CFA piles in sand is independent of pile Figure 7. Normalised base-pressure response of test piles during
diameter and normalised pile length. This finding is in keeping fast load tests
with observations from displacement pile tests (Lehane et al.,
2005), footing tests (Briaud, 2007) and numerical analyses. An test. The base pressure values mobilised in these fast load tests
interesting observation from the field tests presented herein was were comparable to predictions made in FEAs using soil models
that the base pressure response developed in a maintained load that do not account for the effects of creep, reported in Tolooiyan
test was lower than that measured in a constant rate of penetration and Gavin (2013).

Pile Pile diameter: Pile length: Relative CPT qc : qb0:1 : Æ Reference


m m density: % MPa MPa

US59 0.76 9.80 82 24.0 6.60 0.28 Reese et al. (1974)


HH 0.61 7.60 88 24.0 5.50 0.23 Reese et al. (1974)
G1 0.92 18.20 35 9.6 3.14 0.33 Reese et al. (1974)
BB 0.76 20.00 68 20.0 4.58 0.23 Reese et al. (1974)
1B 0.20 4.00 51 5.2 1.26 0.24 BCP Committee (1971)
4B 0.20 4.50 63 8.0 2.20 0.28 BCP Committee (1971)
5C 0.20 11.00 73 20.4 5.40 0.26 BCP Committee (1971)
1 1.10 13.00 55 13.6 4.19 0.31 Franke and Gabrecht (1977)
3 1.50 14.00 54 13.6 4.23 0.31 Franke and Gabrecht (1977)
5 1.50 6.00 81 16.8 4.42 0.26 Franke and Gabrecht (1977)
7 1.50 6.00 80 16.0 3.74 0.23 Franke and Gabrecht (1977)
Pile 1 0.84 24.00 46 15.8 2.80 0.18 Mandolini et al. (2002)
Pile 2 0.61 22.50 34 10.8 2.52 0.23 Mandolini et al. (2002)
CFA 1 0.54 10.50 50 10.0 1.93 0.19 Evers et al. (2003)
CFA 2 0.53 11.00 49 10.0 2.40 0.24 Evers et al. (2003)
P1 0.70 10.50 29 3.7 0.76 0.20 Durham (2006)
T600 0.60 6.00 46 6.0 1.52 0.25 Fellenius et al. (2007)
No.1 1.20 26.50 51 20.0 5.30 0.27 Ogura et al. (1996)
C450 0.45 15.00 43 10.6 2.40 0.23 Current paper
C800 0.80 14.00 45 10.6 2.28 0.22 Current paper

Table 2. Database of static load tests

545
Geotechnical Engineering The base resistance of non-displacement
Volume 166 Issue GE6 piles in sand. Part I: field tests
Gavin, Cadogan, Tolooiyan and Casey

5. Database study by Lunne and Christoffersen (1983) and was found to vary from
The pile test database (see Table 2) comprised 20 static 29% to 100%.
maintained load tests performed on non-displacement piles
:
installed in sand, where the piles were loaded to settlements in 2: Dr ¼ 1=2:91 ln[qc =60 ( v9 )0 71 ]
excess of 10% of the pile diameter. The diameter B of the piles
ranged from 0.2 m to 1.5 m, and their length L ranged from 4 m
to 26.5 m with L/B in the range 4–37. They were founded in sand In the assessment of mobilised Æ values, the design (normalising)
where the CPT end resistance, qc1:5B value ranged from 2 to qc value was averaged over a distance  1.5B from the pile tip.
40 MPa, with SPT N varying from 4 to 100. The relative density The variation of Æ with pile diameter, length, relative density and
of the sand deposits was estimated using the correlation proposed CPT qc value is shown in Figure 8. Although there is consider-

0·35 0·35

0·30 0·30

0·25 0·25
α ⫽ qb0·1/qc

α ⫽ qb0·1/qc

0·20 0·20

0·15 0·15

0·10 0·10

0·05 0·05

0 0
0 0·5 1·0 1·5 2·0 0 10 20 30
Pile diameter, D: m Pile length, L: m
(a) (b)
0·35 0·35

0·30 0·30

0·25 0·25
α ⫽ qb0·1/qc
α ⫽ qb0·1/qc

0·20 0·20

0·15 0·15

0·10 0·10

0·05 0·05

0 0
0 20 40 60 80 100 0 10 20 30 40 50
Relative density, Dr: % Cone end resistance, qc: MPa
(c) (d)

Figure 8. Æ values back-figured from load test database:


(a) effect of pile diameter; (b) effect of pile length; (c) effect of
relative density; (d) effect of soil strength

546
Geotechnical Engineering The base resistance of non-displacement
Volume 166 Issue GE6 piles in sand. Part I: field tests
Gavin, Cadogan, Tolooiyan and Casey

able scatter in the results, there is no suggestion that Æ varied in a Fellenius BH (2001) From strain to load in an instrumented pile.
consistent manner with any of the assumed controlling para- Geotechnical News Magazine 19(1): 35–38.
meters. The average Æ value for the database piles is 0.24, with a Fellenius BH, Santos JA and Viana de Fonseca A (2007) Analysis
standard deviation of 0.04, which is similar to the value mobilised of piles in a residual soil – The ISC’2 prediction. Canadian
during maintained load tests on the CFA piles installed in Geotechnical Journal 19(1): 201–220.
Killarney, Co. Kerry. Foye KC, Abou-Jaoude G, Prezzi M and Salgado R (2009)
Resistance factors for use in load and resistance factor design
6. Summary and conclusion of driven pipe piles in sands. Journal of Geotechnical and
The paper presents the base pressure–settlement response meas- Geoenvironmental Engineering 135(1): 1–13.
ured during static load testing of two CFA piles installed in dense Franke E and Gabrecht F (1977) Test loading on 8 large bored
glacial sand deposits in south-west Ireland. Although the piles piles in sand. Proceedings of the 9th ICSMFE, Tokyo, vol. 1,
were of similar length (between 14 m and 15 m), two diameters pp. 529–532.
(450 mm and 800 mm) were considered in order to investigate Gavin KG and Lehane BM (2003) The shaft capacity of pipe piles
the effect of pile diameter and normalised pile length (L/D) on in sand. Canadian Geotechnical Journal 40(1): 36–45, http://
the mobilised base pressure. The base resistance and stiffness dx.doi.org/10.1139/t02-093.
response of the piles were comparable when the base settlement Gavin KG and Lehane BM (2007) Base load–displacement
was normalised by the pile diameter. Despite the overconsolidated response of piles in sand. Canadian Geotechnical Journal
nature of the sand deposit, the piles experienced significant creep 44(9): 1053–1063.
during loading when the base pressure exceeded  2000 kPa Gavin KG and O’Kelly BO (2007) Effect of friction fatigue on
( 0.2qc ). The base pressures measured in maintained load tests piles in dense sand. ASCE Journal of Geotechnical and
were affected by creep, and resulted in back-figured Æ values in Geoenvironmental Engineering 133(1): 63–71.
the range 0.22–0.23. These were in keeping with values observed Gavin K, Cadogan D and Casey P (2009) The shaft capacity of
from a database of pile load tests collated from the literature, CFA piles in sand. ASCE Journal of Geotechnical and
which suggested that constant Æ factors could be adopted in Geoenvironmental Engineering 135(6): 790–798, http://
design. When creep effects were reduced by performing fast load dx.doi.org/10.1061/(ASCE)GT.1943-5606.0000073.
tests, the mobilised Æ value increased to 0.30. The results suggest ICE (Institution of Civil Engineers) (1996) Specification for Piling
that the Æ factors used to predict the ultimate resistance of piles and Embedded Retaining Walls. Thomas Telford, London,
in practice may be too conservative. UK.
Jardine RJ, Bond AJ and Frank R (1993) Mechanisims of shaft
friction in sand from instrumented pile test. Proceedings of
REFERENCES the American Society of Civil Engineers – Journal of
BCP Committee (1971) Field tests on piles in sand. Soils and Geotechnical Engineering 119(1): 19–35.
Foundations 11(2): 11–20. Jardine RJ, Chow FC, Overy R and Standing J (2005) ICP Design
Briaud JL (2007) Spread footings in sand: load settlement curve Methods for Driven Piles in Sands and Clays. Thomas
approach. Journal of Geotechnical and Geoenvironmental Telford, London, UK.
Engineering, ASCE 133(8): 905–920. Lee J and Salgado R (1999) Determination of pilebase resistance
BSI (2004) BS EN 1997-1: Eurocode 7. Geotechnical design. in sands. Journal of Geotechnical and Geoenvironmental
General rules. BSI, Milton Keynes, UK. Engineering, ASCE 125(8): 673–683.
Bustamante M and Gianeselli L (1982) Pile bearing capacity Lehane BM (2009) Relationships between axial capacity and CPT
prediction by means of static cone penetrometer CPT. qc for bored piles in sand. Proceedings of the 5th
Proceedings of the 2nd European Symposium on Penetration International Symposium on Deep Foundations on Bored and
Testing, Amsterdam, vol. 2, pp. 493–500. Auger Piles, 1, 61–74.
De Cock F, Legrand C and Huybrechts N (2003) Overview of Lehane BM and Gavin KG (2001) Experimental investigation of
design methods of axially loaded piles in Europe – Report of the factors affecting the base resistance of open-ended piles
ERTC3-Piles, ISSMGE Subcommittee. Proceedings of the in sand. Journal of Geotechnical and Geoenviromental
8th European Conference on Soil Mechanics and Engineering, ASCE 127(6): 473–480, http://dx.doi.org/
Geotechnical Engineering, Prague, pp. 663–715. 10.1061/(ASCE)1090-0241(2001)127:6(473).
Durham CJ (2006) The Behaviour of Bored Piles in Perth CBD. Lehane BM and Randolph MF (2002) Evaluation of a minimum
Final year honours project, School of Civil and Resource base resistance for driven piles in siliceous sand. Journal of
Engineering, University of Western Australia, Australia. Geotechnical and Geoenviromental Engineering, ASCE
Evers G, Hass G, Frossard A et al. (2003) Comparative 128(3): 198–205.
performances of continuous flight auger and driven cast in Lehane BM, Jardine RJ, Bond AJ and Frank R (1993) Mechanisms
place piles in sands. In Proceedings of Deep Foundations on of shaft friction in sand from instrumented pile tests.
Bored and Auger Piles (Van Impe WF (ed.). IOS Publishers, Proceedings of the American Society of Civil Engineers –
Ghent, Belgium, pp. 137–14. Journal of Geotechnical Engineering 119(9): 19–35.

547
Geotechnical Engineering The base resistance of non-displacement
Volume 166 Issue GE6 piles in sand. Part I: field tests
Gavin, Cadogan, Tolooiyan and Casey

Lehane BM, Pennington D and Clark S (2003) Jacked end- design. Rankine Lecture. Géotechnique 53(10): 847–875.
bearing piles in the soft alluvial sediments of Perth. Reese LC, O’Neill MW and Touma FT (1974) Behaviour of drilled
Australian Geomechanics Journal 38(3): 123–134. piers under axial loading. Journal of Geotechnical
Lehane BM, Schneider JA and Xu X (2005) The UWA-05 method Engineering, ASCE 102(5): 493–510.
for prediction of axial capacity of driven piles in sand. In Tolooiyan A and Gavin KG (2013) The base resistance of
Proceedings of Frontiers in Offshore Geotechnics: ISFOG, non-displacement piles in sand. Part II: finite element
University of Western Australia, Perth, Australia. analyses. Proceedings of the Institution of Civil Engineers –
Lunne T and Christoffersen HP (1983) Interpretation of cone Geotechnical Engineering 166(6): 549–560.
penetrometer data for offshore sands. Proceedings of the Warren WP (1991) Glacial deposits in southwest Ireland. In
Offshore Technology Conference, OTC 4464, Houston, TX, Glacial Deposits in Great Britain and Ireland (Ehlers J,
USA, pp. 181–182. Gibbard PL and Rose J (eds)). Balkema, Rotterdam, the
Mandolini A, Ramondini M, Russo G and Viggiani C (2002) Full Netherlands, pp. 345–353.
scale loading tests on instrumented CFA piles. Proceedings of White DJ and Bolton M (2005) Comparing CPT and pile base
the International Deep Foundations Congress 2002. ASCE, resistance in sand. Proceedings of the Institution of Civil
Reston, VA, USA, Geotechnical Special Publication No. 116, Engineers – Geotechnical Engineering 158(1): 3–14.
vol. 2, pp. 1088–1097. White DJ and Lehane BM (2004) Friction fatigue on
Ogura T, Sumi M, Kishida H and Yoshifuka T (1996) Application displacement piles in sand. Géotechnique 54(10): 645–658.
of the pile toe test to cast-in-place and precast piles. Wright WB (1927) The Geology of Killarney and Kenmare.
Foundation Drilling Magazine December: 23–28. Memoirs of the Geological Survey of Ireland, Dublin,
Randolph MF (2003) Science and empiricism in pile foundation Ireland.

WHAT DO YOU THINK?


To discuss this paper, please email up to 500 words to the
editor at journals@ice.org.uk. Your contribution will be
forwarded to the author(s) for a reply and, if considered
appropriate by the editorial panel, will be published as a
discussion in a future issue of the journal.
Proceedings journals rely entirely on contributions sent in
by civil engineering professionals, academics and students.
Papers should be 2000–5000 words long (briefing papers
should be 1000–2000 words long), with adequate illustra-
tions and references. You can submit your paper online via
www.icevirtuallibrary.com/content/journals, where you
will also find detailed author guidelines.

548

You might also like