PAINTING WORKS

1.5 1.928571 2.142857 0.214286 0.428571 0.642857


3.5 4.5 5 0.5 1 1.5
3.808 4.896 5.44 0.544 1.088 1.632

cpf 82.56 2 165.1152 25 6.604608 18

doors
2.1
0.9
1.89 2 2 2 15.12 25 0.6048 1.25
facia

5.54
5.54
4.996
4.996
8.4
8.4

37.872 0.25 2 18.936 25 0.75744


199.1712 1.36224 2
199.1712
ROOFING WORKS

1.5 1.928571 2.142857 0.214286 2.357143 0.6428571429


3.5 4.5 5 0.5 5.5 1.5
3.808 4.896 5.44 0.544 5.984 1.632

Length width # sets AREA


5.440 0.70 1.00
0.10 3.00
0.70

5.540 4.40 1.00 24.38

4.896 0.70 1.00


0.10 3.00 #DIV/0!
0.70

4.996 4.40 1.00 21.98

46.36
CARPENTRY WORKS

1.5 1.928571 2.142857 0.214286 0.428571 0.6428571429


3.5 4.5 5 0.5 1 1.5
3.808 4.896 5.44 0.544 1.088 1.632

Length width # sets area


5.385 0.70 1.00
- 3.00
0.70

5.385 4.40 1.00 23.69

4.837 0.70 1.00


- 3.00
0.70

4.837 4.40 1.00 21.28

44.98
PLYWOOD 16.00 pcs
CEILING JOIST 225.00 bd.ft
CEMENT PLASTER FINISH

MAIN WALL
Length height #sets # faces AREA
7.00 2.60 1.00 1.00
7.00
9.00
3.00

26.00 2.60 1.00 1.00 67.60


9.00 2.80 1.00 1.00 25.20
APEX
Length height #sets # faces
7.00 1.50 1.00 1.00 10.50

GROUND
Length height #sets # faces
- 0.20 1.00 1.00
-
-
3.00
-
2.00

5.00 0.20 1.00 1.00

LESS WINDOWS
Length height #sets # faces
0.70 1.177 4.00 (2.00) (6.59)
0.70 1.177 8.00 (1.00) (6.59)
LESS DOORS
Length height #sets # faces
0.90 2.10 2.00 (2.00) (7.56)

82.56
MASONRY WORKS

MAIN WALL
length height # sets AREA
5.00 0.40 1.00
5.00 0.20
3.00 2.60
3.00 (0.25)

16.00 2.95 1.00 47.20

APEX
length height # sets
3.00 1.20 1.00 3.60

ALLEY
length height # sets
3.00 0.20 1.00
1.20 0.20
1.20

5.40 0.40 -

RAMP
length height # sets
2.00 0.20 0.50
2.00
-

4.00 0.20 -

SEPTIC VAULT
length height # sets
1.00 1.50 1.00
1.00
2.40
2.40

6.80 1.50 1.00

LESS WINDOWS #
length height # sets
1.80 1.200 (2.00) (4.32)
1.20 1.200 (2.00) (2.88)
LESS DOORS #
length height # sets 0.4 28 11.2
0.90 2.10 (1.00) (1.89)

41.71
STRUCTURAL CONCRETE

FOOTING
width length depth # sets
0.80 0.80 0.25 4.00 0.64

COLUMN
width length depth # sets
0.15 0.40 1.10 4.00
(0.25)
0.20
2.60
(0.25)

0.15 0.40 3.40 4.00 0.82

COLUMN APEX
width length depth # sets
0.15 0.40 1.50 -

BEAM
width length depth # sets
0.15 5.00 0.25 1.00
5.00
3.00
3.00

0.15 16.00 0.25 1.00 0.60

SLOPING BEAM
width length depth # sets
0.10 2.77 0.20 4.00 0.22

FLOORING SLAB
width length depth # sets
5.00 3.00 0.075 1.00 1.13
1.20 3.00 0.075 -

WALL FOOTING
width length depth # sets
0.30 5.00 0.15 1.00
5.00
3.00
3.00

0.30 16.00 0.15 1.00 0.72

0.30 1.20 0.10


1.20
3.00
0.30 5.40 0.10 -

RAMP
width length depth # sets
1.20 2.00 0.075 -

SEPTIC VAULT
width length depth # sets
1.00 2.40 0.10 1.00
1.00 2.40 0.08 1.00
4.12
REINFORCING STEEL BARS
1.100917 1.090909 1.071429
FOOTING 16mm 12mm 10mm TIE WIRE
Length #pcs # sets kg/m
F-1 0.90 10.00 4.00 0.888 31.97 5.60

COLUMN
Length #pcs # sets kg/m
C-1 0.20
1.10 1.6
0.20 6 6
2.60 8 4.4
0.05
4.15 76.8 1.6
4.15 6.00 4.00 0.888 88.44 237.60 121.1904 1.578 0

TIES 1.1
Length #pcs # sets kg/m 6 #VALUE!
0.80 15.00 4.00 1 1.1
0.30 18.00 20

1.10 33.00 4.00 0.616 89.44 89.4432 0.616 55.09701 22

TIES AT APEX 0.616 40


1.10 10.00 0.616 - 55.0970112 100 0 880

LINTEL BEAM
Length #pcs # sets kg/m
5.40 4.00 1.00
5.40
3.40
3.40

17.60 5.10 1.00 0.888 79.71 177.48 1.578 1.578 0 2.1


#VALUE!
STIRRUPS 0.25
Length #pcs # sets kg/m 4.5 3.5 #VALUE!
0.50 34.00 1.00 0.2 0.2
0.30 34.00 22.5 17.5
0.10 24.00
24.00
#VALUE!
0.90 116.00 1.00 0.616 64.31 0.616 0.616 39.61521
SLOPING BEAM
Length #pcs # sets kg/m
2.77 2.00 4.00

2.77 2.00 4.00 0.616 13.65 50.40


3.93
STIRRUPS 0.2
Length #pcs # sets kg/m
0.20 21.00 4.00 12
0.10 31.65

0.30 21.00 4.00 0.616 15.52

SEPTIC VAULT

1.20 25.00 30.00 31-Dec


2.60 6.00 15.60
-
1.20 8.00 9.60
1.90 4.00 7.60
62.80 0.616

WALL FOOTING
Length #pcs # sets kg/m
5.00 2.00 1.00
5.00
3.00
3.00

16.00 2.00 1.00 0.616 19.71 28.80 19.712 0.616 12.14259

TIES
0.30 16.00
(1.60)

0.30 14.40 0.30 0.616 8.87 5.464166


48.00 17.60676

DOWELS
Perimeter Spacing # pcs Length kg/m
VERTICALS 5.00 0.60 8.00 0.20
5.00 0.60 8.00 0.40
3.00 0.60 4.00 0.20
3.00 0.60 4.00 2.60

24.00 3.40 0.616 50.27 28.80 50.2656 0.616 30.96361

DOWELS
Perimeter Spacing # pcs Length kg/m
HORIZONTALS 0.40 0.60 5.00
0.20 5.00
2.60 3.00
(0.25) 3.00

2.95 0.60 4.00 16.00 0.616 39.42 39.424 0.616 24.28518


528.68
- 200.12 301.20 48.18

1.100000 1.100000 1.100000 10.97


- 220.13 331.32 551.45
10 mm 6 0.4 5.6 1.02 1.092857 1.092857
12 mm 6 0.45 5.55 1.02 1.102703 1.102703
16 mm 6 0.55 5.45 1.02 1.122936 1.122936

#VALUE!
6.666667
6.666667

6.666667
BACKFILL

area main
inside
Length Width Depth # Sets Volume
5.00 3.00 0.125 1.00 1.88
5.00 1.20 0.125 1.00 -
cr
2.00 1.80 0.10 2.00 -

1.88
ramp

1.8 0.5
1.8
1.5
5.1 0.5 2.55
gross 2.55

window #
wid hgt
0.7 1.177 10 8.239

doors
2.1 0.9 2 3.78
2.1 0.6 1 1.26
13.279

net -10.729

septic

wid hght
1 1.5
1
2.4
2.4
6.8
6.8 1.5 10.2
-0.529
Excav

Footing
width length depth # Volume
0.80 0.80 1.10 4.00 2.82

Wall footing
width length depth
0.30 5.00 0.60
5.00
3.00
3.00
(3.20)

0.30 12.80 0.60 2.30

0.30 1.20 0.30


1.20
5.00

0.30 7.40 0.30

septc tnk
width depth height
1.00 2.40 1.40
5.12
BACK-UP COMPUTATION
Construction of 2-units 6-CL School Building (2-storey) at Malasiqui NHS, Malasiqui, Pangasinan

ITEM 803 STRUCTURE EXCAVATION

LENGTH WIDTH DEPTH # SETS QUANTITY


FOOTING
0.80 0.80 1.10 4.00 2.82
WALL FOOTING
13.00 0.30 0.60 1.00 2.34
7.50 0.30 0.30 1.00 0.68

TOTAL 5.83 CU.M

ITEM 104 STRUCTURE BACKFILL

LENGTH WIDTH DEPTH # SETS QUANTITY


MAIN FLOORING
5.00 3.00 0.125 1.00 1.88
CORRIDOR
5.00 1.20 0.125 1.00 0.75

TOTAL 2.63 CU.M

ITEM 404 REINFORCING STEEL BARS

LENGTH # PCS # SETS kg/m F.S. QUANTITY


FOOTING
0.90 10.00 4.00 0.888 1.10 35.16
COLUMN
4.15 6.00 4.00 0.888 1.10 97.29
LATERAL TIES
1.10 33.00 4.00 0.616 1.10 98.39
BEAM
17.60 5.10 1.00 0.888 1.10 87.68
STIRRUPS
0.90 120.00 1.00 0.616 1.10 73.18
SLOPING BEAM
2.77 2.00 4.00 0.616 1.10 15.02
STIRRUPS
0.30 21.00 4.00 0.616 1.10 17.08
WALL FOOTING
16.00 2.00 1.00 0.616 1.10 21.68
STIRRUPS
0.30 50.00 1.00 0.616 1.10 10.16
VERTICAL DOWELS
3.50 24.00 1.00 0.616 1.10 56.92
HORIZONTAL DOWELS
16.00 4.00 1.00 0.616 1.10 43.37

TOTAL 555.92 Kgs.


ITEM 405 STRUCTURAL CONCRETE

LENGTH WIDTH DEPTH # SETS QUANTITY


FOOTING
0.80 0.80 0.25 4.00 0.64
COLUMN
3.40 0.15 0.40 4.00 0.82
BEAM
16.00 0.15 0.25 1.00 0.60
SLOPING BEAM
2.80 0.10 0.20 4.00 0.22
SLAB
3.00 5.00 0.075 1.00 1.13
3.00 1.20 0.075 1.00 0.27
WALL FOOTING
16.00 0.30 0.15 1.00 0.72

TOTAL 4.40 CU.M

ITEM 409 STRUCTURAL STEEL

Q = ALL Q = ALL

ITEM 704 MASONRY WORKS

LENGTH HEIGHT # SETS QUANTITY


MAIN WALL
16.00 3.00 1.00 48.00
APEX
5.40 0.90 1.00 4.86
LESS WINDOWS
1.80 1.20 (2.00) -4.32
1.20 1.20 (2.00) -2.88
LESS DOORS
0.90 2.10 (1.00) -1.89

TOTAL 43.77 SQ.M


ITEM 1013 ROOFING WORKS

LENGTH WIDTH # SETS QUANTITY


MAIN ROOFING
3.00 6.40 1.00 19.20
3.25 6.40 1.00 20.80

TOTAL 40.00 SQ.M

ITEM SPL.1 OCCUPATIONAL SAFETY & HEALTH

Q = ALL Q = ALL

PREPARED BY:

628 CONSTRUCTION ENTERPRISES


CONTRACTOR
NAME OF PROJECT : Construction of 2-units 6-CL School Building (2-storey) at Malasiqui NHS, Malasiqui, Pangasinan
LOCATION: Malasiqui, Pangasinan
CALENDAR DAYS: 75 CD
405
34 CD
MOVE OUT
MOVE IN 803 404 SPL 1 SPL 4 SPL 4
15 CD 1 7CD 1 CD
1 CD 10 CD 21 CD 14 CD
SPL 2
20CD
SPL 5
75 CD

PERT / CPM

BAR CHART/ S- CURVE


CALENDAR DAYS
ITEM No DESCRIPTION QTY UNIT TOTAL ITEM COST % WT
25 50 75
100
#REF!
803 Structural Excavation 2,280.48 cu.m 1,297,017.53 #REF!

#REF!
#REF! #REF! #REF! #REF! #REF! #REF!

#VALUE!
404 Reinforcing Steel Bars #VALUE! kgs. #VALUE! #VALUE!

#VALUE! #VALUE! 75
405 Structural Concrete #VALUE! cu.m. #VALUE! #VALUE!

#REF!
1010 Doors & Windows All LS 34,886.30 #REF!

#REF!
Spl.1 Masonry Works 8,218.97 sq.m. 7,825,762.88 #REF!

#REF! #REF! 50
Spl.2 Plastering Works 16,392.34 sq.m. 5,750,860.21 #REF!

#VALUE!
Spl.3 Roofing Works #VALUE! #REF! #VALUE! #VALUE!

#REF!
#REF! #REF! #REF! #REF! #REF! #REF! 25

#REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!

#REF! #REF! #REF!


Spl.5 Occupational Safety & Health All L.S. 499,996.02 #REF!
0
TOTAL #REF! #REF! #REF! #REF! #REF!
###
CASH FLOW
ACCOMPLISHMENT 25 50 75
PERIODIC P #REF! #REF! #REF!
AMOUNT A
CUMMULATIVE P #REF! #REF! #REF!
A
PERIODIC P #REF! #REF! #REF!
PERCENTAGE A
CUMMULATIVE P #REF! #REF! #REF!
A
SLIPPAGE

Prepared by: Submitted By: Recommending Approval: APPROVED:

ELDRED M. MISLANG BLESILDA P. ESTRADA AQUILINO M. NICER MARIETA B. MENDOZA


Acting Chief, Planning & Design Section OIC-chief, Planning & bDesign Section OIC-Asst. District Engineer OIC-District Engineer
RECAPITULATION
ITEM NO. DESCRIPTION COST
(PESOS)
803(a) Structure Excavation (common earth) 1,753,855.25
803 Structural Excavation 1,297,017.53
403 Structural Steel 27,972.25
404 Reinforcing Steel Bars #VALUE!
405 Structural Concrete #VALUE!
1003 Carpentry & Joinery Works 11,500,196.38
1010 Doors & Windows 34,886.30
1002 Plumbing Works 419,824.06
Spl.1 Masonry Works 7,825,762.88
Spl.2 Plastering Works 5,750,860.21
Spl.3 Roofing Works #VALUE!
Spl.4 Painting Works #VALUE!
Spl.5 Occupational Safety & Health 499,996.02
Spl.6 Project Billboard 6,718.11

Total Direct & Indirect Cost P #VALUE!


Eng'g & Adm. Overhead -
TOTAL PROJECT COST P #VALUE!

Prepared by: Submitted by:

ELDRED M. MISLANG BLESILDA P. ESTRADA


OIC-Asst Chief, Planning & Design Section OIC-Chief, Planning & Design Section

Recommending Approval: APPROVED:

AQUILINO M. NICER MARIETA B. MENDOZA


Assistant District Engineer OIC-District Engineer
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Pangasinan Sub-District Engineering Office
OFFICE OF THE DISTRICT ENGINEER
Area Equipment Compound
Sta. Barbara, Pangasinan

INDIVIDUAL PROGRAM OF WORK


12-Oct-12
NAME/ LOCATION OF PROJECT APPROPRIATION Php 31,413,228.79
SOURCE OF FUND
Construction of 2-units 6-CL School ISSUED OBLIGATED AUTHORITY
Building (2-storey) at Malasiqui NHS, RELEASED
Malasiqui, Pangasinan
CALENDAR DAYS TO COMPLETE 30 C.D
PROJECT CATEGORY DESIRABLE STARTING DATE ASAP
Multi-Purpose Building
PROJECT DESCRIPTION
WORK INCLUDES:
Demolition & Removal of obstruction.
Construction of kitchen with comport room (extension) with roofing, ceiling eaves, doors and windows.
Complete painting works: ceiling, ceiling eaves, wall and partition. (including existing walls and ceiling).
Installation of gutter.
Construction of septic vault with plumbing and fixtures.

MINIMUM EQUIPMENT REQUIREMENTS TECHNICAL PERSONNEL REQUIRED


Description No Description No
Const'n. Foreman 1
Bar Cutter (manually operated) 1 Mason 3
Concrete Mixer (1-Bagger) 1 Carpenter 1
Electric Drill 1 Steelman 2
Riveter 1 Laborer 8
Welding machine 1

ESTIMATED COST OF PROPOSED WORK

ITEM TOTAL ITEM


DESCRIPTION %TOTAL UNIT QUANTITY UNIT COST TOTAL UNIT COST
NO. COST
803(a) Structure Excavation (common earth #VALUE! cu.m. 2,280.48 1,753,855.25 769.07 769.07
803 Structural Excavation #VALUE! cu.m 2,280.48 1,297,017.53 416.24 568.75
403 Structural Steel #VALUE! L.S. All 27,972.25 20,471.49 27,972.25
404 Reinforcing Steel Bars #VALUE! kgs. #VALUE! #VALUE! #VALUE! #VALUE!
405 Structural Concrete #VALUE! cu.m. #VALUE! #VALUE! 5,787.54 #VALUE!
1003 Carpentry & Joinery Works #VALUE! sq.m. 11,127.60 11,500,196.38 756.36 1,033.48
1010 Doors & Windows #VALUE! LS All 34,886.30 25,531.54 34,886.30
1002 Plumbing Works #VALUE! L.S. All 419,824.06 341,737.13 419,824.06
Spl.1 Masonry Works #VALUE! sq.m. 8,218.97 7,825,762.88 696.84 952.16
Spl.2 Plastering Works #VALUE! sq.m. 16,392.34 5,750,860.21 256.75 350.83
Spl.3 Roofing Works #VALUE! #REF! #VALUE! #VALUE! #VALUE! #VALUE!
Spl.4 Painting Works #VALUE! sq.m #VALUE! #VALUE! #VALUE! #VALUE!
Spl.5 Occupational Safety & Health #VALUE! L.S. All 499,996.02 440,913.60 499,996.02
Spl.6 Project Billboard #VALUE! each 1.00 6,718.11 6,718.11 6,718.11
#VALUE! P #VALUE!

file:///conversion/tmp/activity_task_scratch/621624254.xls
BREAKDOWN OF ESTIMATE EXPENDITURE TOTAL AMOUNT
(%) (PESOS)
ESTIMATE COST:

a) DIRECT COST -

1. Mobilization / Demobilization
2. Materials 0.00% -
2.1 Supply/ Delivery
2.2 Testing of Materials
3. Labor ( Including fringe benefit) 0.00% -
4. Equipment Expenses 0.00% -
5. Well Development

b) INDIRECT COST 31,413,228.79

1. Overhead Contingency, Miscellaneous 41.51% 13,040,012.69


7% to 12% of A1 to A4
2. Profit 5% to 10% of A1 to A4 34.59% 10,866,677.24
3. Comprehensive All Risk Insurance 1.5% to A1 to A4
4. VAT 10% of A3 to A4 23.90% 7,506,538.87
5. Preparation of Plans and Detailed Estimates
6. Local Tax
7. Budgetary Reserve
8. Preliminary Engineering
SUB- TOTAL CONTRACT COST 100.00% 31,413,228.79

ESTIMATED GOVERNMENT EXPENDITURES


1. Engineering and Administrative Overhead 3% of A1 to A4 0.00% -
2. ROW/ Site Acquisition
3. Soil Eploration
4. Parcellary Survey
5. Project Supervision
6. Regional/ Central Office Retension

CONTINGENCIES/ RESERVES

1. Physical up to 5% of the estimate Contract Cost


2. Price Escalation up to 12% of the Estimate Contract Cost

100.00% 31,413,228.79

Prepared by: Submitted by:

ELDRED M. MISLANG BLESILDA P. ESTRADA


OIC-Asst Chief, Planning & Design Section OIC-Chief, Planning & Design Section

Recommending Approval: APPROVED:

AQUILINO M. NICER MARIETA B. MENDOZA


Assistant District Engineer OIC-District Engineer
CERTIFICATION

This is to certify that the Preliminary Engineering has been conducted for the
Completion of Multi-Purpose Building (Brgy. Hall) , located at at Brgy. Tarectec
San Carlos City, Pangasinan

This certification was initiated to conform with the implementing rules and
regulations of R.A. 9184.

Conducted by: Checked By:

ELDRED M. MISLANG BLESILDA P. ESTRADA


Act'g Asst. Chief, Planning & Design Section OIC-Chief, Planning & Design Section

Noted:

MARIETA B. MENDOZA
OIC- District Engineer
DETAILED ESTIMATES
Item No. 803(b)
Structure Excavation (sand) QUANTITY 100.00 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 1.2926 cu.m / hour
MATERIAL COST

Sub- Total -
unit cost -
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Unskilled Laborer 2.00 77.36 36.75 5,685.96


2.00 #REF! #REF!

Sub- Total 5,685.96


unit cost 56.86
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total -
unit cost -
Direct Unit Cost 56.86
PREPARED BY: 12% of total DC OCM 6.82
10% of total DC CP 5.69
12% of (total DC+OCM+CP) VAT 8.32
Total Direct & Indirect Unit Cost 77.69
Total Direct & Indirect Cost 7,769.30
DETAILED ESTIMATES
Item No. 803(c)
Structure Excavation (clay) QUANTITY 100.00 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 2.5940 cu.m / hour
MATERIAL COST

Sub- Total -
unit cost -
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Unskilled Laborer 5.00 38.55 36.75 7,083.56


5.00 #REF! #REF!

Sub- Total 7,083.56


unit cost 70.84
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total -
unit cost -
Direct Unit Cost 70.84
PREPARED BY: 12% of total DC OCM 8.50
10% of total DC CP 7.08
12% of (total DC+OCM+CP) VAT 10.37
Total Direct & Indirect Unit Cost 96.79
Total Direct & Indirect Cost 9,678.98
DETAILED ESTIMATES
Item No. 803(d)
Structure Excavation (rock) QUANTITY 1.00 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 0.3225 cu.m / hour
MATERIAL COST

Sub- Total -
unit cost -
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Unskilled Laborer 1.00 3.10 36.75 113.93


1.00 #REF! #REF!

Sub- Total 113.93


unit cost 113.93
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total -
unit cost -
Direct Unit Cost 113.93
PREPARED BY: 12% of total DC OCM 13.67
10% of total DC CP 11.39
12% of (total DC+OCM+CP) VAT 16.68
Total Direct & Indirect Unit Cost 155.67
Total Direct & Indirect Cost 155.67
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name : CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-
STOREY 2-CL RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN
Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

SUMMARY OF LABOR, EQUIPMENT RENTALS & MATERIAL COST

MATERIALS COST

Description Unit Price


Structural Steel Angular Bar ……………………… 52.00 / kgs
Structural Steel Channel Bar ……………………… 52.00 / kgs
10mm dia sagrod w/ nuts & washers at each end ……………………… 75.00 / pcs
10mm dia A-307 anchor bolts ……………………… 10.00 / pcs
10mm dia x 200mm anchor bolts ……………………… 28.00 / pcs
12mm dia x 250mm long bent anchor studs ……………………… 45.00 / pcs
Gusset plates 200mm x 200mm x 6.00mm ……………………… 200.00 / pcs
Base plates 200mm x 200mm x 10.00mm ……………………… 250.00 / pcs
12mm dia cross bracing ……………………… 52.00 / kgs
Welding rod ……………………… 120.00 / pcs
Oxygen (content only) ……………………… 50.00 / kgs
Acetylene (content only) ……………………… 60.00 / kgs
Red lead primer ……………………… 450.00 / gal
Paint thinner ……………………… 220.00 / gal
Paint brush ……………………… 80.00 / pcs
Welding Rod ……………………… 120.00 / kgs.
Red Lead Primer ……………………… 550.00 / gal
Thinner ……………………… 250.00 / gal
Paint brush 4" ……………………… 90.00 / pcs.
Asstd. RSB ……………………… 52.00 / kgs
Tie wire # 16 GI ……………………… 55.00 / kgs
CHB ( 4" x 8" x 16") ……………………… 10.00 / pcs
CHB ( 6" x 8" x 16") ……………………… 12.00 / pcs
Portland Cement, 40 kgs ……………………… 210.00 / bags
Washed Sand ……………………… 500.00 / cu. m.
Crushed Gravel ……………………… 600.00 / cu. m.
River mix ……………………… 300.00 / cu.m
Gravel fill ……………………… 300.00 / cu.m
Plywood - 1/2 x 4' x 8' ……………………… 600.00 / pcs.
Plywood - 1/4 x 4' x 8' ……………………… 300.00 / pcs.
Coco Lumber ……………………… 28.00 / bd.ft
Good Lumber ……………………… 75.00 / bd.ft
Assorted CWN ……………………… 70.00 / kgs
Tanguile Panelled Door ……………………… 2500.00 / sq.m.
Swing Type Steel Casement Window with Glass ……………………… 1800.00 / sq.m.
PVC Doors including Jamb and accessories (0.80m x 2.10m) ……………………… 2800.00 / sets
Hinges 2"x4" ……………………… 70.00 / pairs
CWN (assorted) ……………………… 70.00 / kgs
Corrugated Roofing, Gauge 26 ……………………… 280.00 / sq.m
Pre-painted ready made Ridge Roll (0.40mm) ……………………… 200.00 / L.m
Pre-painted ready made Gutter (0.40mm) ……………………… 200.00 / L.m
Pre-painted ready made wall Flashing (0.40mm) ……………………… 200.00 / L.m
Blind Rivets ……………………… 250.00 / boxes
Tekscrew ……………………… 2.00 / pcs.
Silicone Selant ……………………… 180.00 / pcs.
25mm x 250mm x 12' Fiber Cement Fascia Board ……………………… 650.00 / pcs.
Jalousie Window w/ clear glass blades on std aluminum casing and ………………………
50x150mm thk yakal jamb w/ complete accessories
1550.00 / sq.m
Tanguile Panel Door on 50x150mm thk yakal jamb w/ complete ………………………
accessories 3750.00 / sq.m
Hollow Core Flush Type Swing Door w/ complete accessories (toilet) ……………………… 1500.00 / sq.m
Water Closets ……………………… 4,500.00 / set
Lavatory ……………………… 4,800.00 / set
Male Urinal ……………………… 3,100.00 / set
Facial Mirror ……………………… 650.00 / set
Faucet ……………………… 350.00 / set
PVC pipe 4" dia. ……………………… 580.00 / pcs.
PVC pipe 3" dia. ……………………… 430.00 / pcs.
PVC pipe 2" dia. ……………………… 290.00 / pcs.
PVC pipe 4" dia. Elbow 1/4bend ……………………… 80.00 / pcs.
PVC pipe 4" dia. Elbow 1/8bend ……………………… 60.00 / pcs.
PVC pipe Wye 4" x 4" dia. ……………………… 125.00 / pcs.
PVC pipe Tee 4" x 4" dia. ……………………… 270.00 / pcs.
PVC pipe Reducer Tee 4" x 2" dia. ……………………… 110.00 / pcs.
PVC Clean out w/ plug 4" dia. ……………………… 60.00 / pcs.
PVC pipe 3" dia. Elbow 1/4bend ……………………… 40.00 / pcs.
PVC pipe 2" dia. Elbow 1/4bend ……………………… 25.00 / pcs.
PVC pipe 2" dia. Elbow 1/8bend ……………………… 20.00 / pcs.
PVC pipe 2" dia. Tee ……………………… 75.00 / pcs.
Floor Drain ……………………… 280.00 / pcs.
Solvent ……………………… 190.00 / qrt
G.I pipe 38mm dia. ……………………… 850.00 / pcs.
G.I pipe 20mm dia. ……………………… 610.00 / pcs.
G.I pipe 12mm dia. ……………………… 420.00 / pcs.
G.I coupling elbow ……………………… 25.00 / pcs.
G.I Tee ……………………… 25.00 / pcs.
Ceiling fan ……………………… 1,000.00 / set
Flourescent Lighting Fixtures (40 watts) with box type housing ……………………… 600.00 / set
Compact Incandescent lamp ……………………… 60.00 / pcs.
Porcelain socket # 4"Ø ……………………… 40.00 / pcs.
Light Switch 1 way 2 gang ……………………… 142.00 / pcs.
Light Switch 1 way 1 gang ……………………… 142.00 / pcs.
Utility Box (Deep tape) ……………………… 30.00 / pcs.
PVC Coupling PNS 14, 15mm dia. ……………………… 3.00 / pcs.
PVC Pipe PNS 14,15mm dia. ……………………… 69.00 / pcs.
PVC Pipe PNS 14, 20mm dia. ……………………… 120.00 / pcs.
PVC Adapter PNS 14,15mm dia. ……………………… 8.00 / pcs.
Entrance cap # 15mm dia. ……………………… 62.00 / pcs,
Junction Box (Deep tape w/ Cover) ……………………… 31.00 / pcs.
Copper Wire #3.50mm2 TW ……………………… 24.00 / mtrs
Electrical Tape ……………………… 40.00 / pcs.
Enclosed Air circuit breaker, 220V, 2P, 20AT, 50 AF ……………………… 1,350.00 / set
Equipment for Fire alarm, Vibrating Bell, 10" dia. ……………………… 1,300.00 / set
Exhaust Fan 400mm ……………………… 1,000.00 / unit
Polythelene sheets ……………………… 50.00 / sq.m
Steel railings, 19mm sq. bar welded to 50mmØ GI Pipe handrail ……………………… 725.00 / sq.m
Steel railings, 50mmØ GI Pipe handrail w/ 25mm sq. bracket @ 600mm ……………………… 250.00 / LM
Steel railings, 32mmØ GI Pipe handrail ……………………… 175.00 / LM
32mmØ Stainless Pipe Grab bar ……………………… 400.00 / LM
Ceramic Glazed Tiles (20cm x 20cm) ……………………… 550.00 / sq.m
Ceramic Unglazed Tiles (20cm x 20cm) 600.00 / sq.m
Portland Cement ……………………… 210.00 / bag
Tile adhesive ……………………… 240.00 / bag
Paint Latex Gloss (Boysen) ……………………… 450.00 / gal
Paint Latex Semi-Gloss (Boysen) ……………………… 450.00 / gal
Flat Wall Enamel (Boysen) ……………………… 500.00 / gal
Quick Dry Enamel (Boysen) ……………………… 500.00 / gal
Glazing Putty ……………………… 400.00 / gal
Paint thinner ……………………… 220.00 / gal
Concrete Neutralizer ……………………… 380.00 / gal
Sand paper ……………………… 1500.00 / roll
Paint brush 4" ……………………… 80.00 / pcs
Paint roller ……………………… 85.00 / pcs
Tarpaulin ……………………… 30.00 / sq.ft

LABOR COST

Designation Rate per Day


Construction Foreman ……………………… 530.00
Skilled Laborer ……………………… 400.00
Unskilled Laborer ……………………… 290.00
Part time Safety Practitioner ……………………… 530.00

EQUIPMENT RENTALS

Description Rentals
Plate Compactor ……………………… 600.00
Bar Cutter (manually operated) ……………………… 350.00
Concrete Mixer (1-Bagger) ……………………… 1,390.00
Concrete Vibrator ……………………… 510.00
Welding machine ……………………… 500.00
Electric Drill ……………………… 100.00
Riveter ……………………… 100.00

Submitted By:

BERSONS CONSTRUCTION & TRADING


Name of the Bidder

RUSSELL Q. BERNAL
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-STOREY 2-CL RM SB AT
BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN
Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

BILL OF QUANTITIES
Part No. Part Description:

(Columns (1), (2), (3) and (4) are to be filled up by the


Procuring Entity) (Column (5) and (6) to be filled up by the Bidder)

Pay Item no. Description Unit Quantity Unit Price (Pesos) Amount (Pesos)

In words: Pesos In words: Pesos


three hundred ninety & 18/100 pesos twenty seven thousand four & 36/100 pesos

Structure Excavation
803(a) cu.m. 2,280.48
(common earth)
In figures: In figures:

Php 294.15 Php 670,804.36


In words: Pesos In words: Pesos
seven hundred thirty four & 49/100 pesos six thousand two hundred seventy nine & 89/100 pesos

804 (d-1) Gravel Fill (hand placed) cu.m. 144.50


In figures: In figures:

Php 526.78 Php 76,119.89


In words: Pesos In words: Pesos
seventy seven & 89/100 pesos one hundred twenty three thousand one hundred thirty
nine & 42/100 pesos
Reinforcing Steel for
404 (a.1) kgs. 52,964.57
Column Footing & FTB
In figures: In figures:

Php 62.50 Php 3,310,158.18


In words: Pesos In words: Pesos
three thousand seven hundred sixty five & seventy thousand five hundred thirty six & 24/100 pesos
95/100 pesos
Reinforce Concrete Column
900 (a.1) cu.m 535.34
Footing & FTB
In figures: In figures:

Php 2,859.61 Php 1,530,866.24


In words: Pesos In words: Pesos
seventy seven & 77/100 pesos two hundred eighty seven thousand nine hundred thirty
Reinforcing Steel for
three & 18/100 pesos
404 (a.2) kgs. 51,148.25
Column
In figures: In figures:
Php 60.50 Php 3,094,702.49
In words: Pesos In words: Pesos
nine thousand five hundred eighty five & eighty eight thousand five hundred sixty nine & 72/100
47/100 pesos pesos
Reinforce Concrete for
900 (a.2) cu.m 570.24
Column
In figures: In figures:
Php 8,285.05 Php 4,724,465.83
In words: Pesos In words: Pesos
seventy seven & 77/100 pesos one hundred eighty four thousand five & 25/100 pesos

404 (a.3) Reinforcing Steel for Beam kgs. 189,416.67


In figures: In figures:

Php 58.32 Php 11,046,637.87

Sub-Total (Page 1of 4) Php 24,453,754.86

Submitted By:

BERSONS CONSTRUCTION & TRADING


Name of the Bidder

RUSSELL Q. BERNAL
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-STOREY 2-CL RM SB AT
Contract Location: BOLINGIT
MALASIQUINHS,
ANDSAN
SANCARLOS
CARLOSCITY,
CITY,PANGASINAN
PANGASINAN

BILL OF QUANTITIES
Part No. Part Description:

(Columns (1), (2), (3) and (4) are to be filled up by the


Procuring Entity) (Column (5) and (6) to be filled up by the Bidder)
In words: Pesos In words: Pesos
nine thousand three hundred four & 66 /100 one hundred seven thousand five hundred sixty one &
pesos 84/100 pesos
Reinforce Concrete for
900 (a.3) cu.m 821.45
Beam
In figures: In figures:

Php 6,887.24 Php 5,657,526.47


In words: Pesos In words: Pesos
seventy seven & 78/100 pesos sixteen thousand eight hundred seventy three & 55/100
pesos
Reinforcing Steel for Slab
404 (a.4) kgs. 2,302.79
on Fill
In figures: In figures:

Php 61.23 Php 141,006.95


In words: Pesos In words: Pesos
three thousand seven hundred forty nine &
21/100 pesos thirty four thousand eight hundred sixty seven & 61/100
Reinforce Concrete for Slab pesos
900 (a.4) cu.m 144.50
on Fill
In figures: In figures:

Php 3,007.49 Php 434,581.71


In words: Pesos In words: Pesos

fifty three thousand seven hundred seventy one &


seventy seven & 77/100 pesos
404 (a.5) Reinforcing Steel for Suspended Slab kgs. 82,171.12
19/100 pesos
In figures: In figures:
Php 59.29 Php 4,872,012.39
In words: Pesos In words: Pesos

fourteen thousand six hundred fifty & 80/100 one hundred thirty seven thousand seven hundred
900 (a.5)
Reinforce Concrete for
cu.m 803.65
pesos seventeen & 49/100 pesos
Suspended Slab
In figures: In figures:
Php 7,568.37 Php 6,082,320.78
In words: Pesos In words: Pesos

Reinforcing Steel for seventy nine & 80/100 pesos thirty one thousand fifty two & 00/100 pesos
404 (a.6) S.Vault, Stairs & kgs. 29,944.17
Sunbreaker In figures: In figures:
Php 60.86 Php 1,822,497.79
In words: Pesos In words: Pesos
eight thousand nine hundred eighty seven & forty three thousand two hundred twenty seven &
00 /100 pesos 48/100 pesos
Reinforce Concrete for S.
900 (a.6) cu.m 232.13
Vault, Stairs & Sunbreaker
In figures: In figures:

Php 4,071.60 Php 945,140.16


In words: Pesos In words: Pesos
eight hundred fifty six & 36/100 pesos one hundred seventy six thousand four hundred fifty
three & 74/100 pesos
506(1) Masonry Works (CHB) sq.m 8,218.97
In figures: In figures:

Php 714.00 Php 5,868,372.40

Sub-Total (Page 2 of 4) Php 25,823,458.65

Submitted By:

BERSONS CONSTRUCTION & TRADING


Name of the Bidder

RUSSELL Q. BERNAL
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-STOREY 2-CL RM SB AT
BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN

Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

BILL OF QUANTITIES
Part No. Part Description:

Contract Name:
(Columns (1), (2), (3) and (4) are to be filled up by the
Procuring Entity) (Column (5) and (6) to be filled up by the Bidder)
In words: Pesos In words: Pesos
one hundred seventy & 94/100 pesos
sixty five thousand six hundred forty one & 73/100
pesos
1027 Cement Plaster Finish sq.m 16,392.34
In figures: In figures:

Php 114.79 Php 1,881,693.60


In words: Pesos In words: Pesos

one hundred five thousand nine hundred thirty &


eight hundred eighty nine & 42/100 pesos
1003 Carpentry & Joinery Works sq.m 11,127.60
22/100 pesos
In figures: In figures:
Php #REF! Php #REF!
In words: Pesos In words: Pesos

two hundred twenty three thousand six hundred seventy


one hundred fourteen & 21/100 pesos
403 (a) Steel Trusses kgs. 8,175.59
four & 27/100 pesos
In figures: In figures:
Php #REF! Php #REF!
In words: Pesos In words: Pesos

six hundred sixty five & 57/100 pesos ninety thousand two hundred ninety one & 31/100 pesos
1013 Roofing Works sq.m 1,653.00
In figures: In figures:
Php #REF! Php #REF!
In words: Pesos In words: Pesos
two thousand two hundred forty nine & fifty eight thousand ninety three& 50/100 pesos
94/100 pesos
1009 Jalousie Windows sq.m 836.23
In figures: In figures:

Php 1,693.19 Php 1,415,899.08


In words: Pesos In words: Pesos
four thousand seven hundred two & 88/100 forty five thousand one hundred forty seven & 61/100
pesos pesos
1010 Doors sq.m 426.72
In figures: In figures:

Php 4,007.95 Php 1,710,274.27


In words: Pesos In words: Pesos
nine thousand seven hundred forty five & nine thousand seven hundred forty five & 68/100 pesos
68/100 pesos
1002 Plumbing Works LS All
In figures: In figures:

Php 0.00 Php 0.00

Sub-Total (Page 3 of 4) Php #REF!

Submitted By:

BERSONS CONSTRUCTION & TRADING


Name of the Bidder

RUSSELL Q. BERNAL
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-STOREY 2-CL RM SB AT
BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN

Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

BILL OF QUANTITIES
Part No. Part Description:

(Columns (1), (2), (3) and (4) are to be filled up by the


Procuring Entity) (Column (5) and (6) to be filled up by the Bidder)

In words: Pesos In words: Pesos

sixty four & 42/100 pesos forty nine thousand four hundred sixty & 80/100 pesos
1032 a-1 Masonry Painting sq.m 32,784.68
In figures: In figures:
Php 34.67 Php 1,136,614.24
In words: Pesos In words: Pesos

twenty seven thousand three hundred eight & 55/100


eighty nine & 42/100 pesos
1032 a-2 Wooden Painting sq.m 14,779.88
pesos
In figures: In figures:
Php 40.47 Php 598,081.87
In words: Pesos In words: Pesos

thirty nine thousand two hundred twenty one thirty nine thousand two hundred twenty one & 37 /100
1100 Electrical Works LS All
& 37 /100 pesos pesos
In figures: In figures:
Php 0.00 Php 0.00
In words: Pesos In words: Pesos

seventy three & 24/100 pesos six thousand two hundred sixty one & 63/100 pesos
Damproofing / Moisture
Spl 1 sq.m 1,445.00
Control
In figures: In figures:
Php 55.01 Php 79,482.67
In words: Pesos In words: Pesos
one thousand one hundred four & 33/100 thirty four thousand seven hundred eighty six & 41/100
pesos pesos
Spl 2 Railings L.M 884.64
In figures: In figures:

Php 83.30 Php 73,693.85


In words: Pesos In words: Pesos
eighteen thousand one hundred nineteen & eighteen thousand one hundred nineteen & 31/100 pesos
31/100 pesos
Occupational Safety &
Spl.3 LS All
Health
In figures: In figures:

Php 0.00 Php 0.00


In words: Pesos In words: Pesos
three thousand three hundred fifty two & three thousand three hundred fifty two & 89/100 pesos
89/100 pesos
Spl.4 Project Billboard each 1.00
In figures: In figures:

Php 0.00 Php 0.00

Sub-Total (Page 4 of 4) Php 1,887,872.63


TOTAL AMOUNT IN WORDS

TWO MILLION ONE HUNDRED SIXTY FIVE THOUSAND NINETY NINE & 40/100 pesos.
Php #REF!

Submitted By:

BERSONS CONSTRUCTION & TRADING


Name of the Bidder

RUSSELL Q. BERNAL
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-STOREY 2-CL RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN
Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

Cal. Days: 180CD

BAR CHART/S-CURVE

Item No. Description Unit Amount % 1st QUARTER 2nd QUARTER 3rd QUARTER 4th QUARTER
803(a) Structure Excavation (common earth) cu.m. 685,767.15 #REF! 100

804 (a) Embankment (Backfilling) cu.m. 12,353.06 #REF!

804 (b) Spreading, Tamping & Grading cu.m. 1,379.95 #REF!

804 (d-1) Gravel Fill (hand placed) cu.m. 76,119.89 #REF!

404 (a.1) Reinforcing Steel for Column Footing & FTB kgs 3,342,782.48 #REF!

900 (a.1) Reinforce Concrete Column Footing & FTB cu.m. 1,586,079.32 #REF!

404 (a.2) Reinforcing Steel for Column kgs 3,173,787.15 #REF!

900 (a.2) Reinforce Concrete for Column cu.m. 4,784,917.09 #REF!


75%
404 (a.3) Reinforcing Steel for Beam kgs 11,109,208.81 #REF!

900 (a.3) Reinforce Concrete for Beam cu.m. 5,726,250.60 #REF!

404 (a.4) Reinforcing Steel for Slab on Fill kgs 143,125.81 #REF!

900 (a.4) Reinforce Concrete for Slab on Fill cu.m. 569,927.56 #REF!

404 (a.5) Reinforcing Steel for Suspended Slab kgs 4,872,012.39 #REF!

900 (a.5) Reinforce Concrete for Suspended Slab cu.m. 6,082,320.78 #REF!

404 (a.6) Reinforcing Steel for S.Vault, Stairs & Sunbreaker kgs 1,822,497.79 #REF!

900 (a.6) Reinforce Concrete for S. Vault, Stairs & Sunbreaker cu.m. 945,140.16 #REF!

506(1) Masonry Works (CHB) sq.m 6,221,960.85 #REF!


50%
1027 Cement Plaster Finish sq.m 1,961,838.86 #REF!

1003 Carpentry & Joinery Works sq.m #REF! #REF!

403 (a) Steel Trusses kgs #REF! #REF!

1013 Roofing Works sq.m #REF! #REF!

1009 Jalousie Windows sq.m 1,463,931.02 #REF!

1010 Doors sq.m 1,775,503.37 #REF!

1002 Plumbing Works L.S. 18,227.40 #REF!

1018 Ceramic tiles sq.m 16,313.53 #REF! 25%

1032 a-1 Masonry Painting sq.m 1,197,586.24 #REF!

1032 a-2 Wooden Painting sq.m 638,309.75 #REF!

1100 Electrical Works sq.m 45,908.58 #REF!

Spl 1 Damproofing / Moisture Control L.S. 79,482.67 #REF!

Spl 2 Railings sq.m 73,693.85 #REF!

Spl.3 Occupational Safety & Health L.M 6,371.21 #REF!

Spl.4 Project Billboard LS - #REF! 0

TOTAL AMOUNT OF BID: #REF! #REF! 22.12% 24.63% 28.34% 24.91%

Submitted By:

BERSONS CONSTRUCTION & TRADING


Name of the Bidder

RUSSELL Q. BERNAL
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
DEPARTMENT OF PUBLIC WORKS & HIGHWAYS (DPWH)
NAME OF PROJECT : CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-STOREY 2-CL RM
CONTRACTOR BERSONS CONSTRUCTION & TRADING
CONTRACT AMOUNT : P2,183,000.00
CONTRACT TIME : 180 CD

804(d-1)
804(b) 3 CD
804(a) 2 CD
3 CD
803(a) 404(a-1) 404(a-2)
MOVE IN
11 CD 9 CD 900(a-1) 19 CD
3 CD 506(1)
27 CD

Item No. Description Unit Amount % MARCH 25 -APRIL 30, 2013

803(a) Structure Excavation (common earth) cu.m. 685,767.15 #REF!


#REF!
804 (a) Embankment (Backfilling) cu.m. 12,353.06 #REF! #REF!

804 (b) Spreading, Tamping & Grading cu.m. 1,379.95 #REF! #REF!

804 (d-1) Gravel Fill (hand placed) cu.m. 76,119.89 #REF! #REF!

404 (a.1) Reinforcing Steel for Column Footing & FTB kgs 3,342,782.48 #REF! #REF!

900 (a.1) Reinforce Concrete Column Footing & FTB cu.m. 1,586,079.32 #REF! #REF!

404 (a.2) Reinforcing Steel for Column kgs 3,173,787.15 #REF! #REF! #REF!

900 (a.2) Reinforce Concrete for Column cu.m. 4,784,917.09 #REF!

404 (a.3) Reinforcing Steel for Beam kgs 11,109,208.81 #REF!

900 (a.3) Reinforce Concrete for Beam cu.m. 5,726,250.60 #REF!

404 (a.4) Reinforcing Steel for Slab on Fill kgs 143,125.81 #REF!
900 (a.4) Reinforce Concrete for Slab on Fill cu.m. 569,927.56 #REF!

404 (a.5) Reinforcing Steel for Suspended Slab kgs 4,872,012.39 #REF!

900 (a.5) Reinforce Concrete for Suspended Slab cu.m. 6,082,320.78 #REF!

404 (a.6) Reinforcing Steel for S.Vault, Stairs & Sunbreaker kgs 1,822,497.79 #REF!

900 (a.6) Reinforce Concrete for S. Vault, Stairs & Sunbreaker cu.m. 945,140.16 #REF!

506(1) Masonry Works (CHB) sq.m 6,221,960.85 #REF! #REF!

1027 Cement Plaster Finish sq.m 1,961,838.86 #REF!

1003 Carpentry & Joinery Works sq.m #REF! #REF!

403 (a) Steel Trusses kgs #REF! #REF!

1013 Roofing Works sq.m #REF! #REF!

1009 Jalousie Windows sq.m 1,463,931.02 #REF!

1010 Doors sq.m 1,775,503.37 #REF!

1002 Plumbing Works L.S. 18,227.40 #REF!

1018 Ceramic tiles sq.m 16,313.53 #REF!

1032 a-1 Masonry Painting sq.m 1,197,586.24 #REF!

1032 a-2 Wooden Painting sq.m 638,309.75 #REF!

1100 Electrical Works L.S. 45,908.58 #REF!

Spl 1 Damproofing / Moisture Control sq.m 79,482.67 #REF!

Spl 2 Railings L.M 73,693.85 #REF!

Spl.3 Occupational Safety & Health L.S. 6,371.21 #REF!


#REF!
Spl.4 Project Billboard LS 0.00 #REF!
#REF!

#REF! #REF! #REF!


% Accomp. #REF!
Commulative % Accomp. #REF!
Cash #REF!
Commulative Cash #REF!

Prepared by: Checked By:

BERSONS CONSTRUCTION & TRADING ELDRED M. MISLANG


Contractor Asst Chief, Planning & Design Section
Y 2-CL RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN (CLUSTER I)

404(a-5)
SPL 1 404(a-4) 900(a-4) 3 CD 1100
1 CD 2 CD 9 CD 23 CD
900(a-5)
900(a-2) 404(a-3) 900(a-3) 3 CD 1027 403(a)
12 CD 14 CD 12 CD 19 CD 34 CD 1
06(1) 404(a-6) 1002 1018 SPL 2 1
7 CD 4 CD 6 CD 6 CD
900(a-6) 4 CD 8
2 CD SPL 3 & SPL 4
180 CD

BAR CHART & S-CURVE

MAY 1-31, 2013 JUNE 1-30, 2013 JULY 1-31, 2013 AU

#REF!

#REF!

#REF!

#REF!

#REF!
#REF! #REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF! #REF!

#REF! #REF!

#RE

#REF!

#REF!

#REF! #REF!

#REF!

#REF!

#REF! #REF! #REF!

#REF! #REF! #REF!

CASH FLOW
CASH FLOW

#REF! #REF! #REF!


#REF! #REF! #REF!
#REF! #REF! #REF!
#REF! #REF! #REF!

Submitted By: Recommending Approval:

BLESILDA P. ESTRADA EDITA L. MANUEL


Chief, Planning & Design Section OIC-Asst. District Engineer
1013 1003 1032 (a-1)
10 CD 17 CD 17 CD
MOVE OUT
1009 1010 1032 (a-2)
8 CD 11 CD 10 CD

AUGUST 1-31, 2013 SEPTEMBER 1-20, 2013


100%

75%
75%

50%

#REF! #REF!

#REF!

#REF!

#REF!

25%

#REF!

#REF!

#REF! #REF!

0%

#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!

APPROVED:

MARIETA B. MENDOZA
OIC, District Engineer
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-STOREY 2-CL RM SB AT BOLINGIT NHS, SAN CARLOS CITY,
PANGASINAN

Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

Cal. Days: 180CD

CASH FLOW

CALENDAR DAYS 1st QUARTER 2nd QUARTER 3rd QUARTER 4th QUARTER
% Accomp. 22.12% 24.63% 28.34% 24.91%
Commulative % Accomp. 22.12% 46.75% 75.09% 100.00%
Cash #REF! #REF! #REF! #REF!
Commulative Cash #REF! #REF! #REF! #REF!

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-STOREY 2-CL RM SB AT
BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN

Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

EQUIPMENT UTILIZATION SCHEDULE

DURATION
EQUIPMENT
1st QUARTER 2nd QUARTER 3rd QUARTER 4th QUARTER
Bar Cutter (manually operated) 2 2 2
Plate compactor 1 1
Concrete Mixer (1-Bagger) 1 1 1
Concrete Vibrator 1 1 1
Welding machine 2 2
Electric Drill 1 2
Riveter 2

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name:
CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-STOREY 2-CL RM SB AT
BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN
Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

MANPOWER UTILIZATION SCHEDULE

DURATION
EQUIPMENT
1st QUARTER 2nd QUARTER 3rd QUARTER 4th QUARTER
Construction Foreman 1 1 1 1
Skilled Laborer 4 10 10 6
Unskilled Laborer 20 15 15 10
Part time Safety Practitioner 1 1 1 1

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Procuring Entity : DPWH Pangasinan 2nd Sub-District Enginering Office, Sta. Barbara, Pangasinan

Contract Reference No: 13AJ0006


Name of Contract: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT
LIBAS ES AND 2-STOREY 2-CL RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN

Location of the Contract: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

CONSTRUCTION METHOD

1.0 INTRODUCTION

CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT


LIBAS ES AND 2-STOREY 2-CL RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN

2.0 BRIEF DESCRIPTION OF CONTRACT WORKS

The work to be done in this project entails:

Item No. Description


803(a) Structure Excavation (common earth)
804 (a) Embankment (Backfilling)
804 (d-1) Gravel Fill (hand placed)
404 (a.1) Reinforcing Steel for Column Footing & FTB
900 (a.1) Reinforce Concrete Column Footing & FTB
404 (a.2) Reinforcing Steel for Column
900 (a.2) Reinforce Concrete for Column
404 (a.3) Reinforcing Steel for Beam
900 (a.3) Reinforce Concrete for Beam
404 (a.4) Reinforcing Steel for Slab on Fill
900 (a.4) Reinforce Concrete for Slab on Fill
404 (a.5) Reinforcing Steel for Suspended Slab
900 (a.5) Reinforce Concrete for Suspended Slab
404 (a.6) Reinforcing Steel for S.Vault, Stairs & Sunbreaker
900 (a.6) Reinforce Concrete for S. Vault, Stairs & Sunbreaker
506(1) Masonry Works (CHB)
1027 Cement Plaster Finish
1003 Carpentry & Joinery Works
403 (a) Steel Trusses
1013 Roofing Works
1009 Jalousie Windows
1010 Doors
1002 Plumbing Works
1032 a-1 Masonry Painting
1032 a-2 Wooden Painting
1100 Electrical Works
Spl 1 Damproofing / Moisture Control
Spl 2 Railings
Spl.3 Occupational Safety & Health
Spl.4 Project Billboard

3.0 CONSTRUCTION METHODS AND PROCEDURES

3.1 Methodology or General Approach

Mobilization upon receipt of Notice to Proceed. Installation of Project Billboard and other signages, Excavation & Backfilling,
Fabrication/Installation of RSB, Form works & Pouring of Concrete mix, Masonry & Plastering works, Painting Works,
Roofing works (trusses & roofing sheets),Carpentry & Joinery works, Doors & Windows, Ceramic tiles, Painting works,
Plumbing & Electrical works, Provision of Occupational safety & Health & Demobilization.

3.2 Program of Work

Progress Bar Chart with S-Curve of Activities in the contract works (please see attached S-Curve
and Bar Chart)

3.3 Financial Program

Cash Flow Schedule, provision for the working capital schedule of receipts, etc. (please see attached
cash flow in the financial aspect)

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name : CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES
AND 2-STOREY 2-CL RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN

Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

SUMMARY OF LABOR, EQUIPMENT RENTALS & MATERIAL COST

MATERIALS COST

Description Unit Price


Structural Steel Angular Bar …………………………… 52.00 / kgs
Structural Steel Channel Bar …………………………… 52.00 / kgs
10mm dia sagrod w/ nuts & washers at each end …………………………… 75.00 / pcs
10mm dia A-307 anchor bolts …………………………… 10.00 / pcs
10mm dia x 200mm anchor bolts …………………………… 28.00 / pcs
12mm dia x 250mm long bent anchor studs …………………………… 45.00 / pcs
Gusset plates 200mm x 200mm x 6.00mm …………………………… 200.00 / pcs
Base plates 200mm x 200mm x 10.00mm …………………………… 250.00 / pcs
12mm dia cross bracing …………………………… 52.00 / kgs
Welding rod …………………………… 120.00 / pcs
Oxygen (content only) …………………………… 50.00 / kgs
Acetylene (content only) …………………………… 60.00 / kgs
Red lead primer …………………………… 450.00 / gal
Paint thinner …………………………… 220.00 / gal
Paint brush …………………………… 80.00 / pcs
Welding Rod …………………………… 120.00 / kgs.
Red Lead Primer …………………………… 550.00 / gal
Thinner …………………………… 250.00 / gal
Paint brush 4" …………………………… 90.00 / pcs.
Asstd. RSB …………………………… 50.00 / kgs
Tie wire # 16 GI …………………………… 55.00 / kgs
CHB ( 4" x 8" x 16") …………………………… 10.00 / pcs
CHB ( 6" x 8" x 16") …………………………… 12.00 / pcs
Portland Cement, 40 kgs …………………………… 215.00 / bags
Washed Sand …………………………… 500.00 / cu. m.
Crushed Gravel …………………………… 600.00 / cu. m.
River mix …………………………… 300.00 / cu.m
Gravel fill …………………………… 300.00 / cu.m
Plywood - 1/2 x 4' x 8' …………………………… 600.00 / pcs.
Plywood - 1/4 x 4' x 8' …………………………… 300.00 / pcs.
Coco Lumber …………………………… 28.00 / bd.ft
Good Lumber …………………………… 75.00 / bd.ft
Assorted CWN …………………………… 70.00 / kgs
Tanguile Panelled Door …………………………… 2500.00 / sq.m.
Swing Type Steel Casement Window with Glass …………………………… 1800.00 / sq.m.
PVC Doors including Jamb and accessories (0.80m x 2.10m) …………………………… 2800.00 / sets
Hinges 2"x4" …………………………… 70.00 / pairs
CWN (assorted) …………………………… 70.00 / kgs
Corrugated Roofing, Gauge 26 …………………………… 280.00 / sq.m
Pre-painted ready made Ridge Roll (0.40mm) …………………………… 200.00 / L.m
Pre-painted ready made Gutter (0.40mm) …………………………… 200.00 / L.m
Pre-painted ready made wall Flashing (0.40mm) …………………………… 200.00 / L.m
Blind Rivets …………………………… 250.00 / boxes
Tekscrew …………………………… 2.00 / pcs.
Silicone Selant …………………………… 180.00 / pcs.
25mm x 250mm x 12' Fiber Cement Fascia Board …………………………… 650.00 / pcs.
Jalousie Window w/ clear glass blades on std aluminum ……………………………
casing and 50x150mm thk yakal jamb w/ complete
1550.00 / sq.m
accessories
Tanguile Panel Door on 50x150mm thk yakal jamb w/ ……………………………
complete accessories 3750.00 / sq.m
Hollow Core Flush Type Swing Door w/ complete accessories (toilet) …………………………… 1500.00 / sq.m
Water Closets …………………………… 4,500.00 / set
Lavatory …………………………… 4,800.00 / set
Male Urinal …………………………… 3,100.00 / set
Facial Mirror …………………………… 650.00 / set
Faucet …………………………… 350.00 / set
PVC pipe 4" dia. …………………………… 580.00 / pcs.
PVC pipe 3" dia. …………………………… 430.00 / pcs.
PVC pipe 2" dia. …………………………… 290.00 / pcs.
PVC pipe 4" dia. Elbow 1/4bend …………………………… 80.00 / pcs.
PVC pipe 4" dia. Elbow 1/8bend …………………………… 60.00 / pcs.
PVC pipe Wye 4" x 4" dia. …………………………… 125.00 / pcs.
PVC pipe Tee 4" x 4" dia. …………………………… 270.00 / pcs.
PVC pipe Reducer Tee 4" x 2" dia. …………………………… 110.00 / pcs.
PVC Clean out w/ plug 4" dia. …………………………… 60.00 / pcs.
PVC pipe 3" dia. Elbow 1/4bend …………………………… 40.00 / pcs.
PVC pipe 2" dia. Elbow 1/4bend …………………………… 25.00 / pcs.
PVC pipe 2" dia. Elbow 1/8bend …………………………… 20.00 / pcs.
PVC pipe 2" dia. Tee …………………………… 75.00 / pcs.
Floor Drain …………………………… 280.00 / pcs.
Solvent …………………………… 190.00 / qrt
G.I pipe 38mm dia. …………………………… 850.00 / pcs.
G.I pipe 20mm dia. …………………………… 610.00 / pcs.
G.I pipe 12mm dia. …………………………… 420.00 / pcs.
G.I coupling elbow …………………………… 25.00 / pcs.
G.I Tee …………………………… 25.00 / pcs.
Ceiling fan …………………………… 1,000.00 / set
Flourescent Lighting Fixtures (40 watts) with box type housing …………………………… 600.00 / set
Compact Incandescent lamp …………………………… 60.00 / pcs.
Porcelain socket # 4"Ø …………………………… 40.00 / pcs.
Light Switch 1 way 2 gang …………………………… 142.00 / pcs.
Light Switch 1 way 1 gang …………………………… 142.00 / pcs.
Utility Box (Deep tape) …………………………… 30.00 / pcs.
PVC Coupling PNS 14, 15mm dia. …………………………… 3.00 / pcs.
PVC Pipe PNS 14,15mm dia. …………………………… 69.00 / pcs.
PVC Pipe PNS 14, 20mm dia. …………………………… 120.00 / pcs.
PVC Adapter PNS 14,15mm dia. …………………………… 8.00 / pcs.
Entrance cap # 15mm dia. …………………………… 62.00 / pcs,
Junction Box (Deep tape w/ Cover) …………………………… 31.00 / pcs.
Copper Wire #3.50mm2 TW …………………………… 24.00 / mtrs
Electrical Tape …………………………… 40.00 / pcs.
Enclosed Air circuit breaker, 220V, 2P, 20AT, 50 AF …………………………… 1,350.00 / set
Equipment for Fire alarm, Vibrating Bell, 10" dia. …………………………… 1,300.00 / set
Exhaust Fan 400mm …………………………… 1,000.00 / unit
Polythelene sheets …………………………… 50.00 / sq.m
Steel railings, 19mm sq. bar welded to 50mmØ GI Pipe handrail …………………………… 725.00 / sq.m
Steel railings, 50mmØ GI Pipe handrail w/ 25mm sq. bracket @ 600mm …………………………… 250.00 / LM
Steel railings, 32mmØ GI Pipe handrail …………………………… 175.00 / LM
32mmØ Stainless Pipe Grab bar …………………………… 400.00 / LM
Ceramic Glazed Tiles (20cm x 20cm) …………………………… 550.00 / sq.m
Ceramic Unglazed Tiles (20cm x 20cm) 600.00 / sq.m
Portland Cement …………………………… 215.00 / bag
Tile adhesive …………………………… 240.00 / bag
Paint Latex Gloss (Boysen) …………………………… 450.00 / gal
Paint Latex Semi-Gloss (Boysen) …………………………… 450.00 / gal
Flat Wall Enamel (Boysen) …………………………… 500.00 / gal
Quick Dry Enamel (Boysen) …………………………… 500.00 / gal
Glazing Putty …………………………… 400.00 / gal
Paint thinner …………………………… 220.00 / gal
Concrete Neutralizer …………………………… 380.00 / gal
Sand paper …………………………… 1500.00 / roll
Paint brush 4" …………………………… 80.00 / pcs
Paint roller …………………………… 85.00 / pcs
Tarpaulin …………………………… 30.00 / sq.ft

LABOR COST

Designation Rate per Day


Construction Foreman …………………………… 540.00
Skilled Laborer …………………………… 400.00
Unskilled Laborer …………………………… 280.00
Part time Safety Practitioner …………………………… 540.00

EQUIPMENT RENTALS

Description Rentals
Plate Compactor …………………………… 600.00
Bar Cutter (manually operated) …………………………… 350.00
Concrete Mixer (1-Bagger) …………………………… 1,390.00
Concrete Vibrator …………………………… 510.00
Welding machine …………………………… 500.00
Electric Drill …………………………… 100.00
Riveter …………………………… 100.00

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-STOREY 2-CL
RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN
Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

BILL OF QUANTITIES
Part No. Part Description:

(Columns (1), (2), (3) and (4) are to be filled up


(Column (5) and (6) to be filled up by the Bidder)
by the Procuring Entity)
Pay Item no. Description Unit Quantity Unit Price (Pesos) Amount (Pesos)

In words: Pesos In words: Pesos


three hundred ninety & 18/100 pesos twenty seven thousand four & 36/100 pesos
Structure Excavation
803(a) cu.m. 2,280.48
(common earth)
In figures: In figures:

Php 284.42 Php 648,620.97


In words: Pesos In words: Pesos
seven hundred thirty four & 49/100 six thousand two hundred seventy nine &
pesos 89/100 pesos
804 (d-1) Gravel Fill (hand placed) cu.m. 144.50
In figures: In figures:

Php 522.24 Php 75,463.74


In words: Pesos In words: Pesos
seventy seven & 89/100 pesos one hundred twenty three thousand one
Reinforcing Steel for hundred thirty nine & 42/100 pesos
404 (a.1) kgs. 52,964.57
Column Footing & FTB
In figures: In figures:

Php 60.44 Php 3,201,374.15


In words: Pesos In words: Pesos
three thousand seven hundred sixty seventy thousand five hundred thirty six &
Reinforce Concrete five & 95/100 pesos 24/100 pesos
900 (a.1) cu.m 535.34
Column Footing & FTB
In figures: In figures:

Php 2,902.30 Php 1,553,718.76


In words: Pesos In words: Pesos
seventy seven & 77/100 pesos two hundred eighty seven thousand nine
Reinforcing Steel for hundred thirty three & 18/100 pesos
404 (a.2) kgs. 51,148.25
Column
In figures: In figures:
Php 58.59 Php 2,996,536.13
In words: Pesos In words: Pesos
nine thousand five hundred eighty five eighty eight thousand five hundred sixty nine &
Reinforce Concrete for & 47/100 pesos 72/100 pesos
900 (a.2) cu.m 570.24
Column
In figures: In figures:
Php 8,301.18 Php 4,733,664.42
In words: Pesos In words: Pesos
seventy seven & 77/100 pesos one hundred eighty four thousand five & 25/100
Reinforcing Steel for pesos
404 (a.3) kgs. 189,416.67
Beam
In figures: In figures:

Php 56.28 Php 10,661,315.84

Sub-Total (Page 1of 4) Php 23,870,694.01

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-STOREY 2-CL
Contract Location: MALASIQUI AND SANNHS,
RM SB AT BOLINGIT CARLOS
SANCITY, PANGASINAN
CARLOS CITY, PANGASINAN

BILL OF QUANTITIES
Part No. Part Description:

(Columns (1), (2), (3) and (4) are to be filled up


(Column (5) and (6) to be filled up by the Bidder)
by the Procuring Entity)
In words: Pesos In words: Pesos
nine thousand three hundred four & one hundred seven thousand five hundred sixty
Reinforce Concrete for 66 /100 pesos one & 84/100 pesos
900 (a.3) cu.m 821.45
Beam
In figures: In figures:

Php 6,912.69 Php 5,678,426.55


In words: Pesos In words: Pesos
seventy seven & 78/100 pesos sixteen thousand eight hundred seventy three &
Reinforcing Steel for 55/100 pesos
404 (a.4) kgs. 2,302.79
Slab on Fill
In figures: In figures:

Php 59.36 Php 136,686.08


In words: Pesos In words: Pesos
three thousand seven hundred forty thirty four thousand eight hundred sixty seven
Reinforce Concrete for nine & 21/100 pesos & 61/100 pesos
900 (a.4) cu.m 144.50
Slab on Fill
In figures: In figures:

Php 3,047.32 Php 440,337.82


In words: Pesos In words: Pesos
fifty three thousand seven hundred seventy one
seventy seven & 77/100 pesos
404 (a.5) Reinforcing Steel for Suspended Slab
kgs. 82,171.12 & 19/100 pesos
In figures: In figures:
Php 57.24 Php 4,703,147.56
In words: Pesos In words: Pesos
fourteen thousand six hundred fifty & one hundred thirty seven thousand seven
Reinforce Concrete for
900 (a.5) cu.m 803.65 80/100 pesos hundred seventeen & 49/100 pesos
Suspended Slab
In figures: In figures:
Php 7,612.95 Php 6,118,144.07
In words: Pesos In words: Pesos

Reinforcing Steel for seventy nine & 80/100 pesos thirty one thousand fifty two & 00/100 pesos
404 (a.6) S.Vault, Stairs & kgs. 29,944.17
Sunbreaker In figures: In figures:
Php 58.80 Php 1,760,747.14
In words: Pesos In words: Pesos
eight thousand nine hundred eighty forty three thousand two hundred twenty seven
Reinforce Concrete for seven & 00 /100 pesos & 48/100 pesos
900 (a.6) S. Vault, Stairs & cu.m 232.13
Sunbreaker In figures: In figures:

Php 4,115.78 Php 955,396.33


In words: Pesos In words: Pesos
eight hundred fifty six & 36/100 pesos one hundred seventy six thousand four hundred
fifty three & 74/100 pesos
506(1) Masonry Works (CHB) sq.m 8,218.97
In figures: In figures:

Php 711.44 Php 5,847,328.54

Sub-Total (Page 2 of 4) Php 25,640,214.09

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-STOREY 2-CL
RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN
Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

BILL OF QUANTITIES
Part No. Part Description:

Contract Name:
(Columns (1), (2), (3) and (4) are to be filled up
(Column (5) and (6) to be filled up by the Bidder)
by the Procuring Entity)
In words: Pesos In words: Pesos
one hundred seventy & 94/100 pesos sixty five thousand six hundred forty one &
73/100 pesos
1027 Cement Plaster Finish sq.m 16,392.34
In figures: In figures:

Php 114.97 Php 1,884,622.00


In words: Pesos In words: Pesos
eight hundred eighty nine & 42/100 one hundred five thousand nine hundred thirty
Carpentry & Joinery
1003 sq.m 11,127.60 pesos & 22/100 pesos
Works
In figures: In figures:
Php #REF! Php #REF!
In words: Pesos In words: Pesos
two hundred twenty three thousand six hundred
one hundred fourteen & 21/100 pesos
403 (a) Steel Trusses kgs. 8,175.59 seventy four & 27/100 pesos
In figures: In figures:
Php #REF! Php #REF!
In words: Pesos In words: Pesos
ninety thousand two hundred ninety one &
six hundred sixty five & 57/100 pesos
1013 Roofing Works sq.m 1,653.00 31/100 pesos
In figures: In figures:
Php #REF! Php #REF!
In words: Pesos In words: Pesos
two thousand two hundred forty nine & fifty eight thousand ninety three& 50/100
94/100 pesos pesos
1009 Jalousie Windows sq.m 836.23
In figures: In figures:

Php 1,691.48 Php 1,414,464.19


In words: Pesos In words: Pesos
four thousand seven hundred two & forty five thousand one hundred forty seven &
88/100 pesos 61/100 pesos
1010 Doors sq.m 426.72
In figures: In figures:

Php 4,004.60 Php 1,708,841.54


In words: Pesos In words: Pesos
nine thousand seven hundred forty five nine thousand seven hundred forty five &
& 68/100 pesos 68/100 pesos
1002 Plumbing Works LS All
In figures: In figures:

Php 0.00 Php 0.00

Sub-Total (Page 3 of 4) Php #REF!

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-STOREY 2-CL
RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN
Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

BILL OF QUANTITIES
Part No. Part Description:

(Columns (1), (2), (3) and (4) are to be filled up


(Column (5) and (6) to be filled up by the Bidder)
by the Procuring Entity)
In words: Pesos In words: Pesos
forty nine thousand four hundred sixty &
sixty four & 42/100 pesos
1032 a-1 Masonry Painting sq.m 32,784.68 80/100 pesos
In figures: In figures:
Php 34.46 Php 1,129,724.96
In words: Pesos In words: Pesos
twenty seven thousand three hundred eight &
eighty nine & 42/100 pesos
1032 a-2 Wooden Painting sq.m 14,779.88 55/100 pesos
In figures: In figures:
Php 40.21 Php 594,257.14
In words: Pesos In words: Pesos
thirty nine thousand two hundred thirty nine thousand two hundred twenty one &
1100 Electrical Works LS All twenty one & 37 /100 pesos 37 /100 pesos
In figures: In figures:
Php 0.00 Php 0.00
In words: Pesos In words: Pesos
six thousand two hundred sixty one & 63/100
Damproofing / Moisture seventy three & 24/100 pesos
Spl 1 sq.m 1,445.00 pesos
Control
In figures: In figures:
Php 54.88 Php 79,306.09
In words: Pesos In words: Pesos
one thousand one hundred four & thirty four thousand seven hundred eighty six &
33/100 pesos 41/100 pesos
Spl 2 Railings L.M 884.64
In figures: In figures:

Php 82.90 Php 73,340.64


In words: Pesos In words: Pesos
eighteen thousand one hundred eighteen thousand one hundred nineteen &
Occupational Safety & nineteen & 31/100 pesos 31/100 pesos
Spl.3 LS All
Health
In figures: In figures:

Php 201,272.00 Php 201,272.00


In words: Pesos In words: Pesos
three thousand three hundred fifty two three thousand three hundred fifty two &
& 89/100 pesos 89/100 pesos
Spl.4 Project Billboard each 1.00
In figures: In figures:

Php 0.00 Php 0.00

Sub-Total (Page 4 of 4) Php 2,077,900.83


TOTAL AMOUNT IN WORDS

TWO MILLION ONE HUNDRED SIXTY FIVE THOUSAND NINETY NINE & 40/100 pesos.
Php #REF!

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT
LIBAS ES AND 2-STOREY 2-CL RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN
Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

DETAILED ESTIMATES
A PROPOSED FIVE-STOREY BUILDING OF PRINCETON INTEGRATED SCHOOL: "AN INNOVATIVE GREEN ENGINEERING
DESIGN"

Item 803(a) Structure Excavation (common earth)


QTY. = 2,280.48 cu.m.

B. LABOR
DESCIPRTION NO. DAYS RATE TOTAL
Unskilled Laborer 20 115.00 280.00 644,000.00

Sub-total 644,000.00

Total Direct Cost 644,000.00


Mark-up 4,620.97
Total Item Cost 648,620.97
Unit Cost 284.42

Item 804 (d-1) Gravel Fill (hand placed)


QTY. = 144.50 cu.m.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Gravel fill 145.00 cu.m. 300.00 43,500.00

Sub-total 43,500.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Unskilled Laborer 2 36.00 280.00 20,160.00

Sub-total 20,160.00
C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Plate compactor 1 18.00 600.00 10,800.00

Sub-total 10,800.00

Total Direct Cost 74,460.00


Mark-up 1,003.74
Total Item Cost 75,463.74
Unit Cost 522.24
Item 404 (a.1) Reinforcing Steel for Column Footing & FTB

QTY. = 52,964.57 kgs.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB 52,964.57 kgs. 50.00 2,648,228.50
Tie wire (#16 G.I.) 794.00 kgs. 55.00 43,670.00

Sub-total 2,691,898.50

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (steelman) 4 158.00 400.00 252,800.00
Unskilled Laborer 4 158.00 280.00 176,960.00

Sub-total 429,760.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 158.00 350.00 55,300.00

Sub-total 55,300.00

Total Direct Cost 3,176,958.50


Mark-up 24,415.65
Total Item Cost 3,201,374.15
Unit Cost 60.44

Item 900 (a.1) Reinforce Concrete Column Footing & FTB


QTY. = 535.34 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland cement, 40 kgs 4,819.00 bags 215.00 1,036,085.00
Washed sand 267.70 cu. m. 500.00 133,850.00
Crushed Gravel 536.00 cu. m. 600.00 321,600.00

Sub-total 1,491,535.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 11.00 540.00 5,940.00
Skilled Laborer (carpentry/mason) 2 11.00 400.00 8,800.00
Unskilled Laborer 5 11.00 280.00 15,400.00

Sub-total 30,140.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete mixer (1-bagger) 1 11.00 1,390.00 15,290.00
Minor tools 3,014.00

Sub-total 18,304.00

Total Direct Cost 1,539,979.00


Mark-up 13,739.76
Total Item Cost 1,553,718.76
Unit Cost 2,902.30
Item 404 (a.2) Reinforcing Steel for Column

QTY. = 51,148.25 kgs.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB 51,148.25 kgs. 50.00 2,557,412.50
Tie wire (#16 G.I.) 767.00 kgs. 55.00 42,185.00

Sub-total 2,599,597.50

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (steelman) 2 187.00 400.00 149,600.00
Unskilled Laborer 2 187.00 280.00 104,720.00

Sub-total 254,320.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 187.00 350.00 65,450.00

Sub-total 65,450.00

Total Direct Cost 2,919,367.50


Mark-up 77,168.63
Total Item Cost 2,996,536.13
Unit Cost 58.59

Item 900 (a.2) Reinforce Concrete for Column


QTY. = 570.24 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland cement, 40 kgs 5,133.00 bags 215.00 1,103,595.00
Washed sand 285.20 cu. m. 500.00 142,600.00
Crushed Gravel 571.00 cu. m. 600.00 342,600.00
Plywood, 1/4"x4'x8' 1,899.00 pcs. 300.00 569,700.00
Assorted CWN 855.00 kgs. 70.00 59,850.00
Coco Lumber 28,512.00 bd.ft 28.00 798,336.00

Sub-total 3,016,681.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 328.00 540.00 177,120.00
Skilled Laborer (carpenter/mason) 4 328.00 400.00 524,800.00
Unskilled Laborer 6 328.00 280.00 551,040.00

Sub-total 1,252,960.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete mixer (1-bagger) 1 328.00 1,390.00 455,920.00

Sub-total 455,920.00

Total Direct Cost 4,725,561.00


Mark-up 8,103.42
Total Item Cost 4,733,664.42
Unit Cost 8,301.18
Item 404 (a.3) Reinforcing Steel for Beam

QTY. = 189,416.67 kgs.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB 189,416.67 kgs. 50.00 9,470,833.50
Tie wire (#16 G.I.) 2,841.00 kgs. 55.00 156,255.00

Sub-total 9,627,088.50

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (steelman) 2 576.00 400.00 460,800.00
Unskilled Laborer 2 576.00 280.00 322,560.00

Sub-total 783,360.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 576.00 350.00 201,600.00

Sub-total 201,600.00

Total Direct Cost 10,612,048.50


Mark-up 49,267.34
Total Item Cost 10,661,315.84
Unit Cost 56.28

Item 900 (a.3) Reinforce Concrete for Beam


QTY. = 821.45 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland cement, 40 kgs 7,394.00 bags 215.00 1,589,710.00
Washed sand 410.80 cu. m. 500.00 205,400.00
Crushed Gravel 822.00 cu. m. 600.00 493,200.00
Plywood, 1/4"x4'x8' 2,736.00 pcs. 300.00 820,800.00
Assorted CWN 1,233.00 kgs. 70.00 86,310.00
Coco Lumber 41,073.00 bd.ft 28.00 1,150,044.00

Sub-total 4,345,464.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 229.00 540.00 123,660.00
Skilled Laborer (carpenter/mason) 4 229.00 400.00 366,400.00
Unskilled Laborer 8 229.00 280.00 512,960.00

Sub-total 1,003,020.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete mixer (1-bagger) 1 229.00 1,390.00 318,310.00

Sub-total 318,310.00

Total Direct Cost 5,666,794.00


Mark-up 11,632.55
Total Item Cost 5,678,426.55
Unit Cost 6,912.69
Item 404 (a.4) Reinforcing Steel for Slab on Fill

QTY. = 2,302.79 kgs.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB 2,302.79 kgs. 50.00 115,139.50
Tie wire (#16 G.I.) 35.00 kgs. 55.00 1,925.00

Sub-total 117,064.50

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (steelman) 2 9.00 400.00 7,200.00
Unskilled Laborer 2 9.00 280.00 5,040.00

Sub-total 12,240.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 9.00 350.00 3,150.00

Sub-total 3,150.00

Total Direct Cost 132,454.50


Mark-up 4,231.58
Total Item Cost 136,686.08
Unit Cost 59.36

Item 900 (a.4) Reinforce Concrete for Slab on Fill


QTY. = 144.50 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland cement, 40 kgs 1,301.00 bags 215.00 279,715.00
Washed sand 72.30 cu. m. 500.00 36,150.00
Crushed Gravel 145.00 cu. m. 600.00 87,000.00

Sub-total 402,865.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 6.00 540.00 3,240.00
Skilled Laborer (carpenter/mason) 4 6.00 400.00 9,600.00
Unskilled Laborer 8 6.00 280.00 13,440.00

Sub-total 26,280.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete mixer (1-bagger) 1 6.00 1,390.00 8,340.00

Sub-total 8,340.00

Total Direct Cost 437,485.00


Mark-up 2,852.82
Total Item Cost 440,337.82
Unit Cost 3,047.32
Item 404 (a.5) Reinforcing Steel for Suspended Slab

QTY. = 82,171.12 kgs.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB 82,171.12 kgs. 50.00 4,108,556.00
Tie wire (#16 G.I.) 1,233.00 kgs. 55.00 67,815.00

Sub-total 4,176,371.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (steelman) 2 300.00 400.00 240,000.00
Unskilled Laborer 2 300.00 280.00 168,000.00

Sub-total 408,000.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 300.00 350.00 105,000.00

Sub-total 105,000.00

Total Direct Cost 4,689,371.00


Mark-up 13,776.56
Total Item Cost 4,703,147.56
Unit Cost 57.24

Item 900 (a.5) Reinforce Concrete for Suspended Slab


QTY. = 803.65 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland cement, 40 kgs 7,233.00 bags 215.00 1,555,095.00
Washed sand 401.90 cu. m. 500.00 200,950.00
Crushed Gravel 804.00 cu. m. 600.00 482,400.00
Plywood, 1/4"x4'x8' 2,677.00 pcs. 300.00 803,100.00
Assorted CWN 1,206.00 kgs. 70.00 84,420.00
Coco Lumber 104,475.00 bd.ft 28.00 2,925,300.00

Sub-total 6,051,265.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 3.00 540.00 1,620.00
Skilled Laborer (carpenter/mason) 10 3.00 400.00 12,000.00
Unskilled Laborer 20 3.00 280.00 16,800.00

Sub-total 30,420.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete mixer (1-bagger) 1 3.00 1,390.00 4,170.00

Sub-total 4,170.00

Total Direct Cost 6,085,855.00


Mark-up 32,289.07
Total Item Cost 6,118,144.07
Unit Cost 7,612.95
Item 404 (a.6) Reinforcing Steel for S.Vault, Stairs & Sunbreaker

QTY. = 29,944.17 kgs.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB 29,944.17 kgs. 50.00 1,497,208.50
Tie wire (#16 G.I.) 449.00 kgs. 55.00 24,695.00

Sub-total 1,521,903.50

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (steelman) 2 137.00 400.00 109,600.00
Unskilled Laborer 2 137.00 280.00 76,720.00

Sub-total 186,320.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 137.00 350.00 47,950.00

Sub-total 47,950.00

Total Direct Cost 1,756,173.50


Mark-up 4,573.64
Total Item Cost 1,760,747.14
Unit Cost 58.80

Item 900 (a.6) Reinforce Concrete for S. Vault, Stairs & Sunbreaker
QTY. = 232.13 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland cement, 40 kgs 2,090.00 bags 215.00 449,350.00
Washed sand 116.10 cu. m. 500.00 58,050.00
Crushed Gravel 233.00 cu. m. 600.00 139,800.00
Plywood, 1/4"x4'x8' 20.00 pcs. 300.00 6,000.00
Assorted CWN 349.00 kgs. 70.00 24,430.00
Coco Lumber 9,285.00 bd.ft 28.00 259,980.00

Sub-total 937,610.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 2.00 540.00 1,080.00
Skilled Laborer (carpenter/mason) 2 2.00 400.00 1,600.00
Unskilled Laborer 8 2.00 280.00 4,480.00

Sub-total 7,160.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete mixer (1-bagger) 1 2.00 1,390.00 2,780.00

Sub-total 2,780.00

Total Direct Cost 947,550.00


Mark-up 7,846.33
Total Item Cost 955,396.33
Unit Cost 4,115.78
Item 506(1) Masonry Works (CHB)
QTY. = 8,218.97 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
CHB 6" x 8" x 16" 102,738.00 pcs 12.00 1,232,856.00
Portland Cement 8,367.00 bags 215.00 1,798,905.00
Washed Sand 694.00 cu.m 500.00 347,000.00
RSB 10mm dia. 22,103.00 kgs 50.00 1,105,150.00
#16 G.I. Tie Wire 332.00 kgs 55.00 18,260.00

Sub-total 4,502,171.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Mason) 6 322.00 400.00 772,800.00
Unskilled Laborer 6 322.00 280.00 540,960.00

Sub-total 1,313,760.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 5,815,931.00


Mark-up 31,397.54
Total Item Cost 5,847,328.54
Unit Cost 711.44

Item 1027 Cement Plaster Finish


QTY. = 16,392.34 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland Cement, 40 kgs 3,541.00 bags 215.00 761,315.00
Washed Sand 197.00 cu.m 500.00 98,500.00
Concrete mouldings 12.24 sq.m 400.00 4,896.00

Sub-total 864,711.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Mason) 6 247.00 400.00 592,800.00
Unskilled Laborer 6 247.00 280.00 414,960.00

Sub-total 1,007,760.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total

Total Direct Cost 1,872,471.00


Mark-up 12,151.00
Total Item Cost 1,884,622.00
Unit Cost 114.97
Item 1003 Carpentry & Joinery Works
QTY. = 11,127.60 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Marine Plywood 1/4" x 4' x 8' 4,055.00 pcs. 300.00 1,216,500.00
Ceiling joists (Nailers/Hangers) 50,075.00 bd. Ft. 75.00 3,755,625.00
Assorted CWN 1,169.00 kgs. 70.00 81,830.00
Ceiling ventillation w/ screen #REF! set 400.00 #REF!
Blackboard 12.00 set 3,000.00 36,000.00

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Carpenter) 3 185.00 400.00 222,000.00
Unskilled Laborer 3 185.00 280.00 155,400.00

Sub-total 377,400.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost #REF!


Mark-up 26,282.52
Total Item Cost #REF!
Unit Cost #REF!

Item 403 (a) Steel Trusses


QTY. = 8,175.59 kgs.
A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
LC 120 x 40 x 20 x 2.0mm x 6.00m Purlins 5,312.16 kgs 52.00 276,232.32
2" x 2"x 1/4" x 6.00m AB (T&B) 1,526.58 kgs 52.00 79,382.16
2" x 2"x 3/16" x 6.00m AB (WEB) 69.60 kgs 52.00 3,619.20
2 1/2" x 2 1/2"x 1/4" x 6.00m AB (CLEATS) 310.97 kgs 52.00 16,170.44
10mm dia sagrod w/ nuts & washers at each end 464.00 pcs 75.00 34,800.00
10mm dia A-307 anchor bolts 812.00 pcs 10.00 8,120.00
10mm dia x 200mm anchor bolts 108.00 pcs 28.00 3,024.00
12mm dia x 250mm long bent anchor studs 28.00 pcs 45.00 1,260.00
Gusset plates 200mm x 200mm x 6.00mm 112.00 pcs 200.00 22,400.00
Base plates 200mm x 200mm x 10.00mm 21.00 pcs 250.00 5,250.00
12mm dia cross bracing 16.00 kgs 52.00 832.00
Welding rod 110.00 pcs 120.00 13,200.00
Oxygen (content only) 25.00 kgs 50.00 1,250.00
Acetylene (content only) 25.00 kgs 60.00 1,500.00
Red lead primer 8.00 gal 450.00 3,600.00
Paint thinner 2.00 gal 220.00 440.00
Paint brush 6.00 pcs 80.00 480.00

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Welder) 4 15.00 400.00 24,000.00
Unskilled Laborer 4 15.00 280.00 16,800.00

Sub-total 40,800.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Welding machine 2 15.00 500.00 15,000.00
Minor tools (10% of Labor) 4,080.00

Sub-total 19,080.00

Total Direct Cost #REF!


Mark-up 40,917.24
Total Item Cost #REF!
Unit Cost #REF!
Item 1013 Roofing Works
QTY. = 1,653.00 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Corrugated Roofing, Gauge 26 1,653.00 sq.m 280.00 462,840.00
Pre-painted ready made Ridge Roll (0.40mm) #REF! L.m 200.00 #REF!
Pre-painted ready made Gutter (0.40mm) 3.33 L.m 200.00 665.00
Pre-painted ready made wall Flashing (0.40mm) 1,653.00 L.m 200.00 330,600.00
Blind Rivets #REF! boxes 250.00 #REF!
Tekscrew #REF! pcs. 2.00 #REF!
Silicone Selant #REF! pcs. 180.00 #REF!
25mm x 250mm x 12' Fiber Cement Fascia Board #REF! pcs. 650.00 #REF!
Misc. materials (Basket strainer, GI strap, etc.,) #REF! Lot 500.00 #REF!

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Tinsmithman) 4 17.00 400.00 27,200.00
Unskilled Laborer 4 17.00 280.00 19,040.00

Sub-total 46,240.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Electric Drill 2 17.00 100.00 3,400.00
Riveter 2 17.00 100.00 3,400.00

Sub-total 6,800.00

Total Direct Cost #REF!


Mark-up 14,885.76
Total Item Cost #REF!
Unit Cost #REF!

Item 1009 Jalousie Windows


QTY. = 836.23 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Jalousie Window w/ clear glass blades on std
aluminum casing and 50x150mm thk yakal jamb 836.23 sq.m 1,550.00 1,296,156.50
w/ complete accessories

Sub-total 1,296,156.50

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer 3 52.00 400.00 62,400.00
Unskilled Laborer 3 52.00 280.00 43,680.00

Sub-total 106,080.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 1,402,236.50


Mark-up 12,227.69
Total Item Cost 1,414,464.19
Unit Cost 1,691.48
Item 1010 Doors
QTY. = 426.72 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Tanguile Panel Door on 50x150mm thk yakal 426.72 sq.m 3,750.00 1,600,200.00
jamb w/ complete accessories

Sub-total 1,600,200.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer 2 76.00 400.00 60,800.00
Unskilled Laborer 2 76.00 280.00 42,560.00

Sub-total 103,360.00

Total Direct Cost 1,703,560.00


Mark-up 5,281.54
Total Item Cost 1,708,841.54
Unit Cost 4,004.60

Item 1002 Plumbing Works


QTY. = All LS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
PVC pipe 3" dia. 2.00 pcs. 430.00 860.00
PVC pipe 3" dia. Elbow 1/4bend 67.00 pcs. 40.00 2,680.00
Solvent 10.00 qrt 190.00 1,900.00

Sub-total 5,440.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Plumber) 1 19.00 400.00 7,600.00
Unskilled Laborer 1 19.00 280.00 5,320.00

Sub-total 12,920.00

Total Direct Cost 18,360.00


Mark-up (18,360.00)
Total Item Cost -
Unit Cost -
Item 1032 a-1 Masonry Painting
QTY. = 32,784.68 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Paint Latex Gloss (Boysen) 656.00 gal 450.00 295,200.00
Paint Latex Semi-Gloss (Boysen) 656.00 gal 450.00 295,200.00
Concrete Neutralizer 110.00 gal 380.00 41,800.00
Misc. materials (patching compound, brush, sand paper ,tinting color, etc.,) 5,000.00 5,000.00

Sub-total 637,200.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Painter) 4 178.00 400.00 284,800.00
Unskilled Laborer 4 178.00 280.00 199,360.00

Sub-total 484,160.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 1,121,360.00


Mark-up 8,364.96
Total Item Cost 1,129,724.96
Unit Cost 34.46
Item 1032 a-2 Wooden Painting
QTY. = 14,779.88 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Flat Wall Enamel (Boysen) 296.00 gal 500.00 148,000.00
Quick Dry Enamel (Boysen) 296.00 gal 500.00 148,000.00
Glazing Putty 50.00 gal 400.00 20,000.00
Misc. materials (patching compound, brush, sand paper ,tinting color, etc.,) 5,000.00 5,000.00

Sub-total 321,000.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Painter) 4 99.00 400.00 158,400.00
Unskilled Laborer 4 99.00 280.00 110,880.00

Sub-total 269,280.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 590,280.00


Mark-up 3,977.14
Total Item Cost 594,257.14
Unit Cost 40.21

Item 1100 Electrical Works


QTY. = All LS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Flourescent
Ceiling fan Lighting Fixtures (40 watts) with 72.00 set 1,000.00 72,000.00
box type housing 21.00 set 600.00 12,600.00
Light Switch 1 way 2 gang 12.00 pcs. 142.00 1,704.00
Light Switch 1 way 1 gang 119.00 pcs. 142.00 16,898.00
Utility Box (Deep tape) 3.00 pcs. 30.00 90.00
PVC Coupling PNS 14, 15mm dia. 160.00 pcs. 3.00 480.00
PVC Pipe PNS 14,15mm dia. 1.00 pcs. 69.00 69.00
PVC Pipe PNS 14, 20mm dia. 2.00 pcs. 120.00 240.00
PVC Adapter PNS 14,15mm dia. - pcs. 8.00 -
Entrance cap # 15mm dia. 2.00 pcs, 62.00 124.00
Junction Box (Deep tape w/ Cover) 75.00 pcs. 31.00 2,325.00
Copper Wire #3.50mm2 TW 1.00 mtrs 24.00 24.00
Enclosed
ElectricalAir circuit breaker, 220V, 2P, 20AT,
Tape 8.00 pcs. 40.00 320.00
Equipment
50 AF for Fire alarm, Vibrating Bell, 10" 17.00 set 1,350.00 22,950.00
dia. 5.00 set 1,300.00 6,500.00

Sub-total 138,944.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Electrician) 1 15.00 400.00 6,000.00
Unskilled Laborer 2 15.00 280.00 8,400.00

Sub-total 14,400.00

Total Direct Cost 153,344.00


Mark-up (153,344.00)
Total Item Cost -
Unit Cost -
Item Spl 1 Damproofing / Moisture Control
QTY. = 1,445.00 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Polythelene sheets 1,445.00 sq.m 50.00 72,250.00

Sub-total 72,250.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Unskilled Laborer 3 7.00 280.00 5,880.00

Sub-total 5,880.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 78,130.00


Mark-up 1,176.09
Total Item Cost 79,306.09
Unit Cost 54.88

Item Spl 2 Railings


QTY. = 884.64 L.M

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Steel railings, 19mm sq. bar welded to 50mmØ GI 26.60 sq.m 725.00 19,285.00
Steel railings, 50mmØ GI Pipe handrail w/ 25m 27.06 LM 250.00 6,765.00
Misc. materials (welding rod, paint, etc.,) 1.00 lot 500.00 500.00

Sub-total 26,550.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (welder) 2 21.00 400.00 16,800.00
Unskilled Laborer 2 21.00 280.00 11,760.00

Sub-total 28,560.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Welding machine 1 21.00 500.00 10,500.00
Minor tools (10% of Labor) 2,856.00

Sub-total 13,356.00

Total Direct Cost 68,466.00


Mark-up 4,874.64
Total Item Cost 73,340.64
Unit Cost 82.90
Item Spl.3 Occupational Safety & Health
QTY. = All LS

A. MATERIALS
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Safety Gears All LS 8,000.00 8,000.00
Signages, Barricades & Medicines All LS 2,000.00 2,000.00

Sub-total 10,000.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Part time Safety Practitioner 1.00 336.00 540.00 181,440.00

Sub-total 181,440.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Warning Signs 1 lot 2,000.00 2,000.00

Sub-total 2,000.00

Total Direct Cost 193,440.00


Mark-up 7,832.00
Total Item Cost 201,272.00
Unit Cost 201,272.00

Item Spl.4 Project Billboard


QTY. = 1.00 each

A. MATERIALS
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Tarpaulin 32.00 sq.ft 30.00 960.00
Coco lumber 30.00 bd.ft 28.00 840.00
Assorted CWN 2.00 sq.ft 70.00 140.00

Sub-total 1,940.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer 1.00 1.00 400.00 400.00
Unskilled Laborer 1.00 1.00 280.00 280.00

Sub-total 680.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 2,620.00


Mark-up (2,620.00)
Total Item Cost -
Unit Cost -
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name : CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT
LIBAS ES AND 2-STOREY 2-CL RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN
Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

SUMMARY OF TOTAL BID AMOUNT

Item No. Description Amount


803(a) Structure Excavation (common earth) 648,620.97
804 (d-1) Gravel Fill (hand placed) 75,463.74
404 (a.1) Reinforcing Steel for Column Footing & FTB 3,201,374.15
900 (a.1) Reinforce Concrete Column Footing & FTB 1,553,718.76
404 (a.2) Reinforcing Steel for Column 2,996,536.13
900 (a.2) Reinforce Concrete for Column 4,733,664.42
404 (a.3) Reinforcing Steel for Beam 10,661,315.84
900 (a.3) Reinforce Concrete for Beam 5,678,426.55
404 (a.4) Reinforcing Steel for Slab on Fill 136,686.08
900 (a.4) Reinforce Concrete for Slab on Fill 440,337.82
404 (a.5) Reinforcing Steel for Suspended Slab 4,703,147.56
900 (a.5) Reinforce Concrete for Suspended Slab 6,118,144.07
404 (a.6) Reinforcing Steel for S.Vault, Stairs & Sunbreaker 1,760,747.14
900 (a.6) Reinforce Concrete for S. Vault, Stairs & Sunbreaker 955,396.33
506(1) Masonry Works (CHB) 5,847,328.54
1027 Cement Plaster Finish 1,884,622.00
1003 Carpentry & Joinery Works #REF!
403 (a) Steel Trusses #REF!
1013 Roofing Works #REF!
1009 Jalousie Windows 1,414,464.19
1010 Doors 1,708,841.54
1002 Plumbing Works -
1032 a-1 Masonry Painting 1,129,724.96
1032 a-2 Wooden Painting 594,257.14
1100 Electrical Works -
Spl 1 Damproofing / Moisture Control 79,306.09
Spl 2 Railings 73,340.64
Spl.3 Occupational Safety & Health 201,272.00
Spl.4 Project Billboard -

TOTAL AMOUNT OF BID : #REF!


TOTAL AMOUNT IN WORDS

TWO MILLION ONE HUNDRED SIXTY FIVE THOUSAND NINETY NINE & 40/100 pesos.

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-STOREY 2-CL RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN
Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

Cal. Days: 180CD

BAR CHART/S-CURVE

Item No. Description Unit Amount % 1st QUARTER 2nd QUARTER 3rd QUARTER 4th QUARTER

803(a) Structure Excavation (common earth) cu.m. 663,592.58 #REF! 100

804 (a) Embankment (Backfilling) cu.m. 12,360.41 #REF!

804 (b) Spreading, Tamping & Grading cu.m. 1,380.97 #REF!

804 (d-1) Gravel Fill (hand placed) cu.m. 75,463.74 #REF!

404 (a.1) Reinforcing Steel for Column Footing & FTB kgs 3,234,014.31 #REF!

900 (a.1) Reinforce Concrete Column Footing & FTB cu.m. 1,608,965.12 #REF!

404 (a.2) Reinforcing Steel for Column kgs 3,075,666.73 #REF!

900 (a.2) Reinforce Concrete for Column cu.m. 4,794,152.11 #REF!


75%
404 (a.3) Reinforcing Steel for Beam kgs 10,723,927.19 #REF!

900 (a.3) Reinforce Concrete for Beam cu.m. 5,747,192.08 #REF!

404 (a.4) Reinforcing Steel for Slab on Fill kgs 138,805.95 #REF!

900 (a.4) Reinforce Concrete for Slab on Fill cu.m. 575,765.25 #REF!

404 (a.5) Reinforcing Steel for Suspended Slab kgs 4,703,147.56 #REF!

900 (a.5) Reinforce Concrete for Suspended Slab cu.m. 6,118,144.07 #REF!

404 (a.6) Reinforcing Steel for S.Vault, Stairs & Sunbreaker kgs 1,760,747.14 #REF!

900 (a.6) Reinforce Concrete for S. Vault, Stairs & Sunbreaker cu.m. 955,396.33 #REF!

506(1) Masonry Works (CHB) sq.m 6,201,129.75 #REF!


50%
1027 Cement Plaster Finish sq.m 1,964,815.25 #REF!

1003 Carpentry & Joinery Works sq.m #REF! #REF!

403 (a) Steel Trusses kgs #REF! #REF!

1013 Roofing Works sq.m #REF! #REF!

1009 Jalousie Windows sq.m 1,462,524.99 #REF!

1010 Doors sq.m 1,774,065.67 #REF!

1002 Plumbing Works L.S. 18,238.50 #REF!

1018 Ceramic tiles sq.m 16,323.41 #REF! 25%

1032 a-1 Masonry Painting sq.m 1,190,730.96 #REF!

1032 a-2 Wooden Painting sq.m 634,510.54 #REF!

1100 Electrical Works sq.m 45,936.08 #REF!

Spl 1 Damproofing / Moisture Control L.S. 79,306.09 #REF!

Spl 2 Railings sq.m 73,340.64 #REF!

Spl.3 Occupational Safety & Health L.M 207,647.04 #REF!

Spl.4 Project Billboard LS - #REF! 0

TOTAL AMOUNT OF BID: #REF! #REF! 22.12% 24.63% 28.34% 24.91%

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-STOREY 2-CL RM SB AT BOLINGIT NHS,
SAN CARLOS CITY, PANGASINAN

Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

Cal. Days: 180CD

CASH FLOW

CALENDAR DAYS 1st QUARTER 2nd QUARTER 3rd QUARTER 4th QUARTER
% Accomp. 22.12% 24.63% 28.34% 24.91%
Commulative % Accomp. 22.12% 46.75% 75.09% 100.00%
Cash #REF! #REF! #REF! #REF!
Commulative Cash #REF! #REF! #REF! #REF!

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-STOREY 2-CL
RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN
Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

EQUIPMENT UTILIZATION SCHEDULE

DURATION
EQUIPMENT
1st QUARTER 2nd QUARTER 3rd QUARTER 4th QUARTER
Bar Cutter (manually operated) 2 2 2
Plate compactor 1 1
Concrete Mixer (1-Bagger) 1 1 1
Concrete Vibrator 1 1 1
Welding machine 2 2
Electric Drill 1 2
Riveter 2

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-STOREY 2-CL
RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN
Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

MANPOWER UTILIZATION SCHEDULE

DURATION
EQUIPMENT
1st QUARTER 2nd QUARTER 3rd QUARTER 4th QUARTER
Construction Foreman 1 1 1 1
Skilled Laborer 4 10 10 6
Unskilled Laborer 20 15 15 10
Part time Safety Practitioner 1 1 1 1

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Procuring Entity : DPWH Pangasinan 2nd Sub-District Enginering Office, Sta. Barbara, Pangasinan

Contract Reference No: 13AJ0006


Name of Contract: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL
RM SB AT LIBAS ES AND 2-STOREY 2-CL RM SB AT BOLINGIT NHS, SAN CARLOS CITY,
PANGASINAN

Location of the Contract: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

CONSTRUCTION METHOD

1.0 INTRODUCTION

CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM


SB AT LIBAS ES AND 2-STOREY 2-CL RM SB AT BOLINGIT NHS, SAN CARLOS CITY,
PANGASINAN
2.0 BRIEF DESCRIPTION OF CONTRACT WORKS

The work to be done in this project entails:

Item No.Description
803(a) Structure Excavation (common earth)
804 (a) Embankment (Backfilling)
804 (d-1) Gravel Fill (hand placed)
404 (a.1) Reinforcing Steel for Column Footing & FTB
900 (a.1) Reinforce Concrete Column Footing & FTB
404 (a.2) Reinforcing Steel for Column
900 (a.2) Reinforce Concrete for Column
404 (a.3) Reinforcing Steel for Beam
900 (a.3) Reinforce Concrete for Beam
404 (a.4) Reinforcing Steel for Slab on Fill
900 (a.4) Reinforce Concrete for Slab on Fill
404 (a.5) Reinforcing Steel for Suspended Slab
900 (a.5) Reinforce Concrete for Suspended Slab
404 (a.6) Reinforcing Steel for S.Vault, Stairs & Sunbreaker
900 (a.6) Reinforce Concrete for S. Vault, Stairs & Sunbreaker
506(1) Masonry Works (CHB)
1027 Cement Plaster Finish
1003 Carpentry & Joinery Works
403 (a) Steel Trusses
1013 Roofing Works
1009 Jalousie Windows
1010 Doors
1002 Plumbing Works
1032 a-1 Masonry Painting
1032 a-2 Wooden Painting
1100 Electrical Works
Spl 1 Damproofing / Moisture Control
Spl 2 Railings
Spl.3 Occupational Safety & Health
Spl.4 Project Billboard

3.0 CONSTRUCTION METHODS AND PROCEDURES

3.1 Methodology or General Approach

Mobilization upon receipt of Notice to Proceed. Installation of Project Billboard and other signages,
Excavation & Backfilling, Fabrication/Installation of RSB, Form works & Pouring of Concrete mix, Masonry &
Plastering works, Painting Works, Roofing works (trusses & roofing sheets),Carpentry & Joinery works, Doors
& Windows, Ceramic tiles, Painting works, Plumbing & Electrical works, Provision of Occupational safety &
Health & Demobilization.

3.2 Program of Work

Progress Bar Chart with S-Curve of Activities in the contract works (please see
attached S-Curve and Bar Chart)

3.3 Financial Program

Cash Flow Schedule, provision for the working capital schedule of receipts, etc.
(please see attached cash flow in the financial aspect)

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES
AND 2-STOREY 2-CL RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN
Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

DETAILED ESTIMATES
A PROPOSED FIVE-STOREY BUILDING OF PRINCETON INTEGRATED SCHOOL: "AN INNOVATIVE GREEN ENGINEERING
DESIGN"

Item 803(a) Structure Excavation (common earth)


QTY. = 2,280.48 cu.m.

B. LABOR
DESCIPRTION NO. DAYS RATE TOTAL
Unskilled Laborer 20 115.00 290.00 667,000.00

Sub-total 667,000.00

Total Direct Cost 667,000.00


Mark-up 3,804.36
Total Item Cost 670,804.36
Unit Cost 294.15

Item 804 (d-1) Gravel Fill (hand placed)


QTY. = 144.50 cu.m.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Gravel fill 145.00 cu.m. 300.00 43,500.00

Sub-total 43,500.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Unskilled Laborer 2 36.00 290.00 20,880.00

Sub-total 20,880.00
C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Plate compactor 1 18.00 600.00 10,800.00

Sub-total 10,800.00

Total Direct Cost 75,180.00


Mark-up 939.89
Total Item Cost 76,119.89
Unit Cost 526.78
Item 404 (a.1) Reinforcing Steel for Column Footing & FTB

QTY. = 52,964.57 kgs.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB 52,964.57 kgs. 52.00 2,754,157.64
Tie wire (#16 G.I.) 794.00 kgs. 55.00 43,670.00

Sub-total 2,797,827.64

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (steelman) 4 158.00 400.00 252,800.00
Unskilled Laborer 4 158.00 290.00 183,280.00

Sub-total 436,080.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 158.00 350.00 55,300.00

Sub-total 55,300.00

Total Direct Cost 3,289,207.64


Mark-up 20,950.54
Total Item Cost 3,310,158.18
Unit Cost 62.50

Item 900 (a.1) Reinforce Concrete Column Footing & FTB


QTY. = 535.34 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland cement, 40 kgs 4,819.00 bags 210.00 1,011,990.00
Washed sand 267.70 cu. m. 500.00 133,850.00
Crushed Gravel 536.00 cu. m. 600.00 321,600.00

Sub-total 1,467,440.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 11.00 530.00 5,830.00
Skilled Laborer (carpentry/mason) 2 11.00 400.00 8,800.00
Unskilled Laborer 5 11.00 290.00 15,950.00

Sub-total 30,580.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete mixer (1-bagger) 1 11.00 1,390.00 15,290.00
Minor tools 3,058.00

Sub-total 18,348.00

Total Direct Cost 1,516,368.00


Mark-up 14,498.24
Total Item Cost 1,530,866.24
Unit Cost 2,859.61
Item 404 (a.2) Reinforcing Steel for Column

QTY. = 51,148.25 kgs.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB 51,148.25 kgs. 52.00 2,659,709.00
Tie wire (#16 G.I.) 767.00 kgs. 55.00 42,185.00

Sub-total 2,701,894.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (steelman) 2 187.00 400.00 149,600.00
Unskilled Laborer 2 187.00 290.00 108,460.00

Sub-total 258,060.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 187.00 350.00 65,450.00

Sub-total 65,450.00

Total Direct Cost 3,025,404.00


Mark-up 69,298.49
Total Item Cost 3,094,702.49
Unit Cost 60.50

Item 900 (a.2) Reinforce Concrete for Column


QTY. = 570.24 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland cement, 40 kgs 5,133.00 bags 210.00 1,077,930.00
Washed sand 285.20 cu. m. 500.00 142,600.00
Crushed Gravel 571.00 cu. m. 600.00 342,600.00
Plywood, 1/4"x4'x8' 1,899.00 pcs. 300.00 569,700.00
Assorted CWN 855.00 kgs. 70.00 59,850.00
Coco Lumber 28,512.00 bd.ft 28.00 798,336.00

Sub-total 2,991,016.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 328.00 530.00 173,840.00
Skilled Laborer (carpenter/mason) 4 328.00 400.00 524,800.00
Unskilled Laborer 6 328.00 290.00 570,720.00

Sub-total 1,269,360.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete mixer (1-bagger) 1 328.00 1,390.00 455,920.00

Sub-total 455,920.00

Total Direct Cost 4,716,296.00


Mark-up 8,169.83
Total Item Cost 4,724,465.83
Unit Cost 8,285.05
Item 404 (a.3) Reinforcing Steel for Beam

QTY. = 189,416.67 kgs.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB 189,416.67 kgs. 52.00 9,849,666.84
Tie wire (#16 G.I.) 2,841.00 kgs. 55.00 156,255.00

Sub-total 10,005,921.84

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (steelman) 2 576.00 400.00 460,800.00
Unskilled Laborer 2 576.00 290.00 334,080.00

Sub-total 794,880.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 576.00 350.00 201,600.00

Sub-total 201,600.00

Total Direct Cost 11,002,401.84


Mark-up 44,236.03
Total Item Cost 11,046,637.87
Unit Cost 58.32

Item 900 (a.3) Reinforce Concrete for Beam


QTY. = 821.45 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland cement, 40 kgs 7,394.00 bags 210.00 1,552,740.00
Washed sand 410.80 cu. m. 500.00 205,400.00
Crushed Gravel 822.00 cu. m. 600.00 493,200.00
Plywood, 1/4"x4'x8' 2,736.00 pcs. 300.00 820,800.00
Assorted CWN 1,233.00 kgs. 70.00 86,310.00
Coco Lumber 41,073.00 bd.ft 28.00 1,150,044.00

Sub-total 4,308,494.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 229.00 530.00 121,370.00
Skilled Laborer (carpenter/mason) 4 229.00 400.00 366,400.00
Unskilled Laborer 8 229.00 290.00 531,280.00

Sub-total 1,019,050.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete mixer (1-bagger) 1 229.00 1,390.00 318,310.00

Sub-total 318,310.00

Total Direct Cost 5,645,854.00


Mark-up 11,672.47
Total Item Cost 5,657,526.47
Unit Cost 6,887.24
Item 404 (a.4) Reinforcing Steel for Slab on Fill

QTY. = 2,302.79 kgs.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB 2,302.79 kgs. 52.00 119,745.08
Tie wire (#16 G.I.) 35.00 kgs. 55.00 1,925.00

Sub-total 121,670.08

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (steelman) 2 9.00 400.00 7,200.00
Unskilled Laborer 2 9.00 290.00 5,220.00

Sub-total 12,420.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 9.00 350.00 3,150.00

Sub-total 3,150.00

Total Direct Cost 137,240.08


Mark-up 3,766.87
Total Item Cost 141,006.95
Unit Cost 61.23

Item 900 (a.4) Reinforce Concrete for Slab on Fill


QTY. = 144.50 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland cement, 40 kgs 1,301.00 bags 210.00 273,210.00
Washed sand 72.30 cu. m. 500.00 36,150.00
Crushed Gravel 145.00 cu. m. 600.00 87,000.00

Sub-total 396,360.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 6.00 530.00 3,180.00
Skilled Laborer (carpenter/mason) 4 6.00 400.00 9,600.00
Unskilled Laborer 8 6.00 290.00 13,920.00

Sub-total 26,700.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete mixer (1-bagger) 1 6.00 1,390.00 8,340.00

Sub-total 8,340.00

Total Direct Cost 431,400.00


Mark-up 3,181.71
Total Item Cost 434,581.71
Unit Cost 3,007.49
Item 404 (a.5) Reinforcing Steel for Suspended Slab

QTY. = 82,171.12 kgs.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB 82,171.12 kgs. 52.00 4,272,898.24
Tie wire (#16 G.I.) 1,233.00 kgs. 55.00 67,815.00

Sub-total 4,340,713.24

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (steelman) 2 300.00 400.00 240,000.00
Unskilled Laborer 2 300.00 290.00 174,000.00

Sub-total 414,000.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 300.00 350.00 105,000.00

Sub-total 105,000.00

Total Direct Cost 4,859,713.24


Mark-up 12,299.15
Total Item Cost 4,872,012.39
Unit Cost 59.29

Item 900 (a.5) Reinforce Concrete for Suspended Slab


QTY. = 803.65 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland cement, 40 kgs 7,233.00 bags 210.00 1,518,930.00
Washed sand 401.90 cu. m. 500.00 200,950.00
Crushed Gravel 804.00 cu. m. 600.00 482,400.00
Plywood, 1/4"x4'x8' 2,677.00 pcs. 300.00 803,100.00
Assorted CWN 1,206.00 kgs. 70.00 84,420.00
Coco Lumber 104,475.00 bd.ft 28.00 2,925,300.00

Sub-total 6,015,100.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 3.00 530.00 1,590.00
Skilled Laborer (carpenter/mason) 10 3.00 400.00 12,000.00
Unskilled Laborer 20 3.00 290.00 17,400.00

Sub-total 30,990.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete mixer (1-bagger) 1 3.00 1,390.00 4,170.00

Sub-total 4,170.00

Total Direct Cost 6,050,260.00


Mark-up 32,060.78
Total Item Cost 6,082,320.78
Unit Cost 7,568.37
Item 404 (a.6) Reinforcing Steel for S.Vault, Stairs & Sunbreaker

QTY. = 29,944.17 kgs.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB 29,944.17 kgs. 52.00 1,557,096.84
Tie wire (#16 G.I.) 449.00 kgs. 55.00 24,695.00

Sub-total 1,581,791.84

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (steelman) 2 137.00 400.00 109,600.00
Unskilled Laborer 2 137.00 290.00 79,460.00

Sub-total 189,060.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 137.00 350.00 47,950.00

Sub-total 47,950.00

Total Direct Cost 1,818,801.84


Mark-up 3,695.95
Total Item Cost 1,822,497.79
Unit Cost 60.86

Item 900 (a.6) Reinforce Concrete for S. Vault, Stairs & Sunbreaker
QTY. = 232.13 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland cement, 40 kgs 2,090.00 bags 210.00 438,900.00
Washed sand 116.10 cu. m. 500.00 58,050.00
Crushed Gravel 233.00 cu. m. 600.00 139,800.00
Plywood, 1/4"x4'x8' 20.00 pcs. 300.00 6,000.00
Assorted CWN 349.00 kgs. 70.00 24,430.00
Coco Lumber 9,285.00 bd.ft 28.00 259,980.00

Sub-total 927,160.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 2.00 530.00 1,060.00
Skilled Laborer (carpenter/mason) 2 2.00 400.00 1,600.00
Unskilled Laborer 8 2.00 290.00 4,640.00

Sub-total 7,300.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete mixer (1-bagger) 1 2.00 1,390.00 2,780.00

Sub-total 2,780.00

Total Direct Cost 937,240.00


Mark-up 7,900.16
Total Item Cost 945,140.16
Unit Cost 4,071.60
Item 506(1) Masonry Works (CHB)
QTY. = 8,218.97 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
CHB 6" x 8" x 16" 102,738.00 pcs 12.00 1,232,856.00
Portland Cement 8,367.00 bags 210.00 1,757,070.00
Washed Sand 694.00 cu.m 500.00 347,000.00
RSB 10mm dia. 22,103.00 kgs 52.00 1,149,356.00
#16 G.I. Tie Wire 332.00 kgs 55.00 18,260.00

Sub-total 4,504,542.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Mason) 6 322.00 400.00 772,800.00
Unskilled Laborer 6 322.00 290.00 560,280.00

Sub-total 1,333,080.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 5,837,622.00


Mark-up 30,750.40
Total Item Cost 5,868,372.40
Unit Cost 714.00

Item 1027 Cement Plaster Finish


QTY. = 16,392.34 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland Cement, 40 kgs 3,541.00 bags 210.00 743,610.00
Washed Sand 197.00 cu.m 500.00 98,500.00
Concrete mouldings 12.24 sq.m 400.00 4,896.00

Sub-total 847,006.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Mason) 6 247.00 400.00 592,800.00
Unskilled Laborer 6 247.00 290.00 429,780.00

Sub-total 1,022,580.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total

Total Direct Cost 1,869,586.00


Mark-up 12,107.60
Total Item Cost 1,881,693.60
Unit Cost 114.79
Item 1003 Carpentry & Joinery Works
QTY. = 11,127.60 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Marine Plywood 1/4" x 4' x 8' 4,055.00 pcs. 300.00 1,216,500.00
Ceiling joists (Nailers/Hangers) 50,075.00 bd. Ft. 75.00 3,755,625.00
Assorted CWN 1,169.00 kgs. 70.00 81,830.00
Ceiling ventillation w/ screen #REF! set 400.00 #REF!
Blackboard 12.00 set 3,000.00 36,000.00

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Carpenter) 3 185.00 400.00 222,000.00
Unskilled Laborer 3 185.00 290.00 160,950.00

Sub-total 382,950.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost #REF!


Mark-up 26,038.21
Total Item Cost #REF!
Unit Cost #REF!

Item 403 (a) Steel Trusses


QTY. = 8,175.59 kgs.
A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
LC 120 x 40 x 20 x 2.0mm x 6.00m Purlins 5,312.16 kgs 52.00 276,232.32
2" x 2"x 1/4" x 6.00m AB (T&B) 1,526.58 kgs 52.00 79,382.16
2" x 2"x 3/16" x 6.00m AB (WEB) 69.60 kgs 52.00 3,619.20
2 1/2" x 2 1/2"x 1/4" x 6.00m AB (CLEATS) 310.97 kgs 52.00 16,170.44
10mm dia sagrod w/ nuts & washers at each end 464.00 pcs 75.00 34,800.00
10mm dia A-307 anchor bolts 812.00 pcs 10.00 8,120.00
10mm dia x 200mm anchor bolts 108.00 pcs 28.00 3,024.00
12mm dia x 250mm long bent anchor studs 28.00 pcs 45.00 1,260.00
Gusset plates 200mm x 200mm x 6.00mm 112.00 pcs 200.00 22,400.00
Base plates 200mm x 200mm x 10.00mm 21.00 pcs 250.00 5,250.00
12mm dia cross bracing 16.00 kgs 52.00 832.00
Welding rod 110.00 pcs 120.00 13,200.00
Oxygen (content only) 25.00 kgs 50.00 1,250.00
Acetylene (content only) 25.00 kgs 60.00 1,500.00
Red lead primer 8.00 gal 450.00 3,600.00
Paint thinner 2.00 gal 220.00 440.00
Paint brush 6.00 pcs 80.00 480.00

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Welder) 4 15.00 400.00 24,000.00
Unskilled Laborer 4 15.00 290.00 17,400.00

Sub-total 41,400.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Welding machine 2 15.00 500.00 15,000.00
Minor tools (10% of Labor) 4,140.00

Sub-total 19,140.00

Total Direct Cost #REF!


Mark-up 40,296.15
Total Item Cost #REF!
Unit Cost #REF!
Item 1013 Roofing Works
QTY. = 1,653.00 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Corrugated Roofing, Gauge 26 1,653.00 sq.m 280.00 462,840.00
Pre-painted ready made Ridge Roll (0.40mm) #REF! L.m 200.00 #REF!
Pre-painted ready made Gutter (0.40mm) 3.33 L.m 200.00 665.00
Pre-painted ready made wall Flashing (0.40mm) 1,653.00 L.m 200.00 330,600.00
Blind Rivets #REF! boxes 250.00 #REF!
Tekscrew #REF! pcs. 2.00 #REF!
Silicone Selant #REF! pcs. 180.00 #REF!
25mm x 250mm x 12' Fiber Cement Fascia Board #REF! pcs. 650.00 #REF!
Misc. materials (Basket strainer, GI strap, etc.,) #REF! Lot 500.00 #REF!

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Tinsmithman) 4 17.00 400.00 27,200.00
Unskilled Laborer 4 17.00 290.00 19,720.00

Sub-total 46,920.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Electric Drill 2 17.00 100.00 3,400.00
Riveter 2 17.00 100.00 3,400.00

Sub-total 6,800.00

Total Direct Cost #REF!


Mark-up 14,671.49
Total Item Cost #REF!
Unit Cost #REF!

Item 1009 Jalousie Windows


QTY. = 836.23 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Jalousie Window w/ clear glass blades on std
aluminum casing and 50x150mm thk yakal jamb w/ 836.23 sq.m 1,550.00 1,296,156.50
complete accessories

Sub-total 1,296,156.50

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer 3 52.00 400.00 62,400.00
Unskilled Laborer 3 52.00 290.00 45,240.00

Sub-total 107,640.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 1,403,796.50


Mark-up 12,102.58
Total Item Cost 1,415,899.08
Unit Cost 1,693.19
Item 1010 Doors
QTY. = 426.72 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Tanguile Panel Door on 50x150mm thk yakal jamb w/
complete accessories 426.72 sq.m 3,750.00 1,600,200.00

Sub-total 1,600,200.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer 2 76.00 400.00 60,800.00
Unskilled Laborer 2 76.00 290.00 44,080.00

Sub-total 104,880.00

Total Direct Cost 1,705,080.00


Mark-up 5,194.27
Total Item Cost 1,710,274.27
Unit Cost 4,007.95

Item 1002 Plumbing Works


QTY. = All LS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
PVC pipe 3" dia. 2.00 pcs. 430.00 860.00
PVC pipe 3" dia. Elbow 1/4bend 67.00 pcs. 40.00 2,680.00
Solvent 10.00 qrt 190.00 1,900.00

Sub-total 5,440.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Plumber) 1 19.00 400.00 7,600.00
Unskilled Laborer 1 19.00 290.00 5,510.00

Sub-total 13,110.00

Total Direct Cost 18,550.00


Mark-up (18,550.00)
Total Item Cost -
Unit Cost -
Item 1032 a-1 Masonry Painting
QTY. = 32,784.68 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Paint Latex Gloss (Boysen) 656.00 gal 450.00 295,200.00
Paint Latex Semi-Gloss (Boysen) 656.00 gal 450.00 295,200.00
Concrete Neutralizer 110.00 gal 380.00 41,800.00
Misc. materials (patching compound, brush, sand paper ,tinting color, etc.,) 5,000.00 5,000.00

Sub-total 637,200.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Painter) 4 178.00 400.00 284,800.00
Unskilled Laborer 4 178.00 290.00 206,480.00

Sub-total 491,280.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 1,128,480.00


Mark-up 8,134.24
Total Item Cost 1,136,614.24
Unit Cost 34.67
Item 1032 a-2 Wooden Painting
QTY. = 14,779.88 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Flat Wall Enamel (Boysen) 296.00 gal 500.00 148,000.00
Quick Dry Enamel (Boysen) 296.00 gal 500.00 148,000.00
Glazing Putty 50.00 gal 400.00 20,000.00
Misc. materials (patching compound, brush, sand paper ,tinting color, etc.,) 5,000.00 5,000.00

Sub-total 321,000.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Painter) 4 99.00 400.00 158,400.00
Unskilled Laborer 4 99.00 290.00 114,840.00

Sub-total 273,240.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 594,240.00


Mark-up 3,841.87
Total Item Cost 598,081.87
Unit Cost 40.47

Item 1100 Electrical Works


QTY. = All LS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Ceiling fan Lighting Fixtures (40 watts) with box type
Flourescent 72.00 set 1,000.00 72,000.00
housing 21.00 set 600.00 12,600.00
Light Switch 1 way 2 gang 12.00 pcs. 142.00 1,704.00
Light Switch 1 way 1 gang 119.00 pcs. 142.00 16,898.00
Utility Box (Deep tape) 3.00 pcs. 30.00 90.00
PVC Coupling PNS 14, 15mm dia. 160.00 pcs. 3.00 480.00
PVC Pipe PNS 14,15mm dia. 1.00 pcs. 69.00 69.00
PVC Pipe PNS 14, 20mm dia. 2.00 pcs. 120.00 240.00
PVC Adapter PNS 14,15mm dia. - pcs. 8.00 -
Entrance cap # 15mm dia. 2.00 pcs, 62.00 124.00
Junction Box (Deep tape w/ Cover) 75.00 pcs. 31.00 2,325.00
Copper Wire #3.50mm2 TW 1.00 mtrs 24.00 24.00
Electrical Tape 8.00 pcs. 40.00 320.00
Enclosed Air circuit breaker, 220V, 2P, 20AT, 50 AF 17.00 set 1,350.00 22,950.00
Equipment for Fire alarm, Vibrating Bell, 10" dia. 5.00 set 1,300.00 6,500.00

Sub-total 138,944.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Electrician) 1 15.00 400.00 6,000.00
Unskilled Laborer 2 15.00 290.00 8,700.00

Sub-total 14,700.00

Total Direct Cost 153,644.00


Mark-up (153,644.00)
Total Item Cost -
Unit Cost -
Item Spl 1 Damproofing / Moisture Control
QTY. = 1,445.00 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Polythelene sheets 1,445.00 sq.m 50.00 72,250.00

Sub-total 72,250.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Unskilled Laborer 3 7.00 290.00 6,090.00

Sub-total 6,090.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 78,340.00


Mark-up 1,142.67
Total Item Cost 79,482.67
Unit Cost 55.01

Item Spl 2 Railings


QTY. = 884.64 L.M

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Steel railings, 19mm sq. bar welded to 50mmØ GI Pipe 26.60 sq.m 725.00 19,285.00
Steel railings, 50mmØ GI Pipe handrail w/ 25mm sq. 27.06 LM 250.00 6,765.00
Misc. materials (welding rod, paint, etc.,) 1.00 lot 500.00 500.00

Sub-total 26,550.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (welder) 2 21.00 400.00 16,800.00
Unskilled Laborer 2 21.00 290.00 12,180.00

Sub-total 28,980.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Welding machine 1 21.00 500.00 10,500.00
Minor tools (10% of Labor) 2,898.00

Sub-total 13,398.00

Total Direct Cost 68,928.00


Mark-up 4,765.85
Total Item Cost 73,693.85
Unit Cost 83.30
Item Spl.3 Occupational Safety & Health
QTY. = All LS

A. MATERIALS
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Safety Gears All LS 5,000.00 5,000.00
Signages, Barricades & Medicines All LS 2,000.00 2,000.00

Sub-total 7,000.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Part time Safety Practitioner 1.00 336.00 530.00 178,080.00

Sub-total 178,080.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Warning Signs 1 lot 2,000.00 2,000.00

Sub-total 2,000.00

Total Direct Cost 187,080.00


Mark-up (187,080.00)
Total Item Cost -
Unit Cost -

Item Spl.4 Project Billboard


QTY. = 1.00 each

A. MATERIALS
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Tarpaulin 32.00 sq.ft 30.00 960.00
Coco lumber 30.00 bd.ft 28.00 840.00
Assorted CWN 2.00 sq.ft 70.00 140.00

Sub-total 1,940.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer 1.00 1.00 400.00 400.00
Unskilled Laborer 1.00 1.00 290.00 290.00

Sub-total 690.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 2,630.00


Mark-up (2,630.00)
Total Item Cost -
Unit Cost -
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name : CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES
AND 2-STOREY 2-CL RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN
Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

SUMMARY OF TOTAL BID AMOUNT

Item No. Description Amount


803(a) Structure Excavation (common earth) 670,804.36
804 (d-1) Gravel Fill (hand placed) 76,119.89
404 (a.1) Reinforcing Steel for Column Footing & FTB 3,310,158.18
900 (a.1) Reinforce Concrete Column Footing & FTB 1,530,866.24
404 (a.2) Reinforcing Steel for Column 3,094,702.49
900 (a.2) Reinforce Concrete for Column 4,724,465.83
404 (a.3) Reinforcing Steel for Beam 11,046,637.87
900 (a.3) Reinforce Concrete for Beam 5,657,526.47
404 (a.4) Reinforcing Steel for Slab on Fill 141,006.95
900 (a.4) Reinforce Concrete for Slab on Fill 434,581.71
404 (a.5) Reinforcing Steel for Suspended Slab 4,872,012.39
900 (a.5) Reinforce Concrete for Suspended Slab 6,082,320.78
404 (a.6) Reinforcing Steel for S.Vault, Stairs & Sunbreaker 1,822,497.79
900 (a.6) Reinforce Concrete for S. Vault, Stairs & Sunbreaker 945,140.16
506(1) Masonry Works (CHB) 5,868,372.40
1027 Cement Plaster Finish 1,881,693.60
1003 Carpentry & Joinery Works #REF!
403 (a) Steel Trusses #REF!
1013 Roofing Works #REF!
1009 Jalousie Windows 1,415,899.08
1010 Doors 1,710,274.27
1002 Plumbing Works -
1032 a-1 Masonry Painting 1,136,614.24
1032 a-2 Wooden Painting 598,081.87
1100 Electrical Works -
Spl 1 Damproofing / Moisture Control 79,482.67
Spl 2 Railings 73,693.85
Spl.3 Occupational Safety & Health -
Spl.4 Project Billboard -

TOTAL AMOUNT OF BID : #REF!


TOTAL AMOUNT IN WORDS

TWO MILLION ONE HUNDRED SIXTY FIVE THOUSAND NINETY NINE & 40/100 pesos.

Submitted By:

BERSONS CONSTRUCTION & TRADING


Name of the Bidder

RUSSELL Q. BERNAL
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES
AND 2-STOREY 2-CL RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN
Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

DETAILED ESTIMATES
CONSTRUCTION OF 1-STOREY, 1 CL.RM. PRE-SCHOOL BUILDING WITH COMFORT RM. LIBAS ES, SAN CARLOS CITY,
PANGASINAN

Item 803(a) Structure Excavation (common earth)


QTY. = 14.87 cu.m.

B. LABOR
DESCIPRTION NO. DAYS RATE TOTAL
Unskilled Laborer 4 4.00 290.00 4,640.00

Sub-total 4,640.00

Total Direct Cost 4,640.00


Mark-up 1,164.80
Total Item Cost 5,804.80
Unit Cost 390.37

Item 804 (a) Embankment (Backfilling)


QTY. = 8.83 cu.m.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
River mix (plus 10% loose volume) 10.00 cu.m. 300.00 3,000.00

Sub-total 3,000.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Unskilled Laborer 2 1.00 290.00 580.00

Sub-total 580.00
C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 3,580.00


Mark-up 817.16
Total Item Cost 4,397.16
Unit Cost 497.98

Item 804 (b) Spreading, Tamping & Grading


QTY. = 17.60 cu.m.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL

Sub-total -

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Unskilled Laborer 2 0.50 290.00 290.00

Sub-total 290.00
C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 290.00


Mark-up 192.94
Total Item Cost 482.94
Unit Cost 27.44
Item 404 (a.1) Reinforcing Steel for Column Footing & WF

QTY. = 176.34 kgs.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB 176.34 kgs. 52.00 9,169.68
Tie wire (#16 G.I.) 3.00 kgs. 55.00 165.00

Sub-total 9,334.68

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (steelman) 2 1.00 400.00 800.00

Sub-total 800.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 0.25 350.00 87.50

Sub-total 87.50

Total Direct Cost 10,222.18


Mark-up 650.94
Total Item Cost 10,873.12
Unit Cost 61.66

Item 900 (a.1) Reinforce Concrete Column Footing & FTB


QTY. = 4.38 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland cement, 40 kgs 40.00 bags 210.00 8,400.00
Washed sand 2.20 cu. m. 500.00 1,100.00
Crushed Gravel 5.00 cu. m. 600.00 3,000.00

Sub-total 12,500.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 1.00 530.00 530.00
Skilled Laborer (carpentry/mason) 2 1.00 400.00 800.00
Unskilled Laborer 4 1.00 290.00 1,160.00

Sub-total 2,490.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete mixer (1-bagger) 1 1.00 1,390.00 1,390.00

Sub-total 1,390.00

Total Direct Cost 16,380.00


Mark-up 1,034.88
Total Item Cost 17,414.88
Unit Cost 3,976.00
Item 404 (a.2) Reinforcing Steel for Column

QTY. = 515.28 kgs.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB 515.28 kgs. 52.00 26,794.56
Tie wire (#16 G.I.) 8.00 kgs. 55.00 440.00

Sub-total 27,234.56

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (steelman) 1 2.00 400.00 800.00
Unskilled Laborer 2 2.00 290.00 1,160.00

Sub-total 1,960.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 1.00 350.00 350.00

Sub-total 350.00

Total Direct Cost 29,544.56


Mark-up 2,361.58
Total Item Cost 31,906.14
Unit Cost 61.92

Item 900 (a.2) Reinforce Concrete for Column


QTY. = 2.11 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland cement, 40 kgs 19.00 bags 210.00 3,990.00
Washed sand 1.10 cu. m. 500.00 550.00
Crushed Gravel 3.00 cu. m. 600.00 1,800.00
Plywood, 1/4"x4'x8' 7.00 pcs. 300.00 2,100.00
Assorted CWN 3.00 kgs. 70.00 210.00
Coco Lumber 106.00 bd.ft 28.00 2,968.00

Sub-total 11,618.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 2.00 530.00 1,060.00
Skilled Laborer (carpenter/mason) 2 2.00 400.00 1,600.00
Unskilled Laborer 4 2.00 290.00 2,320.00

Sub-total 4,980.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete mixer (1-bagger) 1 0.50 1,390.00 695.00

Sub-total 695.00

Total Direct Cost 17,293.00


Mark-up 5,452.74
Total Item Cost 22,745.74
Unit Cost 10,779.97
Item 404 (a.3) Reinforcing Steel for Beam

QTY. = 465.39 kgs.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB 465.39 kgs. 52.00 24,200.28
Tie wire (#16 G.I.) 7.00 kgs. 55.00 385.00

Sub-total 24,585.28

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (steelman) 1 2.00 400.00 800.00
Unskilled Laborer 2 2.00 290.00 1,160.00

Sub-total 1,960.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 0.50 350.00 175.00

Sub-total 175.00

Total Direct Cost 26,720.28


Mark-up 2,115.28
Total Item Cost 28,835.56
Unit Cost 61.96

Item 900 (a.3) Reinforce Concrete for Beam


QTY. = 2.38 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland cement, 40 kgs 22.00 bags 210.00 4,620.00
Washed sand 1.20 cu. m. 500.00 600.00
Crushed Gravel 3.00 cu. m. 600.00 1,800.00
Plywood, 1/4"x4'x8' 8.00 pcs. 300.00 2,400.00
Assorted CWN 4.00 kgs. 70.00 280.00
Coco Lumber 119.00 bd.ft 28.00 3,332.00

Sub-total 13,032.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 2.00 530.00 1,060.00
Skilled Laborer (carpenter/mason) 2 2.00 400.00 1,600.00
Unskilled Laborer 4 2.00 290.00 2,320.00

Sub-total 4,980.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete mixer (1-bagger) 1 0.50 1,390.00 695.00

Sub-total 695.00

Total Direct Cost 18,707.00


Mark-up 5,494.17
Total Item Cost 24,201.17
Unit Cost 10,168.56

Item 404e Reinforcing Steel for Slab on Fill

QTY. = 263.59 kgs.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB 263.59 kgs. 52.00 13,706.68
Tie wire (#16 G.I.) 4.00 kgs. 55.00 220.00

Sub-total 13,926.68

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (steelman) 2 1.00 400.00 800.00

Sub-total 800.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 14,726.68


Mark-up 1,610.63
Total Item Cost 16,337.31
Unit Cost 61.98
Item 900e Reinforce Concrete Slab on Fill
QTY. = 7.37 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland cement, 40 kgs 67.00 bags 210.00 14,070.00
Washed sand 3.70 cu. m. 500.00 1,850.00
Crushed Gravel 8.00 cu. m. 600.00 4,800.00

Sub-total 20,720.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 7.00 530.00 3,710.00
Skilled Laborer (carpenter/mason) 2 7.00 400.00 5,600.00
Unskilled Laborer 4 7.00 290.00 8,120.00

Sub-total 17,430.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete mixer (1-bagger) 1 4.00 1,390.00 5,560.00

Sub-total 5,560.00

Total Direct Cost 43,710.00


Mark-up 5,954.59
Total Item Cost 49,664.59
Unit Cost 6,738.75

Item 506(1) Masonry Works (CHB)


QTY. = 117.41 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
CHB 6" x 8" x 16" 1,468.00 pcs 12.00 17,616.00
Portland Cement 120.00 bags 210.00 25,200.00
Washed Sand 10.00 cu.m 500.00 5,000.00
RSB 10mm dia. 316.00 kgs 52.00 16,432.00
#16 G.I. Tie Wire 5.00 kgs 55.00 275.00

Sub-total 64,523.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Mason) 6 9.00 400.00 21,600.00
Unskilled Laborer 6 9.00 290.00 15,660.00

Sub-total 37,260.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 101,783.00


Mark-up 42,323.69
Total Item Cost 144,106.69
Unit Cost 1,227.38
Item 1027 Cement Plaster Finish
QTY. = 197.96 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland Cement, 40 kgs 43.00 bags 210.00 9,030.00
Washed Sand 3.00 cu.m 500.00 1,500.00
Concrete mouldings 12.24 sq.m 400.00 4,896.00

Sub-total 15,426.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Mason) 2 7.00 400.00 5,600.00
Unskilled Laborer 3 7.00 290.00 6,090.00

Sub-total 11,690.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total

Total Direct Cost 27,116.00


Mark-up 4,017.17
Total Item Cost 31,133.17
Unit Cost 157.27

Item 1003 Carpentry & Joinery Works


QTY. = 96.24 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Marine Plywood 1/4" x 4' x 8' 36.00 pcs. 300.00 10,800.00
Ceiling joists (Nailers/Hangers) 434.00 bd. Ft. 75.00 32,550.00
Assorted CWN 11.00 kgs. 70.00 770.00
Ceiling ventillation w/ screen 4.00 set 400.00 1,600.00

Sub-total 45,720.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Carpenter) 3 6.00 400.00 7,200.00
Unskilled Laborer 3 6.00 290.00 5,220.00

Sub-total 12,420.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 58,140.00


Mark-up 14,514.46
Total Item Cost 72,654.46
Unit Cost 754.93
Item 403 (a) Steel Trusses
QTY. = 1,104.36 kgs.
A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
LC 150 x 65 x 20 x 2.0mm x 6.00m Rafter 371.28 kgs 52.00 19,306.56
LC 1000 x 50 x 15 x 2.0mm x 6.00m Purlins 567.00 kgs 52.00 29,484.00
50 x 50 x 4.0mm x 6.00m AB 42.39 kgs 52.00 2,204.28
20 x 20 x 3.0mm x 6.00m AB 124.34 kgs 52.00 6,465.68
10mm dia x 0.85m sagrod w/ nuts & washers 42.00 pcs 75.00 3,150.00
10mm dia x 150mm anchor bolts 24.00 pcs 10.00 240.00
16mm dia x 300mm long bent anchor bolts 16.00 pcs 28.00 448.00
16mm dia x 50mm bolts 136.00 pcs 45.00 6,120.00
Welding rod 20.00 pcs 120.00 2,400.00
Oxygen (content only) 2.00 kgs 50.00 100.00
Acetylene (content only) 1.00 kgs 60.00 60.00
Red lead primer 1.00 gal 450.00 450.00
Paint thinner 1.00 gal 220.00 220.00
Paint brush 3.00 pcs 80.00 240.00

Sub-total 71,693.52

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Welder) 2 10.00 400.00 8,000.00
Unskilled Laborer 2 10.00 290.00 5,800.00

Sub-total 13,800.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Welding machine 1 10.00 500.00 5,000.00
Minor tools (10% of Labor) 1,380.00

Sub-total 6,380.00

Total Direct Cost 91,873.52


Mark-up 12,455.37
Total Item Cost 104,328.89
Unit Cost 94.47

Item 1013.00 Roofing Works


QTY. = 103.10 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Pre-painted Corrugated Sheets (0.40mm) 103.10 sq.m 420.00 43,302.00
Pre-painted ready made Ridge Roll (0.40mm) 8.40 L.m 200.00 1,680.00
Pre-painted ready made wall Flashing (0.40mm) 19.80 L.m 200.00 3,960.00
Blind Rivets 2.00 boxes 250.00 500.00
Tekscrew 450.00 pcs. 2.00 900.00
25mm x 250mm x 12' Fiber Cement Fascia Board 12.00 pcs. 650.00 7,800.00
Misc. materials (Basket strainer, GI strap, etc.,) #REF! Lot 500.00 #REF!
Downspout 3" dia. PVC Pipe (orange) 8.00 pcs. 430.00 3,440.00
PVC Elbow 3" dia. (orange) 8.00 pcs. 40.00 320.00

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Tinsmithman) 2 4.00 400.00 3,200.00
Unskilled Laborer 3 4.00 290.00 3,480.00

Sub-total 6,680.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Electric Drill 2 4.00 100.00 800.00
Riveter 2 4.00 100.00 800.00

Sub-total 1,600.00

Total Direct Cost #REF!


Mark-up 31,758.47
Total Item Cost #REF!
Unit Cost #REF!
Item 1010(2b) Jalousie Window
QTY. = 12.77 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL

Jalousie Window w/ clear glass Glass blades on


12.77 sq.m 900.00 11,493.00
JalouPlus Silver Colored w/ complete accessories

Sub-total 11,493.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer 1 2.00 400.00 800.00
Unskilled Laborer 2 2.00 290.00 1,160.00

Sub-total 1,960.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 13,453.00


Mark-up 2,699.90
Total Item Cost 16,152.90
Unit Cost 1,264.91

Item 1010(b) Doors


QTY. = 6.48 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Panel Type door w/ complete accessories
2.00 set 1,750.00 3,500.00
Sub-total 3,500.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer 1 2.00 400.00 800.00
Unskilled Laborer 2 2.00 290.00 1,160.00

Sub-total 1,960.00

Total Direct Cost 5,460.00


Mark-up 1,688.81
Total Item Cost 7,148.81
Unit Cost 1,103.21
Item 1010 (a) Door Frames & Accessories
QTY. = 3.00 SETS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
2" X 4" Window Jamb (Tanguile)Fabricated with
accessories 3.00 set 2,200.00 6,600.00

Sub-total 6,600.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer 2 2.00 400.00 1,600.00
Unskilled Laborer 2 2.00 290.00 1,160.00

Sub-total 2,760.00

Total Direct Cost 9,360.00


Mark-up 5,204.94
Total Item Cost 14,564.94
Unit Cost 4,854.98

Item 1002 Plumbing Works


QTY. = 30.00 L.M.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Water Closets 1.00 pc. 4,500.00 4,500.00
PVC pipe 4" dia. 3.00 pcs. 583.00 1,749.00
PVC pipe 4 x 2 wye 2.00 pc. 95.00 190.00
PVC pipe 4 x 4 wye 1.00 pc. 113.00 113.00
PVC pipe 4 x 2 Tee 1.00 pc. 100.00 100.00
PVC pipe 4" dia. Elbow 1/4 bend 2.00 pc. 71.00
PVC pipe 4" dia. Elbow 1/8 bend 2.00 pc. 54.00 108.00
PVC pipe 2" dia. P-Trap 2.00 pc. 73.00 146.00
PVC pipe 4" dia. Cleanout w/ plug 2.00 pcs. 55.00 110.00
Solvent 2.00 can 190.00 380.00
Floor drain 4" x 4" H.D. 1.00 pc. 200.00 200.00
G I pipe 1/2" dia 2.00 pcs. 365.00 730.00
G I coupling 1/2" dia. 4.00 pcs. 8.00 32.00
G I elbow 1/2" dia. 4.00 pcs. 10.00 40.00
G I tee 1/2" dia 2.00 pcs. 15.00 30.00
G I adapter 1/2" dia 2.00 pcs. 15.00 30.00
Faucet 1/2" dia 1.00 pcs. 120.00 120.00
Miscellaneous (Teflon & etc.,) All LS 1,500.00 1,500.00

Sub-total 10,078.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Plumber) 1 19.00 400.00 7,600.00
Unskilled Laborer 2 19.00 290.00 11,020.00

Sub-total 18,620.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 28,698.00


Mark-up 5,209.40
Total Item Cost 33,907.40
Unit Cost 1,130.25
Item 1018 Ceramic Tiles
QTY. = 8.66 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Ceramic Unglazed Tiles (20cm x 20cm) 8.66 sq.m 600.00 5,196.00
Portland Cement 5.00 bag 210.00 1,050.00
Tile adhesive 5.00 bag 240.00 1,200.00

Sub-total 7,446.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (mason) 1 6.00 400.00 2,400.00
Unkilled Laborer 2 6.00 290.00 3,480.00

Sub-total 5,880.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 13,326.00


Mark-up 2,987.53
Total Item Cost 16,313.53
Unit Cost 1,883.78

Item 1032a-1 Masonry Painting


QTY. = 200.00 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Paint Latex Gloss (Boysen) 11.00 gal 450.00 4,950.00
Paint Latex Semi-Gloss (Boysen) 11.00 gal 450.00 4,950.00
Concrete Neutralizer 2.00 gal 380.00 760.00
Misc. materials (patching compound, brush, sand paper ,tinting color, etc.,) 5,000.00 5,000.00

Sub-total 15,660.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Painter) 2 6.00 400.00 4,800.00
Unskilled Laborer 2 6.00 290.00 3,480.00

Sub-total 8,280.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 23,940.00


Mark-up 3,102.00
Total Item Cost 27,042.00
Unit Cost 135.21
Item 1032 a-2 Wooden Painting
QTY. = 222.40 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Flat Wall Enamel (Boysen) 5.00 gal 500.00 2,500.00
Quick Dry Enamel (Boysen) 5.00 gal 500.00 2,500.00
Misc. materials (patching compound, brush, sand paper ,tinting color, etc.,) 2,000.00 2,000.00

Sub-total 7,000.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Painter) 1 3.00 400.00 1,200.00
Unskilled Laborer 2 3.00 290.00 1,740.00

Sub-total 2,940.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 9,940.00


Mark-up 4,135.70
Total Item Cost 14,075.70
Unit Cost 63.29

Item 1100 Conduit Boxes & Fittings


QTY. = 66.00 L.M.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
PVC Pipe 15mm x 3.0 meters 20.00 pcs. 69.00 1,380.00
RCS Pipe 20mm x 3.0 mtrs. 2.00 kgs 516.00 1,032.00
Utility Box Deep Type 4.00 pcs 30.00 120.00
Junction Box Deep Type 6.00 pcs 30.00 180.00
Square Box Deep Type 2.00 pcs 37.00 74.00
Locknut and Bushing 20mm, 2.00 pcs 9.00 18.00
Service Entrance Cap 1.00 pcs 65.00 65.00

Sub-total 3,289.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Electrician) 1 2.00 400.00 800.00
Unskilled Laborer 1 2.00 290.00 580.00

Sub-total 1,380.00

Total Direct Cost 4,669.00


Mark-up 1,606.94
Total Item Cost 6,275.94
Unit Cost 95.09
Item 1101.00 Wires & Wiring Devices
QTY. = 250.00 L.M.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Electric Wire 3.5mm2 THW 3.00 mtrs. 24.00 72.00
Electric Wire 5.5mm2 THW 50.00 mtrs. 37.00 1,850.00
Duplex Convenience Outlet 4.00 pcs. 126.00 504.00
Three (3) Gang Tumbler Switch 2.00 pcs. 170.00 340.00
Electric Tape 2.00 pc. 40.00 80.00

Sub-total 2,846.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Electrician) 1 1.00 400.00 400.00
Unskilled Laborer 1 1.00 290.00 290.00

Sub-total 690.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 3,536.00


Mark-up 1,351.50
Total Item Cost 4,887.50
Unit Cost 19.55

Item 1102a Lighting Fixtures


QTY. = 5.00 SETS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
40 Watts CFL 10.00 sets 150.00 1,500.00
Ceiling Fan 2.00 sets 1,000.00 2,000.00

Sub-total 3,500.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Electrician) 1 0.50 400.00 200.00
Unskilled Laborer 1 0.50 290.00 145.00

Sub-total 345.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 3,845.00


Mark-up 1,116.70
Total Item Cost 4,961.70
Unit Cost 992.34
Item 1102 Panel Boards & Cabinets
QTY. = 1.00 set

A. MATERIALS
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Panel Board LP 40AT, 50AF, 220V ,3-20 AT, 50AF, 2P 1.00 set 1,500.00 1,500.00

Sub-total 1,500.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Electrician) 1.00 1.00 400.00 400.00

Sub-total 400.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total

Total Direct Cost 1,900.00


Mark-up 217.42
Total Item Cost 2,117.42
Unit Cost 2,117.42

Item SPL 1 Signages & Barricades


QTY. = 1.00 SETS

A. MATERIALS
DESCRIPTION QTY UNIT UNIT PRICE TOTAL

Sub-total

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Warning Signs 8 300.00 2,400.00

Sub-total 2,400.00

Total Direct Cost 2,400.00


Mark-up 785.51
Total Item Cost 3,185.51
Unit Cost 3,185.51
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name : CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES
AND 2-STOREY 2-CL RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN
Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

SUMMARY OF TOTAL BID AMOUNT

CONSTRUCTION OF 1-STOREY, 1 CL.RM. PRE-SCHOOL BUILDING WITH COMFORT RM. LIBAS ES, SAN CARLOS
CITY, PANGASINAN
Item No. Description Amount
803(a) Structure Excavation (common earth) 5,804.80
804 (a) Embankment (Backfilling) 4,397.16
804 (b) Spreading, Tamping & Grading 482.94
404 (a.1) Reinforcing Steel for Column Footing & WF 10,873.12
900 (a.1) Reinforce Concrete Column Footing & FTB 17,414.88
404 (a.2) Reinforcing Steel for Column 31,906.14
900 (a.2) Reinforce Concrete for Column 22,745.74
404 (a.3) Reinforcing Steel for Beam 28,835.56
900 (a.3) Reinforce Concrete for Beam 24,201.17
404e Reinforcing Steel for Slab on Fill 16,337.31
900e Reinforce Concrete Slab on Fill 49,664.59
506(1) Masonry Works (CHB) 144,106.69
1027 Cement Plaster Finish 31,133.17
1003 Carpentry & Joinery Works 72,654.46
403 (a) Steel Trusses 104,328.89
1013 Roofing Works #REF!
1010(2b) Jalousie Window 16,152.90
1010(b) Doors 7,148.81
1010 (a) Door Frames & Accessories 14,564.94
1012 Plumbing Works 33,907.40
1018 Ceramics Tiles 16,313.53
1032a-1 Masonry Painting 27,042.00
1032a-2 Wooden Painting 14,075.70
1100 Conduit Boxes & Fittings 6,275.94
1101 Wires & Wiring Devices 4,887.50
1102a Lighting Fixtures 4,961.70
1102 Panel Boards & Cabinets 2,117.42
SPL1 Signages & Barricades 3,185.51

TOTAL AMOUNT OF BID : #REF!


TOTAL AMOUNT IN WORDS

Eight Hundred Six Thousand Six Hundred Eighty Pesos and Forty Three Cents

Submitted By:

BERSONS CONSTRUCTION & TRADING


Name of the Bidder

RUSSELL Q. BERNAL
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-STOREY 2-CL RM

Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

DETAILED ESTIMATES
Construction of 1 Storey 2 CL.Rm. School Building,Olea NHS, Malasiqui, Pangasinan

Item 803(a) Structure Excavation (common earth)


QTY. = 23.47 cu.m.

B. LABOR
DESCIPRTION NO. DAYS RATE TOTAL
Unskilled Laborer 6 3.00 290.00 5,220.00

Sub-total 5,220.00

Total Direct Cost 5,220.00


Mark-up 3,937.99
Total Item Cost 9,157.99
Unit Cost 390.20

Item 804 (a) Embankment (Backfilling)


QTY. = 16.78 cu.m.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
River mix (plus 10% loose volume) 19.00 cu.m. 300.00 5,700.00

Sub-total 5,700.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Unskilled Laborer 2 2.00 290.00 1,160.00

Sub-total 1,160.00
C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 6,860.00


Mark-up 1,095.90
Total Item Cost 7,955.90
Unit Cost 474.13

Item 804 (b) Spreading, Tamping & Grading


QTY. = 32.69 cu.m.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL

Sub-total -

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Unskilled Laborer 3 0.80 290.00 696.00

Sub-total 696.00
C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 696.00


Mark-up 201.01
Total Item Cost 897.01
Unit Cost 27.44
Item 404 (a.1) Reinforcing Steel for Column Footing & WF

QTY. = 352.36 kgs.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB 352.36 kgs. 52.00 18,322.72
Tie wire (#16 G.I.) 5.00 kgs. 55.00 275.00

Sub-total 18,597.72

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (steelman) 2 2.00 400.00 1,600.00

Sub-total 1,600.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 0.50 350.00 175.00

Sub-total 175.00

Total Direct Cost 20,372.72


Mark-up 1,378.46
Total Item Cost 21,751.18
Unit Cost 61.73

Item 900 (a.1) Reinforce Concrete Column Footing & FTB


QTY. = 9.49 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland cement, 40 kgs 86.00 bags 210.00 18,060.00
Washed sand 4.80 cu. m. 500.00 2,400.00
Crushed Gravel 10.00 cu. m. 600.00 6,000.00

Sub-total 26,460.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 11.00 530.00 5,830.00
Skilled Laborer (carpentry/mason) 2 11.00 400.00 8,800.00
Unskilled Laborer 4 11.00 290.00 12,760.00

Sub-total 27,390.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete mixer (1-bagger) 1 11.00 1,390.00 15,290.00

Sub-total 15,290.00

Total Direct Cost 69,140.00


Mark-up 7,458.20
Total Item Cost 76,598.20
Unit Cost 8,071.46
Item 404 (a.2) Reinforcing Steel for Column

QTY. = 762.05 kgs.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB 762.05 kgs. 52.00 39,626.60
Tie wire (#16 G.I.) 11.00 kgs. 55.00 605.00

Sub-total 40,231.60

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (steelman) 2 3.00 400.00 2,400.00
Unskilled Laborer 2 3.00 290.00 1,740.00

Sub-total 4,140.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 1.00 350.00 350.00

Sub-total 350.00

Total Direct Cost 44,721.60


Mark-up 2,456.92
Total Item Cost 47,178.52
Unit Cost 61.91

Item 900 (a.2) Reinforce Concrete for Column


QTY. = 3.40 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland cement, 40 kgs 31.00 bags 210.00 6,510.00
Washed sand 1.70 cu. m. 500.00 850.00
Crushed Gravel 4.00 cu. m. 600.00 2,400.00
Plywood, 1/4"x4'x8' 11.00 pcs. 300.00 3,300.00
Assorted CWN 5.00 kgs. 70.00 350.00
Coco Lumber 170.00 bd.ft 28.00 4,760.00

Sub-total 18,170.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 4.00 530.00 2,120.00
Skilled Laborer (carpenter/mason) 2 4.00 400.00 3,200.00
Unskilled Laborer 4 4.00 290.00 4,640.00

Sub-total 9,960.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete mixer (1-bagger) 1 2.00 1,390.00 2,780.00

Sub-total 2,780.00

Total Direct Cost 30,910.00


Mark-up 6,795.52
Total Item Cost 37,705.52
Unit Cost 11,089.86
Item 404 (a.3) Reinforcing Steel for Beam

QTY. = 544.91 kgs.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB 544.91 kgs. 52.00 28,335.32
Tie wire (#16 G.I.) 8.00 kgs. 55.00 440.00

Sub-total 28,775.32

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (steelman) 1 3.00 400.00 1,200.00
Unskilled Laborer 2 3.00 290.00 1,740.00

Sub-total 2,940.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 1.00 350.00 350.00

Sub-total 350.00

Total Direct Cost 32,065.32


Mark-up 1,670.06
Total Item Cost 33,735.38
Unit Cost 61.91

Item 900 (a.3) Reinforce Concrete for Beam


QTY. = 4.28 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland cement, 40 kgs 39.00 bags 210.00 8,190.00
Washed sand 2.20 cu. m. 500.00 1,100.00
Crushed Gravel 5.00 cu. m. 600.00 3,000.00
Plywood, 1/4"x4'x8' 15.00 pcs. 300.00 4,500.00
Assorted CWN 7.00 kgs. 70.00 490.00
Coco Lumber 214.00 bd.ft 28.00 5,992.00

Sub-total 23,272.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 4.00 530.00 2,120.00
Skilled Laborer (carpenter/mason) 2 4.00 400.00 3,200.00
Unskilled Laborer 4 4.00 290.00 4,640.00

Sub-total 9,960.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete mixer (1-bagger) 1 4.00 1,390.00 5,560.00

Sub-total 5,560.00

Total Direct Cost 38,792.00


Mark-up 5,730.96
Total Item Cost 44,522.96
Unit Cost 10,402.56

Item 404 (a.4) Reinforcing Steel for Slab on Fill

QTY. = 459.41 kgs.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB 459.41 kgs. 52.00 23,889.32
Tie wire (#16 G.I.) 7.00 kgs. 55.00 385.00

Sub-total 24,274.32

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (steelman) 2 9.00 400.00 7,200.00
Unskilled Laborer 2 9.00 290.00 5,220.00

Sub-total 12,420.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 9.00 350.00 3,150.00

Sub-total 3,150.00

Total Direct Cost 39,844.32


Mark-up 3,209.56
Total Item Cost 43,053.88
Unit Cost 93.72
Item 900e Reinforce Concrete Slab on Fill
QTY. = 12.60 cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland cement, 40 kgs 114.00 bags 210.00 23,940.00
Washed sand 6.30 cu. m. 500.00 3,150.00
Crushed Gravel 13.00 cu. m. 600.00 7,800.00

Sub-total 34,890.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 10.00 530.00 5,300.00
Skilled Laborer (carpenter/mason) 2 10.00 400.00 8,000.00
Unskilled Laborer 4 10.00 290.00 11,600.00

Sub-total 24,900.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete mixer (1-bagger) 1 10.00 1,390.00 13,900.00

Sub-total 13,900.00

Total Direct Cost 73,690.00


Mark-up 11,991.26
Total Item Cost 85,681.26
Unit Cost 6,800.10

Item 506(1) Masonry Works (CHB)


QTY. = 147.08 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
CHB 6" x 8" x 16" 1,839.00 pcs 12.00 22,068.00
Portland Cement 150.00 bags 210.00 31,500.00
Washed Sand 13.00 cu.m 500.00 6,500.00
RSB 10mm dia. 396.00 kgs 52.00 20,592.00
#16 G.I. Tie Wire 6.00 kgs 55.00 330.00

Sub-total 80,990.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Mason) 6 10.00 400.00 24,000.00
Unskilled Laborer 6 10.00 290.00 17,400.00

Sub-total 41,400.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 122,390.00


Mark-up 43,657.44
Total Item Cost 166,047.44
Unit Cost 1,128.96
Item 1027 Cement Plaster Finish
QTY. = 335.24 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland Cement, 40 kgs 73.00 bags 210.00 15,330.00
Washed Sand 5.00 cu.m 500.00 2,500.00
Concrete mouldings 12.24 sq.m 400.00 4,896.00

Sub-total 22,726.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Mason) 6 5.00 400.00 12,000.00
Unskilled Laborer 6 5.00 290.00 8,700.00

Sub-total 20,700.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total

Total Direct Cost 43,426.00


Mark-up 5,586.09
Total Item Cost 49,012.09
Unit Cost 146.20

Item 1003 Carpentry & Joinery Works


QTY. = 175.40 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Marine Plywood 1/4" x 4' x 8' 64.00 pcs. 300.00 19,200.00
Ceiling joists (Nailers/Hangers) 790.00 bd. Ft. 75.00 59,250.00
Assorted CWN 19.00 kgs. 70.00 1,330.00
Ceiling ventillation w/ screen 4.00 set 400.00 1,600.00

Sub-total 81,380.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Carpenter) 3 5.00 400.00 6,000.00
Unskilled Laborer 3 5.00 290.00 4,350.00

Sub-total 10,350.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 91,730.00


Mark-up 34,975.45
Total Item Cost 126,705.45
Unit Cost 722.38
Item 403 (a) Steel Trusses
QTY. = 1,958.40 kgs.
A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
LC 150 x 65 x 20 x 2.0mm x 6.00m Rafter 628.32 kgs 52.00 32,672.64
LC 1000 x 50 x 15 x 2.0mm x 6.00m Purlins 997.92 kgs 52.00 51,891.84
50 x 50 x 4.0mm x 6.00m AB 84.78 kgs 52.00 4,408.56
20 x 20 x 3.0mm x 6.00m AB 248.68 kgs 52.00 12,931.36
10mm dia x 0.85m sagrod w/ nuts & washers 42.00 pcs 75.00 3,150.00
10mm dia x 150mm anchor bolts 24.00 pcs 10.00 240.00
16mm dia x 300mm long bent anchor bolts 24.00 pcs 28.00 672.00
16mm dia x 50mm bolts 272.00 pcs 45.00 12,240.00
Welding rod 20.00 pcs 120.00 2,400.00
Oxygen (content only) 1.00 kgs 50.00 50.00
Acetylene (content only) 1.00 kgs 60.00 60.00
Red lead primer 3.00 gal 450.00 1,350.00
Paint thinner 2.00 gal 220.00 440.00
Paint brush 3.00 pcs 80.00 240.00

Sub-total 123,551.40

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Welder) 2 13.00 400.00 10,400.00
Unskilled Laborer 2 13.00 290.00 7,540.00

Sub-total 17,940.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Welding machine 1 13.00 500.00 6,500.00
Minor tools (10% of Labor) 1,794.00

Sub-total 8,294.00

Total Direct Cost 149,785.40


Mark-up 27,900.23
Total Item Cost 177,685.63
Unit Cost 90.73

Item 1013.00 Roofing Works


QTY. = 193.94 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Pre-painted Corrugated Sheets (0.40mm) 193.94 sq.m 420.00 81,454.80
Pre-painted ready made Ridge Roll (0.40mm) 19.80 L.m 200.00 3,960.00
Pre-painted ready made wall Flashing (0.40mm) 22.00 L.m 200.00 4,400.00
Blind Rivets 2.00 boxes 250.00 500.00
Tekscrew 700.00 pcs. 2.00 1,400.00
25mm x 250mm x 12' Fiber Cement Fascia Board 24.00 pcs. 650.00 15,600.00
Misc. materials (Basket strainer, GI strap, etc.,) #REF! Lot 500.00 #REF!

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Tinsmithman) 2 4.00 400.00 3,200.00
Unskilled Laborer 3 4.00 290.00 3,480.00

Sub-total 6,680.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Electric Drill 2 4.00 100.00 800.00
Riveter 2 4.00 100.00 800.00

Sub-total 1,600.00

Total Direct Cost #REF!


Mark-up 47,573.11
Total Item Cost #REF!
Unit Cost #REF!
Item 1010(2b) Jalousie Window
QTY. = 26.60 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL

Jalousie Window w/ clear glass Glass blades on


26.60 sq.m 900.00 23,940.00
JalouPlus Silver Colored w/ complete accessories

Sub-total 23,940.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer 2 3.00 400.00 2,400.00
Unskilled Laborer 2 3.00 290.00 1,740.00

Sub-total 4,140.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 28,080.00


Mark-up 3,799.04
Total Item Cost 31,879.04
Unit Cost 1,198.46

Item 1010(b) Doors


QTY. = 8.76 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Panel Type Doors w/ complete accessories
4.00 set 1,750.00 7,000.00
Sub-total 7,000.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer 1 3.00 400.00 1,200.00
Unskilled Laborer 2 3.00 290.00 1,740.00

Sub-total 2,940.00

Total Direct Cost 9,940.00


Mark-up 4,357.63
Total Item Cost 14,297.63
Unit Cost 1,632.15
Item 1010 (a) Door Frames & Accessories
QTY. = 12.00 SETS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
2" X 4" Window Jamb (Tanguile)Fabricated with
accessories 12.00 set 2,200.00 26,400.00

Sub-total 26,400.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer 1 1.00 400.00 400.00
Unskilled Laborer 1 1.00 290.00 290.00

Sub-total 690.00

Total Direct Cost 27,090.00


Mark-up 2,127.72
Total Item Cost 29,217.72
Unit Cost 2,434.81

Item 1032a-1 Masonry Painting


QTY. = 600.00 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Paint Latex Gloss (Boysen) 13.00 gal 450.00 5,850.00
Paint Latex Semi-Gloss (Boysen) 13.00 gal 450.00 5,850.00
Concrete Neutralizer 1.00 gal 380.00 380.00
Misc. materials (patching compound, brush, sand paper ,tinting color, etc.,) 5,000.00 5,000.00

Sub-total 17,080.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Painter) 2 6.00 400.00 4,800.00
Unskilled Laborer 2 6.00 290.00 3,480.00

Sub-total 8,280.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 25,360.00


Mark-up 8,570.00
Total Item Cost 33,930.00
Unit Cost 56.55
Item 1032 a-2 Wooden Painting
QTY. = 415.84 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Flat Wall Enamel (Boysen) 10.00 gal 500.00 5,000.00
Quick Dry Enamel (Boysen) 10.00 gal 500.00 5,000.00
Misc. materials (patching compound, brush, sand paper ,tinting color, etc.,) 5,000.00 5,000.00

Sub-total 15,000.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Painter) 2 5.00 400.00 4,000.00
Unskilled Laborer 2 5.00 290.00 2,900.00

Sub-total 6,900.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 21,900.00


Mark-up 4,252.18
Total Item Cost 26,152.18
Unit Cost 62.89

Item 1100 Conduit Boxes & Fittings


QTY. = 132.00 L.M.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
PVC Pipe 15mm x 3.0 meters 40.00 pcs. 69.00 2,760.00
RCS Pipe 20mm x 3.0 mtrs. 3.00 kgs 516.00 1,548.00
Utility Box Deep Type 8.00 pcs 30.00 240.00
Junction Box Deep Type 12.00 pcs 30.00 360.00
Square Box Deep Type 4.00 pcs 37.00 148.00
Locknut and Bushing 20mm, 4.00 pcs 9.00 36.00
Service Entrance Cap 1.00 pcs 65.00 65.00
Misc. etc. All L.S. 1,500.00 1,500.00

Sub-total 7,497.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Electrician) 1 4.00 400.00 1,600.00
Unskilled Laborer 1 4.00 290.00 1,160.00

Sub-total 2,760.00

Total Direct Cost 10,257.00


Mark-up 2,558.88
Total Item Cost 12,815.88
Unit Cost 97.09
Item 1101.00 Wires & Wiring Devices
QTY. = 500.00 L.M.

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Electric Wire 3.5mm2 THW 3.00 mtrs. 24.00 72.00
Electric Wire 5.5mm2 THW 50.00 mtrs. 37.00 1,850.00
Duplex Convenience Outlet 4.00 pcs. 126.00 504.00
Three (3) Gang Tumbler Switch 2.00 pcs. 170.00 340.00
Electric Tape 2.00 pc. 40.00 80.00
Miscellanous etc. All L.S. 1,500.00 1,500.00

Sub-total 4,346.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Electrician) 1 2.00 400.00 800.00
Unskilled Laborer 2 2.00 290.00 1,160.00

Sub-total 1,960.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 6,306.00


Mark-up 1,149.00
Total Item Cost 7,455.00
Unit Cost 14.91

Item 1102a Lighting Fixtures


QTY. = 12.00 SETS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
40 Watts CFL 10.00 sets 150.00 1,500.00
Ceiling Fan 2.00 sets 1,000.00 2,000.00

Sub-total 3,500.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Electrician) 1 1.00 400.00 400.00
Unskilled Laborer 1 1.00 290.00 290.00

Sub-total 690.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost 4,190.00


Mark-up 1,087.72
Total Item Cost 5,277.72
Unit Cost 439.81
Item 1102 Panel Boards & Cabinets
QTY. = 1.00 set

A. MATERIALS
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Panel Board LP 40AT, 50AF, 220V ,3-20 AT, 50AF, 2P 1.00 set 1,500.00 1,500.00

Sub-total 1,500.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Skilled Laborer (Electrician) 1.00 1.00 400.00 400.00

Sub-total 400.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total

Total Direct Cost 1,900.00


Mark-up 217.42
Total Item Cost 2,117.42
Unit Cost 2,117.42

Item SPL 1 Signages & Barricades


QTY. = 1.00 SETS

A. MATERIALS
DESCRIPTION QTY UNIT UNIT PRICE TOTAL

Sub-total

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Warning Signs 8 300.00 2,400.00

Sub-total 2,400.00

Total Direct Cost 2,400.00


Mark-up 787.70
Total Item Cost 3,187.70
Unit Cost 3,187.70
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name : CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES
AND 2-STOREY 2-CL RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN
Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

SUMMARY OF TOTAL BID AMOUNT

Item No. Description Amount


803(a) Structure Excavation (common earth) 9,157.99
804 (a) Embankment (Backfilling) 7,955.90
804 (b) Spreading, Tamping & Grading 897.01
404 (a.1) Reinforcing Steel for Column Footing & WF 21,751.18
900 (a.1) Reinforce Concrete Column Footing & FTB 76,598.20
404 (a.2) Reinforcing Steel for Column 47,178.52
900 (a.2) Reinforce Concrete for Column 37,705.52
404 (a.3) Reinforcing Steel for Beam 33,735.38
900 (a.3) Reinforce Concrete for Beam 44,522.96
404 (a.4) Reinforcing Steel for Slab on Fill 43,053.88
900e Reinforce Concrete Slab on Fill 85,681.26
506(1) Masonry Works (CHB) 166,047.44
1027 Cement Plaster Finish 49,012.09
1003 Carpentry & Joinery Works 126,705.45
403 (a) Steel Trusses 177,685.63
1013 Roofing Works #REF!
1010(2b) Jalousie Window 31,879.04
1010(b) Doors 14,297.63
1010 (a) Door Frames & Accessories 29,217.72
1032a-1 Masonry Painting 33,930.00
1032a-2 Wooden Painting 26,152.18
1100 Conduit Boxes & Fittings 12,815.88
1101 Wires & Wiring Devices 7,455.00
1102a Lighting Fixtures 5,277.72
1102 Panel Boards & Cabinets 2,117.42
SPL 1 Signages & Barricades 3,187.70

TOTAL AMOUNT OF BID : #REF!


TOTAL AMOUNT IN WORDS

One Million Two Hundred Five Thousand Forty Six Pesos and Sixty Cents

Submitted By:

BERSONS CONSTRUCTION & TRADING


Name of the Bidder

RUSSELL Q. BERNAL
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 13AJ0006
Contract Name: CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-STOREY 2-CL RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN
Contract Location: MALASIQUI AND SAN CARLOS CITY, PANGASINAN

Cal. Days: 180CD

BAR CHART/S-CURVE

Item No. Description Unit BOLINGIT LIBAS OLEA Amount %


803(a) Structure Excavation (common earth) cu.m. - 115.00 5,828.67 4.00 9,195.58 3.00 15,024.25 122.00 0.74%

804 (a) Embankment (Backfilling) cu.m. - 4,415.22 1.00 7,988.64 2.00 12,403.87 3.00 0.61%

804 (b) Spreading, Tamping & Grading cu.m. 484.91 0.50 900.75 0.80 1,385.66 2.00 0.07%

804 (d-1) Gravel Fill (hand placed) cu.m. - 36.00 - 36.00 0.00%

404 (a.1) Reinforcing Steel for Column Footing & FTB kgs - 158.00 10,917.39 1.00 21,839.84 2.00 32,757.23 161.00 1.62%

900 (a.1) Reinforce Concrete Column Footing & FTB cu.m. - 11.00 17,486.59 1.00 37,953.81 11.00 55,440.40 23.00 2.74%

404 (a.2) Reinforcing Steel for Column kgs - 187.00 32,035.14 2.00 47,373.30 3.00 79,408.44 192.00 3.93%

900 (a.2) Reinforce Concrete for Column cu.m. - 328.00 22,839.39 2.00 37,860.76 4.00 60,700.14 334.00 3.00%

404 (a.3) Reinforcing Steel for Beam kgs - 576.00 28,954.98 2.00 33,876.03 3.00 62,831.01 581.00 3.11%

900 (a.3) Reinforce Concrete for Beam cu.m. - 229.00 24,300.80 2.00 44,706.27 4.00 69,007.07 235.00 3.42%

404 (a.4) Reinforcing Steel for Slab on Fill kgs - 9.00 2,127.44 1.00 2,127.44 10.00 0.11%

900 (a.4) Reinforce Concrete for Slab on Fill cu.m. - 6.00 49,869.07 7.00 86,033.99 9.00 135,903.06 22.00 6.73%

404 (a.5) Reinforcing Steel for Suspended Slab kgs - 300.00 - 300.00 0.00%

900 (a.5) Reinforce Concrete for Suspended Slab cu.m. - 3.00 - 3.00 0.00%

404 (a.6) Reinforcing Steel for S.Vault, Stairs & Sunbreaker kgs - 137.00 - 137.00 0.00%

900 (a.6) Reinforce Concrete for S. Vault, Stairs & Sunbreaker cu.m. - 2.00 - 2.00 0.00%

506(1) Masonry Works (CHB) sq.m - 322.00 158,976.57 9.00 196,067.61 10.00 355,044.19 341.00 17.58%

1027 Cement Plaster Finish sq.m - 247.00 31,261.19 7.00 49,213.69 5.00 80,474.88 259.00 3.98%

1003 Carpentry & Joinery Works sq.m - 185.00 72,953.87 6.00 127,227.45 5.00 200,181.32 196.00 9.91%

403 (a) Steel Trusses kgs - 15.00 104,760.01 10.00 178,412.34 13.00 283,172.35 38.00 14.02%

1013 Roofing Works sq.m - 17.00 107,280.20 4.00 164,340.77 4.00 271,620.96 25.00 13.45%

1009 Jalousie Windows sq.m - 52.00 16,219.34 2.00 32,010.21 3.00 48,229.55 57.00 2.39%

1010 Doors sq.m - 76.00 21,803.14 4.00 43,694.45 4.00 65,497.60 84.00 3.24%

1002 Plumbing Works L.S. - 19.00 18,302.54 19.00 18,302.54 38.00 0.91%

1018 Ceramic tiles sq.m 16,380.73 6.00 16,380.73 6.00 0.81%

1032 a-1 Masonry Painting sq.m - 178.00 27,153.13 6.00 34,067.24 6.00 61,220.37 190.00 3.03%

1032 a-2 Wooden Painting sq.m - 99.00 14,134.76 3.00 26,259.52 5.00 40,394.28 107.00 2.00%

1100 Electrical Works sq.m - 15.00 18,316.23 4.50 27,779.02 8.00 46,095.25 28.00 2.28%

Spl 1 Damproofing / Moisture Control L.S. - 7.00 - 7.00 0.00%

Spl 2 Railings sq.m - 21.00 - 21.00 0.00%

Spl.3 Occupational Safety & Health L.M - 3,198.72 3,198.72 6,397.44 - 0.32%

Spl.4 Project Billboard LS - 1.00 - 1.00 0.00%

TOTAL AMOUNT OF BID: - 810,000.00 1,210,000.00 2,020,000.00 3,561.00 100.00%

Submitted By:

BERSONS CONSTRUCTION & TRADING


Name of the Bidder

RUSSELL Q. BERNAL
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
PUBLIC WORKS & HIGHWAYS (DPWH)
NAME OF PROJECT : CONSTRUCTION OF 1-STOREY 2-CL RM SB AT OLEA NHS, MALASIQUI, 1-STOREY 1-CL RM SB AT LIBAS ES AND 2-STOREY 2-CL RM SB AT BOLINGIT NHS, SAN CARLOS CITY, PANGASINAN (CLUSTER
ABC : 2,020,000.00
CONTRACT TIME : 180 CD

804(d-1)
804(b) 3 CD 404(a-5)
804(a) 2 CD SPL 1 404(a-4) 900(a-4) 3 CD
3 CD 1 CD 2 CD 9 CD 900(a-
803(a) 404(a-1) 404(a-2) 900(a-2) 404(a-3) 900(a-3) 3 CD
MOVE IN
11 CD 9 CD 900(a-1) 19 CD 12 CD 14 CD 12 CD
3 CD 506(1) 404(a-6)
27 CD 4 CD
900(a-6)
2 CD

BAR CHART & S-CURVE

Item No. Description Unit Amount % MARCH 25 -APRIL 30, 2013 MAY 1-31, 2013 JUNE 1-

803(a) Structure Excavation (common earth) cu.m. 15,024.25 0.74%


0.74%
804 (a) Embankment (Backfilling) cu.m. 12,403.87 0.61% 0.61%

804 (b) Spreading, Tamping & Grading cu.m. 1,385.66 0.07% 0.07%

804 (d-1) Gravel Fill (hand placed) cu.m. 0.00 0.00% 0.00%

404 (a.1) Reinforcing Steel for Column Footing & FTB kgs 32,757.23 1.62% 1.62%

900 (a.1) Reinforce Concrete Column Footing & FTB cu.m. 55,440.40 2.74% 2.74%

404 (a.2) Reinforcing Steel for Column kgs 79,408.44 3.93% 2.90% 1.03%

900 (a.2) Reinforce Concrete for Column cu.m. 60,700.14 3.00% 3.00%

404 (a.3) Reinforcing Steel for Beam kgs 62,831.01 3.11% 3.11%

900 (a.3) Reinforce Concrete for Beam cu.m. 69,007.07 3.42% 3.42%

404 (a.4) Reinforcing Steel for Slab on Fill kgs 2,127.44 0.11% 0.11%

900 (a.4) Reinforce Concrete for Slab on Fill cu.m. 135,903.06 6.73% 5.23% 1.50%

404 (a.5) Reinforcing Steel for Suspended Slab kgs 0.00 0.00% 0.00%

900 (a.5) Reinforce Concrete for Suspended Slab cu.m. 0.00 0.00%

404 (a.6) Reinforcing Steel for S.Vault, Stairs & Sunbreaker kgs 0.00 0.00% 0.00%

900 (a.6) Reinforce Concrete for S. Vault, Stairs & Sunbreaker cu.m. 0.00 0.00% 0.00%

506(1) Masonry Works (CHB) sq.m 355,044.19 17.58% 9.11% 8.46%

1027 Cement Plaster Finish sq.m 80,474.88 3.98%

1003 Carpentry & Joinery Works sq.m 200,181.32 9.91%

403 (a) Steel Trusses kgs 283,172.35 14.02%

1013 Roofing Works sq.m 271,620.96 13.45%

1009 Jalousie Windows sq.m 48,229.55 2.39%

1010 Doors sq.m 65,497.60 3.24%

1002 Plumbing Works L.S. 18,302.54 0.91%

1018 Ceramic tiles sq.m 16,380.73 0.81%

1032 a-1 Masonry Painting sq.m 61,220.37 3.03%

1032 a-2 Wooden Painting sq.m 40,394.28 2.00%

1100 Electrical Works L.S. 46,095.25 2.28%


1100 Electrical Works L.S. 46,095.25 2.28%

Spl 1 Damproofing / Moisture Control sq.m 0.00 0.00% 0.00%

Spl 2 Railings L.M 0.00 0.00%

Spl.3 Occupational Safety & Health L.S. 6,397.44 0.32% 0.05% 0.0
0.07%
Spl.4 Project Billboard LS 0.00 0.00%
0.00%

2,020,000.00 100.00% 17.87% 21.01% 9.0

CASH

% Accomp. 17.87% 21.01% 9.0


Commulative % Accomp. 17.87% 38.87% 47.
Cash 360,934.90 424,306.91 182
Commulative Cash 360,934.90 785,241.81 968

Prepared by: Checked By: Submitted By:

JAYSON L. SALVADOR ELDRED M. MISLANG BLESILDA P. ESTRADA


Engineer II Asst Chief, Planning & Design Section Chief, Planning & Design Section
CARLOS CITY, PANGASINAN (CLUSTER I)

404(a-5)
3 CD 1100
900(a-5) 23 CD
3 CD 1027 403(a) 1013 1003 1032 (a-1)
19 CD 34 CD 10 CD 17 CD 17 CD
MOVE OUT
1002 1018 1032 (a-2)
SPL 2 1009 1010
6 CD 6 CD 10 CD
4 CD 8 CD 11 CD
SPL 3 & SPL 4
180 CD

CHART & S-CURVE

JUNE 1-30, 2013 JULY 1-31, 2013 AUGUST 1-31, 2013 SEPTEMBER 1-20, 2013
100%

75%

3.42%

0.00%

0.00%

50%

2.60% 1.39%

8.16% 1.75%

11.13% 2.89%

13.45%

2.39%

3.24%

0.91%

25%
0.81%

3.03%

2.00%
1.49% 0.79%

0.00%

0.05% 0.05% 0.05% 0.04%

0%

9.05% 15.08% 30.18% 6.81%

CASH FLOW

9.05% 15.08% 30.18% 6.81%


47.92% 63.01% 93.19% 100.00%
182,819.72 304,681.60 609,605.29 137,651.59
968,061.53 1,272,743.13 1,882,348.42 2,020,000.00

Recommending Approval: APPROVED:

EDITA L. MANUEL MARIETA B. MENDOZA


OIC-Asst. District Engineer OIC, District Engineer
BACK-UP COMPUTATION

Princeton Integrated School: An Innovative Green Engineer Design

ITEM 803 STRUCTURE EXCAVATION

LENGTH WIDTH DEPTH # SETS QUANTITY


FOOTING
FI 5.49 3.80 1.60 4 133.47
F2 5.70 4.50 1.60 4 164.02
F3 5.46 5.10 1.60 8 356.69
F4 6.63 4.00 1.60 4 169.75
F5 6.50 4.10 1.60 20 853.06
F6 3.30 3.30 1.60 16 278.78
F7 5.69 4.50 1.60 4 163.96
0
WF1 4.50 0.35 0.60 76 71.82
WF2 3.50 0.35 0.60 60 3.68
SEPTIC VAULT 7.40 3.20 1.80 2 85.25

TOTAL 2,280.48 CU.M

ITEM 804 EMBANKMENT (BACKFILLING & TAMPERING)

LENGTH WIDTH DEPTH # SETS QUANTITY


EMBANKMENT
85.00 17.00 0.80 1.00 1.00 1,156.00
2,280.48
TOTAL 3,436.48 CU.M

ITEM 1000 (a) TERMITE CONTROL WORKS


LENGTH WIDTH QUANTITY
MAIN FLOORING
85.00 17.00 1445.00
CORRIDOR
85.00 2.50 212.50
1657.50 SQ.M

SPL.1 SOIL EXPLORATION

Q =3 HOLE Q =3 HOLE

SPL.2 HAULING OF MATERIALS ( DOUBLE HANDLING) ALL/L.S.

ITEM 804 d-1 EMBANKMENT (GRAVEL FILL & TAMPERING)

LENGTH WIDTH DEPTH # SETS QUANTITY


GRAVEL FILL
85.00 17.00 0.10 1.00 1.00 144.50

TOTAL 144.50 CU.M

ITEM SPL 3 DAMPROOFING / MOISTURE CONTROL

LENGTH WIDTH # SETS QUANTITY


EMBANKMENT
85.00 17.00 1.00 1.00 1,445.00

TOTAL 1,445.00 SQ.M

ITEM 404 REINFORCING STEEL BARS

LENGTH # PCS # SETS kg/m F.S. QUANTITY


FOOTING
TOP FI 5.50 14.00 4.00 3.854 1.02 1,210.33
BOTT&TOP 3.80 32.00 4.00 1.578 1.02 782.89
TOP 3.80 8.00 4.00 3.854 1.02 478.02
BOTT 5.50 14.00 4.00 3.854 1.02 1,210.33
TOP F2 5.70 14.00 4.00 4.833 1.02 1,572.17

181
BOTT&TOP 4.50 26.00 4.00 1.578 1.02 753.27
TOP 4.50 8.00 4.00 4.833 1.02 709.87
BOTT 5.70 14.00 4.00 4.833 1.02 1,572.17
TOP F3 5.65 15.00 8.00 4.833 1.02 3,339.94
BOTT&TOP 5.10 26.00 8.00 1.578 1.02 1,707.42
TOP 5.10 10.00 8.00 4.833 1.02 2,011.30
BOTT 5.65 15.00 8.00 4.833 1.02 3,339.94
TOP F4 6.63 12.00 4.00 4.833 1.02 1,569.05
BOTT 4.00 30.00 4.00 1.578 1.02 772.59
TOP 4.00 8.00 4.00 4.833 1.02 631.00
BOTT 6.63 12.00 4.00 4.833 1.02 1,569.05
TOP F5 6.50 12.00 20.00 4.833 1.02 7,692.64
BOTT 4.10 22.00 20.00 1.578 1.02 2,903.65
TOP 4.10 8.00 20.00 4.833 1.02 3,233.86
BOTT 6.50 12.00 20.00 4.833 1.02 7,692.64
TOP F6 3.30 17.00 16.00 2.467 1.02 2,258.67
BOTT 3.30 17.00 16.00 2.467 1.02 2,258.67
TOP F7 5.69 14.00 4.00 2.467 1.02 802.23
BOTT 4.50 26.00 4.00 2.467 1.02 1,177.65
TOP 4.50 8.00 4.00 2.467 1.02 362.35
BOTT 5.69 14.00 4.00 2.467 1.02 802.23
WF1 4.50 3.00 19.00 0.888 1.02 232.33
0.35 12.00 19.00 1.578 1.02 128.44
WF2 4.50 3.00 10.00 0.888 1.02 122.28
0.35 12.00 10.00 1.578 1.02 67.60

TOTAL 52,964.57 SQ.M

COLUMN
C-1 (FOUNDATION) 3.20 4.00 4.00 2.467 1.02 1.00 128.84
TIES 1 2.20 6.00 4.00 0.616 1.02 1.00 33.18
TIES 2 2.20 10.00 4.00 0.616 1.02 1.00 55.29
C-1 (GROUND FLR.) 3.20 4.00 4.00 2.467 1.02 1.00 128.84
TIES 1 2.20 6.00 4.00 0.616 1.02 1.00 33.18
TIES 2 2.20 10.00 4.00 0.616 1.02 1.00 55.29
C-1 (2ND FLR) 3.20 4.00 4.00 2.467 1.02 1.00 128.84
TIES 1 2.20 6.00 4.00 0.616 1.02 1.00 33.18
TIES 2 2.20 10.00 4.00 0.616 1.02 1.00 55.29
C-1 (3RD FLR) 3.20 4.00 4.00 1.578 1.02 1.00 82.41
TIES 1 2.20 6.00 4.00 0.616 1.02 1.00 33.18
TIES 2 2.20 10.00 4.00 0.616 1.02 1.00 55.29
C-1 (4TH FLR) 3.20 4.00 4.00 1.578 1.02 1.00 82.41
TIES 1 2.20 6.00 4.00 0.616 1.02 1.00 33.18
TIES 2 2.20 12.00 4.00 0.616 1.02 1.00 66.35
C-1 (5TH FLR) 3.20 4.00 4.00 1.578 1.02 1.00 82.41
2.20 6.00 4.00 0.616 1.02 1.00 33.18
2.20 12.00 4.00 0.616 1.02 1.00 66.35
C-2 (FOUNDATION) 3.20 8.00 4.00 2.467 1.02 1.00 257.67
TIES 1 3.60 6.00 4.00 0.616 1.02 1.00 54.29
TIES 2 3.60 10.00 4.00 0.616 1.02 1.00 90.48
C-2 (GROUND FLR. ) 3.20 8.00 4.00 2.467 1.02 1.00 257.67
TIES 1 3.60 6.00 4.00 0.616 1.02 1.00 54.29
TIES 2 3.60 10.00 4.00 0.616 1.02 1.00 90.48
C-2 (2ND FLR) 3.20 6.00 4.00 2.467 1.02 1.00 193.25
TIES 1 2.90 6.00 4.00 0.616 1.02 1.00 43.73
TIES 2 2.90 10.00 4.00 0.616 1.02 1.00 72.89
C-2 (3RD FLR) 3.20 4.00 4.00 1.578 1.02 1.00 82.41
TIES 1 2.20 6.00 4.00 0.616 1.02 1.00 33.18
TIES 2 2.20 10.00 4.00 0.616 1.02 1.00 55.29
C-2 (4THFLR) 3.20 4.00 4.00 1.578 1.02 1.00 82.41

182
TIES 1 2.20 6.00 4.00 0.616 1.02 1.00 33.18
TIES 2 2.20 12.00 4.00 0.616 1.02 1.00 66.35
C-2 (5TH FLR) 3.20 4.00 4.00 1.578 1.02 1.00 82.41
TIES 1 2.20 6.00 4.00 0.616 1.02 1.00 33.18
TIES 2 2.20 12.00 4.00 0.616 1.02 1.00 66.35
C-3 (FOUNDATION) 3.20 8.00 16.00 2.467 1.02 1.00 1,030.69
TIES 1 3.60 6.00 16.00 0.616 1.02 1.00 217.15
TIES 2 3.60 10.00 16.00 0.616 1.02 1.00 361.91
C-3 (GROUND FLR. ) 3.20 8.00 16.00 2.467 1.02 1.00 1,030.69
TIES 1 3.60 6.00 16.00 0.616 1.02 1.00 217.15
TIES 2 3.60 10.00 16.00 0.616 1.02 1.00 361.91
C-3 (2ND FLR) 3.20 6.00 16.00 2.467 1.02 1.00 773.02
2.90 6.00 16.00 0.616 1.02 1.00 174.92
2.90 10.00 16.00 0.616 1.02 1.00 291.54
C-3 (3RD FLR) 3.20 4.00 16.00 1.578 1.02 1.00 329.64
2.20 6.00 16.00 0.616 1.02 1.00 132.70
2.20 10.00 16.00 0.616 1.02 1.00 221.17
C-3 (4TH FLR) 3.20 4.00 16.00 1.578 1.02 1.00 329.64
2.20 6.00 16.00 0.616 1.02 1.00 132.70
2.20 12.00 16.00 0.616 1.02 1.00 265.40
C-3 (5TH FLR) 3.20 4.00 16.00 1.578 1.02 1.00 329.64
2.20 6.00 16.00 0.616 1.02 1.00 132.70
2.20 12.00 16.00 0.616 1.02 1.00 265.40
C-4 (FOUNDATION) 3.20 8.00 12.00 2.467 1.02 1.00 773.02
TIES 1 3.60 6.00 12.00 0.616 1.02 1.00 162.86
TIES 2 3.60 10.00 12.00 0.616 1.02 1.00 271.43
C-4 (GROUND FLR. ) 3.20 8.00 12.00 2.467 1.02 1.00 773.02
TIES 1 3.60 6.00 12.00 0.616 1.02 1.00 162.86
TIES 2 3.60 10.00 12.00 0.616 1.02 1.00 271.43
C-4(2ND FLR) 3.20 6.00 12.00 2.467 1.02 1.00 579.76
2.90 6.00 12.00 0.616 1.02 1.00 131.19
2.90 10.00 12.00 0.616 1.02 1.00 218.66
C-4 (3RDFLR) 3.20 4.00 12.00 1.578 1.02 1.00 247.23
2.20 6.00 12.00 0.616 1.02 1.00 99.53
2.20 10.00 12.00 0.616 1.02 1.00 165.88
C-4(4TH FLR) 3.20 4.00 12.00 1.578 1.02 1.00 247.23
2.20 6.00 12.00 0.616 1.02 1.00 99.53
2.20 12.00 12.00 0.616 1.02 1.00 199.05
C-4(5TH FLR) 3.20 4.00 12.00 1.578 1.02 1.00 247.23
2.20 6.00 12.00 0.616 1.02 1.00 99.53
2.20 12.00 12.00 0.616 1.02 1.00 199.05
C-5 (FOUNDATION) 3.20 6.00 4.00 3.854 1.02 1.00 301.91
TIES 1 2.90 6.00 4.00 0.616 1.02 1.00 43.73
TIES 2 2.90 8.00 4.00 0.616 1.02 1.00 58.31
C-5 (GROUND FLR.) 3.20 6.00 4.00 3.854 1.02 1.00 301.91
TIES 1 2.90 6.00 4.00 0.616 1.02 1.00 43.73
TIES 2 2.90 8.00 4.00 0.616 1.02 1.00 58.31
C-5(2NDFLR) 3.20 6.00 4.00 3.854 1.02 1.00 301.91
2.90 6.00 4.00 0.616 1.02 1.00 43.73
2.90 8.00 4.00 0.616 1.02 1.00 58.31
C-5 (3RD FLR) 3.20 6.00 4.00 3.854 1.02 1.00 301.91
2.90 6.00 4.00 0.616 1.02 1.00 43.73
2.90 8.00 4.00 0.616 1.02 1.00 58.31
C-5 (4TH FLR) 3.20 4.00 4.00 1.578 1.02 1.00 82.41
2.20 6.00 4.00 0.616 1.02 1.00 33.18
2.20 12.00 4.00 0.616 1.02 1.00 66.35
C-5 (5TH FLR) 3.20 4.00 4.00 1.578 1.02 1.00 82.41
2.20 6.00 4.00 0.616 1.02 1.00 33.18
2.20 12.00 4.00 0.616 1.02 1.00 66.35
C-6& C-10 (FOUNDATION) 3.20 8.00 12.00 3.854 1.02 1.00 1,207.63
TIES 1 3.60 6.00 12.00 0.616 1.02 1.00 162.86
TIES 2 3.60 8.00 12.00 0.616 1.02 1.00 217.15
C-6& C10 (GROUND FLR.) 3.20 8.00 12.00 3.854 1.02 1.00 1,207.63
TIES 1 3.60 6.00 12.00 0.616 1.02 1.00 162.86
TIES 2 3.60 8.00 12.00 0.616 1.02 1.00 217.15
C-6&C10(2NDFLR) 3.20 6.00 12.00 3.854 1.02 1.00 905.72
2.90 6.00 12.00 0.616 1.02 1.00 131.19
2.90 8.00 12.00 0.616 1.02 1.00 174.92
C-6& C10(3RD FLR) 3.20 4.00 12.00 3.854 1.02 1.00 603.81
2.20 6.00 12.00 0.616 1.02 1.00 99.53
2.20 8.00 12.00 0.616 1.02 1.00 132.70
C-6 & C10(4TH FLR) 3.20 4.00 12.00 3.854 1.02 1.00 603.81
2.20 6.00 12.00 0.616 1.02 1.00 99.53
2.20 8.00 12.00 0.616 1.02 1.00 132.70
C-6 & C10 (5TH FLR) 3.20 4.00 12.00 3.854 1.02 1.00 603.81

183
2.20 6.00 12.00 0.616 1.02 1.00 99.53
2.20 8.00 12.00 0.616 1.02 1.00 132.70
C-7 (FOUNDATION) 3.20 6.00 4.00 2.467 1.02 1.00 193.25
TIES 1 2.90 6.00 4.00 0.616 1.02 1.00 43.73
TIES 2 2.90 10.00 4.00 0.616 1.02 1.00 72.89
C-7 (GROUND FLR.) 3.20 6.00 4.00 2.467 1.02 1.00 193.25
TIES 1 2.90 6.00 4.00 0.616 1.02 1.00 43.73
TIES 2 2.90 10.00 4.00 0.616 1.02 1.00 72.89
C-7(2NDFLR) 3.20 6.00 4.00 2.467 1.02 1.00 193.25
2.90 6.00 4.00 0.616 1.02 1.00 43.73
2.90 10.00 4.00 0.616 1.02 1.00 72.89
C-7(3RD FLR) 3.20 4.00 4.00 2.467 1.02 1.00 128.84
2.20 6.00 4.00 0.616 1.02 1.00 33.18
2.20 10.00 4.00 0.616 1.02 1.00 55.29
C-7(4TH FLR) 3.20 4.00 4.00 2.467 1.02 1.00 128.84
2.20 6.00 4.00 0.616 1.02 1.00 33.18
2.20 10.00 4.00 0.616 1.02 1.00 55.29
C-7 (5TH FLR) 3.20 4.00 4.00 2.467 1.02 1.00 128.84
2.20 6.00 4.00 0.616 1.02 1.00 33.18
2.20 10.00 4.00 0.616 1.02 1.00 55.29
C-8 (FOUNDATION) 3.20 10.00 4.00 2.467 1.02 1.00 322.09
TIES 1 4.30 6.00 4.00 0.616 1.02 1.00 64.84
TIES 2 4.30 10.00 4.00 0.616 1.02 1.00 108.07
C-8 (GROUND FLR.) 3.20 10.00 4.00 2.467 1.02 1.00 322.09
TIES 1 4.30 6.00 4.00 0.616 1.02 1.00 64.84
TIES 2 4.30 10.00 4.00 0.616 1.02 1.00 108.07
C-8(2NDFLR) 3.20 8.00 4.00 2.467 1.02 1.00 257.67
3.60 6.00 4.00 0.616 1.02 1.00 54.29
3.60 10.00 4.00 0.616 1.02 1.00 90.48
C-8(3RD FLR) 3.20 6.00 4.00 2.467 1.02 1.00 193.25
2.90 6.00 4.00 0.616 1.02 1.00 43.73
2.90 10.00 4.00 0.616 1.02 1.00 72.89
C-8(4TH FLR) 3.20 4.00 4.00 2.467 1.02 1.00 128.84
2.20 6.00 4.00 0.616 1.02 1.00 33.18
2.20 10.00 4.00 0.616 1.02 1.00 55.29
C-8 (5TH FLR) 3.20 4.00 4.00 2.467 1.02 1.00 128.84
2.20 6.00 4.00 0.616 1.02 1.00 33.18
2.20 10.00 4.00 0.616 1.02 1.00 55.29
C-9 (FOUNDATION) 3.20 8.00 8.00 3.854 1.02 1.00 805.09
TIES 1 3.72 6.00 8.00 0.616 1.02 1.00 112.19
TIES 2 3.72 8.00 8.00 0.616 1.02 1.00 149.59
C-9 (GROUND FLR.) 3.20 8.00 8.00 3.854 1.02 1.00 805.09
TIES 1 3.72 6.00 8.00 0.616 1.02 1.00 112.19
TIES 2 3.72 8.00 8.00 0.616 1.02 1.00 149.59
C-9(2NDFLR) 3.20 8.00 8.00 3.854 1.02 1.00 805.09
3.72 6.00 8.00 0.616 1.02 1.00 112.19
3.72 8.00 8.00 0.616 1.02 1.00 149.59
C-9(3RD FLR) 3.20 6.00 8.00 3.854 1.02 1.00 603.81
3.00 6.00 8.00 0.616 1.02 1.00 90.48
3.00 8.00 8.00 0.616 1.02 1.00 120.64
C-9(4TH FLR) 3.20 4.00 8.00 3.854 1.02 1.00 402.54
2.28 6.00 8.00 0.616 1.02 1.00 68.76
2.28 8.00 8.00 0.616 1.02 1.00 91.68
C-9 (5TH FLR) 3.20 4.00 8.00 3.854 1.02 1.00 402.54
2.28 6.00 8.00 0.616 1.02 1.00 68.76
2.28 8.00 8.00 0.616 1.02 1.00 91.68
C-11&C-12(FOUNDATION) 3.20 8.00 16.00 3.854 1.02 2.00 3,220.34
TIES 1 3.72 6.00 16.00 0.616 1.02 2.00 448.77
TIES 2 3.72 8.00 16.00 0.616 1.02 2.00 598.36
C-11&C-12(GROUND FLR.) 3.20 8.00 16.00 3.854 1.02 2.00 3,220.34
TIES 1 3.72 6.00 16.00 0.616 1.02 2.00 448.77
TIES 2 3.72 8.00 16.00 0.616 1.02 2.00 598.36
C-11&C12(2NDFLR) 3.20 6.00 16.00 3.854 1.02 2.00 2,415.26
3.00 6.00 16.00 0.616 1.02 2.00 361.91
3.00 8.00 16.00 0.616 1.02 2.00 482.55
C-11&C12(3RD FLR) 3.20 4.00 16.00 3.854 1.02 2.00 1,610.17
2.28 6.00 16.00 0.616 1.02 2.00 275.05
2.28 8.00 16.00 0.616 1.02 2.00 366.74
C-11&C12(4TH FLR) 3.20 4.00 16.00 3.854 1.02 2.00 1,610.17
2.80 6.00 16.00 0.616 1.02 2.00 337.78
2.80 8.00 16.00 0.616 1.02 2.00 450.38
C-11&C-12 (5TH FLR) 3.20 4.00 16.00 3.854 1.02 2.00 1,610.17
2.80 6.00 16.00 0.616 1.02 2.00 337.78
2.80 8.00 16.00 0.616 1.02 2.00 450.38
DC 1.40 4.00 2.00 1.578 1.02 4.00 72.11

184
0.64 14.00 2.00 1.578 1.02 4.00 115.37
BEAM AT 2ND FLR. & 3RD FLR. SUB-TOTAL: 51,148.25
BEAM
TYP C G-1 4.50 4.00 19.00 4.833 1.02 1.00 2 3,371.89
1.98 3.00 19.00 4.833 1.02 2.00 2 2,219.83
STIRR. 1.96 27.00 19.00 0.616 1.02 1.00 2 1,263.53
TYP A G-2 4.50 4.00 19.00 4.833 1.02 1.00 2 3,371.89
1.98 1.00 19.00 4.833 1.02 2.00 2 739.94
STIRR. 1.96 27.00 19.00 0.616 1.02 1.00 2 1,263.53
TYP A G-3 4.50 4.00 10.00 4.833 1.02 1.00 2 1,774.68
1.30 1.00 10.00 4.833 1.02 2.00 2 256.34
STIRR. 1.96 22.00 10.00 0.616 1.02 1.00 2 541.86
TYP C G-4 4.50 4.00 10.00 4.833 1.02 1.00 2 1,774.68
1.30 3.00 10.00 4.833 1.02 2.00 2 769.03
STIRR. 1.96 21.00 10.00 0.616 1.02 1.00 2 517.23
G-5 4.50 4.00 10.00 4.833 1.02 1.00 2 1,774.68
1.30 3.00 10.00 4.833 1.02 2.00 2 769.03
STIRR. 1.96 21.00 10.00 0.616 1.02 1.00 2 517.23
TYP C G-6 4.50 7.00 10.00 4.833 1.02 1.00 2 3,105.69
1.30 3.00 10.00 4.833 1.02 2.00 2 769.03
STIRR. 1.96 21.00 10.00 0.616 1.02 1.00 2 517.23
TYP C G-7 4.50 7.00 10.00 4.833 1.02 1.00 2 3,105.69
1.30 3.00 10.00 4.833 1.02 2.00 2 769.03
STIRR. 1.96 21.00 10.00 0.616 1.02 1.00 2 517.23
BEAM AT 4rd flr. FLR.
BEAM
G-1 4.50 4.00 19.00 4.833 1.02 1.00 1.00 1,685.94
1.98 2.00 19.00 4.833 1.02 2.00 1.00 739.94
STIRR. 1.96 26.00 19.00 0.616 1.02 1.00 1.00 608.36
G-2 4.50 4.00 19.00 4.833 1.02 1.00 1.00 1,685.94
1.98 1.00 19.00 4.833 1.02 2.00 1.00 369.97
STIRR. 1.96 26.00 19.00 0.616 1.02 1.00 1.00 608.36
G-3 4.50 4.00 10.00 4.833 1.02 1.00 1.00 887.34
1.65 1.00 10.00 4.833 1.02 2.00 1.00 162.68
STIRR. 1.96 22.00 10.00 0.616 1.02 1.00 1.00 270.93
G-4 4.50 4.00 10.00 4.833 1.02 1.00 1.00 887.34
1.65 2.00 10.00 4.833 1.02 2.00 1.00 325.36
STIRR. 1.96 21.00 10.00 0.616 1.02 1.00 1.00 258.62
G-5 4.50 4.00 10.00 4.833 1.02 1.00 1.00 887.34
1.65 2.00 10.00 4.833 1.02 2.00 1.00 325.36
STIRR. 1.96 21.00 10.00 0.616 2.02 1.00 1.00 512.16
G-6 4.50 4.00 10.00 4.833 1.02 1.00 1.00 887.34
1.65 2.00 10.00 4.833 1.02 2.00 1.00 325.36
STIRR. 1.96 21.00 10.00 0.616 1.02 1.00 1.00 258.62
G-7 4.50 4.00 10.00 4.833 1.02 1.00 1.00 887.34
1.65 2.00 10.00 4.833 1.02 2.00 1.00 325.36
STIRR. 1.96 21.00 10.00 0.616 1.02 1.00 1.00 258.62

BEAM AT 5TH FLR.


BEAM
G-1 4.50 4.00 19.00 3.854 1.02 1.00 1.00 1,344.43
1.95 2.00 19.00 3.854 1.02 2.00 1.00 582.59
STIRR. 1.70 28.00 19.00 0.616 1.02 1.00 1.00 568.25
G-2 4.50 5.00 19.00 3.854 1.02 1.00 1.00 1,680.54
1.95 1.00 19.00 3.854 1.02 2.00 1.00 291.29
STIRR. 1.70 28.00 19.00 0.616 1.02 1.00 1.00 568.25
G-3 4.50 4.00 10.00 3.854 1.02 1.00 1.00 707.59
1.65 1.00 10.00 3.854 1.02 2.00 1.00 129.73
STIRR. 1.70 22.00 10.00 0.616 1.02 1.00 1.00 234.99
G-4 4.50 4.00 10.00 3.854 1.02 1.00 1.00 707.59
1.65 2.00 10.00 3.854 1.02 2.00 1.00 259.45
STIRR. 1.70 22.00 10.00 0.616 1.02 1.00 1.00 234.99
G-5 4.50 4.00 10.00 4.833 1.02 1.00 1.00 887.34
1.65 2.00 10.00 4.833 1.02 2.00 1.00 325.36
STIRR. 1.76 22.00 10.00 0.616 1.02 1.00 1.00 243.29
G-6 4.50 4.00 10.00 4.833 1.02 1.00 1.00 887.34
1.65 2.00 10.00 4.833 1.02 1.00 1.00 162.68
STIRR. 1.76 22.00 10.00 0.616 1.02 1.00 1.00 243.29
G-7 4.50 4.00 10.00 4.833 1.02 1.00 1.00 887.34
1.65 2.00 10.00 4.833 1.02 1.00 1.00 162.68
STIRR. 1.76 22.00 10.00 0.616 1.02 1.00 1.00 243.29

BEAM AT RD FLR
BEAM
G-1 4.50 4.00 19.00 2.467 1.02 1.00 1.00 860.59

185
1.91 2.00 19.00 2.467 1.02 2.00 1.00 365.27
STIRR. 1.30 36.00 19.00 0.616 1.02 1.00 1.00 558.70
G-2 4.50 4.00 19.00 3.854 1.02 1.00 1.00 1,344.43
1.60 49.00 19.00 0.616 1.02 1.00 1.00 935.95
G-3 4.50 4.00 10.00 2.467 1.02 1.00 1.00 452.94
1.91 1.00 10.00 2.467 1.02 2.00 1.00 96.12
2.50 1.00 10.00 2.467 1.02 2.00 1.00 125.82
STIRR. 1.60 22.00 10.00 0.616 1.02 1.00 1.00 221.17
G-4 4.50 4.00 10.00 2.467 1.02 1.00 1.00 452.94
1.91 1.00 10.00 2.467 1.02 2.00 1.00 96.12
2.50 1.00 10.00 2.467 1.02 2.00 1.00 125.82
STIRR. 1.60 21.00 10.00 0.616 1.02 1.00 1.00 211.12
G-5 4.50 4.00 10.00 2.467 1.02 1.00 1.00 452.94
1.91 1.00 10.00 2.467 1.02 2.00 1.00 96.12
2.50 1.00 10.00 2.467 1.02 2.00 1.00 125.82
STIRR. 1.60 21.00 10.00 0.616 1.02 1.00 1.00 211.12
G-6 4.50 4.00 10.00 2.467 1.02 1.00 1.00 452.94
1.91 1.00 10.00 2.467 1.02 2.00 1.00 96.12
2.50 1.00 10.00 2.467 1.02 2.00 1.00 62.91
STIRR. 1.60 21.00 10.00 0.616 1.02 1.00 1.00 211.12
G-7 4.50 4.00 10.00 2.467 1.02 1.00 1.00 452.94
1.91 1.00 10.00 2.467 1.02 2.00 1.00 96.12
2.50 1.00 10.00 2.467 1.02 2.00 1.00 62.91
STIRR. 1.60 21.00 10.00 0.616 1.02 1.00 1.00 211.12

BEAMS 2ND
B-1 & B-4 4.50 4.00 19.00 4.833 1.02 1.00 2.00 3,371.89
1.98 8.00 19.00 4.833 1.02 2.00 2.00 5,919.54
1.56 30.00 19.00 0.616 1.02 1.00 2.00 1,117.40
B-2 & B-3 4.50 4.00 19.00 4.833 1.02 1.00 2.00 3,371.89
1.98 6.00 19.00 4.833 1.02 2.00 2.00 4,439.65
1.56 30.00 19.00 0.616 1.02 1.00 2.00 1,117.40
B5- B9 4.50 4.00 10.00 4.833 1.02 1.00 5.00 4,436.69
1.65 4.00 10.00 4.833 1.02 2.00 5.00 3,253.58
1.56 24.00 10.00 0.616 1.02 1.00 5.00 1,176.22
B10-B11 4.50 4.00 10.00 4.833 1.02 1.00 2.00 1,774.68
1.65 1.00 10.00 4.833 1.02 2.00 2.00 325.36
1.90 2.00 10.00 4.833 1.02 1.00 2.00 374.65
1.56 22.00 10.00 0.616 1.02 1.00 2.00 431.28

BEAMS 3RD
B-1 & B-4 4.50 4.00 19.00 4.833 1.02 1.00 2.00 3,371.89
1.98 7.00 19.00 4.833 1.02 2.00 2.00 5,179.59
1.56 30.00 19.00 0.616 1.02 1.00 2.00 1,117.40
B-2 & B-3 4.50 4.00 19.00 4.833 1.02 1.00 2.00 3,371.89
1.98 4.00 19.00 4.833 1.02 2.00 2.00 2,959.77
1.56 30.00 19.00 0.616 1.02 1.00 2.00 1,117.40
B5- B9 4.50 4.00 10.00 4.833 1.02 1.00 5.00 4,436.69
1.65 3.00 10.00 4.833 1.02 2.00 5.00 2,440.18
1.56 24.00 10.00 0.616 1.02 1.00 5.00 1,176.22
B10-B11 4.50 4.00 10.00 4.833 1.02 1.00 2.00 1,774.68
1.65 1.00 10.00 4.833 1.02 2.00 2.00 325.36
1.90 2.00 10.00 4.833 1.02 1.00 2.00 374.65
1.20 22.00 10.00 0.616 1.02 1.00 2.00 331.75

BEAMS 4TH
B-1 & B-4 4.50 4.00 19.00 4.833 1.02 1.00 2.00 3,371.89
1.98 4.00 19.00 4.833 1.02 2.00 2.00 2,959.77
1.56 30.00 19.00 0.616 1.02 1.00 2.00 1,117.40
B-2 & B-3 4.50 4.00 19.00 4.833 1.02 1.00 2.00 3,371.89
1.98 3.00 19.00 4.833 1.02 2.00 2.00 2,219.83
1.56 30.00 19.00 0.616 1.02 1.00 2.00 1,117.40
B5- B9 4.50 4.00 10.00 4.833 1.02 1.00 5.00 4,436.69
1.65 3.00 10.00 4.833 1.02 2.00 5.00 2,440.18
1.56 24.00 10.00 0.616 1.02 1.00 5.00 1,176.22
B10-B11 4.50 4.00 10.00 4.833 1.02 1.00 2.00 1,774.68
1.65 1.00 10.00 4.833 1.02 2.00 2.00 325.36
1.90 2.00 10.00 4.833 1.02 1.00 2.00 374.65
1.20 22.00 10.00 0.616 1.02 1.00 2.00 331.75

BEAMS 5TH
B-1 , B-4& B-2 4.50 4.00 19.00 3.854 1.02 1.00 3.00 4,033.29
1.95 4.00 19.00 3.854 1.02 2.00 3.00 3,495.52
1.40 33.00 19.00 0.616 1.02 1.00 3.00 1,654.62
B-3 4.50 4.00 19.00 4.667 1.02 1.00 2.00 3,256.07
1.98 3.00 19.00 4.833 1.02 2.00 1.00 1,109.91
2.56 1.00 18.00 4.833 1.02 2.00 1.00 454.32

186
1.50 30.00 19.00 0.616 1.02 1.00 1.00 537.21
B5&B9 4.50 4.00 10.00 3.854 1.02 1.00 1.00 707.59
1.95 2.00 10.00 3.854 1.02 2.00 1.00 306.62
1.56 33.00 10.00 0.616 1.02 1.00 1.00 323.46
B6&B7 4.50 4.00 10.00 3.854 1.02 1.00 1.00 707.59
1.98 2.00 10.00 3.854 1.02 2.00 1.00 311.34
1.50 30.00 10.00 0.616 1.02 1.00 1.00 282.74
B8 4.50 4.00 10.00 3.854 1.02 1.00 1.00 707.59
1.60 4.00 10.00 3.854 1.02 2.00 1.00 503.18
1.30 30.00 10.00 0.616 1.02 1.00 1.00 245.04
B10-B11 4.50 4.00 10.00 4.833 1.02 1.00 2.00 1,774.68
1.65 1.00 10.00 4.833 1.02 2.00 2.00 325.36
1.90 2.00 10.00 4.833 1.02 1.00 2.00 374.65
1.20 22.00 10.00 0.616 1.02 1.00 2.00 331.75

BEAMS RD
B-1 , B-4& B-2 4.50 4.00 19.00 3.854 1.02 1.00 3.00 4,033.29
1.95 3.00 19.00 3.854 1.02 2.00 3.00 2,621.64
2.56 1.00 19.00 3.854 1.02 2.00 3.00 183.37
1.40 33.00 19.00 0.616 1.02 1.00 3.00 1,654.62
B-3 4.50 4.00 19.00 4.833 1.02 1.00 2.00 3,371.89
1.98 3.00 19.00 4.833 1.02 2.00 1.00 1,109.91
2.56 1.00 18.00 4.833 1.02 2.00 1.00 454.32
1.50 30.00 19.00 0.616 1.02 1.00 1.00 537.21
B5,B6&B7 4.50 4.00 10.00 2.467 1.02 1.00 3.00 1,358.82
1.95 2.00 10.00 2.467 1.02 2.00 3.00 588.82
1.60 1.00 10.00 2.467 1.02 1.00 3.00 120.78
1.56 33.00 10.00 0.616 1.02 1.00 3.00 970.38
B8&B9 4.50 4.00 10.00 3.854 1.02 1.00 1.00 707.59
1.98 2.00 10.00 3.854 1.02 2.00 1.00 311.34
1.50 30.00 10.00 0.616 1.02 1.00 1.00 282.74
B10-B11 4.50 4.00 10.00 4.833 1.02 1.00 2.00 1,774.68
1.65 1.00 10.00 4.833 1.02 2.00 2.00 325.36
1.90 2.00 10.00 4.833 1.02 1.00 2.00 374.65
1.20 22.00 10.00 0.616 1.02 1.00 2.00 331.75
STB 1.40 4.00 8.00 1.578 1.02 1.00 1.00 72.11
1.20 14.00 8.00 0.616 1.02 1.00 1.00 84.45
TOTAL 189,416.67

STAIR SLAB 1.20 10.00 2.00 0.616 1.02 5.00 75.40


0.40 10.00 2.00 0.616 1.02 5.00 25.13
STAIR LANDING
LONGI 1.20 13.00 1.00 1.578 1.02 4.00 100.44
2.40 9.00 1.00 0.888 1.02 1.00 19.56
TRANSVERSE 1.20 13.00 1.00 1.578 1.02 4.00 100.44
2.40 9.00 1.00 0.888 1.02 1.00 19.56
CONCRETE SUNBREAKER
0.60 23.00 88.00 0.888 1.02 1.00 1,099.95
4.50 3.00 88.00 0.888 1.02 1.00 1,076.04
SEPTIC VAULT SLAB
TOP SLAB 7.60 50.00 1.00 0.616 1.02 2.00 477.52
3.40 17.00 1.00 0.616 1.02 2.00 72.63
BOTT.SLAB 7.60 50.00 1.00 0.616 1.02 2.00 477.52
3.40 17.00 1.00 0.616 1.02 2.00 72.63
WALLS 7.60 4.00 1.00 0.616 1.02 4.00 76.40
1.80 38.00 1.00 0.616 1.02 4.00 171.91
3.40 4.00 1.00 0.616 1.02 4.00 34.18
1.80 18.00 1.00 0.616 1.02 4.00 81.43
CISTERN SLAB
TOP SLAB 25.00 41.00 2.00 0.888 1.02 1,856.81
15.00 126.00 2.00 0.616 1.02 2,375.05
BOTT. SLAB 25.00 61.00 2.00 0.888 1.02 2,762.57
15.00 126.00 2.00 0.616 1.02 2,375.05
DOWELS MAIN BUILDING
VERTICAL 3.20 24.00 1.00 0.616 1.02 50.00 5 12,063.74
HORIZONTAL 4.50 7.00 1.00 0.616 1.02 38.00 5 3,760.50
3.50 7.00 1.00 0.616 1.02 10.00 5 769.69
SUB-TOTAL: 29,944.17
SLAB-ON-FILL
TOP 4.50 11.00 18.00 0.616 1.02 559.83
BOTT. 3.50 14.00 18.00 0.616 1.02 554.18
4.50 10.00 19.00 0.616 1.02 537.21
3.00 14.00 19.00 0.616 1.02 501.40
4.00 15.00 2.00 0.616 1.02 75.40
3.50 17.00 2.00 0.616 1.02 74.77
SUB-TOTAL: 2,302.79
FOR 2ND & 5th FLR.SLAB

187
SUSPENDED SLAB
S1 & S2 LONG.
TOP 1.13 26.00 24.00 0.888 1.02 4.00 2,543.37
BOTT. 4.50 13.00 24.00 0.888 1.02 4.00 5,086.75
SHORT
TOP 0.88 32.00 24.00 0.888 1.02 4.00 2,434.68
BOTT. 3.50 16.00 24.00 0.888 1.02 4.00 4,869.37
S3 LONG.
TOP 1.00 32.00 4.00 0.888 1.02 4.00 463.75
BOTT. 4.00 13.00 4.00 0.888 1.02 4.00 753.59
SHORT
TOP 0.88 32.00 4.00 0.888 1.02 4.00 405.78
BOTT. 3.50 15.00 4.00 0.888 1.02 4.00 760.84
S4(2ND-4TH) LONG.
TOP 1.13 26.00 18.00 0.888 1.02 3.00 1,437.01
BOTT. 4.50 13.00 18.00 0.888 1.02 3.00 2,861.30
SHORT
TOP 0.88 32.00 18.00 0.888 1.02 3.00 1,369.51
BOTT. 3.50 16.00 18.00 0.888 1.02 3.00 2,739.02
S4 (5TH LONG.
TOP 1.13 33.00 4.00 0.888 1.02 1.00 135.10
BOTT. 4.50 13.00 4.00 0.888 1.02 1.00 211.95
SHORT
TOP 0.88 32.00 4.00 0.888 1.02 1.00 101.45
BOTT. 3.50 16.00 4.00 0.888 1.02 1.00 202.89
S5-S6 LONG.
TOP 1.13 26.00 24.00 0.888 1.02 4.00 2,554.68
BOTT. 4.50 13.00 24.00 0.888 1.02 4.00 5,086.75
SHORT
TOP 0.88 26.00 24.00 0.888 1.02 4.00 1,978.18
BOTT. 3.50 16.00 24.00 0.888 1.02 4.00 4,869.37
S7 & S8 LONG.
TOP 1.13 26.00 60.00 0.888 1.02 1.00 1,589.61
BOTT. 4.50 13.00 60.00 0.888 1.02 1.00 3,179.22
SHORT
TOP 0.88 32.00 60.00 0.888 1.02 1.00 1,521.68
BOTT. 3.50 16.00 60.00 0.888 1.02 1.00 3,043.35
S7 & S8 LONG.
TOP 1.13 78.00 36.00 0.888 1.02 1.00 2,861.30
BOTT. 4.50 13.00 36.00 0.888 1.02 1.00 1,907.53
SHORT
TOP 0.88 79.00 36.00 0.888 1.02 1.00 2,253.98
BOTT. 3.50 16.00 36.00 0.888 1.02 1.00 1,826.01
S9 3.50 6.00 2.00 0.888 1.02 4.00 152.17
1.50 40.00 2.00 0.888 1.02 4.00 434.76
S10 3.50 13.00 1.00 0.888 1.02 4.00 164.85
2.00 24.00 1.00 0.888 1.02 4.00 173.91
FOR RD
SUSPENDED SLAB
S1-S2 1.13 26.00 24.00 0.888 1.02 1.00 638.67
0.88 32.00 24.00 0.888 1.02 1.00 612.15
4.50 16.00 24.00 0.888 1.02 1.00 1,565.15
3.50 13.00 24.00 0.888 1.02 1.00 989.09
S3 1.00 40.00 4.00 0.888 1.02 1.00 144.92
0.88 69.00 4.00 0.888 1.02 1.00 219.99
4.00 21.00 4.00 0.888 1.02 1.00 304.34
3.50 32.00 4.00 0.888 1.02 1.00 405.78
S4-S6-S8 1.13 32.00 36.00 0.888 1.02 1.00 1,179.08
0.88 44.00 36.00 0.888 1.02 1.00 1,262.56
4.50 17.00 36.00 0.888 1.02 1.00 2,494.46
3.50 17.00 36.00 0.888 1.02 1.00 1,940.14
S5-S7 1.13 44.00 24.00 0.888 1.02 1.00 1,080.83
0.88 59.00 24.00 0.888 1.02 1.00 1,128.65
4.50 17.00 24.00 0.888 1.02 1.00 1,662.98
3.50 17.00 24.00 0.888 1.02 1.00 1,293.43
S9 3.50 5.00 2.00 0.888 1.02 1.00 31.70
1.50 40.00 2.00 0.888 1.02 1.00 108.69
S10 3.50 7.00 1.00 0.888 1.02 1.00 22.19
2.00 40.00 1.00 0.888 1.02 1.00 72.46
SUB-TOTAL: 77,130.93

Canopy 1.75 23.00 19.00 0.888 1.02 4.00 2,770.72


4.70 5.00 19.00 0.888 1.02 4.00 348.89
0.60 23.00 19.00 0.888 1.02 4.00 949.96
4.70 3.00 19.00 0.888 1.02 4.00 970.61
SUB-TOTAL: 5,040.18
TOTAL: 82,171.12

188
ITEM 405 STRUCTURAL CONCRETE

LENGTH WIDTH DEPTH # SETS QUANTITY


FOOTING
FI 5.49 3.80 0.40 4.00 1.00 33.37
F2 5.70 4.50 0.40 4.00 1.00 41.00
F3 5.46 5.10 0.40 8.00 1.00 89.17
F4 6.63 4.00 0.40 4.00 1.00 42.44
F5 6.50 4.10 0.40 20.00 1.00 213.27
F6 3.30 3.30 0.40 16.00 1.00 69.70
F7 5.69 4.50 0.40 4.00 1.00 40.99
WALL FOOTING
WF1 4.50 0.35 0.15 19.00 4.00 4.49
WF2 3.50 0.35 0.15 5.00 12 0.92

SUB-TOTAL: 535.34 CU.M


COLUMN
FOUNDATION C-1,C-2 c5 0.60 0.60 1.60 24.00 13.82
grnd.flr. C6,C7,C8 0.60 0.60 3.20 24.00 1.00 27.65
2nd flr. 0.60 0.60 3.20 24.00 1.00 27.65
3rd.flr. 0.60 0.60 3.20 24.00 27.65
4th flr. 0.60 0.60 3.20 24.00 27.65
5th flr. 0.60 0.60 3.20 24.00 27.65
FOUNDATION 0.60 0.60 1.60 16.00 9.22
grnd.flr. C-3 0.60 0.60 3.20 16.00 1.00 18.43
2nd flr. 0.60 0.60 3.20 16.00 1.00 18.43
3rd.flr. 0.60 0.60 3.20 16.00 18.43
4th flr. 0.60 0.60 3.20 16.00 18.43
5th flr. 0.60 0.60 3.20 16.00 18.43
FOUNDATION 0.60 0.60 1.60 12.00 6.91
grnd.flr. C-4 0.60 0.60 3.20 12.00 1.00 13.82
2nd flr. 0.60 0.60 3.20 12.00 1.00 13.82
3rd.flr. 0.60 0.60 3.20 12.00 13.82
4th flr. 0.60 0.60 3.20 12.00 13.82
5th flr. 0.60 0.60 3.20 12.00 13.82
FOUNDATION 0.60 0.60 1.60 16.00 1.00 9.22
grnd.flr. C-9& C-10 0.60 0.60 3.20 16.00 1.00 18.43
2nd flr. 0.60 0.60 3.20 16.00 1.00 18.43
3rd.flr. 0.60 0.60 3.20 16.00 1.00 18.43
4th flr. 0.60 0.60 3.20 16.00 1.00 18.43
5th flr. 0.60 0.60 3.20 16.00 1.00 18.43
FOUNDATION 0.55 0.55 1.60 32.00 15.49
grnd.flr. C-11& C-12 0.55 0.55 3.20 32.00 30.98
2nd flr. 0.55 0.55 3.20 32.00 30.98
3rd.flr. 0.55 0.55 3.20 32.00 30.98
4th flr. 0.55 0.55 3.20 32.00 30.98
5th flr. 0.55 0.55 3.20 32.00 30.98
2nd & RD FLR. SUB-TOTAL: 570.24 CU.M
BEAM
G-1 85.00 0.40 0.50 10.00 1.00 170.00
G-2 85.00 0.40 0.50 10.00 1.00 170.00
G-3 17.00 0.40 0.50 10.00 1.00 34.00
G-4 17.00 0.40 0.50 10.00 1.00 34.00
G-5 17.00 0.40 0.50 10.00 1.00 34.00
G-6 17.00 0.40 0.50 10.00 1.00 34.00
G-7 17.00 0.40 0.50 10.00 1.00 34.00
B-1 85.00 0.30 0.40 5.00 1.00 51.00
B-2 85.00 0.30 0.40 5.00 1.00 51.00
B-3 85.00 0.30 0.40 5.00 1.00 51.00
B-4 85.00 0.30 0.40 5.00 1.00 51.00
B-5 17.00 0.30 0.40 10.00 1.00 20.40
B-6 17.00 0.30 0.40 10.00 1.00 20.40
B-7 17.00 0.30 0.40 10.00 1.00 20.40
B-8 17.00 0.30 0.40 10.00 1.00 20.40
B-9 17.00 0.30 0.40 10.00 1.00 20.40
B-10 3.50 0.20 0.40 10.00 1.00 2.80
B-11 3.50 0.20 0.40 5.00 1.00 1.40
STB-1 1.56 0.20 0.40 10.00 1.00 1.25
STB-2 1.56 0.20 0.40 10.00 1.00 1.25
SUB-TOTAL: 821.45 CU.M

STAIR SLAB
landing 4.50 1.50 0.10 4.00 1 2 5.40
STEP 0.60 0.22 0.17 16.00 5.00 2 3.55
CONCRETE SUNBREAKER
4.50 0.15 0.60 88.00 1.00 35.64
SEPTIC VAULT SLAB
TOP & BOT.SLAB 3.40 7.60 0.10 2.00 1.00 5.17
7.60 1.80 0.10 1.00 1.00 1.37
WALL 15.20 6.80 0.15 2.00 1.00 31.01
CISTERN SLAB
TOP & BOT. SLAB 25.00 15.00 0.10 2.00 2.00 150.00
-
SUB-TOTAL: 232.13 CU.M

189
SLAB-ON-FILL
SOF 85.00 17.00 0.10 1.00 1.00 144.50
TOTAL 144.50 CU.M
SLAB AT 2ND & 5TH FLR.
SUSPENDED SLAB
85.00 17.00 0.10 5.00 722.50
CANOPY 85.00 1.50 0.10 5.00 63.75
85.00 0.60 0.10 5.00 25.50
LESS 3.00 3.00 0.10 4.00 (3.60)
3.00 3.00 0.10 5.00 (4.50)
SUB-TOTAL: 803.65 CU.M

ITEM 1003 CARPENTRY & JOINERY WORKS

LENGTH WIDTH # SETS QUANTITY


CEILING (interior)
BEAM 4.50 1.10 110.00 3.00 1,633.50
4.50 1.00 110.00 2.00 990.00
GIRDER 4.50 1.40 88.00 3.00 1,663.20
4.50 1.25 88.00 2.00 990.00
COLUMN 3.20 1.80 108.00 5.00 3,110.40
SLAB 0.90 7.00 87.00 5.00 2,740.50
TOTAL 11,127.60 SQ.M

ITEM 1009 WINDOW


LENGTH HEIGHT # SETS QUANTITY
W-1 1.80 2.10 88.00 1.00 332.64
W-2 1.80 1.20 224.00 1.00 483.84
W-3 0.50 0.50 79.00 19.75
TOTAL 836.23 SQ.M
ITEM 1009 WINDOW JALOUSIE
ITEM 1010 DOORS
LENGTH HEIGHT # SETS 1.00 QUANTITY
D-1 1.00 2.10 178.00 1.00 373.80
D-2 0.70 2.10 36.00 1.00 52.92
TOTAL 426.72 SQ.M
ITEM 1009 WINDOW JALOUSIE
ITEM 1018 CERAMIC TILE WORKS

LENGTH WIDTH # SETS QUANTITY


UNGLAZED
C.R AT GRND.to 4th FLR.
F(2ND TO 5th FLR.) FLR TILES 7.00 3.00 2.00 4 168.00
M(2ND TO 5th FLR.) FLR TILES 4.50 3.50 2.00 4 126.00
AT 3RD FLR.ONLY FLR TILES 4.50 3.50 1.00 15.75
1.M&F GRND FLR. 1.50 1.50 2.00 4.50
M&F GRND FLR. 4.50 3.50 2.00 31.50
TILE WOrKS AT HALLWAy GRND TO 5th F 85.00 3.00 5.00 1,275.00
TILE WOrKS AT GRND TO 5TH FLR.CLAS 72.00 14.00 2.00 5 10,080.00
SUB TOTAL 11,700.75
GRAND TOTAL 11,700.75 SQ.M

ITEM 1010 DOORS

Q = ALL Q = ALL

ITEM 506 MASONRY WORKS CHB

LENGTH HEIGHT # SETS QUANTITY


GROUND FLOOR
EXTERIOR 157.00 3.20 1.00 1.00 502.40
17.00 3.20 2.00 1.00 108.80
CORRIDOR 72.00 3.20 2.00 1.00 460.80
PARTITION 7.00 3.20 22.00 1.00 492.80
CR PARTITION 3.50 3.20 8.00 1.00 89.60
LESS WINDOWS & DOORS
W-1 1.80 2.10 88.00 1.00 (332.64)
W-2 1.80 1.20 224.00 1.00 (483.84)
W-3 0.50 0.50 79.00 1.00 (19.75)
D-1 1.00 2.10 178.00 1.00 (373.80)
D-2 0.70 2.10 36.00 (52.92)
2nd to 5th flr.
SECOND FLOOR no.of flr.
EXTERIOR 157.00 3.20 1.00 1.00 4.00 2,009.60
17.00 3.20 2.00 1.00 4.00 435.20
CORRIDOR 72.00 3.20 2.00 1.00 4.00 1,843.20
PARTITION 7.00 3.20 24.00 1.00 4.00 2,150.40

190
C.R. PARTITION 3.50 3.20 14.00 1.00 4.00 627.20

SV WALL 21.20 1.80 2.00 1.00 76.32


PLANT BOX 19.00 0.60 2.00 2.00 45.60
CISTERN 40.00 8.00 2.00 1.00 640.00
TOTAL 8,218.97 SQ.M

ITEM 1027 PLASTERING WORKS

LENGTH HEIGHT # SETS #FACES QUANTITY


GROUND FLOOR
EXTERIOR 157.00 3.20 1.00 2.00 1.00 1,004.80
17.00 3.20 2.00 2.00 1.00 217.60
CR PARTITION 3.50 3.20 8.00 2.00 1.00 179.20
PARTITION 7.00 3.20 22.00 2.00 1.00 985.60
CORRIDOR 72.00 3.20 2.00 2.00 1.00 921.60
LESS WINDOWS & DOORS
W-1 1.80 2.10 88.00 2.00 1.00 (665.28)
W-2 1.80 1.20 224.00 2.00 1.00 (967.68)
W-3 0.50 0.50 79.00 2.00 1.00 (39.50)
D-1 1.00 2.10 178.00 2.00 1.00 (747.60)
D-2 0.70 2.10 36.00 2.00 1.00 (105.84)
2nd to 4th flr.
SECOND FLOOR
EXTERIOR 157.00 3.20 1.00 2.00 1.00 4.00 4,019.20
17.00 3.20 2.00 2.00 4.00 870.40
CORRIDOR 72.00 3.20 2.00 2.00 1.00 4.00 3,686.40
PARTITION 7.00 3.20 24.00 2.00 1.00 4.00 4,300.80
C.R. PARTITION 3.50 3.20 14.00 2.00 1.00 4.00 1,254.40
SV WALL 21.20 1.80 2.00 2.00 1.00 152.64
PLANT BOX 19.00 0.60 2.00 2.00 1.00 45.60
CISTERN 40.00 8.00 2.00 2.00 1.00 1,280.00

TOTAL 16,392.34 SQ.M

ITEM 1032 PAINTING WORKS


ITEM 1032 PAINTING WORKS

Masonry Painting LENGTH HEIGHT #SETS #FACES #COATS QUANTITY


WALL (PLASTERED AREA)
16,392.34 SQ.M 2.00 1.00 32,784.68
Wood Painting SUB-TOTAL: 32,784.68 SQ.M
CEILING & EAVES AT 2ND FLR.
7,225.00 SQ.M 2.00 1.00 14,450.00
D1 0.90 2.10 24.00 2.00 2.00 181.44
D2 0.80 2.10 2.00 2.00 2.00 1.00 13.44
D3 0.80 2.10 8.00 2.00 2.00 53.76
D4 0.60 1.20 18.00 2.00 2.00 51.84
D5 0.70 2.10 5.00 2.00 2.00 29.40
SUB-TOTAL: 14,779.88 SQ.M

ITEM SPL.4 RAILINGS

LENGTH HEIGHT # SETS QUANTITY


GI PIPE HANDRAIL
HOR.RAILINGS 85.00 1.20 8.00 1.00 816.00 L.M.
VERT. 1.20 1.00 1.00 1.20
stair along wall 4.00 1.10 6.00 26.40 SQ.M.
GI PIPE WITH SQUARE BAR
at STAIR grnd. & 2nd flr. 3.80 0.90 12.00 1.00 41.04 SQ.M.
TOTAL 884.64 SQ.M

ITEM SPL.5 OCCUPATIONAL SAFETY & HEALTH

Q = ALL Q = ALL

ITEM SPL.6 PROJECT BILLBOARD

Q = 1 EACH Q = 1 EACH

191
Prepared by: Checked by: Submitted by:

192
APPROVED BUDGET FOR THE CONTRACT

PROJECT TITLE: CONSTRUCTION OF 4-STOREY,12-CLASSROOM SCHOOL BUILDING


PANGALANGAN NHS, SAN CARLOS CITY, PANGASINAN
Contract Duration = 210 CD
ITEM NO. DESCRIPTION QUANTITY UNIT MARK-UP IN % TOTAL MARK-UP TOTAL INDIRECT
TOTAL DIRECT
VAT COST TOTAL COST (pesos) UNIT COST (pesos)
COST
OCM CP TOTAL (%) VALUE (pesos)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 ) ( 11 ) ( 12 ) ( 13 )
A-1 Assistance for the Engineers 7.00 Mo. 47,000.00 0% 8% 8% 3,760.00 2,538.00 6,298.00 53,298.00 7,614.00
803(a) Structure Excavation (common earth) 2,280.48 cu.m. 1,753,855.25 9% 8% 17% 298,155.39 102,600.53 400,755.92 2,154,611.17 944.81
804 (a) Embankment (Backfilling) 3,436.48 cu.m. 1,690,032.90 9% 8% 17% 287,305.59 98,866.92 386,172.52 2,076,205.42 604.17
1000 (a) Soil Poisoning 1,657.50 SQ.M 76,319.55 9% 8% 17% 12,974.32 4,464.69 17,439.02 93,758.57 46.04
SPL.1 Soil Exploration 3.00 hole 150,000.00 0% 0% 0% 0.00 0.00 0.00 150,000.00 50,000.00
SPL.2 Hauling of Materials (Double Handling) 1.00 L.S. 69,825.00 9% 8% 17% 11,870.25 4,084.76 15,955.01 85,780.01 69,825.00
804 (d-1) Gravel Fill (hand placed) 144.50 cu.m. 98,015.06 9% 8% 17% 16,662.56 5,733.88 22,396.44 120,411.50 833.30
404 (a.1) Reinforcing Steel for Column Footing 52,964.57 kgs 7,899,576.33 9% 8% 17% 1,342,927.98 462,125.22 1,805,053.19 9,704,629.52 183.23
900 (a.1) Reinforce Concrete Column Footing 535.34 cu.m. 2,328,908.80 9% 8% 17% 395,914.50 136,241.16 532,155.66 2,861,064.46 5,344.39
404 (a.2) Reinforcing Steel for Column 51,148.25 kgs 7,305,927.30 9% 8% 17% 1,242,007.64 427,396.75 1,669,404.39 8,975,331.69 175.48
900 (a.2) Reinforce Concrete for Column 570.24 cu.m. 6,448,788.85 9% 8% 17% 1,096,294.10 377,254.15 1,473,548.25 7,922,337.10 13,892.99
404 (a.3) Reinforcing Steel for Beam 189,416.67 kgs 25,766,423.44 9% 8% 17% 4,380,291.98 1,507,335.77 5,887,627.76 31,654,051.19 167.11
900 (a.3) Reinforce Concrete for Beam 821.45 cu.m. 8,805,419.75 9% 8% 17% 1,496,921.36 515,117.06 2,012,038.41 10,817,458.16 13,168.74
404 (a.4) Reinforcing Steel for Slab on Fill 2,302.79 kgs 163,285.93 9% 8% 17% 27,758.61 9,552.23 37,310.83 200,596.76 87.11
900 (a.4) Reinforce Concrete for Slab on Fill 144.50 cu.m. 606,166.55 9% 8% 17% 103,048.31 35,460.74 138,509.06 744,675.61 5,153.46
404 (a.5) Reinforcing Steel for Suspended Slab 82,171.12 kgs 8,084,139.39 9% 8% 17% 1,374,303.70 472,922.15 1,847,225.85 9,931,365.23 120.86
900 (a.5) Reinforce Concrete for Suspended Slab 803.65 cu.m. 12,665,645.90 9% 8% 17% 2,153,159.80 740,940.28 2,894,100.09 15,559,745.98 19,361.35
404 (a.6) Reinforcing Steel for Stairs & Sunbreaker 29,944.17 kgs 2,527,994.20 9% 8% 17% 429,759.01 147,887.66 577,646.67 3,105,640.87 103.71
900 (a.6) Reinforce Concrete for Stairs & Sunbreaker 232.13 cu.m. 1,781,742.55 9% 8% 17% 302,896.23 104,231.94 407,128.17 2,188,870.72 9,429.42
506(1) Masonry Works (CHB) 8,218.97 sq.m 6,575,504.95 9% 8% 17% 1,117,835.84 384,667.04 1,502,502.88 8,078,007.83 982.85
1027 Cement Plaster Finish 16,392.34 sq.m 2,528,188.02 9% 8% 17% 429,791.96 147,899.00 577,690.96 3,105,878.98 189.47
1003 Carpentry & Joinery Works 11,127.60 sq.m 3,742,424.02 9% 8% 17% 636,212.08 218,931.81 855,143.89 4,597,567.91 413.17
403 (a) Steel Trusses 8,175.59 kgs 703,321.23 9% 8% 17% 119,564.61 41,144.29 160,708.90 864,030.13 105.68
1013 Roofing Works 1,653.00 sq.m 160,658.24 9% 8% 17% 27,311.90 9,398.51 36,710.41 197,368.65 119.40
1009 Windows 836.23 sq.m 1,690,371.13 9% 8% 17% 287,363.09 98,886.71 386,249.80 2,076,620.93 2,483.31
1010 Doors 426.72 sq.m 1,430,886.38 9% 8% 17% 243,250.68 83,706.85 326,957.54 1,757,843.91 4,119.43
1018 Ceramic Tiles 11,700.75 sq.m 19,538,420.00 9% 8% 17% 3,321,531.40 1,142,997.57 4,464,528.97 24,002,948.97 2,051.40
1002 Plumbing Works 1.00 L.S. 341,737.13 9% 8% 17% 58,095.31 19,991.62 78,086.93 419,824.06 419,824.06
1032 a-1 Masonry Painting 32,784.68 sq.m 1,520,212.00 9% 8% 17% 258,436.04 88,932.40 347,368.44 1,867,580.44 56.97
1032 a-2 Wooden Painting 14,779.88 sq.m 795,966.06 9% 8% 17% 135,314.23 46,564.01 181,878.24 977,844.31 66.16
1100 Electrical Works 1.00 L.S. 426,931.65 9% 8% 17% 72,578.38 24,975.50 97,553.88 524,485.53 524,485.53
Spl 3 Damproofing / Moisture Control 1,445.00 sq.m 96,794.70 9% 8% 17% 16,455.10 5,662.49 22,117.59 118,912.29 82.29
Spl 4 Railings 884.64 sq.m. 280,223.00 9% 8% 17% 47,637.91 16,393.05 64,030.96 344,253.96 389.15
Spl.5 Occupational Safety & Health 1.00 LS 440,913.60 0% 8% 8% 35,273.09 23,809.33 59,082.42 499,996.02 499,996.02
Spl.6 Project Billboard 1.00 each 6,718.11 0% 8% 8% 537.45 362.78 900.23 7,618.34 7,618.34
TWENTY TWO MILLION EIGHTY NINE THOUSAND PESOS 21,480,747.58 7,506,538.87 TOTAL: 157,840,614.23

PREPARED/SUBMITTED BY: RECOMMENDING APPROVAL: APPROVED

ALEX S. MAIQUEZ EDITA L. MANUEL MARIETA B. MENDOZA


Chief, Planning & Design Section Assistant District Engineer Distric Engineer
Republic of the Philippines
AMALGAN CONSTRUCTION INCORPORATED
PHINMA-University of Pangasinan
College of Engineering and Architecture
Civil Engineering Department
Arellano St., Dagupan City, Pangasinan
9-Mar-17
INDIVIDUAL PROGRAM OF WORK
Name of Project : A PROPOSED FIVE-STOREY BUILDING OF PRINCETON
INTEGRATED SCHOOL: "AN INNOVATIVE GREEN
Location : ENGINEERING DESIGN"
Palaris St., San Carlos City, Pangasinan Issued Obligated Authority :

Project Category : Building Calendar Days to Complete 284 CD


Appropriation : Php.129,384,045.00 Desirable Starting Date : 22-Mar-17
Source of Fund : Owner Net Length :
DESCRIPTION OF WORK TO BE DONE % OF TOTAL EQUIPMENT/Nos.
A-1 Assistance for the Engineers One (1) Portalift
803(a) Mobilization and Demobilization Two (2) Plate Compactor
804 (d-1) Structure Excavation (common earth) Two (2) Bar Cutter (Manually Operated)
804 (a) Gravel Fill (hand placed) Two (2) Concrete Mixer
1000 (a) Embankment (Backfilling) Two (2) Concrete Vibrator
SPL.1 Soil Poisoning Two (2) Welding Machine
404 (a.1) Soil Exploration Two (2) Transit Mixer
900 (a.1) Reinforcing Steel for Column Footing One (1) Water Truck w/ Pump (1000 gal.)
404 (a.2) Reinforce Concrete Column Footing One (1) Pump, Grout & Conc. Truckmounted
900 (a.2) Reinforcing Steel for Column One (1) Concrete Batching Plant
404 (a.3) Reinforce Concrete for Column Two (2) Electric Drill
900 (a.3) Reinforcing Steel for Beam Two (2) Riveter
404 (a.4) Reinforce Concrete for Beam
TECHNICAL PERSONNEL REQUIRED
900 (a.4) Reinforcing Steel for Slab on Fill
404 (a.5) Reinforce Concrete for Slab on Fill One (1) Const'n.Foreman .
900 (a.5) Reinforcing Steel for Suspended Slab Three (3) Welder
404 (a.6) Reinforce Concrete for Suspended Slab Four (4) Tinsmithman
900 (a.6) Reinforcing Steel for Stairs & Sunbreaker Six (6) Mason
506(1) Reinforce Concrete for Stairs & Sunbreaker Six (6) Carpenter
1027 Masonry Works (CHB) Five (5) Steelman
1003 Cement Plaster Finish Twenty (20) Laborer
403 (a) Carpentry & Joinery Works
1013 Steel Trusses
1009 Roofing Works
BRIEF DESCRIPTION OF WORK TO BE DONE:
1010 Windows
1018 Doors 1. Const'n of Princeton Integrated School elevated 0.8 m from NGL.
1002 Ceramic Tiles 2. Complete Reinforcing steel and concrete.
1032 a-1 Plumbing Works 3. Complete Masonry works with plastering.
1032 a-2 Masonry Painting 4. Complete Roofing works with flashing and gutter including downspout.
1100 Wooden Painting 5. Complete Ceiling works, Doors and Windows with accessories.
Spl 3 Electrical Works 6. Complete Electrical & Plumbing works w/ fixtures.
Spl 4 Damproofing / Moisture Control 7. Ceramic tile works at all floor levels.
Spl.5 Railings 8. Complete painting works.
Spl.6 Occupational Safety & Health 9. Fabrication & Installation of project billboard (1-set)each.
Project Billboard 10. Provision of Occupational safety & health.
11.With complete railing (G.I.)
12. Complete windows.
13. With concrete pathways.
total % wt. 0.00%
ESTIMATED COST OF PROPOSED WORK
ITEM NO. DESCRIPTION UNIT QUANTITY
AMOUNT
A-1 Assistance for the Engineers Mo. 7.00
803(a) Structure Excavation (common earth) cu.m. 2,280.48
804 (a) Embankment (Backfilling) cu.m. 3,436.48
1000 (a) Soil Poisoning SQ.M 1,657.50
SPL.1 Soil Exploration hole 3.00
SPL.2 Hauling of Materials (Double Handling) L.S. ALL
804 (d-1) Gravel Fill (hand placed) cu.m. 144.50
404 (a.1) Reinforcing Steel for Column Footing kgs 52,964.57
900 (a.1) Reinforce Concrete Column Footing cu.m. 535.34
404 (a.2) Reinforcing Steel for Column kgs 51,148.25
900 (a.2) Reinforce Concrete for Column cu.m. 570.24
404 (a.3) Reinforcing Steel for Beam kgs 189,416.67
900 (a.3) Reinforce Concrete for Beam cu.m. 821.45
404 (a.4) Reinforcing Steel for Slab on Fill kgs 2,302.79
900 (a.4) Reinforce Concrete for Slab on Fill cu.m. 144.50
404 (a.5) Reinforcing Steel for Suspended Slab kgs 82,171.12
900 (a.5) Reinforce Concrete for Suspended Slab cu.m. 803.65
404 (a.6) Reinforcing Steel for Stairs & Sunbreaker kgs 29,944.17
900 (a.6) Reinforce Concrete for Stairs & Sunbreaker cu.m. 232.13
506(1) Masonry Works (CHB) sq.m 8,218.97
1027 Cement Plaster Finish sq.m 16,392.34
1003 Carpentry & Joinery Works sq.m 11,127.60
403 (a) Steel Trusses kgs 8,175.59
1013 Roofing Works sq.m 1,653.00
1009 Windows sq.m 836.23
1010 Doors sq.m 426.72
1018 Ceramic Tiles sq.m 11,700.75
1002 Plumbing Works L.S. All
1032 a-1 Masonry Painting sq.m 32,784.68
1032 a-2 Wooden Painting sq.m 14,779.88
1100 Electrical Works L.S. All
Spl 3 Damproofing / Moisture Control sq.m 1,445.00
Spl 4 Railings sq.m. 884.64
Spl.5 Occupational Safety & Health LS All
Spl.6 Project Billboard each 1.00
TOTAL AMNT.

Page 193
TOTAL AMNT.

Page 194
DETAILED ESTIMATES
Item No. A-1
Assistance for the Engineers QUANTITY 7.00 Mo.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Progress Photograph (Photo printing for
reports ) 1.00 set 7,000.00 7,000.00
-
Ink Cartidge, (Black & Colored) 1.00 L.S. 5,000.00 5,000.00
MATERIAL COST

Sub- Total 12,000.00


unit cost 1,714.29
DESCRIPTION mo. RATE(Pesos) TOTAL(Pesos)

Utilityman 1.00 7.00 1,000.00 7,000.00


Electricity & Water Supply 1.00 7.00 1,500.00 10,500.00
LABOR COST

Sub- Total 17,500.00


unit cost 2,500.00
DESCRIPTION mo. RATE(Pesos) TOTAL(Pesos)

Space Rental(for Bankhouse/Office) 1.00 7.00 2,500.00 17,500.00


EQUIPMENT COST

Sub- Total 17,500.00


unit cost 2,500.00
Direct Unit Cost 6,714.29
PREPARED BY: 0% of total DC OCM -
8% of total DC CP 537.14
5% of (total DC+OCM+CP) VAT 362.57
Total Direct & Indirect Unit Cost 7,614.00
Total Direct & Indirect Cost 53,298.00
DETAILED UNIT PRICE ANALYSIS
Item No. 803(a)
Structure Excavation (common earth) QUANTITY 2,280.48 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 1.8750 cu.m / hour

MATERIAL COST 2,509.00 350.00 878,150.00

Sub- Total 878,150.00


unit cost 385.07
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Unskilled Laborer 15.00 1216.260 47.50 866,585.25


15.00 152.03 2,280.49

Sub- Total 866,585.25


unit cost 380.00
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Plate compactor 1.00 120.00 100.00 9,120.00

Sub- Total 9,120.00


unit cost 4.00
Direct Unit Cost 769.07
Total Direct & Indirect Unit Cost 769.07
Sub- Total 1,753,855.25
DETAILED UNIT PRICE ANALYSIS
Item No. 804 (a)
Embankment (Backfilling) QUANTITY 3,436.48 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 8.3000 cu.m / hour

MATERIAL COST River mix (plus 10% loose volume) 3,780.00 cu.m 400.00 1,512,000.00

Sub- Total 1,512,000.00


unit cost 439.99
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Unskilled Laborer 8.00 414.03 47.50 157,331.40


8.00 51.75

Sub- Total 157,331.40


unit cost 45.78
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Plate compactor 1.00 207.02 100.00 20,701.50

Sub- Total 20,701.50


unit cost 6.02
Direct Unit Cost 491.79
Total Direct & Indirect Unit Cost 491.79
Total Direct & Indirect Cost 1,690,032.90
UNIT PRICED ANALYSIS
Item No. 1000 (a)
Soil Poisoning QUANTITY 1,657.50 SQ.M
DESCRIPTION QUANTITY UNIT U- PRICE(P)TOTAL(Pesos)
Output rate: 8.1000 sq.m. / hour

Termite x 15.00 liters 1,200.00 18,000.00


MATERIAL COST

Sub- Total 18,000.00


unit cost 10.86
DESCRIPTION NO HOURSRATE(Pesos)
TOTAL(Pesos)
Output rate:
LABOR COST

Unskilled Laborer 6.00 204.630 47.50 58,319.55


6.00 25.58 153.47

Sub- Total 58,319.55


unit cost 35.19
DESCRIPTION NO HOURSRATE(Pesos)
TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total -
unit cost -
Direct Unit Cost 46.04
Total Direct & Indirect Unit Cost 46.04
Total Direct & Indirect Cost 76,319.55
DETAILED ESTIMATES
Item No. SPL.1
Soil Exploration QUANTITY 3.00 hole
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)

Soil Exploration 3.00 hole 50,000.00 150,000.00


MATERIAL COST

Sub- Total 150,000.00


unit cost 50,000.00
DESCRIPTION NO HOUR RATE(Pesos) TOTAL(Pesos)
LABOR COST

-
-

Sub- Total -
unit cost
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Sub- Total -
unit cost
Direct Unit Cost 50,000.00
Total Direct & Indirect Unit Cost 50,000.00
Total Direct & Indirect Cost 150,000.00
DETAILED ESTIMATES
Item No. SPL.2
Hauling of Materials (Double Handling) QUANTITY ALL L.S.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
-
-
-
MATERIAL COST

Sub- Total -
unit cost
DESCRIPTION NO HOUR RATE(Pesos) TOTAL(Pesos)

Unskilled Laborer 5.00 380.00 36.75 69,825.00


LABOR COST

Sub- Total 69,825.00


unit cost 69,825.00
DESCRIPTION mo. RATE(Pesos) TOTAL(Pesos)

-
EQUIPMENT COST

Sub- Total -
unit cost
Direct Unit Cost 69,825.00
Total Direct & Indirect Unit Cost 69,825.00
Total Direct & Indirect Cost 69,825.00
DETAILED UNIT PRICE ANALYSIS
Item No. 804 (d-1)
Gravel Fill (hand placed) QUANTITY 144.50 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 1.3600 cu.m / hour

MATERIAL COST Gravel Fill 144.50 cu.m 300.00 43,350.00

Sub- Total 43,350.00


unit cost 300.00
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
Construction foreman 1.00 106.25 77.50 8,234.38
LABOR COST

Unskilled Laborer 8.00 106.25 47.50 40,375.00


8.00 13.28 106.25

Sub- Total 48,609.38


unit cost 336.40
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Plate compactor 3.00 26.56 76.00 6,055.68

Sub- Total 6,055.68


unit cost 41.91
Direct Unit Cost 678.30
Total Direct & Indirect Unit Cost 678.30
Total Direct & Indirect Cost 98,015.06
DETAILED UNIT PRICE ANALYSIS
Item No. 404 (a.1)
Reinforcing Steel for Column Footing QUANTITY 52,964.57 kgs
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: fabrication = 51.0000 kgs / hour
placing = 71.8050 kgs / hour
MATERIAL COST
Assorted RSB 52,964.57 kgs 130.00 6,885,394.10
#16 Tie Wire 794.50 kgs 70.00 55,615.00

Sub- Total 6,941,009.10


unit cost 131.05
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
Construction foreman 1.00 1,259.81 77.50 97,635.28
Skilled Laborer (steelman) 6.00 1,259.81 57.50 434,634.45
LABOR COST

Unskilled Laborer 4.00 1,259.81 47.50 239,363.90


11.00 157.48 1,732.24

Sub- Total 771,633.63


unit cost 14.57
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Bar cutter (manually operated) 3.00 1,038.52 60.00 186,933.60

Sub- Total 186,933.60


unit cost 3.53
Direct Unit Cost 149.15
Total Direct & Indirect Unit Cost 149.15
Total Direct & Indirect Cost 7,899,576.33
DETAILED UNIT PRICE ANALYSIS
Item No. 900 (a.1)
Reinforce Concrete Column Footing QUANTITY 535.34 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 0ne-bagger mixing = 6.6682 cu.m / hour
placing = 5.8100 cu.m / hour

Portland cement 6,424.10 bags 250.00 1,606,025.00


MATERIAL COST

Washed sand 267.70 cu.m 700.00 187,390.00


Crushed gravel 535.40 cu.m 800.00 428,320.00

Sub- Total 2,221,735.00


unit cost 4,150.14
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:

Construction foreman 1.00 80.28 77.50 6,221.70


LABOR COST

Skilled Laborer 6.00 80.28 57.50 27,696.60


Unskilled Laborer 7.00 80.28 47.50 26,693.10
14.00 10.04 140.49

Sub- Total 60,611.40


unit cost 113.22
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

One-bagger mixer 2.00 80.28 200.00 32,112.00


Concrete Vibrator 2.00 80.28 90.00 14,450.40

Sub- Total 46,562.40


unit cost 86.98
Direct Unit Cost 4,350.34
Total Direct & Indirect Unit Cost 4,350.34
Total Direct & Indirect Cost 2,328,908.80
DETAILED UNIT PRICE ANALYSIS
Item No. 404 (a.2)
Reinforcing Steel for Column QUANTITY 51,148.25 kgs
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: fabrication = 42.5000 kgs / hour
placing = 53.1250 kgs / hour
MATERIAL COST
Assorted RSB 51,148.25 kgs 120.00 6,137,790.00
#16 Tie Wire 767.20 kgs 70.00 53,704.00

Sub- Total 6,191,494.00


unit cost 121.05
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
Construction foreman 1.00 1,492.33 77.50 115,655.58
Skilled Laborer (steelman) 5.00 1,492.33 57.50 429,044.88
LABOR COST

Unskilled Laborer 6.00 1,492.33 47.50 425,314.05


12.00 186.54 2,238.50

Sub- Total 970,014.50


unit cost 18.96
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Bar cutter (manually operated) 2.00 1203.49 60.00 144,418.80

Sub- Total 144,418.80


unit cost 2.82
Direct Unit Cost 142.84
Total Direct & Indirect Unit Cost 142.84
Total Direct & Indirect Cost 7,305,927.30
DETAILED UNIT PRICE ANALYSIS
Item No. 900 (a.2)
Reinforce Concrete for Column QUANTITY 570.24 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 0ne-bagger mixing = 4.7630 cu.m / hour
placing = 1.6575 cu.m / hour
Area = 10,332.7500 sq.m
formwork installation = 4.6475 sq.m / hour
stripping = 12.9350 sq.m / hour
MATERIAL COST

Portland cement 6,842.90 bags 250.00 1,710,725.00


Washed sand 285.10 cu.m 700.00 199,570.00
Crushed gravel 570.20 cu.m 800.00 456,160.00
Coco lumber 42,768.00 bd.ft 35.00 1,496,880.00
Assosted CWN 855.40 kgs 70.00 59,878.00
Plywood 4' x 8' x 1/4" 1,898.90 pcs 340.00 645,626.00

Sub- Total 4,568,839.00


unit cost 8,012.13
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:

Construction foreman 1.00 2622.70 77.50 203,259.25


LABOR COST

Skilled Laborer 2.00 2622.70 57.50 301,610.50


Unskilled Laborer 10.00 2622.70 47.50 1,245,782.50
13.00 327.84 4,261.89

Sub- Total 1,750,652.25


unit cost 3,070.03
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

One-bagger mixer 2.00 119.72 200.00 47,888.00


Portalift 1.00 119.72 500.00 59,860.00
Concrete Vibrator 2.00 119.72 90.00 21,549.60

Sub- Total 129,297.60


unit cost 226.74
Direct Unit Cost 11,308.90
Total Direct & Indirect Unit Cost 11,308.90
Total Direct & Indirect Cost 6,448,788.85
DETAILED UNIT PRICE ANALYSIS
Item No. 404 (a.4)
Reinforcing Steel for Slab on Fill QUANTITY 2,302.79 kgs
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: fabrication = 42.5000 kgs / hour
placing = 53.1250 kgs / hour
MATERIAL COST
Assorted RSB 2,302.79 kgs 55.00 126,653.45
#16 Tie Wire 34.50 kgs 70.00 2,415.00

Sub- Total 129,068.45


unit cost 56.05
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
Construction foreman 1.00 67.19 77.50 5,207.23
Skilled Laborer (steelman) 5.00 67.19 57.50 19,317.13
LABOR COST

Unskilled Laborer 1.00 67.19 47.50 3,191.53


5.00 8.40 41.99

Sub- Total 27,715.88


unit cost 12.04
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Bar cutter (manually operated) 2.00 54.18 60.00 6,501.60

Sub- Total 6,501.60


unit cost 2.82
Direct Unit Cost 70.91
PREPARED BY: 9% of total DC OCM 6.38
8% of total DC CP 5.67
5% of (total DC+OCM+CP) VAT 4.15
Total Direct & Indirect Unit Cost 87.11
Total Direct & Indirect Cost 200,596.76
DETAILED UNIT PRICE ANALYSIS
Item No. 404 (a.3)
Reinforcing Steel for Beam QUANTITY 189,416.67 kgs
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: fabrication = 51.0000 kgs / hour
placing = 63.7500 kgs / hour
MATERIAL COST
Assorted RSB 189,416.67 kgs 115.00 21,782,916.94
#16 Tie Wire 2,841.30 kgs 70.00 198,891.00

Sub- Total 21,981,807.94


unit cost 116.05
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:

Skilled Laborer (steelman) 6.00 4,605.42 57.50 1,588,869.90


LABOR COST

Unskilled Laborer 8.00 4,605.42 47.50 1,750,059.60


14.00 575.68 8,059.49

Sub- Total 3,338,929.50


unit cost 17.63
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Bar cutter (manually operated) 2.00 3714.05 60.00 445,686.00

Sub- Total 445,686.00


unit cost 2.35
Direct Unit Cost 136.03
Total Direct & Indirect Unit Cost 136.03
Total Direct & Indirect Cost 25,766,423.44
DETAILED UNIT PRICE ANALYSIS
Item No. 900 (a.3)
Reinforce Concrete for Beam QUANTITY 821.45 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 0ne-bagger mixing = 7.1445 cu.m / hour
placing = 2.8050 cu.m / hour
Area = 9,413.8200 sq.m
formwork installation = 5.9950 sq.m / hour
stripping = 18.1500 sq.m / hour
MATERIAL COST

Portland cement 9,857.40 bags 250.00 2,464,350.00


Washed sand 410.70 cu.m 700.00 287,490.00
Crushed gravel 821.50 cu.m 800.00 657,200.00
Coco lumber 61,608.80 bd.ft 35.00 2,156,308.00
Assosted CWN 1,232.20 kgs 70.00 86,254.00
Plywood 4' x 8' x 1/4" 2,735.40 pcs 340.00 930,036.00

Sub- Total 6,581,638.00


unit cost 8,012.22
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:

Construction foreman 1.00 1829.61 77.50 141,794.78


LABOR COST

Skilled Laborer 6.00 1829.61 57.50 631,215.45


Unskilled Laborer 15.00 1829.61 47.50 1,303,597.13
22.00 228.70 5,031.43

Sub- Total 2,076,607.35


unit cost 2,527.98
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

One-bagger mixer 3.00 114.98 200.00 68,988.00


Portalift 1.00 114.98 500.00 57,490.00
Concrete Vibrator 2.00 114.98 90.00 20,696.40

Sub- Total 147,174.40


unit cost 179.16
Direct Unit Cost 10,719.36
Total Direct & Indirect Unit Cost 10,719.36
Total Direct & Indirect Cost 8,805,419.75
DETAILED UNIT PRICE ANALYSIS
Item No. 900 (a.4)
Reinforce Concrete for Slab on Fill QUANTITY 144.50 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 0ne-bagger mixing = 3.3341 cu.m / hour
placing = 2.9050 cu.m / hour

Portland cement 1,589.50 bags 250.00 397,375.00


MATERIAL COST

Washed sand 72.30 cu.m 700.00 50,610.00


Crushed gravel 144.50 cu.m 800.00 115,600.00

Sub- Total 563,585.00


unit cost 3,900.24
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:

Construction foreman 1.00 43.34 77.50 3,358.85


LABOR COST

Skilled Laborer 2.00 43.34 57.50 4,984.10


Unskilled Laborer 4.00 43.34 47.50 8,234.60
7.00 5.42 37.92

Sub- Total 16,577.55


unit cost 114.72
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

One-bagger mixer 3.00 43.34 200.00 26,004.00

Sub- Total 26,004.00


unit cost 179.96
Direct Unit Cost 4,194.92
Total Direct & Indirect Unit Cost 4,194.92
Total Direct & Indirect Cost 606,166.55
DETAILED UNIT PRICE ANALYSIS
Item No. 404 (a.5)
Reinforcing Steel for Suspended Slab QUANTITY 82,171.12 kgs
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: fabrication = 42.5000 kgs / hour
placing = 53.1250 kgs / hour
MATERIAL COST
Assorted RSB 82,171.12 kgs 70.00 5,751,978.19
#16 Tie Wire 1,232.60 kgs 70.00 86,282.00

Sub- Total 5,838,260.19


unit cost 71.05
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
Construction foreman 1.00 2,397.46 77.50 185,803.15
Skilled Laborer (steelman) 5.00 2397.46 57.50 689,269.75
LABOR COST

Unskilled Laborer 10.00 2397.46 47.50 1,138,793.50


15.00 299.68 4,495.24

Sub- Total 2,013,866.40


unit cost 24.51
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Bar cutter (manually operated) 2.00 1933.44 60.00 232,012.80

Sub- Total 232,012.80


unit cost 2.82
Direct Unit Cost 98.38
Total Direct & Indirect Unit Cost 98.38
Total Direct & Indirect Cost 8,084,139.39
DETAILED UNIT PRICE ANALYSIS
Item No. 900 (a.5)
Reinforce Concrete for Suspended Slab QUANTITY 803.65 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 0ne-bagger mixing = 7.1445 cu.m / hour
placing = 2.4225 cu.m / hour
Area = 9,209.8300 sq.m
formwork installation = 5.1775 sq.m / hour
stripping = 15.6750 sq.m / hour
Area = 8,036.5000 sq.m
forming & shoring = 3.5700 sq.m / hour
MATERIAL COST

stripping = 11.5500 sq.m / hour

Portland cement 10,045.60 bags 250.00 2,511,400.00


Washed sand 401.80 cu.m 700.00 281,260.00
Crushed gravel 803.70 cu.m 800.00 642,960.00
Coco lumber 80,365.00 bd.ft 35.00 2,812,775.00
Assosted CWN 1,205.50 kgs 70.00 84,385.00
Plywood 4' x 8' x 1/2" 2,791.00 pcs 650.00 1,814,150.00

Sub- Total 8,146,930.00


unit cost 10,137.41
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:

Construction foreman 1.00 2251.12 77.50 174,461.80


1.00 281.39 281.39
Placing Concrete
LABOR COST

Skilled Laborer 4.00 331.74 57.50 76,300.20


Unskilled Laborer 15.00 331.74 47.50 236,364.75
19.00 41.47 787.88
Shoring & Formworks
Skilled Laborer 8.00 2251.12 57.50 1,035,515.20
Unskilled Laborer 6.00 2251.12 47.50 641,569.20
14.00 281.39 5,008.73

Sub- Total 2,164,211.15


unit cost 2,692.98
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
EQUIPMENT COST

Transit mixer (5 cu.m. cap) 2.00 331.74 1,279.00 848,590.92


Concrete Vibrator 3.00 331.74 82.00 81,608.04
Water Trunk w/ pump (1000 gal) 1.00 331.74 968.00 321,124.32
Pump, Grout & Concrete Truckmounted 1.00 331.74 2,735.00 907,308.90
Concrete Batching Plant 1.00 331.74 590.44 195,872.57
Sub- Total 2,354,504.75
unit cost 2,929.76
Direct Unit Cost 15,760.15
Total Direct & Indirect Unit Cost 15,760.15
Total Direct & Indirect Cost 12,665,645.90
DETAILED UNIT PRICE ANALYSIS
Item No. 404 (a.6)
Reinforcing Steel for Stairs & Sunbreaker QUANTITY 29,944.17 kgs
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: fabrication = 34.0000 kgs / hour
placing = 42.5000 kgs / hour
MATERIAL COST
Assorted RSB 29,944.17 kgs 60.00 1,796,650.20
#16 Tie Wire 449.20 kgs 70.00 31,444.00

Sub- Total 1,828,094.20


unit cost 61.05
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
Construction foreman 1.00 1,092.08 77.50 84,636.20
Skilled Laborer (steelman) 4.00 1,092.08 57.50 251,178.40
LABOR COST

Unskilled Laborer 6.00 1,092.08 47.50 311,242.80


10.00 136.51 1,365.10

Sub- Total 647,057.40


unit cost 21.61
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Bar cutter (manually operated) 1.00 880.71 60.00 52,842.60

Sub- Total 52,842.60


unit cost 1.76
Direct Unit Cost 84.42
Total Direct & Indirect Unit Cost 84.42
Total Direct & Indirect Cost 2,527,994.20
DETAILED UNIT PRICE ANALYSIS
Item No. 900 (a.6)
Reinforce Concrete for Stairs & Sunbreaker QUANTITY 232.13 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 0ne-bagger mixing = 2.8578 cu.m / hour
placing = 1.1475 cu.m / hour
Area = 363.0000 sq.m
formwork installation = 2.4525 sq.m / hour
stripping = 7.4250 sq.m / hour
MATERIAL COST

Portland cement 2,785.60 bags 250.00 696,400.00


Washed sand 116.10 cu.m 700.00 81,270.00
Crushed gravel 232.10 cu.m 800.00 185,680.00
Coco lumber 17,409.90 bd.ft 35.00 609,346.50
Assosted CWN 348.20 kgs 70.00 24,374.00
Plywood 4' x 8' x 1/2" 15.00 pcs 600.00 9,000.00

Angular bar nosing at step w/ flat bar strap 420.00 kgs 52.00 21,840.00

Sub- Total 1,627,910.50


unit cost 7,012.86
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:

Construction foreman 1.00 172.46 77.50 13,365.65


LABOR COST

Skilled Laborer 2.00 172.46 57.50 19,832.90


Unskilled Laborer 6.00 172.46 47.50 49,151.10
9.00 21.56 194.02

Sub- Total 82,349.65


unit cost 354.75
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

One-bagger mixer 1.00 81.23 200.00 16,246.00


Portalift 1.00 81.23 500.00 40,615.00
Concrete Vibrator 2.00 81.23 90.00 14,621.40

Sub- Total 71,482.40


unit cost 307.94
Direct Unit Cost 7,675.55
Total Direct & Indirect Unit Cost 7,675.55
Total Direct & Indirect Cost 1,781,742.55
DETAILED UNIT PRICE ANALYSIS
Item No. 506(1)
Masonry Works (CHB) QUANTITY 8,218.97 sq.m
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: CHB Laying = 3.1878 sq.m / hour
MATERIAL COST

CHB 6" x 8" x 16" 102,737.00 pcs 17.00 1,746,529.00


Portland Cement 6,271.00 bags 250.00 1,567,750.00
Washed Sand 693.70 cu.m 700.00 485,590.00
RSB 10mm dia. 22,102.50 kgs 42.00 928,305.00
#16 G.I. Tie Wire 331.60 kgs 70.00 23,212.00
Concrete Louver Block - pcs 30.00 -

Sub- Total 4,751,386.00


unit cost 578.10
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
Construction foreman 1.00 2578.26 77.50 199,815.15
Skilled Laborer (mason) 6.00 2578.26 57.50 889,499.70
LABOR COST

Unskilled Laborer 6.00 2578.26 47.50 734,804.10


12.00 322.28 3,867.39

Sub- Total 1,824,118.95


unit cost 221.94
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total -
unit cost -
Direct Unit Cost 800.04
Total Direct & Indirect Unit Cost 800.04
Total Direct & Indirect Cost 6,575,504.95
DETAILED UNIT PRICE ANALYSIS
Item No. 1027
Cement Plaster Finish QUANTITY 16,392.34 sq.m
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: Plastering = 8.3125 sq.m / hour

MATERIAL COST
Portland Cement 4,721.00 bags 250.00 1,180,250.00
Washed Sand 361.00 cu.m 700.00 252,700.00
Concrete mouldings 6.12 sq.m 500.00 3,060.00

Sub- Total 1,436,010.00


unit cost 87.60
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:

Skilled Laborer (mason) 7.00 1972.01 47.62 657,349.81


LABOR COST

Unskilled Laborer 6.00 1972.01 36.75 434,828.21


13.00 246.50 3,204.52

Sub- Total 1,092,178.02


unit cost 66.63
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total -
unit cost -
Direct Unit Cost 154.23
Total Direct & Indirect Unit Cost 154.23
Total Direct & Indirect Cost 2,528,188.02
DETAILED UNIT PRICE ANALYSIS
Item No. 1003
Carpentry & Joinery Works QUANTITY 11,127.60 sq.m
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: Frame Works = 10.2000 sq.m / hour
Plywood Installation = 8.5000 sq.m / hour

3/16" X 4"X 8",Fiber Cement Plywood 4,057.00 pcs 340.00 1,379,380.00


Double Furring (19x50x.40mmx 5.0m.) 3,783.38 pcs. 120.00 454,006.08
Wall Angle (25x25x0.40mm x 2.44m.) 2,448.07 pcs. 55.00 134,643.96

Carrying Channel (12x38x0.80mmx5.0m.) 2,114.24 pcs. 125.00 264,280.50


MATERIAL COST

W-Clip 17,804.16 pcs. 6.00 106,824.96


Blind Rivets (1/8x3/8) 37,388.74 pcs. 3.00 112,166.21
Insect Screen 10.00 sq.m. 170.00 1,700.00
Assorted CWN 1,168.40 kgs 70.00 81,788.00
Fab.Louver Vent(0.30x1.17m) 16.00 pcs. 900.00 14,400.00
Blackboard 12.00 set 3,500.00 42,000.00
120 x 150 x 70mm Chalkdust Bob 12.00 pcs 350.00 4,200.00
Misc. 50mm x 6mm thk.plywood, hanger
rod etc. All L.S. 4,200.00 4,200.00
FOR DRY WALL PARTITON
2" x 2" Nailers 88.26 pcs. 85.00 7,502.36
1/4" X 4"X 8",Ordinary Plywood 13.13 pcs. 335.00 4,396.88

Sub- Total 2,611,488.94


unit cost 234.69
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
Construction foreman 1.00 1483.68 65.55 97,255.22
Skilled Laborer (carpenter) 10.00 1483.68 47.62 706,528.42
LABOR COST

Unskilled Laborer 6.00 1483.68 36.75 327,151.44


16.00 185.46

Sub- Total 1,130,935.08


unit cost 101.63
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total -
unit cost -
Direct Unit Cost 336.32
Total Direct & Indirect Unit Cost 336.32
Total Direct & Indirect Cost 3,742,424.02
DETAILED UNIT PRICE ANALYSIS
Item No. 403 (a)
Steel Trusses QUANTITY 8,175.59 kgs
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: fabrication = 170.0000 kgs / hour
erection/Installation = 0.3000 kgs / hour
painting = 29.7500 L.M/ hour

186 LC 150 x 50 x 20 x 2.0mm x 6.00m Purlins 5,312.16 kgs 52.00 276,232.32


9 LC 150 x 50 x 20 x 2.0mm x 6.00m Purlins(BCST) 257.04 kgs. 52.00 13,366.08
13 LC 100 x 50 x 12 x 1.2mm x 6.00m Purlins 278.46 kgs 52.00 14,479.92
54 50 x 50 x6.0mm x 6.00m AB Top & Bott.chord 1,526.58 kgs 52.00 79,382.16
2 75 x 75 x 4.5mm x 6.0m AB (shelf angle) 69.60 kgs 52.00 3,619.20
6 50 x 50 x6.0mm x 6.00m AB (V1) 169.62 kgs 52.00 8,820.24
19 50 x 50 x4.50mm x 6.00m AB (V2) 85.50 kgs 53.00 4,531.50
11 50 x 50 x6.0mm x 6.00m AB (D1) 310.97 kgs 52.00 16,170.44
8 50 x 50 x4.5mm x 6.00m AB (D2) 36.00 kgs 52.00 1,872.00
MATERIAL COST

7 50 x 50 x4.5mm x 6.00m AB (H1) 31.50 kgs. 52.00 1,638.00


6 40 x 40 x5mm x 600mm 98.16 kgs. 52.00 5,104.32
12mm dia sagrod w/ nuts & washers at each end 464.00 pcs 80.00 37,120.00
125x 125 x 50 x 4mm Bent Plate Leg 293.00 pcs. 120.00 35,160.00
75 x 75 x 6mm MS Plate 63.00 pcs. 80.00 5,040.00
12mm dia. A-307 bolts w/n/w 812.00 pcs 10.00 8,120.00
16mm dia x 350mm anchor bolts 108.00 pcs 120.00 12,960.00
12mm dia A 307 bolts x 250mm w/n/w (AB2) 28.00 pcs 50.00 1,400.00
Gusset plates 200mm x 200mm x 10.00mm 112.00 pcs 250.00 28,000.00
Base plates 400mm x 4000mm x 12.00mm 21.00 pcs 350.00 7,350.00
16mm dia cross bracing w/ standard turn buckle 16.00 pcs. 185.00 2,960.00
Welding rod 110.00 pcs 120.00 13,200.00
Oxygen (content only) 25.00 kgs 45.00 1,125.00
Acetylene (content only) 25.00 kgs 65.00 1,625.00
Red lead primer 8.00 gal 430.00 3,440.00
Paint thinner 2.00 gal 200.00 400.00
Paint brush 6.00 pcs 80.00 480.00
Misc.stiffener bar,plate connector. Bolts,etc. All L.S. 12,000.00
Sub- Total 595,596.18
unit cost 72.85
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
Construction foreman 1.00 95.08 65.55 6,232.49
Skilled Laborer (welder) 3.00 95.08 47.62 13,583.13
LABOR COST

Unskilled Laborer 7.00 95.08 36.75 24,459.33


10.00 11.89 118.85

Sub- Total 44,274.95


unit cost 5.42
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
EQUIPMENT COST

Welding machine 2 95.08 62.50 11,885.00


Electric Consumption, Acetylene, Oxygen & etc. 1 lot 20,000.00 20,000.00
Scaffolding 1 lot 31,565.10 31,565.10

Sub- Total 63,450.10


unit cost 7.76
Direct Unit Cost 86.03
PREPARED BY: 9% of total DC OCM 7.74
8% of total DC CP 6.88
5% of (total DC+OCM+CP) VAT 5.03
Total Direct & Indirect Unit Cost 105.68
Total Direct & Indirect Cost 864,030.13
DETAILED UNIT PRICE ANALYSIS
Item No. 1013
Roofing Works QUANTITY 1,653.00
DESCRIPTION QUANTITY UNIT U- PRICE(P)
Output rate: fabrication = 12.4500 sq.m / hour

MATERIAL COST
Concrete Gutter (250mm) 3.33 CU. M 350.00
WATER PROOFING 1,653.00 SQ. M 21.20

Sub- Total
unit cost
DESCRIPTION NO HOURS RATE(Pesos)
Output rate:
Construction foreman 1.00 132.77 77.50
Skilled Laborer (tinsmithman) 3.00 132.77 57.50
LABOR COST

Unskilled Laborer 9.00 132.77 47.50


12.00 16.60 199.16

Sub- Total
unit cost
DESCRIPTION NO HOURS RATE(Pesos)
EQUIPMENT COST

Output rate:

Electric Drill 2.00 132.77 10.63


Riveter 2.00 132.77 10.63
Scaffoldings 1 lot 28,853.83

Sub- Total
unit cost
Direct Unit Cost
PREPARED BY: 9% of total DC OCM
8% of total DC CP
5% of (total DC+OCM+CP) VAT
Total Direct & Indirect Unit Cost
Total Direct & Indirect Cost
DETAILED UNIT PRICE ANALYSIS
sq.m
TOTAL(Pesos)

1,163.75
35,043.60

36,207.35
21.90
TOTAL(Pesos)

10,289.68
22,902.83
56,759.18

89,951.68
54.42
TOTAL(Pesos)

2,822.69
2,822.69
28,853.83

34,499.21
20.87
97.19
8.75
7.78
5.69
119.40
197,368.65
DETAILED UNIT PRICE ANALYSIS
Item No. 1010
Doors QUANTITY 426.72 sq.m
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: installation = 0.7089 sq.m / hour

(D-1) Tanguile Panel Door on 50x150mm thk wood


jamb w/ complete accessories 178.00 set 7,425.00 1,321,650.00
A=2.10mx0.90mx24sets= 336.42 sq.m
MATERIAL COST

(D-2) Hollow Core Flush Type Swing Door provide w/


kick plate w/ complete accessories (for disabled)
2.00 set 2,700.00 5,400.00
A=2.10mx0.90mx2set= 3.78 sq.m

#VALUE! 180.00
Sub- Total 1,327,050.00
unit cost 3,109.88
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Skilled Laborer (Carpenter) 3.00 601.95 57.50 103,836.38


3.00 75.24 225.73

Sub- Total 103,836.38


unit cost 243.34
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total -
unit cost -
Direct Unit Cost 3,353.22
Total Direct & Indirect Unit Cost 3,353.22
Total Direct & Indirect Cost 1,430,886.38
DETAILED UNIT PRICE ANALYSIS
Item No. 1009
Windows QUANTITY 836.23
DESCRIPTION QUANTITY UNIT U- PRICE(P)
Output rate: installation = 2.0250 sq.m / hour

(W-1) Window w/ clear glass blades on jalou-plus-silver


coated frame and 50x150mm thk wood jamb w/
MATERIAL COST complete accessories 88.00 set 5,435.00
A=1.20mx2.50mx24sets= 264.00 sq.m
(W-2) Window w/ clear glass blades on jalou-plus-silver
coated frame and 50x150mm thk wood jamb w/
complete accessories 224.00 set 3,705.00
A=1.20mx1.40mx24sets= 376.32 sq.m
(W-3) Window w/ clear glass blades on jalouplus-silver
coated frame and 50x150mm thk wood jamb w/
complete accessories 79.00 set 3,034.22
A=1.90mx0.635mx8set= 95.31 sq.m
Sub- Total
unit cost
DESCRIPTION NO HOURS RATE(Pesos)
Output rate:
LABOR COST

Skilled Laborer (Carpenter) 6.00 412.95 57.50


6.00 51.62 309.71

Sub- Total
unit cost
DESCRIPTION NO HOURS RATE(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total
unit cost
Direct Unit Cost
Total Direct & Indirect Unit Cost
Total Direct & Indirect Cost
DETAILED UNIT PRICE ANALYSIS
sq.m
TOTAL(Pesos)

478,280.00

829,920.00

239,703.38

1,547,903.38
1,851.05
TOTAL(Pesos)

142,467.75

142,467.75
170.37
TOTAL(Pesos)

-
-
2,021.42
2,021.42
1,690,371.13
DETAILED UNIT PRICE ANALYSIS
Item No. 1032 a-1
Masonry Painting QUANTITY 32,784.68
DESCRIPTION QUANTITY UNIT U- PRICE(P)
Output rate: painting = 23.0504 sq.m / hour

MATERIAL COST
Paint Latex Gloss (Boysen) 656.00 gal 600.00
Paint Latex Semi-Gloss (Boysen) 656.00 gal 600.00
Water proofing paint 8.00 gal 600.00
Concrete Neutralizer 110.00 gal 340.00
Misc. materials (patching compound, brush, sand paper ,tinting color, etc.,)

Sub- Total
unit cost
DESCRIPTION NO HOURS RATE(Pesos)
Output rate:

Skilled Laborer (painter) 6.00 1422.30 57.50


LABOR COST

Unskilled Laborer 2.00 1422.30 47.50


8.00 177.79

Sub- Total
unit cost
DESCRIPTION NO HOURS RATE(Pesos)
EQUIPMENT COST

Output rate:

Scaffolding 1.00 lot 40,000.00

Sub- Total
unit cost
Direct Unit Cost
Total Direct & Indirect Unit Cost
Total Direct & Indirect Cost
DETAILED UNIT PRICE ANALYSIS
sq.m
TOTAL(Pesos)

393,600.00
393,600.00
4,800.00
37,400.00
25,000.00

854,400.00
26.06
TOTAL(Pesos)

-
490,693.50
135,118.50

625,812.00
19.09
TOTAL(Pesos)

40,000.00

40,000.00
1.22
46.37
46.37
1,520,212.00
DETAILED UNIT PRICE ANALYSIS
Item No. 1032 a-2
Wooden Painting QUANTITY 14,779.88
DESCRIPTION QUANTITY UNIT U- PRICE(P)
Output rate: painting = 18.8217 sq.m / hour

MATERIAL COST
Flat Wall Enamel (Boysen) 296.00 gal 600.00
Quick Dry Enamel (Boysen) 296.00 gal 600.00
Glazing Putty 50.00 gal 400.00
Misc. materials (paint thinner,patching compound, brush, sand paper,tinting color, etc.,)

Sub- Total
unit cost
DESCRIPTION NO HOURS RATE(Pesos)
Output rate:

Skilled Laborer (painter) 5.00 785.26 57.50


LABOR COST

Unkilled Laborer 4.00 785.26 47.50


9.00 98.16

Sub- Total
unit cost
DESCRIPTION NO HOURS RATE(Pesos)
EQUIPMENT COST

Output rate:

Scaffolding 1.00 lot 25,804.41

Sub- Total
unit cost
Direct Unit Cost
Total Direct & Indirect Unit Cost
Total Direct & Indirect Cost
DETAILED UNIT PRICE ANALYSIS
sq.m
TOTAL(Pesos)

177,600.00
177,600.00
20,000.00
20,000.00

395,200.00
26.74
TOTAL(Pesos)

-
225,762.25
149,199.40

374,961.65
25.37
TOTAL(Pesos)

25,804.41

25,804.41
1.75
53.85
53.85
795,966.06
DETAILED UNIT PRICE ANALYSIS
Item No. 1002
Plumbing Works QUANTITY All L.S.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: installation = 12.5250 L.M / hour

Water Closets 20.00 set 4,300.00 86,000.00


Lavatory/complete with accessories 2.00 set 4,500.00 9,000.00
Facial Mirror 0.80 X 0.60 m 10.00 set 950.00 9,500.00
Faucet 26.00 set 350.00 9,100.00
Floor Drain 44.00 pcs. 280.00 12,320.00
PVC pipe 4" dia. 30.00 pcs. 583.00 17,490.00
PVC pipe 100mm Ø 78.00 pcs. 583.00 45,474.00
PVC pipe 150mm Ø 45.00 pcs. 786.00 35,370.00
PVC pipe 50mm Ø 50.00 pcs. 291.00 14,550.00
PVC P-TRAP W/ PLUG 50mm Ø 67.00 pcs. 107.00 7,169.00
MATERIAL COST

PVC Wye 100 x 100mm Ø 10.00 pcs. 126.00 1,260.00


PVC Tee 100 x 100mm Ø 16.00 pcs. 270.00 4,320.00
PVC Reducer Tee 100 x 50mm Ø 12.00 pcs. 110.00 1,320.00
PVC Clean out w/ plug 100mm Ø 20.00 pcs. 59.00 1,180.00
PVC pipe 100mm Ø Elbow 1/8bend 10.00 pcs. 60.00 600.00
PVC 100mm Ø Elbow 1/4bend 48.00 pcs. 38.00 1,824.00
PVC 50mm Ø Elbow 1/4bend 33.00 pcs. 26.00 858.00
PVC 50mm Ø Elbow 1/8bend 28.00 pcs. 21.00 588.00
PVC 50mm Ø Tee 25.00 pcs. 74.00 1,850.00
Solvent 10.00 qrt 190.00 1,900.00
G.I pipe 12mm dia. 20.00 pcs. 610.00 12,200.00
G.I pipe 12mm dia. 47.00 pcs. 350.00 16,450.00
G.I elbow 12mm Ø 44.00 pcs. 20.00 880.00
G.I coupling 12mm Ø 35.00 pcs. 20.00 700.00
G.I Tee 12mm Ø 50.00 pcs. 22.00 1,100.00
L-Type Grab Bar (Stainless) 2.00 set 1,200.00 2,400.00
Miscellaneous materials teplon tape,etc., All LS 10,000.00 10,000.00
Sub- Total 305,403.00
unit cost 305,403.00
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day installation = 12.53
LABOR COST

Skilled Laborer (Plumber) 2.00 150.00 47.62 14,287.13


Unskilled Laborer 4.00 150.00 36.75 22,047.00
6.00 18.75

Sub- Total 36,334.13


unit cost 36,334.13
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day installation = 12.53
EQUIPMENT COST

Sub- Total -
unit cost -
Direct Unit Cost 341,737.13
PREPARED BY: 9% of total DC OCM 30,756.34
8% of total DC CP 27,338.97
5% of (total DC+OCM+CP) VAT 19,991.62
Total Direct & Indirect Unit Cost 419,824.06
Total Direct & Indirect Cost 419,824.06
DETAILED UNIT PRICE ANALYSIS
Item No. 1100
Electrical Works QUANTITY All L.S.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: installation =
Wall Fan 24.00 set 2,300.00 55,200.00
Flourescent Lighting Fixtures (2X40 watts)
Aluminum Louver Recess 72.00 set 1,450.00 104,400.00
Flourescent Lighting Fixtures (1X40 watts)
Aluminum Louver Recess 46.00 set 1,120.00 51,520.00
Compact LED lamp 21.00 pcs. 350.00 7,350.00
Porcelain socket # 4"Ø 21.00 set 60.00 1,260.00
Light Switch 1 way 1 gang 35.00 set 210.00 7,350.00
Light Switch 1 way 2 gang 12.00 set 235.00 2,820.00
Light Switch 3 way 1 gang 4.00 set 280.00 1,120.00
Light Switch 3 way 2 gang 12.00 set 330.00 3,960.00
Utility Box (G.I. TYPE) 119.00 pcs. 35.00 4,165.00
PVC Conduit Long Elbow, 19mm Ø 3.00 pcs. 22.00 66.00
PVC Conduit Long Elbow , 12.50mm Ø 160.00 pcs. 16.00 2,560.00
PVC Conduit Pipe,12.50mm Ø 260.00 pcs. 79.00 20,540.00
PVC Conduit Pipe, 19mm Ø 48.00 pcs. 98.00 4,704.00
PVC Conduit Pipe, 25mm Ø 12.00 pcs. 127.00 1,524.00
MATERIAL COST

Electrical Rigid Steel Conduit 25.4mm Ø 2.00 pcs. 880.00 1,760.00


Service Entrance cap # 25.4mm Ø 1.00 pcs, 191.00 191.00
Junction Box (G.I. TYPE) 133.00 pcs. 36.00 4,788.00
Bushing and Locknut 25.4 mm Ø 2.00 pcs. 12.00 24.00
Copper Wire #3.50mm2 THWN/THHN 12.00 rolls 3,600.00 43,200.00
Copper Wire #8.00mm2 THWN/THHN 1.00 rolls 6,750.00 6,750.00
Copper Wire #30.00mm2 THWN/THHN 50.00 mtrs. 127.00 6,350.00
Duplex Convenience Outlet 56.00 sets. 245.00 13,720.00
Equipment for Fire Alarm Bell / with accesso. 4.00 set 2,850.00 11,400.00
Enclosed Air Circuit Breaker 30 amp. 1.00 set 1,200.00 1,200.00
spool insulator and secondary rack w/ bolt 2.00 set 780.00 1,560.00

mica tube 2.00 rolls 2,250.00 4,500.00


Electrical Tape 3/4" x 20 yds 75.00 pcs. 30.00 2,250.00
bolt-on Circuit Breaker 100 amp. 1.00 sets 1,250.00 1,250.00
bolt-on Circuit Breaker 60 amp. 8.00 sets 550.00 4,400.00
bolt-on Circuit Breaker 30 amp. 17.00 sets 400.00 6,800.00
Panelboard & cabinet 6-U bolt-on type 5.00 sets 1,500.00 7,500.00
Misc. materials (clamps,batteries, kerosene,
sand paper, etc.,) ALL L.S. 10,000.00 10,000.00
-

Sub- Total 404,532.00


unit cost 404,532.00
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day installation = -
Construction foreman 1.00 120.00 65.55 7,866.00
Skilled Laborer (Electrician) 1.00 120.00 47.62 5,714.85
LABOR COST

Unskilled Laborer 2.00 120.00 36.75 8,818.80


3.00 15.00 45.00

Sub- Total 22,399.65


unit cost 22,399.65
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day installation = -
EQUIPMENT COST

Sub- Total -
unit cost -
Direct Unit Cost 426,931.65
PREPARED BY: 9% of total DC OCM 38,423.85
8% of total DC CP 34,154.53
5% of (total DC+OCM+CP) VAT 24,975.50
Total Direct & Indirect Unit Cost 524,485.53
Total Direct & Indirect Cost 524,485.53
DETAILED UNIT PRICE ANALYSIS
Item No. 1018
Ceramic Tiles QUANTITY 11,700.75 sq.m
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: Laying glazed tiles = 0.8400 sq.m / hour
Laying unglazed tiles = 0.5850 sq.m / hour
MATERIAL COST

Ceramic Unglazed Tiles 11,700.75 sq.m 1,600.00 18,721,200.00


Portland Cement 1,007.00 bag 250.00 251,750.00
Tile adhesive 1,288.00 bag 300.00 386,400.00
Misc. Tile Grout etc. All L.S. 10,000.00 10,000.00

Sub- Total 19,369,350.00


unit cost 1,655.39
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
Construction foreman 1.00 250.00 77.50 19,375.00
Skilled Laborer (mason) 3.00 500.00 57.50 86,250.00
LABOR COST

Unskilled Laborer 2.00 500.00 47.50 47,500.00


6.00 62.50 375.00

Sub- Total 153,125.00


unit cost 13.09
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Tile Cutter 3.00 500.00 10.63 15,945.00

Sub- Total 15,945.00


unit cost 1.36
Direct Unit Cost 1,669.84
Total Direct & Indirect Unit Cost 1,669.84
Total Direct & Indirect Cost 19,538,420.00
DETAILED UNIT PRICE ANALYSIS
Item No. Spl 3
Damproofing / Moisture Control QUANTITY 1,445.00 sq.m
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Output rate: 27.2000 sq.m / hour

MATERIAL COST Polythelene sheets 1445.00 sq.m 60.00 86,700.00

Sub- Total 86,700.00


unit cost 60.00
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
Output rate:
LABOR COST

Unskilled Laborer 4.00 53.13 47.50 10,094.70


4.00 6.64 26.57

Sub- Total 10,094.70


unit cost 6.99
DESCRIPTION NO HOURS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Output rate:

Sub- Total -
unit cost -
Direct Unit Cost 66.99
PREPARED BY: 9% of total DC OCM 6.03
8% of total DC CP 5.36
5% of (total DC+OCM+CP) VAT 3.92
Total Direct & Indirect Unit Cost 82.29
Total Direct & Indirect Cost 118,912.29
DETAILED UNIT PRICE ANALYSIS
Item No. Spl 4
Railings QUANTITY 884.64
DESCRIPTION QUANTITY UNIT U- PRICE(P)
Output rate: installation = 3.0000 L.M / hour
G.I. Pipe along corridor, 50mmØ
A=4.10*4+3*2+2.10*2 26.60 L.M. 26.60 L.M. 300.00
Steel railings, 19mm sq. bar welded to 50mmØ GI Pipe
handrail along stair
A=(3.8*12)x0.90m 41.04 sq.m 41.04 sq.m 950.00
Steel railings, 19mm sq. bar welded to 50mmØ GI Pipe
handrail along stair wall
MATERIAL COST

A=(4*6)x1.10m 27.06 sq.m 27.06 sq.m 1,000.00


Steel railings, 12mm sq. bar welded to 50mmØ GI Pipe
handrail along corridor at 2nd to 4TH flr.
A=(.6*24*4.1)+2.10*.60*6 66.60 sq.m 66.60 sq.m. 1,000.00
Steel railings, 50mmØ GI Pipe handrail w/ 25mm sq. bracket
@ 600mm 45.60 LM 300.00
Steel railings, 38mmØ GI Pipe handrail at ramp 86.20 LM 225.00
32mmØ Stainless Pipe Grab bar 3.60 LM 450.00
Misc. materials (welding rod, paint, etc.,) All L.S. 8,500.00

#VALUE!

Sub- Total
unit cost
DESCRIPTION NO HOURS RATE(Pesos)
Output rate:
Construction foreman 1.00 160.00 77.50
Skilled Laborer (Welder) 2.00 160.00 57.50
LABOR COST

Unskilled Laborer 6.00 160.00 47.50


8.00 20.00 160.00

Sub- Total
unit cost
DESCRIPTION NO HOURS RATE(Pesos)
EQUIPMENT COST

Output rate:

Welding machine 2.00 160.00 62.50

Sub- Total
unit cost
Direct Unit Cost
Total Direct & Indirect Unit Cost
Total Direct & Indirect Cost
DETAILED UNIT PRICE ANALYSIS

sq.m.
TOTAL(Pesos)

7,980.00

38,988.00

-
27,060.00

-
66,600.00

13,680.00
19,395.00
1,620.00
8,500.00
-

183,823.00
207.79
TOTAL(Pesos)

12,400.00
18,400.00
45,600.00

76,400.00
86.36
TOTAL(Pesos)

20,000.00

20,000.00
22.61
316.77
316.77
280,223.00
DETAILED UNIT PRICE ANALYSIS
Item No. Spl.5
Occupational Safety & Health QUANTITY All LS
DESCRIPTION QUANTITY MAN-DAY U- PRICE(P) TOTAL(Pesos)
Safety Gears

MATERIAL COST
Safety Shoes 13440.00 Man-Day 3.77 50,668.80
Safety Helmet 13440.00 Man-Day 0.75 10,080.00
Safety Gloves 13440.00 Man-Day 8.67 116,524.80

Sub- Total 177,273.60


DESCRIPTION NO UNIT RATE(Pesos) TOTAL(Pesos)
Part Time Safety Practitioner 336.00 Day 740.00 248,640.00
LABOR COST

Sub- Total 248,640.00


DESCRIPTION NO UNIT RATE TOTAL
EQUIPMENT COST

Warning Signs 30.00 LOT 15,000.00 15,000.00

15,000.00
Total Direct Cost 440,913.60
PREPARED BY: 0% of total DC OCM -
8% of total DC CP 35,273.09
5% of (total DC+OCM+CP) VAT 23,809.33
Total Item Cost 499,996.02
Adjusted Unit Cost 499,996.02
DETAILED UNIT PRICE ANALYSIS
Item No. Spl.6
Project Billboard QUANTITY 1.00 each
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Assumed Output/day 1.00 gal./man-day
ACI BILLBOARD
Tarpaulin 32.00 sq.m. 30.00 960.00
Ordinary Plywood 1/4 1.00 pcs. 315.00 315.00
Coco Lumber 2 x 3 x 12 12.00 bd.ft. 28.00 336.00
Coco Lumber 2 x 2 x 12 16.00 bd.ft. 28.00 448.00
MATERIAL COST

Assorted CWN 2.00 kgs. 70.00 140.00

COA BILLBOARD
Tarpaulin 64.00 sq.m. 30.00 1,920.00
Ordinary Plywood 1/4 2.00 pcs. 315.00 630.00
Coco Lumber 2 x 3 x 12 24.00 bd.ft. 28.00 672.00
Coco Lumber 2 x 2 x 12 32.00 bd.ft. 28.00 896.00
Assorted CWN 4.00 kgs. 70.00 280.00

Sub- Total 6,597.00


unit cost 6,597.00
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 1.00 gal./man-day

Skilled Laborer 1.00 1.00 47.62 47.62


LABOR COST

Unskilled Laborer 1.00 2.00 36.75 73.49


2.00 #REF! #REF!

Sub- Total 121.11


unit cost 121.11
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 1.00 gal./man-day
EQUIPMENT COST

Sub- Total
unit cost -
Direct Unit Cost 6,718.11
Total Direct & Indirect Unit Cost 6,718.11
Total Direct & Indirect Cost 6,718.11
DETAILED ESTIMATES
Item No. 803
Structural Excavation QUANTITY 2,280.48 cu.m
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Assumed Output/day 5.00 cu.m/day
MATERIAL COST

Sub- Total -
unit cost -
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 5.00 cu.m./day

Construction Foreman 1.00 1.00 524.36 524.36


LABOR COST

Skilled Laborer 1.00 1.00 380.99 380.99


Unskilled Laborer 4.00 1.00 293.96 1,175.84
6.00 1.00 6.00

Sub- Total 2,081.19


unit cost 416.24
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 5.00 cu.m./day
EQUIPMENT COST

Sub- Total -
unit cost -
Direct Unit Cost 416.24
PREPARED BY: 12% of total DC OCM 49.95
10% of total DC CP 41.62
12% of (total DC+OCM+CP) VAT 60.94
Total Direct & Indirect Unit Cost 568.75
Total Direct & Indirect Cost 1,297,017.53
DETAILED ESTIMATES
Item No. 403
Structural Steel QUANTITY All L.S.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Assumed Output/day

46.80 x 46.80 x 5.00mm AB (TC & BC) 3.00 pcs. 1,400.00 4,200.00
46.80 x 46.80 x 4.25mm AB (web & Cleats) 2.00 pcs. 980.00 1,960.00
C-Purlins 44 x 75 x 1.00mm 7.00 pcs. 455.00 3,185.00
MATERIAL COST

C-Purlins 44 x 250 x 1.00mm (Facia) 1.00 pcs. 1,000.00 1,000.00


Sag rod (10mm dia) with bolts & nuts at both e 7.00 pcs 80.00 560.00
Welding Rod 6.00 pcs 120.00 720.00
Red Lead Primer 1.00 gal 430.00 430.00
Paint Thinner 0.50 gal 200.00 100.00
Paint Brush 2.00 pcs 80.00 160.00
Miscellaneous 800.00

Sub- Total 13,115.00


unit cost 13,115.00
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day - -

Construction Foreman 1.00 2.50 524.36 1,310.90


LABOR COST

Skilled Laborer (Welder) 1.00 2.50 380.99 952.48


Unskilled Laborer 2.00 2.50 293.96 1,469.80
4.00 2.50 10.00

Sub- Total 3,733.18


unit cost 3,733.18
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day - -
EQUIPMENT COST

Welding machine 1.00 2.50 500.00 1,250.00


Electricity,Acetylane,oxygen & etc. All LS 2,000.00 2,000.00
Minor tools (10% of Labor) 373.32

Sub- Total 3,623.32


unit cost 3,623.32
Direct Unit Cost 20,471.49
PREPARED BY: 12% of total DC OCM 2,456.58
10% of total DC CP 2,047.15
12% of (total DC+OCM+CP) VAT 2,997.03
Total Direct & Indirect Unit Cost 27,972.25
Total Direct & Indirect Cost 27,972.25
DETAILED ESTIMATES
Item No. 404
Reinforcing Steel Bars QUANTITY #VALUE! kgs.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Assumed Output/day 450.00 kgs./day

Asstd. RSB (16mm, 12mm & 10mm) 450.00 kgs 55.00 24,750.00
MATERIAL COST

Tie wire # 16 G.I #VALUE! kgs 57.00 #VALUE!

Sub- Total #VALUE!


unit cost #VALUE!
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 450.00 cu.m./day

Construction Foreman 1.00 1.00 524.36 524.36


LABOR COST

Skilled Laborer (Steelman) 2.00 1.00 380.99 761.98


Unskilled Laborer 4.00 1.00 293.96 1,175.84
7.00 1.00 7.00

Sub- Total 2,462.18


unit cost 5.47
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 450.00 cu.m./day
EQUIPMENT COST

Bar Cutter (manually operated) 1 1.00 350.00 350.00

Sub- Total 350.00


unit cost 0.78
Direct Unit Cost #VALUE!
PREPARED BY: 12% of total DC OCM #VALUE!
10% of total DC CP #VALUE!
12% of (total DC+OCM+CP) VAT #VALUE!
Total Direct & Indirect Unit Cost #VALUE!
Total Direct & Indirect Cost #VALUE!
DETAILED UNIT PRICE ANALYSIS
Item No. 405
Structural Concrete QTY. #VALUE! cu.m.
DESCRIPTION QUANTITY UNIT U-PRICE(Pesos) TOTAL(P)
Assumed Output/day 7.20 cu.m./day
MATERIAL COST

Portland Cement, 40 kgs 69.00 bags 225.00 15,525.00


Washed Sand 3.60 cu. m. 500.00 1,800.00
3/4" Crushed Gravel 8.00 cu. m. 600.00 4,800.00
Form Lumber 324.00 bd.ft 28.00 9,072.00
Plywood 1/2" x 4' x 8' 5.00 pcs 650.00 3,250.00
Assorted CWN . 7.00 kgs 70.00 490.00

Sub- Total 34,937.00


unit cost 4,852.36
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 7.20 cu.m./day

Construction Foreman 1.00 1.00 524.36 524.36


LABOR COST

Skilled Laborer (Mason) 4.00 1.00 380.99 1,523.96


Unskilled Laborer 8.00 1.00 293.96 2,351.68
13.00 1.00 13.00

Sub- Total 4,400.00


unit cost 611.11
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 7.20 cu.m./day
EQUIPMENTCOST

Concrete Mixer (1-Bagger) 1.00 1.00 1,384.00 1,384.00


Concrete Vibrator 1.00 1.00 509.28 509.28
Minor tools (10% of Labor) 440.00

Sub- Total 2,333.28


unit cost 324.07
Direct Unit Cost 5,787.54
PREPARED BY: 12% of total DC OCM 694.50
10% of total DC CP 578.75
12% of (total DC+OCM+CP) VAT 847.30
Total Direct & Indirect Unit Cost 7,908.09
Total Direct & Indirect Cost #VALUE!
DETAILED ESTIMATES
Item No. 1003
Carpentry & Joinery Works QUANTITY 11,127.60 sq.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Assumed Output/day 16.00 sq.m./day
MATERIAL COST

1/4" Marine plywood 6.00 pcs 355.00 2,130.00


2" x 2" Nailing Joists & Hangers 96.00 bd.ft 75.00 7,200.00
Assorted CWN 3.00 kgs 70.00 210.00

Sub- Total 9,540.00


unit cost 596.25
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 16.00 sq.m./day

Construction Foreman 1.00 1.00 524.36 524.36


LABOR COST

Skilled Laborer (carpenter) 2.00 1.00 380.99 761.98


Unskilled Laborer 2.00 1.00 293.96 587.92
5.00 1.00 5.00

Sub- Total 1,874.26


unit cost 117.14
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 16.00 sq.m./day
EQUIPMENT COST

Scaffoldings 1.00 lot 500.00 500.00


Minor tools (10% of Labor) 187.43

Sub- Total 687.43


unit cost 42.96
Direct Unit Cost 756.36
PREPARED BY: 12% of total DC OCM 90.76
10% of total DC CP 75.64
12% of (total DC+OCM+CP) VAT 110.73
Total Direct & Indirect Unit Cost 1,033.48
Total Direct & Indirect Cost 11,500,196.38
DETAILED UNIT PRICE ANALYSIS
Item No. 1010
Doors & Windows QTY. All LS
DESCRIPTION QUANTITY UNIT U-PRICE(Pesos) TOTAL(P)
Assumed Output/day 1.00 cu.m./day

Tanguile Panelled Door (2 sets - 0.90m x 2.10m) 3.78 sq.m. 2,500.00 9,450.00

Swing Type Steel Casement Window with Glass


MATERIAL COST

(1 set - 1.20mx 1.20m & 1 set - 0.60m x 0.60m) 1.80 sq.m. 1,850.00 3,330.00
PVC Doors including Jamb and accessories
(0.80m x 2.10m) 1.00 sets 2,800.00 2,800.00
2" x 6" Door Jamb 35.00 bd.ft 75.00 2,625.00
Door knob 2.00 sets 1,550.00 3,100.00
Hinges 2"x4" 4.00 pairs 65.00 260.00
CWN (assorted) 4.00 kgs 70.00 280.00
Concrete Louver 8.00 pcs 25.00 200.00
Miscellaneous materials. All LS 500.00 500.00

Sub- Total 22,545.00


unit cost 22,545.00
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 7.20 cu.m./day

Construction Foreman 1.00 2.00 524.36 1,048.72


LABOR COST

Skilled Laborer (Carpenter) 1.00 2.00 380.99 761.98


Unskilled Laborer 2.00 2.00 293.96 1,175.84
4.00 2.00 8.00

Sub- Total 2,986.54


unit cost 2,986.54
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
EQUIPMENTCOST

Assumed Output/day 7.20 cu.m./day

Sub- Total -
unit cost -
Direct Unit Cost 25,531.54
PREPARED BY: 12% of total DC OCM 3,063.78
10% of total DC CP 2,553.15
12% of (total DC+OCM+CP) VAT 3,737.82
Total Direct & Indirect Unit Cost 34,886.30
Total Direct & Indirect Cost 34,886.30
DETAILED ESTIMATES
Item No. Spl.1
Masonry Works QUANTITY 8,218.97 sq.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Assumed Output/day 16.00 sq.m./day
MATERIAL COST

CHB ( 4" x 8" x 16") 200.00 pcs 10.00 2,000.00


Portland Cement, 40 kgs 9.00 bags 225.00 2,025.00
Washed Sand 1.00 cu.m 500.00 500.00
RSB 10mmØ 45.00 kgs 55.00 2,475.00
Tie wire # 16 GI 1.00 kgs 57.00 57.00

Sub- Total 7,057.00


unit cost 441.06
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 16.00 sq.m./day

Construction Foreman 1.00 1.00 524.36 524.36


LABOR COST

Skilled Laborer (Mason) 2.00 1.00 380.99 761.98


Unskilled Laborer 4.00 1.00 293.96 1,175.84
7.00 1.00 7.00

Sub- Total 2,462.18


unit cost 153.89
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 16.00 sq.m./day
EQUIPMENT COST

Concrete Mixer (1-Bagger) 1.00 1.00 1,384.00 1,384.00


Minor tools (10% of Labor) 246.22

Sub- Total 1,630.22


unit cost 101.89
Direct Unit Cost 696.84
PREPARED BY: 12% of total DC OCM 83.62
10% of total DC CP 69.68
12% of (total DC+OCM+CP) VAT 102.02
Total Direct & Indirect Unit Cost 952.16
Total Direct & Indirect Cost 7,825,762.88
DETAILED ESTIMATES
Item No. Spl.2
Plastering Works QUANTITY 16,392.34 sq.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Assumed Output/day 20.00 sq.m./day
MATERIAL COST

Portland Cement, 40 kgs 10.00 bags 225.00 2,250.00


Washed Sand 1.00 cu.m 500.00 500.00

Sub- Total 2,750.00


unit cost 137.50
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 20.00 sq.m./day

Construction Foreman 1.00 1.00 524.36 524.36


LABOR COST

Skilled Laborer (Mason) 2.00 1.00 380.99 761.98


Unskilled Laborer 3.00 1.00 293.96 881.88
6.00 1.00 6.00

Sub- Total 2,168.22


unit cost 108.41
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 20.00 sq.m./day
EQUIPMENT COST

Minor tools (10% of Labor) 216.82

Sub- Total 216.82


unit cost 10.84
Direct Unit Cost 256.75
PREPARED BY: 12% of total DC OCM 30.81
10% of total DC CP 25.68
12% of (total DC+OCM+CP) VAT 37.59
Total Direct & Indirect Unit Cost 350.83
Total Direct & Indirect Cost 5,750,860.21
DETAILED UNIT PRICE ANALYSIS
Item No. Spl.3
Roofing Works QTY. #VALUE! #REF!
DESCRIPTION QUANTITY UNIT U-PRICE(Pesos) TOTAL(P)
Assumed Output/day 1.00 cu.m./day

Pre-painted Tri-wave Sheets (0.40mm) #VALUE! sq.m 450.00 #VALUE!


MATERIAL COST

Pre-painted ready made Ridge Roll (0.40mm) 2.00 L.m 220.00 440.00
Pre-painted ready made Gutter (0.40mm) 27.00 L.m 220.00 5,940.00
Pre-painted ready made wall Flashing (0.40mm) 8.00 L.m 220.00 1,760.00
Blind Rivets 2.00 boxes 200.00 400.00
Tekscrew 150.00 pcs. 2.00 300.00
Silicone Selant 4.00 pcs. 170.00 680.00

Sub- Total #VALUE!


unit cost #VALUE!
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 7.20 cu.m./day

Construction Foreman 1.00 3.00 524.36 1,573.08


LABOR COST

Skilled Laborer (Tinsmithman) 1.00 3.00 380.99 1,142.97


Unskilled Laborer 2.00 3.00 293.96 1,763.76
4.00 3.00 12.00

Sub- Total 4,479.81


unit cost #VALUE!
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 7.20 cu.m./day
EQUIPMENTCOST

Electric Drill 1 3.00 85.00 255.00


Riveter 1 3.00 85.00 255.00
Scaffoldings 1 lot 1,000.00 1,000.00

Sub- Total 1,510.00


unit cost #VALUE!
Direct Unit Cost #VALUE!
PREPARED BY: 12% of total DC OCM #VALUE!
10% of total DC CP #VALUE!
12% of (total DC+OCM+CP) VAT #VALUE!
Total Direct & Indirect Unit Cost #VALUE!
Total Direct & Indirect Cost #VALUE!
DETAILED ESTIMATES
Item No. Spl.4
Painting Works QUANTITY #VALUE! sq.m
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Assumed Output/day 1.50 gal./man-day

Paint Latex Gloss (Boysen) 1,640.00 gal 480.00 787,200.00


Paint Latex Semi-Gloss (Boysen) 1,640.00 gal 480.00 787,200.00
Paint Enamel 739.00 gal 600.00 443,400.00
MATERIAL COST

Quick Dry Enamel (Boysen) 1.00 gal 600.00 600.00


Tinting Colors (Assorted) 1.00 ltr 135.00 135.00
Paint thinner 1.00 gal 200.00 200.00
Concrete Neutralizer 513.00 gal 400.00 205,200.00
Sand paper 1.00 roll 1,600.00 1,600.00
Paint brush 4" 5.00 pcs 80.00 400.00
Paint roller 4.00 pcs 60.00 240.00
Miscellaneous materials (patching compound,etc.,) 1,000.00

Sub- Total 2,227,175.00


unit cost #VALUE!
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 1.50 gal./man-day

Construction Foreman 1.00 447.00 524.36 234,388.92


LABOR COST

Skilled Laborer (Painter) 1.00 447.00 380.99 170,302.53


Unskilled Laborer 5.00 447.00 293.96 657,000.60
7.00 447.00 3,129.00

Sub- Total 1,061,692.05


unit cost #VALUE!
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day 1.50 gal./man-day
EQUIPMENT COST

Scaffoldings 1.00 lot 1,500.00 1,500.00

Sub- Total 1,500.00


unit cost #VALUE!
Direct Unit Cost #VALUE!
PREPARED BY: 12% of total DC OCM #VALUE!
10% of total DC CP #VALUE!
12% of (total DC+OCM+CP) VAT #VALUE!
Total Direct & Indirect Unit Cost #VALUE!
Total Direct & Indirect Cost #VALUE!
DETAILED ESTIMATES
Item No. Spl.5
Steel Gate & Perimeter Fences QUANTITY All L.S.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Assumed Output/day

Steel Gate (2sets- 4.00m x 2.45m) 19.60 sq.m 2,500.00 49,000.00


Steel Gate (1set- 2.00m x 2.30m) 4.60 sq.m 2,500.00 11,500.00
MATERIAL COST

Steel junior Gate (1set-1.80m x 2.45m) 4.41 sq.m 2,500.00 11,025.00


Fences (10sets- 3.00m x 1.30m) 39.00 sq.m 2,500.00 97,500.00
Red Lead Primer 20.00 gal 430.00 8,600.00
Paint Thinner 5.00 gal 200.00 1,000.00
Paint Brush 10.00 pcs 80.00 800.00
Rush Converter/Remover 6.00 gal 450.00 2,700.00
Miscellaneous materials (sand paper, steel brush, welding rod,etc.,) 3,000.00

Sub- Total
unit cost -
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day - -

Construction Foreman 1.00 524.36 -


LABOR COST

Skilled Laborer (Welder) 2.00 0.00 380.99 -


Unskilled Laborer 5.00 0.00 293.96 -
8.00 - -

Note:
Labor includes repair & installation of old fences.

Sub- Total -
unit cost -
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day - -

Welding machine 1.00 - 500.00 -


EQUIPMENT COST

Grinder (handy) 1.00 - 150.00 -


Electricity,Acetylane,oxygen & etc. All LS 7,193.04 7,193.04
Minor tools (10% of Labor) -

Sub- Total
unit cost -
Direct Unit Cost -
PREPARED BY: 12% of total DC OCM -
12% of total DC CP -
12% of (total DC+OCM+CP) VAT -
Total Direct & Indirect Unit Cost -
Total Direct & Indirect Cost -
Department of Public Works and Highways (DPWH)
Contract ID : 12AJ0017
Contract Name : Completion of Multi-Purpose Building at Buenlag 1st & Manabong Sur, Bayambang, Pangasinan, Construction of 2-Cl at
Arenas NHS, Ambayat 2nd, Bayambang, Pangasinan, Construction of 1-Cl at Bogaoan E/S, San Carlos City and Completion
of Multi-Purpose Building (Gym) at Brgy. Coliling & Brgy. Quintong, San Carlos City, Pangasinan (CLUSTER I)

Contract Location: Bayambang & San Carlos City, Pangasinan

SUMMARY OF LABOR, EQUIPMENT RENTALS & MATERIAL COST

MATERIALS COST

Description Unit Price


C-Rafter 46mm x 148mm (1.20mm) ………………………… 1,050.00 / pcs.
C-Purlins 44mm x 75mm (1.00mm) ………………………… 460.00 / pcs.
C-Purlins 44mm x 100mm (1.00mm) ………………………… 510.00 / pcs.
C-Purlins 50mm x 150mm (1.40mm) ………………………… 1,075.00 / pcs.
Facia Board 50mm x 250mm (0.98mm) ………………………… 900.00 / pcs.
Anchor Bolt, 16mmØ x 200mm ………………………… 150.00 / pcs.
Anchor Bolt, 16mmØ x 250mm ………………………… 170.00 / pcs.
Anchor Bolt, 12mmØ x 150mm ………………………… 100.00 / pcs.
20mm dia. X 50 Machine Bolts w/ nuts ………………………… 100.00 / pcs.
20mm dia. X 500 Straight Bolts w/ nuts ………………………… 250.00 / pcs.
16mm dia. X 200 Anchor Bolts w/ nuts ………………………… 120.00 / pcs.
10mm Thk. Steel Plate ………………………… 18,500.00 / pcs.
Gusset Plates 4 x 8 x 4mm ………………………… 12,550.00 / pcs.
Base Plate 150mm x 300mm x 4mm ………………………… 300.00 / pcs.
Base Plate 150mm x 150mm x 4mm ………………………… 150.00 / pcs.
Base Plate 250mm x 200mm x 4mm ………………………… 200.00 / pcs.
71.2 x 71.2 x 5.00mm Angle Bar ………………………… 2,425.00 / pcs.
46.8 x 46.8 x 5.00mm Angle Bar ………………………… 1,400.00 / pcs.
46.8 x 46.8 x 4.25mm Angle Bar ………………………… 980.00 / pcs.
46.8 x 46.8 x 3.50mm Angle Bar ………………………… 800.00 / pcs.
38.0 x 38.0 x 3.50mm Angle Bar ………………………… 685.00 / pcs.
20mm dia. Tension Rod (Strut 1) ………………………… 50.00 / kgs.
Plain 12mm dia w/ nuts & washer at both ends (Sag Rod) ………………………… 80.00 / pcs.
Plain 12mm dia (Cross bracing) ………………………… 50.00 / kgs.
Std. Turn Buckel 12mm dia. ………………………… 200.00 / pcs.
C-Rafter 46mmx150mm (1.20mm) ………………………… 1,050.00 / pcs.
C-Purlins 44mm x 100mm (1.0mm) ………………………… 510.00 / pcs.
Facia Board 50mm x 250mm (0.98mm) ………………………… 900.00 / pcs.
Anchor Bolt, 16mmØ x .200mm ………………………… 150.00 / pcs.
Anchor Bolt, 12mmØ x 150mm ………………………… 100.00 / pcs.
Base / Sole Plate 150mm x 150mm x 4mm ………………………… 150.00 / pcs.
Base Plate 300mm x 150mm x 4mm ………………………… 300.00 / pcs.
Cleats 48.1 x 48.1 x 3.5mm Angular bar ………………………… 950.00 / pcs.
Sag Rod(10mm ø) Plain bar with Bolts & Washers ………………………… 80.00 / pcs.
Paint brush 4" ………………………… 90.00 / pcs.
Thinner ………………………… 250.00 / gal
Red Lead Primer ………………………… 550.00 / gal
Welding Rod ………………………… 120.00 / kgs.
Hacksaw blade ………………………… 65.00 / pcs.
150X150X4mm, Base Plate ………………………… 150.00 / pcs.
10mm dia.Sag rod w/n/b ………………………… 80.00 / pcs.
10mm dia,x0.70m.Dowels ………………………… 25.00 / pcs.
12mm dia. X 150mm long Anchor Bolt ………………………… 80.00 / pcs.

Ceramics Glazed Tiles & Trims ………………………… 750.00 / sq.m.


Ceramics Unglazed Tiles & Trims ………………………… 850.00 / sq.m.
Tile Grout ………………………… 70.00 / kls.

Paint brush 4" ………………………… 90.00 / pcs.


Paint brush 2" ………………………… 45.00 / pcs.
Paint Tinner ………………………… 240.00 / gal
Red Lead Primer ………………………… 580.00 / gal
Welding Rod ………………………… 120.00 / kgs.
Hacksaw blade ………………………… 75.00 / pcs.
Portland Cement, 40 kgs ………………………… 220.00 / bags
Washed Sand ………………………… 500.00 / cu. m.
Gravel Fill ………………………… 450.00 / cu. m.
River mix ………………………… 300.00 / cu.m.
Crushed Gravel ………………………… 600.00 / cu. m.
Plywood - 1/2 x 4' x 8' ………………………… 625.00 / pcs.
Plywood - 1/4 x 4' x 8' ………………………… 355.00 / pcs.
Good Lumber ………………………… 75.00 / bd.ft
Coco Lumber ………………………… 28.00 / bd.ft
Air ventillation ………………………… 450.00 / set
Assorted CWN ………………………… 70.00 / kgs
Asstd. RSB ………………………… 52.00 / kgs
Tie wire # 16 GI ………………………… 55.00 / kgs
CHB ( 4" x 8" x 16") ………………………… 10.00 / pcs
Security Steel Grills (10mm) ………………………… 1,200.00 / sq.m.
Sliding Analuk Windows ………………………… 3,000.00 / sq.m.
Jalousie window w/ Aluminum Frame ………………………… 850.00 / sq.m.
Swing type Steel Casement window with glass ………………………… 1,850.00 / sq.m.
Panel type door (2.10m X 0.90m) incl. Door jambs & …………………………
Hinges with screw. 5,000.00 / sets
5/8"Glass Door With Aluminum Frames ………………………… 6,500.00 / sq.m.
Flush hollow core door ………………………… 920.00 / sq.m.
PVC Door (2.10m x 0.80m) incl. Door jambs & Hinges with …………………………
screw. 2,850.00 / units
Improvised Door Lock (Hook-in flat bar 4mm Thk with …………………………
padlock and puller) 380.00 / pcs.
Door lock w/ screw ………………………… 450.00 / pcs.
Hinges ………………………… 35.00 / pcs.
Pre-painted Tri-wave (0.40mm) ………………………… 420.00 / sq.m.
Pre-painted ready made ridge roll (0.40mm) ………………………… 220.00 / L.M.
Pre-painted ready made Flashing S-Type (0.40mm) ………………………… 220.00 / L.M.
Pre-painted ready made End Flashing (0.40mm) ………………………… 220.00 / L.M.
Pre-painted ready made Gutter (0.40mm) ………………………… 220.00 / L.M.
Tekscrew ………………………… 2.00 / pcs.
Blind rivets ………………………… 250.00 / box
Silicon Sealant ………………………… 180.00 / pcs.
Toilet Bowl ………………………… 1,000.00 / set
Water Closet ………………………… 6,750.00 / set
PVC pipe 4" dia. ………………………… 580.00 / pcs.
PVC pipe 2" dia. ………………………… 290.00 / pc.
PVC pipe 4 x 2 wye ………………………… 95.00 / pc.
PVC pipe 4 x 4 wye ………………………… 125.00 / pc.
PVC pipe 4 x 4 tee ………………………… 125.00 / pc.
PVC pipe 4 x 2 Tee ………………………… 80.00 / pc.
PVC pipe 2" dia. Elbow 1/4 bend ………………………… 25.00 / pc.
PVC pipe 2" dia. Elbow 1/8 bend ………………………… 20.00 / pc.
PVC pipe 4" dia. Elbow 1/4 bend ………………………… 80.00 / pc.
PVC pipe 4" dia. Elbow 1/8 bend ………………………… 55.00 / pc.
PVC pipe 2" dia. P-Trap ………………………… 105.00 / pc.
PVC pipe 4" dia. Cleanout w/ plug ………………………… 60.00 / pcs.
PVC pipe Reducer Tee 4" x 2" dia. ………………………… 110.00 / pcs.
Solvent ………………………… 185.00 / can
Floor drain 4" x 4" H.D. ………………………… 290.00 / pc.
G I pipe 1/2" dia ………………………… 365.00 / pcs.
G I coupling 1/2" dia. ………………………… 8.00 / pcs.
G I elbow 1/2" dia. ………………………… 10.00 / pcs.
G I tee 1/2" dia ………………………… 22.00 / pcs.
G I adapter 1/2" dia ………………………… 15.00 / pcs.
Faucet 1/2" dia ………………………… 170.00 / pcs.
PVC pipe 3" dia. (downspout) ………………………… 430.00 / pcs.
PVC pipe 3" dia. Elbow 1/4 bend ………………………… 80.00 / pc.

Flourescent Lighting Fixtures (40 watts) with box type housing ………………………… 650.00 / sets
Lighting Fixture (CFL 20 A) 150.00 / sets
Bulb Receptacles 45.00 / pcs.
Light Switch 1 way 2 gang 140.00 / pc.
Light Switch 1 way 1 gang 140.00 / pc.
Copper Wire #3.50mm2 TW 26.00 / mtrs.
Electrical Tape 40.00 / roll
PVC Pipe Flexible 1/2"dia. 15.00 / mtrs.
PVC Coupling PNS 14,1/2" dia. 10.00 / pcs.
PVC Pipe PNS 14,1/2"dia. 70.00 / pcs.
PVC Pipe PNS 14 1"dia. 140.00 / pcs.
PVC Adapter PNS 14,1/2"dia. 15.00 / pcs.
Entrance cap # 1/2"Ø 65.00 / pcs,
Junction Box (Deep tape w/ Cover) 30.00 / pcs.
Utility Box (Deep tape) ………………………… 25.00 / pcs.
PVC Pipe Flexible 1/2"dia. ………………………… 15.00 / mtrs.
1 set enclosed Panel box w/ 30 AT 2,450.00 / set
main Breaker and 2-20 AT Branch
Convenience outlet/w plate 150.00 / pcs.

Compact flourescent lamp ………………………… 110.00 / sets


Porcelain socket # 4"Ø ………………………… 30.00 / pcs.

Light Switch 1 way 2 gang ………………………… 150.00 / pcs.


Light Switch 1 way 1 gang ………………………… 150.00 / pcs.
Duplex Convenient Outlet ………………………… 200.00 / pcs.
Copper Wire #3.50mm2 TW ………………………… 24.00 / mtrs.
Electrical Tape ………………………… 50.00 / roll
PVC Coupling PNS 14,1/2" dia. ………………………… 10.00 / pcs.
PVC Pipe PNS 14,1/2"dia. ………………………… 70.00 / pcs.
PVC Adapter PNS 14,1/2"dia. ………………………… 25.00 / pcs.
Entrance cap # 1/2"Ø ………………………… 80.00 / pcs,
Junction Box (Deep tape w/ Cover) ………………………… 30.00 / pcs.
Air circuit breaker 20 AT ………………………… 600.00 / sets
Lighting Fixture GI pipe Hanger ………………………… 350.00 / sets

Flat wall Latex (Boysen) ………………………… 490.00 / gals.


Latex Paint Semi- Gloss ………………………… 490.00 / gals.
Flatwall Enamel (White Boysen) ………………………… 600.00 / gals.
Quick Drying Enamel ………………………… 500.00 / gals.
Paint Thinner ………………………… 250.00 / gals.
Paint Brush 4" ………………………… 90.00 / pcs.
Paint roller 12" ………………………… 160.00 / pc.
Assorted Acry Color (Latex) ………………………… 135.00 / ltr.
Assorted Tintin Color (Enamel) ………………………… 150.00 / ltr.
Sandpaper #100 ………………………… 1,600.00 / roll
Calsumine powder ………………………… 15.00 / kg.
Concrete Neutralizer ………………………… 220.00 / gals.
Plasalux GlazingPutty 550.00 gal.
LABOR COST

Designation Rate per Day


Construction Foreman ………………………… 530.00
Skilled Laborer ………………………… 400.00
Semi-skilled Laborer ………………………… 350.00
Unskilled Laborer ………………………… 290.00
First Aider ………………………… 290.00
Part time Safety Practitioner ………………………… 530.00

EQUIPMENT RENTALS

Description Rentals
Plate Compactor ………………………… 610.00
Bar Cutter (manually operated) ………………………… 350.00
Concrete Mixer (1-Bagger) ………………………… 1,390.00
Concrete Vibrator ………………………… 510.00
Water truck (1000 gal) ………………………… 7,750.00
Welding machine ………………………… 500.00
Cutting Outfit w/ complete accessories ………………………… 150.00
Demountable Beam w/ Ropes ………………………… 700.00
Electric Drill ………………………… 100.00
Riveter ………………………… 100.00
Angle Grinder ………………………… 100.00

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 12AJ0030
Contract Name: Completion of Hospital at Bayambang District Hospital and Construction of Multi-Purpose Bldg. (Daycare) at
Brgy. Sanlibo, Bayamabang, Pangasinan, Improvement of Multi-Purpose Bldg at Doyong NHS, Construction of
Multi-Purpose Bldg. at Bureau of Jail Management and Penology, Construction of Multi-Purpose Pavement at
Brgys. Sapinit, Polo and Turac, San Carlos City, Pangasinan (CLUSTER VI)
Contract Location: Bayambang & San Carlos City, Pangasinan

DETAILED ESTIMATES
Construction of 2-units 6-CL School Building (2-storey) at Malasiqui NHS, Malasiqui, Pangasinan

Item No.103 Structure Excavation


QTY. = 2,280.48 CU.M.

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 2.00 530.00 1,060.00
Semi-skilled Laborer (Leadman) 1 2.00 350.00 700.00
Unskilled Laborer 4 2.00 290.00 2,320.00

Sub-total 4,080.00

Total Direct Cost 4,080.00


Mark-up 2,100.07
Total Item Cost 6,180.07
Unit Cost 2.71

Item No. 404 Reinforcing Steel Bars


QTY. = #VALUE! kgs.
A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB (12mm & 10mm) #VALUE! kgs. 52.00 #VALUE!
Tie wire (#16 G.I.) #VALUE! kgs. 55.00 #VALUE!

Sub-total #VALUE!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 1.00 530.00 530.00
Skilled Laborer (Steelman) 2 1.00 400.00 800.00
Unskilled Laborer 4 1.00 290.00 1,160.00

Sub-total 2,490.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 1.00 350.00 350.00

Sub-total 350.00

Total Direct Cost #VALUE!


Mark-up 4,218.79
Total Item Cost #VALUE!
Unit Cost #VALUE!
Item No. 405 Structural Concrete
QTY. = #VALUE! cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland Cement, 40 kgs #VALUE! bags 220.00 #VALUE!
Washed Sand #VALUE! cu. m. 500.00 #VALUE!
3/4" Crushed Gravel #VALUE! cu. m. 600.00 #VALUE!
Gravel fill 4.00 cu. m. 450.00 1,800.00
Forms All LS 5,000.00 5,000.00

Sub-total #VALUE!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 4.00 530.00 2,120.00
Skilled Laborer (Mason/Carpenter) 4 4.00 400.00 6,400.00
Unskilled Laborer 8 4.00 290.00 9,280.00

Sub-total 17,800.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete Mixer (1-Bagger) 1 4.00 1,390.00 5,560.00
Minor tools (10% of Labor) 1,780.00

Sub-total 7,340.00

Total Direct Cost #VALUE!


Mark-up 34,822.39
Total Item Cost #VALUE!
Unit Cost #VALUE!

Item No. 1003 Carpentry & Joinry Works


QTY. = 11,127.60 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Marine Plywood 1/4" x 4' x 8' 4,055.00 pcs. 355.00 1,439,525.00
Ceiling joists (Nailers/Hangers) 66,766.00 bd. Ft. 75.00 5,007,450.00
Assorted CWN 35.00 kgs. 70.00 2,450.00

Sub-total 6,449,425.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 12.00 530.00 6,360.00
Skilled Laborer (Carpenter) 2 12.00 400.00 9,600.00
Unskilled Laborer 2 12.00 290.00 6,960.00

Sub-total 22,920.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Scaffoldings LS All 3,000.00 3,000.00

Sub-total 3,000.00

Total Direct Cost 6,475,345.00


Mark-up 62,155.68
Total Item Cost 6,537,500.68
Unit Cost 587.50
Item No. 1010 Doors and Windows
QTY. = All LS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Swing Type Steel Casement Window with Glass (1 s 1.80 sq.m. 1,850.00 3,330.00
#REF! #REF! #REF! 920.00 #REF!
#REF! #REF! #REF! 6,500.00 #REF!
PVC Doors including Jamb and accessories (0.80m 1.00 sets 2,850.00 2,850.00
#REF! #REF! #REF! 75.00 #REF!
#REF! #REF! #REF! 450.00 #REF!
#REF! #REF! #REF! 35.00 #REF!
CWN (assorted) 4.00 kgs 70.00 280.00
Miscellaneous materials. All LS 1,000.00 1,000.00

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 2.00 530.00 1,060.00
Skilled Laborer (Carpenter) 1 2.00 400.00 800.00
Unskilled Laborer 2 2.00 290.00 1,160.00

Sub-total 3,020.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Electric drill 1 2.00 100.00 200.00
Minor tools (10% of Labor) 302.00

Sub-total 502.00

Total Direct Cost #REF!


Mark-up #REF!
Total Item Cost #REF!
Unit Cost #REF!

Item No. 1100 Electrical Works


QTY. = All LS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL

Compact LED lamp 21.00 pcs. 650.00 13,650.00


Porcelain socket # 4"Ø 23.00 pcs. 150.00 3,450.00
Light Switch 1 way 1 gang 31.00 set 45.00 1,395.00
#REF! #REF! #REF! 140.00 #REF!
Light Switch 3 way 2 gang 12.00 set 140.00 1,680.00
Utility Box (G.I. TYPE) 119.00 pcs. 140.00 16,660.00
PVC Conduit Long Elbow , 12.50mm Ø 160.00 pcs. 15.00 2,400.00
Enclosed Air Circuit Breaker 30 amp. 1.00 set 70.00 70.00
spool insulator and secondary rack w/ bolt 2.00 set 140.00 280.00
0.00 - 0 15.00 -
mica tube 2.00 rolls 65.00 130.00
Electrical Tape 3/4" x 20 yds 75.00 pcs. 30.00 2,250.00
bolt-on Circuit Breaker 100 amp. 1.00 sets 26.00 26.00
bolt-on Circuit Breaker 60 amp. 8.00 sets 40.00 320.00
#REF! #REF! #REF! 25.00 #REF!
#REF! #REF! #REF! 15.00 #REF!
bolt-on Circuit Breaker 30 amp. 17.00 sets 2,450.00 41,650.00
0.00 500.00 500.00

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman #REF! #REF! 530.00 #REF!
Skilled Laborer (Electrician) 1 #REF! 400.00 #REF!
Unskilled Laborer 2 #REF! 290.00 #REF!

Sub-total #REF!

Total Direct Cost #REF!


Mark-up #REF!
Total Item Cost #REF!
Unit Cost #REF!
Item No. 1002 Plumbing Works
QTY. = All LS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
#REF! #REF! #REF! 6,750.00 #REF!
Faucet 26.00 set 80.00 2,080.00
#REF! #REF! #REF! 25.00 #REF!
PVC pipe 4" dia. 30.00 pcs. 125.00 3,750.00
PVC pipe 100mm Ø 78.00 pcs. 125.00 9,750.00
PVC pipe 150mm Ø 45.00 pcs. 110.00 4,950.00
PVC pipe 50mm Ø 50.00 pcs. 60.00 3,000.00
#REF! #REF! #REF! 290.00 #REF!
#REF! #REF! #REF! 580.00 #REF!
PVC Clean out w/ plug 100mm Ø 20.00 pcs. 290.00 5,800.00
PVC pipe 100mm Ø Elbow 1/8bend 10.00 pcs. 185.00 1,850.00
#REF! #REF! #REF! 500.00 500.00

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 0 0.00 530.00 -
Skilled Laborer (Plumber) 2 0.00 400.00 -
Unskilled Laborer 4 0.00 290.00 -

Sub-total -

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost #REF!


Mark-up #REF!
Total Item Cost #REF!
Unit Cost #REF!

Item Spl-1 Masonry Works


QTY. = 8,218.97 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
CHB ( 4" x 8" x 16") 102,738.00 pcs 10.00 1,027,380.00
Portland Cement, 40 kgs 4,291.00 bags 220.00 944,020.00
Washed Sand 358.00 cu.m 500.00 179,000.00
RSB 10mmØ 22,753.00 kgs 52.00 1,183,156.00
Tie wire # 16 GI 25.00 kgs 55.00 1,375.00

Sub-total 3,334,931.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 514.00 530.00 272,420.00
Skilled Laborer (Mason) 2 514.00 400.00 411,200.00
Unskilled Laborer 4 514.00 290.00 596,240.00

Sub-total 1,279,860.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete Mixer (1-Bagger) 1 514.00 1,390.00 714,460.00
Minor tools (10% of Labor) 127,986.00

Sub-total 842,446.00

Total Direct Cost 5,457,237.00


Mark-up 101,233.34
Total Item Cost 5,558,470.34
Unit Cost 676.30
Item Spl 2 Cement Plaster Finish
QTY. = 16,392.34 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland Cement, 40 kgs 7,377.00 bags 220.00 1,622,940.00
Washed Sand 328.00 cu.m 500.00 164,000.00

Sub-total 1,786,940.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 820.00 530.00 434,600.00
Skilled Laborer (Mason) 2 820.00 400.00 656,000.00
Unskilled Laborer 3 820.00 290.00 713,400.00

Sub-total 1,804,000.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Scaffoldings 1 lot 2,500.00 2,500.00

Sub-total 2,500.00

Total Direct Cost 3,593,440.00


Mark-up 79,235.22
Total Item Cost 3,672,675.22
Unit Cost 224.05

Item Spl 3 Roofing Works


QTY. = All LS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Pre-painted Tri-wave Sheets (0.40mm) #VALUE! sq.m 220.00 #VALUE!
Blind Rivets 2.00 boxes 250.00 500.00
Silicone Selant 4.00 pcs. 180.00 720.00

#REF!
#REF! #REF! #REF! 430.00 #REF!
#REF! #REF! #REF! 80.00 #REF!
Miscellaneous #REF! #REF! 500.00 500.00

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 3.00 530.00 1,590.00
Skilled Laborer (Tinsmithman) 1 3.00 400.00 1,200.00
Unskilled Laborer 2 3.00 290.00 1,740.00

Sub-total 4,530.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Electric Drill 1 3.00 100.00 300.00
Riveter 1 3.00 100.00 300.00
Scaffoldings 1 lot 2,500.00 2,500.00

Sub-total 3,100.00

Total Direct Cost #REF!


Mark-up #VALUE!
Total Item Cost #REF!
Unit Cost #REF!

Item Spl 4 Occupational Safety & Health


QTY. = All LS

A. MATERIALS
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Safety Gears All LS 5,000.00 5,000.00
Signages, Barricades & Medicines All LS 8,000.00 8,000.00

Sub-total 13,000.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
First Aider 1.00 6.00 290.00 1,740.00
Part time Safety Practitioner 1.00 4.00 530.00 2,120.00

Sub-total 3,860.00

Total Direct Cost 16,860.00


Mark-up 480,386.04
Total Item Cost 497,246.04
Unit Cost 497,246.04
Department of Public Works and Highways (DPWH)
Contract ID : 12AJ0030
Contract Name : Completion of Hospital at Bayambang District Hospital and Construction of Multi-Purpose Bldg. (Daycare) at
Brgy. Sanlibo, Bayamabang, Pangasinan, Improvement of Multi-Purpose Bldg at Doyong NHS, Construction of
Multi-Purpose Bldg. at Bureau of Jail Management and Penology, Construction of Multi-Purpose Pavement at
Brgys. Sapinit, Polo and Turac, San Carlos City, Pangasinan (CLUSTER VI)
Contract Location: Bayambang & San Carlos City, Pangasinan

SUMMARY OF TOTAL BID AMOUNT

Construction of 2-units 6-CL School Building (2-storey) at Malasiqui NHS, Malasiqui, Pangasinan
Item No. Description Amount
803 Structural Excavation 6,180.07
404 Reinforcing Steel Bars #VALUE!
405 Structural Concrete #VALUE!
1003 Carpentry & Joinery Works 6,537,500.68
1010 Doors & Windows #REF!
1100 Electrical Works #REF!
1002 Plumbing Works #REF!
Spl.1 Masonry Works 5,558,470.34
Spl.2 Plastering Works 3,672,675.22
Spl.3 Roofing Works #REF!
Spl.5 Occupational Safety & Health 497,246.04

TOTAL AMOUNT OF BID : #VALUE!


TOTAL AMOUNT IN WORDS

One Million One Hundred Ninety Three Thousand Four Hundred Three & 23/100 pesos.

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 12AJ0030
Contract Name: Completion of Hospital at Bayambang District Hospital and Construction of Multi-Purpose Bldg. (Daycare) at Brgy. Sanlibo, Bayamabang,
Pangasinan, Improvement of Multi-Purpose Bldg at Doyong NHS, Construction of Multi-Purpose Bldg. at Bureau of Jail Management and
Penology, Construction of Multi-Purpose Pavement at Brgys. Sapinit, Polo and Turac, San Carlos City, Pangasinan (CLUSTER VI)

Contract Location: Bayambang & San Carlos City, Pangasinan

BILL OF QUANTITIES
Part No. Part Description:

Construction of 2-units 6-CL School Building (2-storey) at Malasiqui NHS, Malasiqui, Pangasinan
(Columns (1), (2), (3) and (4) are to be filled up by the
Procuring Entity) (Column (5) and (6) to be filled up by the Bidder)

Pay Item no. Description Unit Quantity Unit Price (Pesos) Amount (Pesos)

In words: Pesos In words: Pesos


five hundred seventy four & 89/100 pesos six thousand one hundred eighty &
07/100 pesos
803 Structural Excavation CU.M. 2,280.48
In figures: In figures:

Php 2.71 Php 6,180.07


In words: Pesos In words: Pesos
eighty five & 29/100 pesos eighteen thousand seven hundred eighty
nine & 39/100 pesos
404 Reinforcing Steel Bars kgs. #VALUE!
In figures: In figures:

Php #VALUE! Php #VALUE!


In words: Pesos In words: Pesos
six thousand thirty eight & 10/100 pesos one hundred thirty two thousand two
hundred thirty four & 39/100 pesos
405 Structural Concrete cu.m #VALUE!
In figures: In figures:

Php #VALUE! Php #VALUE!


In words: Pesos In words: Pesos
one thousand forty four & 65/100 pesos two hundred three thousand three hundred
thirty & 68/100 pesos
1003 Carpentry & Joinery Works sq.m 11,127.60
In figures: In figures:
Php 587.50 Php 6,537,500.68
In words: Pesos In words: Pesos
one hundred fifty eight thousand seven one hundred fifty eight thousand seven
hundred forty two & 59/100 pesos hundred forty two & 59/100 pesos
1010 Doors & Windows LS All
In figures: In figures:
Php #REF! Php #REF!
In words: Pesos In words: Pesos
fifty one thousand one hundred twenty fifty one thousand one hundred twenty
eight & 12/100 pesos eight & 12/100 pesos
1100 Electrical Works LS All
In figures: In figures:

Php #REF! Php #REF!


In words: Pesos In words: Pesos
twenty three thousand four hundred twenty three thousand four hundred
twenty one & 02/100 pesos twenty one & 02/100 pesos
1002 Plumbing Works LS All
In figures: In figures:

Php #REF! Php #REF!


In words: Pesos In words: Pesos
nine hundred sixty two & 45 pesos three hundred thirty five thousand one
hundred forty four & 34/100 pesos
Spl.1 Masonry Works sq.m 8,218.97
In figures: In figures:

Php 676.30 Php 5,558,470.34


In words: Pesos In words: Pesos
three hundred fifty four & 62/100 pesos
two hundred sixteen thousand four
hundred thirty five & 22/100 pesos
Spl.2 Plastering Works sq.m 16,392.34
In figures: In figures:

Php 224.05 Php 3,672,675.22


In words: Pesos In words: Pesos

twenty six thousand sixteen & 42/100 twenty six thousand sixteen & 42/100
Spl.3 Roofing Works LS All
pesos pesos
In figures: In figures:
Php #REF! Php #REF!
In words: Pesos In words: Pesos

twenty one thousand nine hundred eighty twenty one thousand nine hundred eighty
Spl.5
Occupational Safety &
LS All
& 99/100 pesos & 99/100 pesos
Health
In figures: In figures:
Php 497,246.04 Php 497,246.04
TOTAL AMOUNT IN WORDS

One Million One Hundred Ninety Three Thousand Four Hundred Three & 23/100 pesos.
Php #VALUE!

Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
Submitted By:

KENWOOD CONSTRUCTION ENTERPRISES


Name of the Bidder

GEORGE T. LI
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
STATEMENT OF WORK ACCOMPLISHED
as of August 25, 2012

Name of Project: Name of Contractor: KENWOOD CONSTRUCTION ENTERPRISES


Completion of Hospital at Bayambang District Hospital and Construction of Multi-Purpose Bldg. (Daycare) at Brgy. Sanlibo, Bayamabang, Pangasinan, Contract Amount: 3,777,072.52
Improvement of Multi-Purpose Bldg at Doyong NHS, Construction of Multi-Purpose Bldg. at Bureau of Jail Management and Penology, Construction of Multi-
Purpose Pavement at Brgys. Sapinit, Polo and Turac, San Carlos City, Pangasinan (CLUSTER VI) Contract Effectivity: JULY 30, 2012
Contract Expiry: JANUARY 25, 2013
FUNDING SOURCE Actual Starting Date: JULY 30, 2012
Calendar Days: 180 CD

Construction of 2-units 6-CL School Building (2-storey) at Malasiqui NHS, Malasiqui, Pangasinan
APPROVED QUANTITY TOTAL VALUE OF WORK ACCOMP
ITEM NO. DESCRIPTION UNIT TOTAL QTY: UNIT COST ITEM COST % Wt.
PREVIOUS THIS BILLING TO DATE PREVIOUS THIS BILLING TO DATE (%)

803 Structural Excavation cu.m 2,280.48 2.71 6,180.07 #VALUE! 10.75 10.75 29.13 29.13 #VALUE!
404 Reinforcing Steel Bars kgs. #VALUE! #VALUE! #VALUE! #VALUE! 178.78 178.78 #VALUE! #VALUE! #VALUE!
405 Structural Concrete cu.m. #VALUE! #VALUE! #VALUE! #VALUE! 3.65 3.65 #VALUE! #VALUE! #VALUE!
1003 Carpentry & Joinery Works sq.m. 11,127.60 587.50 6,537,500.68 #VALUE! - - - - #VALUE!
1010 Doors & Windows LS All #REF! #REF! #REF! - - #REF! #REF! #REF!
1100 Electrical Works L.S. All #REF! #REF! #REF! 0.20 0.20 #REF! #REF! #REF!
1002 Plumbing Works L.S. All #REF! #REF! #REF! - - #REF! #REF! #REF!
Spl.1 Masonry Works sq.m. 8,218.97 676.30 5,558,470.34 #VALUE! 279.72 279.72 189,170.61 189,170.61 #VALUE!
Spl.2 Plastering Works sq.m. 16,392.34 224.05 3,672,675.22 #VALUE! - - - - #VALUE!
Spl.3 Roofing Works #REF! #VALUE! #REF! #REF! #REF! - - #REF! #REF! #REF!
Spl.5 Occupational Safety & Health L.S. All 497,246.04 497,246.04 #VALUE! 0.27 0.27 134,256.43 134,256.43 #VALUE!

TOTAL #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!


I hereby certify that the accounts and the work accomplished stated above are correct and I hereby certify that all work items were duly verified by the I hereby certify that the materials used in
the labor and materials in connection with this project were already paid, and payment thereof undersigned and have been accomplished in accordance with the plans the project have been tested and passed all the
requested specifications and progress thereof. requirements.

By:
KENWOOD CONSTRUCTION ENTERPRISES ISADORA D. PORTUGUEZ ELDRED M. MISLANG BLESILDA P. ESTRADA ALEX S. MAIQUEZ
Contractor Architech II Project Engineer II OIC-Chief Planning & Design Section. OIC-Chief MQC Section

RECOMMENDING APPROVAL: APPROVED:

AQUILINO M. NICER MARIETA B. MENDOZA


OIC-Asst. District Engineer OIC- District Engineer
BACK-UP COMPUTATION
Construction of 2-units 6-CL School Building (2-storey) at Malasiqui NHS, Malasiqui, Pangasinan

ITEM 803 STRUCTURE EXCAVATION

LENGTH WIDTH DEPTH # SETS QUANTITY


WALL FOOTING (WF)
60.75 0.30 0.40 1.00 7.29
SEPTIC VAULT
2.40 1.20 1.20 1.00 3.46

TOTAL 10.75 CU.M

ITEM 404 REINFORCING STEEL BARS

LENGTH # PCS # SETS kg/m F.S. QUANTITY


WALL FOOTING (WF)
60.75 3.00 1.00 0.616 1.10 123.49
0.40 204.00 1.00 0.616 1.10 55.29
SEPTIC VAULT (COVER)
3.10 7.00 1.00 0.888 1.10
1.30 16.00 1.00 0.888 1.10

TOTAL 178.78 Kgs.

ITEM 405 STRUCTURAL CONCRETE

LENGTH WIDTH DEPTH # SETS QUANTITY


WALL FOOTING (WF)
60.75 0.30 0.20 1.00 3.65
FLOORING SLAB
15.00 10.00 0.10 1.00
entrance 10.00 2.25 0.10 1.00
SLAB (SEPTIC VAULT)
3.00 1.20 0.10 1.00
2.00 1.20 0.10 1.00
WALL FOOTING (SEPTIC VAULT)
9.00 0.30 0.15 1.00

TOTAL 3.65 CU.M


ITEM 1003 CARPENTRY & JOINERY WORKS

LENGTH WIDTH # SETS QUANTITY


CEILING (interior)
15.00 10.00 1.00
CEILING (eaves)
55.80 0.80 1.00

TOTAL 0.00 SQ.M

ITEM 1010 DOORS & WINDOWS

Q = ALL Q = ALL

ITEM 1002 PLUMBING WORKS

Q = ALL Q = ALL

ITEM 1100 ELECTRICAL WORKS

Q = ALL Q = ALL

ITEM SPL-1 MASONRY WORKS

LENGTH HEIGHT # SETS QUANTITY


EXTERIOR WALL
40.00 3.10 1.00 124.00
WALL PARTITION
60.75 3.30 1.00 200.48
APEX
10.00 2.40 2.00
LESS WINDOWS & DOOR
2.40 1.20 3.00 -8.64
1.20 1.20 7.00 -10.08
1.50 1.20 1.00 -1.80
0.60 0.60 2.00 -0.72
1.80 2.10 1.00 -3.78
1.00 2.10 7.00 -14.70
0.80 2.10 3.00 -5.04
SEPTIC VAULT
9.00 1.50 1.00

TOTAL 279.72 SQ.M


ITEM SPL-2 PLASTERING WORKS

LENGTH HEIGHT # SETS #FACES QUANTITY


EXTERIOR WALL
40.00 3.10 1.00 2.00
WALL PARTITION
60.75 2.90 1.00 2.00
APEX
10.00 2.40 2.00 1.00
LESS WINDOWS & DOOR
2.40 1.20 3.00 2.00
1.20 1.20 7.00 2.00
1.50 1.20 1.00 2.00
0.60 0.60 2.00 2.00
1.80 2.10 1.00 2.00
1.00 2.10 7.00 2.00
0.80 2.10 3.00 2.00
SEPTIC VAULT
9.00 1.50 1.00 1.00

TOTAL 0.00 SQ.M

ITEM SPL-3 ROOFING WORKS

Q = ALL Q = ALL

ITEM SPL.4 OCCUPATIONAL SAFETY & HEALTH

Q = ALL Q = ALL
STATEMENT OF WORK ACCOMPLISHED
as of August 25, 2012

Name of Project: Name of Contractor: KENWOOD CONSTRUCTION ENTERPRISES


Completion of Hospital at Bayambang District Hospital and Construction of Multi-Purpose Bldg. (Daycare) at Contract Amount: 3,777,072.52
Brgy. Sanlibo, Bayamabang, Pangasinan, Improvement of Multi-Purpose Bldg at Doyong NHS, Construction of
Multi-Purpose Bldg. at Bureau of Jail Management and Penology, Construction of Multi-Purpose Pavement at Contract Effectivity: JULY 30, 2012
Brgys. Sapinit, Polo and Turac, San Carlos City, Pangasinan (CLUSTER VI)
Contract Expiry: JANUARY 25, 2013
FUNDING SOURCE Actual Starting Date: JULY 30, 2012
Calendar Days: 180 CD

APPROVED QUANTITY TOTAL VALUE OF WORK ACCOMP


NO. NAME OF PROJECT TOTAL COST % Wt.
PREVIOUS THIS BILLING TO DATE PREVIOUS THIS BILLING TO DATE (%)

Construction of Multi-Purpose Building at Brgy. Sanlibo,


I 596,702.26 15.80% 76,967.61 76,967.61 2.04%
Bayambang, Pangasinan
Improvement of Multi-purpose Bldg. at Doyong NHS, San
II 298,349.65 7.90% - - 0.00%
Carlos City, Pangasinan
Completion of Bayambang District Hospital
III 1,193,403.23 31.60% #VALUE! #VALUE! #VALUE!
(OPD/Laboratory Complex Bldg.), Bayambang, Pangasinan
Construction of Multi-Purpose Bldg. at Bureau of Jail
IV 497,243.12 13.16% - - 0.00%
Management and Penology, San Carlos City, Pangasinan
Construction of Multi-Purpose Concrete Pavement at Brgy.
V 397,799.76 10.53% 397,799.76 397,799.76 10.53%
Sapinit, San Carlos City, Pangasinan
Construction of Multi-Purpose Concrete Pavement at Brgy.
VI 396,787.25 10.51% 204,215.93 204,215.93 5.41%
Polo, San Carlos City, Pangasinan
Construction of Multi-Purpose Concrete Pavement at Brgy.
VII 396,787.25 10.51% - - 0.00%
Turac, San Carlos City, Pangasinan

TOTAL 3,777,072.52 100.00% #VALUE! #VALUE! #VALUE!


I hereby certify that the accounts and the work accomplished stated above I hereby certify that all work items were duly verified by the I hereby certify that the materials used in
are correct and the labor and materials in connection with this project were already undersigned and have been accomplished in accordance with the plans the project have been tested and passed all the
paid, and payment thereof requested specifications and progress thereof. requirements.

By:
KENWOOD CONSTRUCTION ENTERPRISES ISADORA D. PORTUGUEZ ELDRED M. MISLANG BLESILDA P. ESTRADA ALEX S. MAIQUEZ
Contractor Architech II Project Engineer II OIC-Chief Planning & Design Se OIC-Chief MQC Section

Recommending Approval: APPROVED:

AQUILINO M. NICER MARIETA B. MENDOZA


OIC-Asst. District Engineer OIC- District Engineer
STATEMENT OF WORK ACCOMPLISHED
as of September 27, 2012

Name of Project: Name of Contractor: KENWOOD CONSTRUCTION ENTERPRISES


Completion of Hospital at Bayambang District Hospital and Construction of Multi-Purpose Bldg. (Daycare) at Brgy. Sanlibo, Bayamabang, Contract Amount: 3,777,072.52
Pangasinan, Improvement of Multi-Purpose Bldg at Doyong NHS, Construction of Multi-Purpose Bldg. at Bureau of Jail Management and
Penology, Construction of Multi-Purpose Pavement at Brgys. Sapinit, Polo and Turac, San Carlos City, Pangasinan (CLUSTER VI) Contract Effectivity: JULY 30, 2012
Contract Expiry: JANUARY 25, 2013
FUNDING SOURCE Actual Starting Date: JULY 30, 2012
Calendar Days: 180 CD

Construction of 2-units 6-CL School Building (2-storey) at Malasiqui NHS, Malasiqui, Pangasinan
APPROVED QUANTITY TOTAL VALUE OF WORK ACCOMP
ITEM NO. DESCRIPTION UNIT TOTAL QTY: UNIT COST ITEM COST % Wt.
PREVIOUS THIS BILLING TO DATE PREVIOUS THIS BILLING TO DATE (%)

803 Structural Excavation cu.m 2,280.48 2.71 6,180.07 #VALUE! 10.75 2,269.73 2,280.48 6,180.07 - 6,180.07 #VALUE!
404 Reinforcing Steel Bars kgs. #VALUE! #VALUE! #VALUE! #VALUE! 178.78 #VALUE! #VALUE! 15,248.15 #VALUE! #VALUE! #VALUE!
405 Structural Concrete cu.m. #VALUE! #VALUE! #VALUE! #VALUE! 3.65 #VALUE! #VALUE! 22,039.07 #VALUE! #VALUE! #VALUE!
1003 Carpentry & Joinery Works sq.m. 11,127.60 587.50 6,537,500.68 #VALUE! 11,127.60 11,127.60 6,537,500.68 6,537,500.68 #VALUE!
1010 Doors & Windows LS All #REF! #REF! #REF! 1.00 1.00 #REF! #REF! #REF!
1100 Electrical Works L.S. All #REF! #REF! #REF! 0.20 0.80 1.00 10,225.62 #REF! #REF! #REF!
1002 Plumbing Works L.S. All #REF! #REF! #REF! 1.00 1.00 #REF! #REF! #REF!
Spl.1 Masonry Works sq.m. 8,218.97 676.30 5,558,470.34 #VALUE! 279.72 7,939.25 8,218.97 269,211.70 5,289,258.64 5,558,470.34 #VALUE!
Spl.2 Plastering Works sq.m. 16,392.34 224.05 3,672,675.22 #VALUE! 16,392.34 16,392.34 3,672,675.22 3,672,675.22 #VALUE!
Spl.3 Roofing Works #REF! #VALUE! #REF! #REF! #REF! 1.00 1.00 #REF! #REF! #REF!
Spl.5 Occupational Safety & Health L.S. All 497,246.04 497,246.04 #VALUE! 0.27 0.73 1.00 5,934.87 491,311.17 497,246.04 #VALUE!

TOTAL #VALUE! #VALUE! 328,839.48 #VALUE! #VALUE! #VALUE!


I hereby certify that the accounts and the work accomplished stated above I hereby certify that all work items were duly verified by the I hereby certify that the materials used in
are correct and the labor and materials in connection with this project were undersigned and have been accomplished in accordance with the plans the project have been tested and passed all the
already paid, and payment thereof requested specifications and progress thereof. requirements.

By:
KENWOOD CONSTRUCTION ENTERPRISES ISADORA D. PORTUGUEZ ELDRED M. MISLANG BLESILDA P. ESTRADA ALEX S. MAIQUEZ
Contractor Architech II Project Engineer II OIC-Chief Planning & Design Section. OIC-Chief MQC Section

RECOMMENDING APPROVAL: APPROVED:

AQUILINO M. NICER MARIETA B. MENDOZA


OIC-Asst. District Engineer OIC- District Engineer
STATEMENT OF WORK ACCOMPLISHED
as of September 27, 2012

Name of Project: Name of Contractor: KENWOOD CONSTRUCTION ENTERPRISES


Completion of Hospital at Bayambang District Hospital and Construction of Multi-Purpose Bldg. (Daycare) at Contract Amount: 3,777,072.52
Brgy. Sanlibo, Bayamabang, Pangasinan, Improvement of Multi-Purpose Bldg at Doyong NHS, Construction of
Multi-Purpose Bldg. at Bureau of Jail Management and Penology, Construction of Multi-Purpose Pavement at Contract Effectivity: JULY 30, 2012
Brgys. Sapinit, Polo and Turac, San Carlos City, Pangasinan (CLUSTER VI)
Contract Expiry: JANUARY 25, 2013
FUNDING SOURCE Actual Starting Date: JULY 30, 2012
Calendar Days: 180 CD

APPROVED QUANTITY TOTAL VALUE OF WORK ACCOMP


NO. NAME OF PROJECT TOTAL COST % Wt.
PREVIOUS THIS BILLING TO DATE PREVIOUS THIS BILLING TO DATE (%)

Construction of Multi-Purpose Building at Brgy. Sanlibo,


I 596,702.26 15.80% 76,967.61 519,734.65 596,702.26 15.80%
Bayambang, Pangasinan
Improvement of Multi-purpose Bldg. at Doyong NHS, San
II 298,349.65 7.90% - - 0.00%
Carlos City, Pangasinan
Completion of Bayambang District Hospital
III 1,193,403.23 31.60% 328,839.48 #VALUE! #VALUE! #VALUE!
(OPD/Laboratory Complex Bldg.), Bayambang, Pangasinan
Construction of Multi-Purpose Bldg. at Bureau of Jail
IV 497,243.12 13.16% Err:540 Err:540 Err:540
Management and Penology, San Carlos City, Pangasinan
Construction of Multi-Purpose Concrete Pavement at Brgy.
V 397,799.76 10.53% 397,799.76 - 397,799.76 10.53%
Sapinit, San Carlos City, Pangasinan
Construction of Multi-Purpose Concrete Pavement at Brgy.
VI 396,787.25 10.51% 201,089.11 Err:540 Err:540 Err:540
Polo, San Carlos City, Pangasinan
Construction of Multi-Purpose Concrete Pavement at Brgy.
VII 396,787.25 10.51% 320,429.80 320,429.80 8.48%
Turac, San Carlos City, Pangasinan

TOTAL 3,777,072.52 100.00% 1,004,695.96 #VALUE! #VALUE! #VALUE!


I hereby certify that the accounts and the work accomplished stated above I hereby certify that all work items were duly verified by the I hereby certify that the materials used in
are correct and the labor and materials in connection with this project were already undersigned and have been accomplished in accordance with the plans the project have been tested and passed all the
paid, and payment thereof requested specifications and progress thereof. requirements.

By:
KENWOOD CONSTRUCTION ENTERPRISES ISADORA D. PORTUGUEZ ELDRED M. MISLANG BLESILDA P. ESTRADA ALEX S. MAIQUEZ
Contractor Architech II Project Engineer II OIC-Chief Planning & Design Secti OIC-Chief MQC Section

Recommending Approval: APPROVED:

AQUILINO M. NICER MARIETA B. MENDOZA


OIC-Asst. District Engineer OIC- District Engineer
Department of Public Works and Highways (DPWH)
Contract ID : 12AJ0017
Contract Name : Completion of Multi-Purpose Building at Buenlag 1st & Manabong Sur, Bayambang, Pangasinan, Construction of 2-Cl at
Arenas NHS, Ambayat 2nd, Bayambang, Pangasinan, Construction of 1-Cl at Bogaoan E/S, San Carlos City and Completion
of Multi-Purpose Building (Gym) at Brgy. Coliling & Brgy. Quintong, San Carlos City, Pangasinan (CLUSTER I)

Contract Location: Bayambang & San Carlos City, Pangasinan

SUMMARY OF LABOR, EQUIPMENT RENTALS & MATERIAL COST

MATERIALS COST

Description Unit Price


C-Rafter 46mm x 148mm (1.20mm) ………………………… 1,050.00 / pcs.
C-Purlins 44mm x 75mm (1.00mm) ………………………… 460.00 / pcs.
C-Purlins 44mm x 100mm (1.00mm) ………………………… 510.00 / pcs.
C-Purlins 50mm x 150mm (1.40mm) ………………………… 1,075.00 / pcs.
Facia Board 50mm x 250mm (0.98mm) ………………………… 900.00 / pcs.
Anchor Bolt, 16mmØ x 200mm ………………………… 150.00 / pcs.
Anchor Bolt, 16mmØ x 250mm ………………………… 170.00 / pcs.
Anchor Bolt, 12mmØ x 150mm ………………………… 100.00 / pcs.
20mm dia. X 50 Machine Bolts w/ nuts ………………………… 100.00 / pcs.
20mm dia. X 500 Straight Bolts w/ nuts ………………………… 250.00 / pcs.
16mm dia. X 200 Anchor Bolts w/ nuts ………………………… 120.00 / pcs.
10mm Thk. Steel Plate ………………………… 18,500.00 / pcs.
Gusset Plates 4 x 8 x 4mm ………………………… 12,550.00 / pcs.
Base Plate 150mm x 300mm x 4mm ………………………… 300.00 / pcs.
Base Plate 150mm x 150mm x 4mm ………………………… 150.00 / pcs.
Base Plate 250mm x 200mm x 4mm ………………………… 200.00 / pcs.
71.2 x 71.2 x 5.00mm Angle Bar ………………………… 2,425.00 / pcs.
46.8 x 46.8 x 5.00mm Angle Bar ………………………… 1,400.00 / pcs.
46.8 x 46.8 x 4.25mm Angle Bar ………………………… 980.00 / pcs.
46.8 x 46.8 x 3.50mm Angle Bar ………………………… 800.00 / pcs.
38.0 x 38.0 x 3.50mm Angle Bar ………………………… 685.00 / pcs.
20mm dia. Tension Rod (Strut 1) ………………………… 50.00 / kgs.
Plain 12mm dia w/ nuts & washer at both ends (Sag Rod) ………………………… 80.00 / pcs.
Plain 12mm dia (Cross bracing) ………………………… 50.00 / kgs.
Std. Turn Buckel 12mm dia. ………………………… 200.00 / pcs.
C-Rafter 46mmx150mm (1.20mm) ………………………… 1,050.00 / pcs.
C-Purlins 44mm x 100mm (1.0mm) ………………………… 510.00 / pcs.
Facia Board 50mm x 250mm (0.98mm) ………………………… 900.00 / pcs.
Anchor Bolt, 16mmØ x .200mm ………………………… 150.00 / pcs.
Anchor Bolt, 12mmØ x 150mm ………………………… 100.00 / pcs.
Base / Sole Plate 150mm x 150mm x 4mm ………………………… 150.00 / pcs.
Base Plate 300mm x 150mm x 4mm ………………………… 300.00 / pcs.
Cleats 48.1 x 48.1 x 3.5mm Angular bar ………………………… 950.00 / pcs.
Sag Rod(10mm ø) Plain bar with Bolts & Washers ………………………… 80.00 / pcs.
Paint brush 4" ………………………… 90.00 / pcs.
Thinner ………………………… 250.00 / gal
Red Lead Primer ………………………… 550.00 / gal
Welding Rod ………………………… 120.00 / kgs.
Hacksaw blade ………………………… 65.00 / pcs.
150X150X4mm, Base Plate ………………………… 150.00 / pcs.
10mm dia.Sag rod w/n/b ………………………… 80.00 / pcs.
10mm dia,x0.70m.Dowels ………………………… 25.00 / pcs.
12mm dia. X 150mm long Anchor Bolt ………………………… 80.00 / pcs.

Ceramics Glazed Tiles & Trims ………………………… 750.00 / sq.m.


Ceramics Unglazed Tiles & Trims ………………………… 850.00 / sq.m.
Tile Grout ………………………… 70.00 / kls.

Paint brush 4" ………………………… 90.00 / pcs.


Paint brush 2" ………………………… 45.00 / pcs.
Paint Tinner ………………………… 240.00 / gal
Red Lead Primer ………………………… 580.00 / gal
Welding Rod ………………………… 120.00 / kgs.
Hacksaw blade ………………………… 75.00 / pcs.
Portland Cement, 40 kgs ………………………… 225.00 / bags
Washed Sand ………………………… 480.00 / cu. m.
Gravel Fill ………………………… 450.00 / cu. m.
River mix ………………………… 300.00 / cu.m.
Crushed Gravel ………………………… 580.00 / cu. m.
Plywood - 1/2 x 4' x 8' ………………………… 625.00 / pcs.
Plywood - 1/4 x 4' x 8' ………………………… 355.00 / pcs.
Good Lumber ………………………… 75.00 / bd.ft
Coco Lumber ………………………… 28.00 / bd.ft
Air ventillation ………………………… 450.00 / set
Assorted CWN ………………………… 70.00 / kgs
Asstd. RSB ………………………… 55.00 / kgs
Tie wire # 16 GI ………………………… 57.00 / kgs
CHB ( 4" x 8" x 16") ………………………… 10.00 / pcs
Security Steel Grills (10mm) ………………………… 1,200.00 / sq.m.
Sliding Analuk Windows ………………………… 3,000.00 / sq.m.
Jalousie window w/ Aluminum Frame ………………………… 850.00 / sq.m.
Swing type Steel Casement window with glass ………………………… 1,850.00 / sq.m.
Panel type door (2.10m X 0.90m) incl. Door jambs & …………………………
Hinges with screw. 5,000.00 / sets
5/8"Glass Door With Aluminum Frames ………………………… 6,500.00 / sq.m.
Flush hollow core door ………………………… 920.00 / sq.m.
PVC Door (2.10m x 0.80m) incl. Door jambs & Hinges with …………………………
screw. 2,850.00 / units
Improvised Door Lock (Hook-in flat bar 4mm Thk with …………………………
padlock and puller) 380.00 / pcs.
Door lock w/ screw ………………………… 450.00 / pcs.
Hinges ………………………… 35.00 / pcs.
Pre-painted Tri-wave (0.40mm) ………………………… 420.00 / sq.m.
Pre-painted ready made ridge roll (0.40mm) ………………………… 220.00 / L.M.
Pre-painted ready made Flashing S-Type (0.40mm) ………………………… 220.00 / L.M.
Pre-painted ready made End Flashing (0.40mm) ………………………… 220.00 / L.M.
Pre-painted ready made Gutter (0.40mm) ………………………… 220.00 / L.M.
Tekscrew ………………………… 2.00 / pcs.
Blind rivets ………………………… 250.00 / box
Silicon Sealant ………………………… 180.00 / pcs.
Toilet Bowl ………………………… 1,000.00 / set
Water Closet ………………………… 6,750.00 / set
PVC pipe 4" dia. ………………………… 580.00 / pcs.
PVC pipe 2" dia. ………………………… 290.00 / pc.
PVC pipe 4 x 2 wye ………………………… 95.00 / pc.
PVC pipe 4 x 4 wye ………………………… 125.00 / pc.
PVC pipe 4 x 4 tee ………………………… 125.00 / pc.
PVC pipe 4 x 2 Tee ………………………… 80.00 / pc.
PVC pipe 2" dia. Elbow 1/4 bend ………………………… 25.00 / pc.
PVC pipe 2" dia. Elbow 1/8 bend ………………………… 20.00 / pc.
PVC pipe 4" dia. Elbow 1/4 bend ………………………… 80.00 / pc.
PVC pipe 4" dia. Elbow 1/8 bend ………………………… 55.00 / pc.
PVC pipe 2" dia. P-Trap ………………………… 105.00 / pc.
PVC pipe 4" dia. Cleanout w/ plug ………………………… 60.00 / pcs.
PVC pipe Reducer Tee 4" x 2" dia. ………………………… 110.00 / pcs.
Solvent ………………………… 185.00 / can
Floor drain 4" x 4" H.D. ………………………… 290.00 / pc.
G I pipe 1/2" dia ………………………… 365.00 / pcs.
G I coupling 1/2" dia. ………………………… 8.00 / pcs.
G I elbow 1/2" dia. ………………………… 10.00 / pcs.
G I tee 1/2" dia ………………………… 22.00 / pcs.
G I adapter 1/2" dia ………………………… 15.00 / pcs.
Faucet 1/2" dia ………………………… 170.00 / pcs.
PVC pipe 3" dia. (downspout) ………………………… 430.00 / pcs.
PVC pipe 3" dia. Elbow 1/4 bend ………………………… 80.00 / pc.

Flourescent Lighting Fixtures (40 watts) with box type housing ………………………… 650.00 / sets
Lighting Fixture (CFL 20 A) 150.00 / sets
Bulb Receptacles 45.00 / pcs.
Light Switch 1 way 2 gang 140.00 / pc.
Light Switch 1 way 1 gang 140.00 / pc.
Copper Wire #3.50mm2 TW 26.00 / mtrs.
Electrical Tape 40.00 / roll
PVC Pipe Flexible 1/2"dia. 15.00 / mtrs.
PVC Coupling PNS 14,1/2" dia. 10.00 / pcs.
PVC Pipe PNS 14,1/2"dia. 70.00 / pcs.
PVC Pipe PNS 14 1"dia. 140.00 / pcs.
PVC Adapter PNS 14,1/2"dia. 15.00 / pcs.
Entrance cap # 1/2"Ø 65.00 / pcs,
Junction Box (Deep tape w/ Cover) 30.00 / pcs.
Utility Box (Deep tape) ………………………… 25.00 / pcs.
PVC Pipe Flexible 1/2"dia. ………………………… 15.00 / mtrs.
1 set enclosed Panel box w/ 30 AT 2,450.00 / set
main Breaker and 2-20 AT Branch
Convenience outlet/w plate 150.00 / pcs.

Compact flourescent lamp ………………………… 110.00 / sets


Porcelain socket # 4"Ø ………………………… 30.00 / pcs.

Light Switch 1 way 2 gang ………………………… 150.00 / pcs.


Light Switch 1 way 1 gang ………………………… 150.00 / pcs.
Duplex Convenient Outlet ………………………… 200.00 / pcs.
Copper Wire #3.50mm2 TW ………………………… 24.00 / mtrs.
Electrical Tape ………………………… 50.00 / roll
PVC Coupling PNS 14,1/2" dia. ………………………… 10.00 / pcs.
PVC Pipe PNS 14,1/2"dia. ………………………… 70.00 / pcs.
PVC Adapter PNS 14,1/2"dia. ………………………… 25.00 / pcs.
Entrance cap # 1/2"Ø ………………………… 80.00 / pcs,
Junction Box (Deep tape w/ Cover) ………………………… 30.00 / pcs.
Air circuit breaker 20 AT ………………………… 600.00 / sets
Lighting Fixture GI pipe Hanger ………………………… 350.00 / sets

Flat wall Latex (Boysen) ………………………… 490.00 / gals.


Latex Paint Semi- Gloss ………………………… 490.00 / gals.
Flatwall Enamel (White Boysen) ………………………… 600.00 / gals.
Quick Drying Enamel ………………………… 500.00 / gals.
Paint Thinner ………………………… 250.00 / gals.
Paint Brush 4" ………………………… 90.00 / pcs.
Paint roller 12" ………………………… 160.00 / pc.
Assorted Acry Color (Latex) ………………………… 135.00 / ltr.
Assorted Tintin Color (Enamel) ………………………… 150.00 / ltr.
Sandpaper #100 ………………………… 1,600.00 / roll
Calsumine powder ………………………… 15.00 / kg.
Concrete Neutralizer ………………………… 220.00 / gals.
Plasalux GlazingPutty 550.00 gal.
LABOR COST

Designation Rate per Day


Construction Foreman ………………………… 540.00
Skilled Laborer ………………………… 400.00
Semi-skilled Laborer ………………………… 350.00
Unskilled Laborer ………………………… 280.00
First Aider ………………………… 280.00
Part time Safety Practitioner ………………………… 540.00

EQUIPMENT RENTALS

Description Rentals
Plate Compactor ………………………… 610.00
Bar Cutter (manually operated) ………………………… 350.00
Concrete Mixer (1-Bagger) ………………………… 1,390.00
Concrete Vibrator ………………………… 510.00
Water truck (1000 gal) ………………………… 7,750.00
Welding machine ………………………… 500.00
Cutting Outfit w/ complete accessories ………………………… 150.00
Demountable Beam w/ Ropes ………………………… 700.00
Electric Drill ………………………… 100.00
Riveter ………………………… 100.00
Angle Grinder ………………………… 100.00

Submitted By:

ROADTECH CONSTRUCTION
Name of the Bidder

KENNETH C. TAN
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 12AJ0030
Contract Name: Completion of Hospital at Bayambang District Hospital and Construction of Multi-Purpose Bldg. (Daycare) at Brgy.
Sanlibo, Bayamabang, Pangasinan, Improvement of Multi-Purpose Bldg at Doyong NHS, Construction of Multi-Purpose
Bldg. at Bureau of Jail Management and Penology, Construction of Multi-Purpose Pavement at Brgys. Sapinit, Polo and
Turac, San Carlos City, Pangasinan (CLUSTER VI)
Contract Location: Bayambang & San Carlos City, Pangasinan

DETAILED ESTIMATES
Construction of 2-units 6-CL School Building (2-storey) at Malasiqui NHS, Malasiqui, Pangasinan

Item No.103 Structure Excavation


QTY. = 2,280.48 CU.M.

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 2.00 540.00 1,080.00
Semi-skilled Laborer (Leadman) 1 2.00 350.00 700.00
Unskilled Laborer 4 2.00 280.00 2,240.00

Sub-total 4,020.00

Total Direct Cost 4,020.00


Mark-up 2,169.42
Total Item Cost 6,189.42
Unit Cost 2.71

Item No. 404 Reinforcing Steel Bars


QTY. = #VALUE! kgs.
A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Assorted RSB (12mm & 10mm) #VALUE! kgs. 55.00 #VALUE!
Tie wire (#16 G.I.) #VALUE! kgs. 57.00 #VALUE!

Sub-total #VALUE!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 1.00 540.00 540.00
Skilled Laborer (Steelman) 2 1.00 400.00 800.00
Unskilled Laborer 4 1.00 280.00 1,120.00

Sub-total 2,460.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Bar Cutter 1 1.00 350.00 350.00

Sub-total 350.00

Total Direct Cost #VALUE!


Mark-up 3,606.53
Total Item Cost #VALUE!
Unit Cost #VALUE!
Item No. 405 Structural Concrete
QTY. = #VALUE! cu.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland Cement, 40 kgs #VALUE! bags 225.00 #VALUE!
Washed Sand #VALUE! cu. m. 480.00 #VALUE!
3/4" Crushed Gravel #VALUE! cu. m. 580.00 #VALUE!
Gravel fill 4.00 cu. m. 450.00 1,800.00
Forms All LS 5,000.00 5,000.00

Sub-total #VALUE!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 4.00 540.00 2,160.00
Skilled Laborer (Mason/Carpenter) 4 4.00 400.00 6,400.00
Unskilled Laborer 8 4.00 280.00 8,960.00

Sub-total 17,520.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete Mixer (1-Bagger) 1 4.00 1,390.00 5,560.00
Minor tools (10% of Labor) 1,752.00

Sub-total 7,312.00

Total Direct Cost #VALUE!


Mark-up 35,032.68
Total Item Cost #VALUE!
Unit Cost #VALUE!

Item No. 1003 Carpentry & Joinry Works


QTY. = 11,127.60 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Marine Plywood 1/4" x 4' x 8' 4,055.00 pcs. 355.00 1,439,525.00
Ceiling joists (Nailers/Hangers) 66,766.00 bd. Ft. 75.00 5,007,450.00
Assorted CWN 35.00 kgs. 70.00 2,450.00

Sub-total 6,449,425.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 12.00 540.00 6,480.00
Skilled Laborer (Carpenter) 2 12.00 400.00 9,600.00
Unskilled Laborer 2 12.00 280.00 6,720.00

Sub-total 22,800.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Scaffoldings LS All 3,000.00 3,000.00

Sub-total 3,000.00

Total Direct Cost 6,475,225.00


Mark-up 62,581.26
Total Item Cost 6,537,806.26
Unit Cost 587.53
Item No. 1010 Doors and Windows
QTY. = All LS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Swing Type Steel Casement Window with Glass (1 set - 1.80 sq.m. 1,850.00 3,330.00
#REF! #REF! #REF! 920.00 #REF!
#REF! #REF! #REF! 6,500.00 #REF!
PVC Doors including Jamb and accessories (0.80m x 2. 1.00 sets 2,850.00 2,850.00
#REF! #REF! #REF! 75.00 #REF!
#REF! #REF! #REF! 450.00 #REF!
#REF! #REF! #REF! 35.00 #REF!
CWN (assorted) 4.00 kgs 70.00 280.00
Miscellaneous materials. All LS 1,000.00 1,000.00

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 2.00 540.00 1,080.00
Skilled Laborer (Carpenter) 1 2.00 400.00 800.00
Unskilled Laborer 2 2.00 280.00 1,120.00

Sub-total 3,000.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Electric drill 1 2.00 100.00 200.00
Minor tools (10% of Labor) 300.00

Sub-total 500.00

Total Direct Cost #REF!


Mark-up #REF!
Total Item Cost #REF!
Unit Cost #REF!

Item No. 1100 Electrical Works


QTY. = All LS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL

Compact LED lamp 21.00 pcs. 650.00 13,650.00


Porcelain socket # 4"Ø 23.00 pcs. 150.00 3,450.00
Light Switch 1 way 1 gang 31.00 set 45.00 1,395.00
#REF! #REF! #REF! 140.00 #REF!
Light Switch 3 way 2 gang 12.00 set 140.00 1,680.00
Utility Box (G.I. TYPE) 119.00 pcs. 140.00 16,660.00
PVC Conduit Long Elbow , 12.50mm Ø 160.00 pcs. 15.00 2,400.00
Enclosed Air Circuit Breaker 30 amp. 1.00 set 70.00 70.00
spool insulator and secondary rack w/ bolt 2.00 set 140.00 280.00
0.00 - 0 15.00 -
mica tube 2.00 rolls 65.00 130.00
Electrical Tape 3/4" x 20 yds 75.00 pcs. 30.00 2,250.00
bolt-on Circuit Breaker 100 amp. 1.00 sets 26.00 26.00
bolt-on Circuit Breaker 60 amp. 8.00 sets 40.00 320.00
#REF! #REF! #REF! 25.00 #REF!
#REF! #REF! #REF! 15.00 #REF!
bolt-on Circuit Breaker 30 amp. 17.00 sets 2,450.00 41,650.00
0.00 500.00 500.00

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman #REF! #REF! 540.00 #REF!
Skilled Laborer (Electrician) 1 #REF! 400.00 #REF!
Unskilled Laborer 2 #REF! 280.00 #REF!

Sub-total #REF!

Total Direct Cost #REF!


Mark-up #REF!
Total Item Cost #REF!
Unit Cost #REF!
Item No. 1002 Plumbing Works
QTY. = All LS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
#REF! #REF! #REF! 6,750.00 #REF!
Faucet 26.00 set 80.00 2,080.00
#REF! #REF! #REF! 25.00 #REF!
PVC pipe 4" dia. 30.00 pcs. 125.00 3,750.00
PVC pipe 100mm Ø 78.00 pcs. 125.00 9,750.00
PVC pipe 150mm Ø 45.00 pcs. 110.00 4,950.00
PVC pipe 50mm Ø 50.00 pcs. 60.00 3,000.00
#REF! #REF! #REF! 290.00 #REF!
#REF! #REF! #REF! 580.00 #REF!
PVC Clean out w/ plug 100mm Ø 20.00 pcs. 290.00 5,800.00
PVC pipe 100mm Ø Elbow 1/8bend 10.00 pcs. 185.00 1,850.00
#REF! #REF! #REF! 500.00 500.00

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 0 0.00 540.00 -
Skilled Laborer (Plumber) 2 0.00 400.00 -
Unskilled Laborer 4 0.00 280.00 -

Sub-total -

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL

Sub-total -

Total Direct Cost #REF!


Mark-up #REF!
Total Item Cost #REF!
Unit Cost #REF!

Item Spl-1 Masonry Works


QTY. = 8,218.97 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
CHB ( 4" x 8" x 16") 102,738.00 pcs 10.00 1,027,380.00
Portland Cement, 40 kgs 4,291.00 bags 225.00 965,475.00
Washed Sand 358.00 cu.m 480.00 171,840.00
RSB 10mmØ 22,753.00 kgs 55.00 1,251,415.00
Tie wire # 16 GI 25.00 kgs 57.00 1,425.00

Sub-total 3,417,535.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 514.00 540.00 277,560.00
Skilled Laborer (Mason) 2 514.00 400.00 411,200.00
Unskilled Laborer 4 514.00 280.00 575,680.00

Sub-total 1,264,440.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Concrete Mixer (1-Bagger) 1 514.00 1,390.00 714,460.00
Minor tools (10% of Labor) 126,444.00

Sub-total 840,904.00

Total Direct Cost 5,522,879.00


Mark-up 98,932.26
Total Item Cost 5,621,811.26
Unit Cost 684.00
Item Spl 2 Cement Plaster Finish
QTY. = 16,392.34 sq.m

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Portland Cement, 40 kgs 7,377.00 bags 225.00 1,659,825.00
Washed Sand 328.00 cu.m 480.00 157,440.00

Sub-total 1,817,265.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 820.00 540.00 442,800.00
Skilled Laborer (Mason) 2 820.00 400.00 656,000.00
Unskilled Laborer 3 820.00 280.00 688,800.00

Sub-total 1,787,600.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Scaffoldings 1 lot 2,500.00 2,500.00

Sub-total 2,500.00

Total Direct Cost 3,607,365.00


Mark-up 79,043.70
Total Item Cost 3,686,408.70
Unit Cost 224.89

Item Spl 3 Roofing Works


QTY. = All LS

A. MATERIALS:
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Pre-painted Tri-wave Sheets (0.40mm) #VALUE! sq.m 220.00 #VALUE!
Blind Rivets 2.00 boxes 250.00 500.00
Silicone Selant 4.00 pcs. 180.00 720.00

#REF!
#REF! #REF! #REF! 430.00 #REF!
#REF! #REF! #REF! 80.00 #REF!
Miscellaneous #REF! #REF! 500.00 500.00

Sub-total #REF!

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
Construction Foreman 1 3.00 540.00 1,620.00
Skilled Laborer (Tinsmithman) 1 3.00 400.00 1,200.00
Unskilled Laborer 2 3.00 280.00 1,680.00

Sub-total 4,500.00

C. EQUIPMENT COST
DESCRIPTION NO. DAYS RATE TOTAL
Electric Drill 1 3.00 100.00 300.00
Riveter 1 3.00 100.00 300.00
Scaffoldings 1 lot 2,500.00 2,500.00

Sub-total 3,100.00

Total Direct Cost #REF!


Mark-up #VALUE!
Total Item Cost #REF!
Unit Cost #REF!

Item Spl 4 Occupational Safety & Health


QTY. = All LS

A. MATERIALS
DESCRIPTION QTY UNIT UNIT PRICE TOTAL
Safety Gears All LS 5,000.00 5,000.00
Signages, Barricades & Medicines All LS 8,000.00 8,000.00

Sub-total 13,000.00

B. LABOR
DESCRIPTION NO. DAYS RATE TOTAL
First Aider 1.00 6.00 280.00 1,680.00
Part time Safety Practitioner 1.00 4.00 540.00 2,160.00

Sub-total 3,840.00

Total Direct Cost 16,840.00


Mark-up 481,156.04
Total Item Cost 497,996.04
Unit Cost 497,996.04
Department of Public Works and Highways (DPWH)
Contract ID : 12AJ0030
Contract Name : Completion of Hospital at Bayambang District Hospital and Construction of Multi-Purpose Bldg. (Daycare) at Brgy.
Sanlibo, Bayamabang, Pangasinan, Improvement of Multi-Purpose Bldg at Doyong NHS, Construction of Multi-Purpose
Bldg. at Bureau of Jail Management and Penology, Construction of Multi-Purpose Pavement at Brgys. Sapinit, Polo and
Turac, San Carlos City, Pangasinan (CLUSTER VI)

Contract Location: Bayambang & San Carlos City, Pangasinan

SUMMARY OF TOTAL BID AMOUNT

Construction of 2-units 6-CL School Building (2-storey) at Malasiqui NHS, Malasiqui, Pangasinan
Item No. Description Amount
803 Structural Excavation 6,189.42
404 Reinforcing Steel Bars #VALUE!
405 Structural Concrete #VALUE!
1003 Carpentry & Joinery Works 6,537,806.26
1010 Doors & Windows #REF!
1100 Electrical Works #REF!
1002 Plumbing Works #REF!
Spl.1 Masonry Works 5,621,811.26
Spl.2 Plastering Works 3,686,408.70
Spl.3 Roofing Works #REF!
Spl.5 Occupational Safety & Health 497,996.04

TOTAL AMOUNT OF BID : #VALUE!


TOTAL AMOUNT IN WORDS

One Million One Hundred Ninety Five Thousand One Hundred Ninety Eight & 76/100 pesos.

Submitted By:

ROADTECH CONSTRUCTION
Name of the Bidder

KENNETH C. TAN
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
Department of Public Works and Highways (DPWH)
Contract ID : 12AJ0030
Contract Name: Completion of Hospital at Bayambang District Hospital and Construction of Multi-Purpose Bldg. (Daycare) at Brgy. Sanlibo, Bayamabang,
Pangasinan, Improvement of Multi-Purpose Bldg at Doyong NHS, Construction of Multi-Purpose Bldg. at Bureau of Jail Management and
Penology, Construction of Multi-Purpose Pavement at Brgys. Sapinit, Polo and Turac, San Carlos City, Pangasinan (CLUSTER VI)

Contract Location: Bayambang & San Carlos City, Pangasinan

BILL OF QUANTITIES
Part No. Part Description:

Construction of 2-units 6-CL School Building (2-storey) at Malasiqui NHS, Malasiqui, Pangasinan
(Columns (1), (2), (3) and (4) are to be filled up by the
Procuring Entity) (Column (5) and (6) to be filled up by the Bidder)

Pay Item no. Description Unit Quantity Unit Price (Pesos) Amount (Pesos)

In words: Pesos In words: Pesos


five hundred seventy five & 76/100 pesos six thousand one hundred eighty nine &
42/100 pesos
803 Structural Excavation CU.M. 2,280.48
In figures: In figures:

Php 2.71 Php 6,189.42


In words: Pesos In words: Pesos
eighty five & 42/100 pesos eighteen thousand eight hundred eighteen
& 03/100 pesos
404 Reinforcing Steel Bars kgs. #VALUE!
In figures: In figures:

Php #VALUE! Php #VALUE!


In words: Pesos In words: Pesos
six thousand forty seven & 20/100 pesos one hundred thirty two thousand four
hundred thirty three & 68/100 pesos
405 Structural Concrete cu.m #VALUE!
In figures: In figures:

Php #VALUE! Php #VALUE!


In words: Pesos In words: Pesos
one thousand forty six & 22/100 pesos two hundred three thousand six hundred
thirty six & 26/100 pesos
1003 Carpentry & Joinery Works sq.m 11,127.60
In figures: In figures:
Php 587.53 Php 6,537,806.26
In words: Pesos In words: Pesos
one hundred fifty eight thousand nine one hundred fifty eight thousand nine
hundred eighty two & 02/100 pesos hundred eighty two & 02/100 pesos
1010 Doors & Windows LS All
In figures: In figures:
Php #REF! Php #REF!
In words: Pesos In words: Pesos
fifty one thousand two hundred five & fifty one thousand two hundred five &
24/100 pesos 24/100 pesos
1100 Electrical Works LS All
In figures: In figures:

Php #REF! Php #REF!


In words: Pesos In words: Pesos
twenty three thousand four hundred fifty twenty three thousand four hundred fifty
six & 35/100 pesos six & 35/100 pesos
1002 Plumbing Works LS All
In figures: In figures:

Php #REF! Php #REF!


In words: Pesos In words: Pesos
nine hundred sixty three & 90/100 pesos three hundred thirty five thousand six
hundred forty nine & 26/100 pesos
Spl.1 Masonry Works sq.m 8,218.97
In figures: In figures:

Php 684.00 Php 5,621,811.26


In words: Pesos In words: Pesos
three hundred fifty five & 15/100 pesos
two hundred sixteen thousand seven
hundred fifty eight & 70/100 pesos
Spl.2 Plastering Works sq.m 16,392.34
In figures: In figures:

Php 224.89 Php 3,686,408.70


In words: Pesos In words: Pesos

twenty six thousand fifty five & 66/100 twenty six thousand fifty five & 66/100
Spl.3 Roofing Works LS All
pesos pesos
In figures: In figures:
Php #REF! Php #REF!
In words: Pesos In words: Pesos

twenty two thousand fourteen & 14/100 twenty two thousand fourteen & 14/100
Spl.5
Occupational Safety &
LS All
pesos pesos
Health
In figures: In figures:
Php 497,996.04 Php 497,996.04
TOTAL AMOUNT IN WORDS

One Million One Hundred Ninety Five Thousand One Hundred Ninety Eight & 76/100 pesos.
Php #VALUE!

Submitted By:

ROADTECH CONSTRUCTION
Name of the Bidder

KENNETH C. TAN
(Name & Signature of the duly Authorized Bidder's Representative)
Submitted By:

ROADTECH CONSTRUCTION
Name of the Bidder

KENNETH C. TAN
(Name & Signature of the duly Authorized Bidder's Representative)
MANAGER
(Position of the duly Authorized Bidder's Representative)
DETAILED ESTIMATES
Item No. Spl.4
Steel Gate & Perimeter Fences QUANTITY All L.S.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
Assumed Output/day
MATERIAL COST

Steel Gate (4.00m width) 3.00 set 30,000.00 90,000.00


Steel Gate (3.00m width) 1.00 set 21,150.00 21,150.00
Steel junior Gate (1.20m width) 1.00 set 9,000.00 9,000.00
Fences (3.00m width) 11.00 set 11,700.00 128,700.00
Miscellaneous materials (primer, paint thinner, welding rod,etc.,) 2,500.00

Sub- Total 251,350.00


unit cost 251,350.00
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day - -

Construction Foreman 1.00 14.00 524.36 7,341.04


LABOR COST

Skilled Laborer (Welder) 2.00 14.00 380.99 10,667.72


Unskilled Laborer 5.00 14.00 293.96 20,577.20
8.00 14.00 112.00

Note:
Labor includes repair & installation of old fences.

Sub- Total 38,585.96


unit cost 38,585.96
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Assumed Output/day - -

Welding machine 1.00 14.00 500.00 7,000.00


EQUIPMENT COST

Grinder (handy) 1.00 14.00 150.00 2,100.00


Electricity,Acetylane,oxygen & etc. All LS 5,890.93 5,890.93
Minor tools (10% of Labor) 3,858.60

Sub- Total 18,849.53


unit cost 18,849.53
Direct Unit Cost 308,785.49
PREPARED BY: 12% of total DC OCM 37,054.26
12% of total DC CP 37,054.26
12% of (total DC+OCM+CP) VAT 45,947.28
Total Direct & Indirect Unit Cost 428,841.28
Total Direct & Indirect Cost 428,841.28
DETAILED ESTIMATES
Item No. Spl 1
Roofing Works QTY. #REF! sq.m.
DESCRIPTION QUANTITY UNIT U-PRICE(Pesos) TOTAL(P)
Pre-painted Tri-wave (0.40mm) #REF! sq.m. 450.00 #REF!
Pre-painted ready made Flashing(0.40mm) 5.00 pcs. 462.00 2,310.00
MATERIALS COST

Pre-painted ready made Ridge Roll(0.40mm) 2.00 pcs. 462.00 924.00


Tekscrew 150.00 pcs. 2.00 300.00
Blind Rivets 0.50 boxes 200.00 100.00
Silicone Selant 1.00 pcs. 170.00 170.00
Pre-painted ready made S. Gutter 3.00 pcs. 462.00 1,386.00
Miscellaneous All LS 800.00 800.00

Sub- Total #REF!


DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Const'n. Foreman 1 1.00 524.36 524.36
Tinsmithman 1 1.00 380.99 380.99
LABOPR COST

Laborer 2 1.00 293.96 587.92


4 1.00 4
4 1.00 4

12 1.00 12
Sub- Total 1,493.27
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Electric Drill 1 1.00 85.00 85.00
EQUIPMENT COST

Riveter 1 1.00 85.00 85.00


Scafoldings 1 lot 1,000.00 1,000.00

Sub- Total 1,170.00


Total Direct Cost #REF!
Total Indirect Cost #REF!
12% (TDC) 0.15 CP #REF!
12% (TDC) 0.13 OCM #REF!
12% (TDC+CP+OCM) VAT #REF!
Total Item Cost #REF!
Adjusted Unit Cost #REF!
DETAILED ESTIMATES
Item No. 803
Structural Excavation QUANTITY 2,280.48 cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
MATREIAL COST

Sub- Total -
DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Construction Foreman 1.00 1.00 524.36 524.36
Semi-skilled Laborer (Leadman) 1.00 1.00 351.21 351.21
Unskilled Laborer 3.00 1.00 293.96 881.88
LABOAR COST

5.00 1.00 5.00

Sub- Total 1,757.45


DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Sub- Total -
Total Direct Cost 1,757.45
PREPARED BY: 12% of total DC OCM 210.89
12% of total DC CP 210.89
12% of (total DC+OCM+CP) VAT 261.51
Total Item Cost 2,440.75
Adjusted Unit Cost 1.07
DETAILED ESTIMATES
Item No. 104
Structure Backfill QUANTITY #VALUE! cu.m.
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
River mix #VALUE! cu.m. 300.00 #VALUE!
MATERIAL COST

Sub- Total #VALUE!


DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Construction Foreman 1.00 0.50 524.36 262.18
Unskilled Laborer 2.00 0.50 293.96 293.96
3.00 0.50 1.50
LABOR COST

Sub- Total 556.14


DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)

Sub- Total -
Total Direct Cost #VALUE!
PREPARED BY: 12% of total DC OCM #VALUE!
12% of total DC CP #VALUE!
12% of (total DC+OCM+CP) VAT #VALUE!
Total Item Cost #VALUE!
Adjusted Unit Cost #VALUE!
DETAILED ESTIMATES
Item No. 409
Structural Steel QUANTITY All L.S
DESCRIPTION QUANTITY UNIT U- PRICE(P) TOTAL(Pesos)
C-Rafter 46mmx150mm (1.20mm) 7.00 pcs. 1,060.00 7,420.00
C-Purlins 44mm x 75mm (1.0mm) 12.00 pcs. 455.00 5,460.00
Facia Board 50mm x 250mm (0.98mm) 5.00 pcs. 1,000.00 5,000.00
Anchor Bolt, 12mmØ x 150mm 12.00 pcs. 100.00 1,200.00
Anchor Bolt, 12mmØ x 100mm 12.00 pcs. 70.00 840.00
Base Plate 150mm x 150mm x 4mm 2.00 pcs. 150.00 300.00
MATERIAL COST

Base Plate 300mm x 150mm x 4mm 4.00 pcs. 300.00 1,200.00


Cleats 48.1 x 48.1 x 3.5mm Angular bar 1.00 pcs. 800.00 800.00
Sag Rod(10mm ø) Plain bar with Bolts & Washers 22.00 pcs. 80.00 1,760.00
Paint brush 4" 2.00 pcs. 85.00 170.00
Thinner 1.00 gal 240.00 240.00
Red Lead Primer 2.00 gal 600.00 1,200.00
Welding Rod 10.00 kgs. 75.00 750.00
Hacksaw blade 2.00 pcs. 65.00 130.00

Sub- Total 26,470.00


DESCRIPTION NO DAYS RATE(Pesos) TOTAL(Pesos)
Construction Foreman 1.00 2.50 524.36 1,310.90
Skilled Laborer (Welder) 1.00 2.50 380.99 952.48
LABOR COST

Unskilled Laborer 3.00 2.50 293.96 2,204.70


5.00 2.50 12.50

Sub- Total 4,468.08


DESCRIPTION NO DAYS Rental(Pesos) TOTAL(Pesos)
EQUIPMENT COST

Welding machine 1.00 2.50 500.00 1,250.00


Scaffolding 1.00 lot 800.00 800.00
Electricity,Acetylane,oxygen & etc. All LS 2,000.00 2,000.00

Sub- Total 4,050.00


Total Direct Cost 34,988.08
PREPARED BY: 12% of total DC OCM 4,198.57
12% of total DC CP 4,198.57
12% of (total DC+OCM+CP) VAT 5,206.23
Total Item Cost 48,591.44
Adjusted Unit Cost 48,591.44
DETAILED ESTIMATES
Item No. 1013
Roofing Works QUANTITY 16,392.34 sq.m.
DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL(Pesos)
Pre-painted Tri-wave (0.40mm) 16,392.34 sq.m. 400.00 6,556,936.00
MATERIAL COST

Pre-painted ready made ridge roll (0.40mm) 3.00 pcs. 475.00 1,425.00
Pre-painted ready made Flashing (0.40mm) 7.00 pcs. 475.00 3,325.00
Pre-painted ready made Gutter (0.40mm) 3.00 pcs. 475.00 1,425.00
Tekscrew 350.00 pcs. 1.85 647.50
Miscellaneous (sealant, blind revits, etc.,) All LS 300.00 300.00

6,564,058.50
DESCRIPTION NO DAYS RATE TOTAL(Pesos)
Construction Foreman 1.00 1.00 524.36 524.36
Skilled Laborer (Tinsmithman) 1.00 1.00 380.99 380.99
LABOR COST

Unskilled Laborer 2.00 1.00 293.96 587.92


4.00 1.00 4.00

Sub- Total 1,493.27


EQUIPMENT COST

Electric Drill 1.00 1.00 85.00 85.00


Riveter 1.00 1.00 85.00 85.00
Scaffoldings 1.00 lot 500.00 500.00

Sub- Total 670.00


Total Direct Cost 6,566,221.77
PREPARED BY: 12% of total DC OCM 787,946.61
12% of total DC CP 787,946.61
12% of (total DC+OCM+CP) VAT 977,053.80
Total Item Cost 9,119,168.79
Adjusted Unit Cost 556.31