Professional Documents
Culture Documents
ABSA Journal4 2007 - P220 238 - RegulatoryComplianceofaBSL 3LaboratoryUnitinaDrugDiscoveryEnvironment
ABSA Journal4 2007 - P220 238 - RegulatoryComplianceofaBSL 3LaboratoryUnitinaDrugDiscoveryEnvironment
net/publication/279448471
CITATIONS READS
3 4,000
7 authors, including:
Arnold Brunner
Lucerne University of Applied Sciences and Arts
7 PUBLICATIONS 3 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Arnold Brunner on 30 June 2015.
Pharma AG, Basel, Switzerland, 4Novartis Institute for Tropical Diseases, Singapore, and 5Novartis Singapore, Singapore
tional biosafety legislations. The subsequent objectives a well defined volume. This could be a tight flask, tube or
were to draw the line from the recommendations to the container for handling the organisms. The wall of the
realisation of the facility. We then evaluated the imple- flask is not only a liquid enclosure, but also the first line
mentation in comparison with the specifications during of defence. In addition, if this first line of defence is re-
the installation approval. The system was qualified during moved by breaking the flask, there must be another con-
the functional approval and validated during the opera- tainment volume encompassing the inner one to contain
tional approval. Finally, we needed to constitute the con- the microorganisms from unintended release. This is
ditions for the certification of the laboratory before called the “shell-in-a-shell” principle.
switching to the so called “hot operation” mode. Each shell has a certain probability of failure. The
To achieve these goals, biosafety standards and work- probability of an installation, or available detection
ing practices had to be defined that complied with a con- method for failing, will determine the degree and number
sensus of local, country-specific and international and of safety measures to be applied to rule out any release of
local regulations and guidelines. The follow-up objective organisms into the environment. In this view, one could
was to provide information regarding the specific user draw the false conclusion that the risk of unintended
requirements for: release of organisms could be significantly reduced by
• Design and construction of the laboratory using additional containment shells.
• Technical equipment Therefore, the question is how many containment
• Organisational measures including safety and security shells are technically needed to provide safety? Obviously,
guidelines the outer shell will have a greater volume than the inner
This integrated approach is not only a collection of inter- one, leading to a certain rate of distribution and dilution
national ordinances, but also the basis for creating a state- (volume expansion) of organisms in case the inner con-
of-the-art effective research environment providing a high tainment volume fails. In the case of one individual shell
safety level. failing, one should be able to prevent a release of organ-
isms with the help of the negative pressure cascade. If the
Biosafety pressure cascade also fails, a retrograde airflow into the
inner shell will prevent any release until pressure equilib-
General Requirements and Considerations rium is reached. In the state of equilibrium, no exchange
Modern biosafety legislation is directed at the protec- of air will happen. Minor aerosolic contaminations can
tion of workers as well as protection of the public and the be minimized and removed by air exchange. To protect
environment. The fundamental assumption is that the workers from contamination, it may be—as another hy-
unintended release of pathogenic or genetically modified pothesis—sufficient to lower the contamination level by
organisms might exert major harm or, at the very least, dilution, or inactivation until a concentration of the
pose non-quantifiable risks to human beings and the envi- pathogen well below the critical infectious dose is
ronment. achieved. In an analogous manner, numerous agents for
Consequently, the central principle of biosafety is the disinfection do not achieve sterile conditions, but reduce
containment of microorganisms to prevent their unin- the level of viable infectious organisms, which in effect
tended release. The current understanding of modern will be below the critical infectious dose.
biosafety legislation is that all pathogenic, or genetically From the viewpoint of the legal “zero release” re-
modified organisms have to be effectively blocked from quirements, such as Genetically Modified Organisms
release from the laboratory or facility during handling. (GMO) things may look different. Theoretically, a “zero
This is a completely different view as compared to the release requirement” calls for an unlimited number of
classic hygiene related fields such as infectious diseases. In shells. Such a demand cannot be met under realistic cir-
the latter, minimization of release, or inactivation below a cumstances.
critical infection dose is the most relevant requirement. The minimum detection level (by modern detection
In contrast to this—as a hypothesis—modern biosafety methods like MALDI-TOF mass spectroscopy) for organ-
legislation, as it is understood by many biosafety experts isms limits the number of shells required to maximise the
in Europe, bases its approach on the assumption that containment effect. Generally, a statistically low failure
organisms with new properties may wreak havoc on hu- probability for a single containment shell also rules out
mans and the environment. This holds true only as long the necessity for a higher number of shells. In practice,
as very little is known of biological safety research and no three elements of containment can be found in a standard
better data exists on the real risks of the release of patho- level-3 laboratory: the container for the organisms, the
genic or genetically modified organisms. biosafety cabinet (BSC), and the laboratory suite itself.
Containment shells are sensitive to damage at the
Containment Principles interface to the outer environment. The integrity of fol-
“Shell-in-a-Shell” Principle—Measures of contain- lowing systems might be affected:
ment have to restrict the spreading of microorganisms to • Construction elements of the shell
Figure 1
Dengue fever lab—individual ventilated cages (IVC) and biosafety cabinet.
Figure 2
a) Cable penetration with multiple cable transfer unit (MCT); b) Cable penetration with gland.
• Action plans in case of an emergency, release or spill- order to provide a continuous (24/7) safe operation. We
age have set up this design in order to allow for continuous
• Major accident and fire prevention schemes operation even under circumstances when parts of the
• Major accident coverage plans installation have to be set out of order for maintenance
• Alarm schemes of different levels in the organization purposes. This way, down times can be effectively limited
• Security regulations to rare cases of emergency.
• List of registered personal and permissions Separate Work Area—A separate work area, as it is
Security and Biosafety—Security is an integral part of required by Swiss legislation, has to be understood as a
a biosafety concept. Security measures shall provide the work space with limited access dedicated to level 3 activi-
means for secure and uninterrupted operation of the con- ties. This is one of the most basic requirements in inter-
tainment and ensure that only authorized and competent national biosafety legislation. It is a precondition for ef-
staff has access to dangerous material. fective control of personal access and material transfer
Badge Access Control and Interlocking Doors Keypad— and allows for an efficient application of the rules for safe
Two security barriers control access to the containment microbiological laboratory practice while minimizing the
area: One system consists of authorization of access rights probabilities of cross contamination and unintended re-
assigned by responsible and trained staff for the BSL-3 lease. Therefore, this feature is implemented in the basic
laboratory and site security. The second is an interlocking design of the laboratories at the outset.
system provided with a keypad through which authorized Airlock—Access to the containment area must occur
people can access the facility with a digital access code via an airlock with interlocking doors. This is also a basic
that is personalised and changed on a quarterly basis. requirement, which, in combination with a badge access
Holding Area (Vestibule and Dressing/Undressing)—Staff control, will guarantee the integrity of the containment
members change their lab coats with one-way overalls by preventing the unintended release of potentially con-
(bunny suits) in a holding area before entering the taminated aerosols through the access area. Additionally,
experiment area. It is also equipped with a shower it provides the means for access control as well.
room that can be used when leaving the laboratory. The Rodent Barriers—Rodent barriers and pest control
shower room can also be used to treat chemical spillage measures must be present in the laboratory as part of the
in case of an accident. From this area onwards, the whole hygiene concept. They must prevent the escape of in-
laboratory is under negative air pressure. fected animals from, and the intrusion of wild animals
into the restricted area.
Recommendations and User Observation of Work Area—An observation gallery
alongside the laboratory for visitors as well as for security
Requirements checks and glass windows between the laboratory rooms
are recommended to be installed so that about 75% of
We base our recommendations on the comparative
the facility can be visually monitored from outside the
overview of national and international legislation and
BSL-3 zone (Figure 3). An additional CCTV system com-
guidelines (Table 1). A close cooperation between
pletes the security measures.
scientists, management and suppliers is essential to
Resistant Surfaces—Most modern standard labora-
achieve a well-elaborated design proposal that is
tory benches and furniture are sufficient. They must have
in compliance with user requirements. For the
non-porous and non-absorbent surfaces, such as glass,
determination of the final design, it is important to
ceramics, and synthetic material with appropriate acid
integrate strategic management decisions with future
and alkali resistance. Cavities and hidden surfaces that
action plans and research activities. Some key decisions
are not easily accessible for cleaning have to be avoided.
such as final lab layout and future research plans, are
Cleaning and Maintenance—Floor corners have to be
needed to determine the advancement of the project
“smooth” in order for easy cleaning and sanitation.
development. Not addressing these topics at an early
Smooth and slip-preventing floor material also facilitates
project stage could lead to abortive design, lost time and
daily cleaning.
could further jeopardise a successful project, its financial
Liquid Waste and Waste-Water Treatment—With a
plan and timely construction completion.
so called “semi-dry” sanitation concept, no floor drains
need to exist in the laboratory area. All effluents, includ-
Design and Concept of the Laboratory ing collected spills, leaving the containment laboratory
The following collection of requirements, rules, and
area have to undergo waste water treatment. Since waste
guidelines reflect the requirements of international bio-
water from cleaning and sinks is a potential source of
safety legislation. On the other hand, they are, in their
contamination, it must be retained in the containment
individual compilation, an adaptation to circumstances in
area until inactivation. Floors have to be designed accord-
a multi-user environment. In the design of the laboratory,
ingly with 10cm-retaining-water barriers at door openings
a major emphasis was placed on a moderately high degree
and a removable water barrier in the airlock (Figure 6).
of redundancy in critical installations that affect safety in
Table 1
Overview on international ordinances and guidelines (as per July 2003).
Figure 3
a) Observation gallery from inside the BSL-3 laboratory; b) Glass windows between the laboratories inside the BSL-3 zone.
Figure 4
Liquid nitrogen supply from outside the BSL-3 laboratory.
This way, any spills or water ejected by sprinklers during • The design must be leak proof.
an alarm situation can be retained for chemical or ther- • There must be a leakage monitoring system
mal inactivation treatment. Alternatively, sinks with a (electronic liquid detectors) in all critical areas, (under
built-in thermal “inactivation flow through device” may water-cooled devices such as centrifuges, freezers, and
be applied, but in the present case, a decision was made biosafety cabinets).
for a centralized inactivation installation for economic • All circulated media, such as cooling devices, must be
reasons. Generally, any waste water and liquid waste must designed as closed systems, if necessary, with a heat ex-
be inactivated chemically or thermally. changer.
Media Supply—Regarding media supply the following • Sealable doors with two panels (1.4 m [w] x 2.10 m
aspects have to be considered: [h]) for roll-in and roll-out of larger lab equipment) are
• Media ducts must be sealed by using compressed rub- highly advisable.
ber sealants. • Showers are optional and can be available as a safety
• All media and power lines that supply the BSL-3 pe- shower in the dressing air lock. If showers are present,
rimeter have to be disengageable from outside the labora- waste-water must be collected and inactivated appropri-
tory (Figure 4, the liquid nitrogen supply). ately.
• All liquid media must be equipped with one-way Air Handling and Pressure Cascading—Negative air
valves to prevent back flow. pressure has to be maintained permanently in an uninter-
Figure 5
Pass-through autoclaves of a BSL-3 laboratory.
rupted 24/7 operation mode. To assess the risk of a tech- this manner, working and living conditions (for animals)
nical failure, pressure has been considered in decreasing are kept favourable, and electronic equipment is pro-
levels from areas of moderate risk (corridor, i.e., -25 Pa) to tected from detrimental moisture. We recommend in-
areas of higher risk (animal rooms, i.e., -65 Pa) to force creasing the air exchange rate in the front of, and behind,
directed airflow. For the worker’s comfort, air velocity autoclaves in order to minimise humidity and to remove
should not exceed 20cm/s. Back flow, oscillations and unpleasant odours. An increased air exchange rate is also
noisy air movements are prevented by careful balancing advisable in the air lock as a safety measure, because con-
of supply and exhaust air. taminated aerosols could accidentally be generated inside,
The system must offer the option to isolate any spe- or near the air lock. During the air exchange process, the
cific compartments as well as to control the individual doors are interlocked. In case of an emergency, the
volume flows and pressure levels at any time. interlocking door principle will be overrun automatically
High Efficiency Particulate Absorption (HEPA) to allow for unhindered exit of the laboratory. This
Filtration—The exhaust air shall not be recirculated to procedure is required by the owner based on a current
any other building area and has to be discharged to the interpretation of the Swiss biosafety ordinances and is
outside via HEPA filters. If chemical fume hoods are accepted by the Singaporean legal authorities.
needed within the BSL-3 lab, exhaust air has to be HEPA-
filtered, too. This can be achieved with the installation of Technical Equipment
a biosafety cabinet (class II B2, which is hard-ducted), Solid Waste Treatment—According to the WHO,
often called a “workstation” in the European market. autoclaves or incineration systems must be available in
Such “workstations” are offered by various suppliers. the laboratories. In particular cases, chemical treatment
Air Conditioning—The air-conditioning units in air may serve as an alternative. If so, an individual SOP must
handling supply lines lead low turbulence air into the be integrated into the safety concept. Nevertheless, there
laboratory, maintaining stable conditions with respect must be room for temporary storage of waste within the
to temperature and humidity. In practice, significant facility and without constraint for internal traffic, or free
amounts of waste heat can be removed from the laborato- access to emergency escape routes.
ries without forming condensates on cooling surfaces. In Prevention of Aerosol Formation—To avoid aerosol
formation, the following conditions and devices should air handling and pressure control systems must be de-
be identified and installed: signed to handle huge differences in the net air exchange
• Centrifuges with aerosol-tight rotors rate, which is dependent on the number of currently ac-
• Homogenizers designed as closed systems (using mini tive BSCs. Volume changes in the net air exchange rate
devices with a lid) may not have any influence on the pressure cascade ar-
• Fluorescence activated cell sorting devices (FACS) rangement of the individual laboratories.
will make individually designed measures for the removal Autoclave (in the BSL-3 Laboratory)—Some manu-
of aerosols necessary facturers offer autoclave models that do not require a
• Microscopy of living higher-risk-level organisms also vacuum operation mode, but meet high pathogen specifi-
demand individually designed measures cation (3.4 bar, 134°C). The decision for a particular type
• Double containment of high-risk microorganisms at must be based upon the kind of waste and material to be
all times outside the biosafety cabinets (BSC) sterilised. If porous materials, such as HEPA filters, are to
Instruments and Equipment—The entire BSL-3 labo- be treated, the penetration depth of the steam or steam-
ratory area has to be equipped with materials and instru- air mixture must be sufficient to permeate the material
ments dedicated only for its rooms and specific purposes. completely. Preferably, the main autoclave should be a
Refrigerated Storage—Freezers of all three standard pass-through model (Figure 6) to simplify waste logistics as
temperature levels (near 0°C, -20°C, and -80°C) must far as possible. Another (maybe smaller) autoclave should
be available as a standard in biological laboratories in be available in the laboratory as a backup autoclave in case
each containment area to avoid unnecessary pass-in/pass- of the other autoclave being inspected or out of order. It
out procedures. Since containment areas are restricted does not necessarily need to be a pass-through model.
in space, this can lead to temperature disturbances due Further specifications that must apply:
to the great heat dissipated by 80°C deep-freezers. In • All programs must be designed in a way to ensure
Europe, some suppliers offer freezers and other laboratory that after a non-successful termination of a sterilisation
equipment (like ultracentrifuges) with a built in water cycle, the contents can only be discharged into the BSL-3
cooling unit to limit additional heat dissipation to the laboratory
laboratory space. Consequently, the choice of liquid- • In case of an emergency, it is only possible to unload
media cooled freezers is highly recommended. the autoclave into the BSL-3 laboratory.
Biosafety Cabinets—Some suppliers offer Class II (B1 • Some pass-through autoclaves can be programmed as
or B2) biosafety cabinets (BSC) with a built-in water- a pass-in airlock (without thermal cycle on the way in) for
operated cooling unit (SCAN AG, www.skan.ch) to re- the transfer of living animals and test specimens into the
duce heat dissipation to the lab space. For safety reasons, containment. Even in this particular case, an opening of
the cooling systems should be operated in closed circles. the autoclave from outside may only be possible after
Class-II-B2 BSCs are also suitable for handling small termination of an additional sterilisation cycle.
amounts of toxic chemicals and radioactive compounds; • If a model with a vacuum operation mode is chosen,
they are hard-ducted to the exhaust air system and do not the exhaust air from the vacuum pump has to pass
redirect exhaust air to the lab space. Additionally, the through an high efficiency particulate air (HEPA) filter, or
ducts are equipped with mechanical flow indicator flaps an equivalent inactivation device (air incineration unit).
for easy flow control. Because air removed from the labo- • All condensates have to be sterilised, ideally by inacti-
ratory will be fully substituted by the supply of fresh air, vation simultaneously with the main process, or by in-line
Figure 6
Water barrier in the airlock.
• Appropriate air-exchange rate (12 air exchanges per at any time. Consequently, electric power should be sup-
hour) plied by two independent power lines: One regular power
• Strobe alarm lights for emergency situations supply as well as an emergency power generator. A moni-
• Full capacity of heating, ventilation, air conditioning toring system, equipped with a battery-operated backup
(HVAC) system running all time without turn-downs at device, provides additional reliability. An uninterrupted
night. power supply (UPS) has to safeguard most critical installa-
tions in addition to the emergency power generator. The
Safety and Security surveillance devices, in particular the BMS, should be
Fire Protection—As a part of a multi-tenant complex, backed up by an independent (battery) power supply to
the fire-fighting strategy for BSL-3 laboratories must be allow for a self-initialising restart procedure after a power
seamlessly integrated into the fire-fighting strategy for the failure. Generally, an optimal power-supply system is ex-
whole building. Knowledge of municipal fire authorities’ pected to exhibit some “self healing” characteristics. En-
policy is a prerequisite for the development of a gapless ergy-consuming installations like autoclaves only need
fire alarm and fire fighting strategies. The installation of a monitoring since they will automatically restart after hav-
high-pressure sprinkling system reduces the amount of ing returned to normal power.
water used in case of a fire. Alternatively, a gas suppres- Room Fumigation—Room fumigation is a standard
sion system can minimise, or even avoid, water use. requirement in international biosafety legislation. In its
Water used for fire-fighting in a BSL-3 containment essence, it is quite an “old” requirement stemming from a
must be held back (Figure 6). The floors within the con- time when (biosafety) research was in its very early stages.
tainment shell can be shaped as shallow watertight trays In practice, fumigation is a safety measure for exceptional
to withhold any water for chemical or thermal treatment rare events. In the current legal enforcement of biosafety
before final disposal. Alternatively, floor drains may be ordinances, fumigation is often seen as an ultimate meas-
provided with a separate effluent collecting system. ure after a major accident. Nowadays, numerous experts
Smoke Detection—As it is important to detect fire in tend to interpret room fumigation as a measure of mini-
the early stage of spreading, a state-of-the-art smoke and mising the risks of re-entering a hazard area, but not as a
fire detection is the most efficient and effective way of fire standard disinfection measure. The latter interpretation
protection. The system is part of the integral alarm cas- results from the numerous difficulties encountered in
cade system concept. successfully validating all the parameters that influence
Alarms and Coverage of Malfunction Events— the effectiveness of the fumigation process (agent concen-
Automatic fire alarm systems with direct alert of the fire tration, agent consumption, penetration of porous mate-
departments control centre and redundant design are rials, and accessibility of cavities).
standard nowadays. In some countries and areas, mixed Fumigation is feasible in single compartments such as
alarm systems, with segments which meet older, but not filter stations or biosafety cabinets. In a single compart-
current, standards are still in operation. It is the duty of ment, fumigation can work as a sanitation measure on a
the safety experts in charge to ensure that the reliability of regular basis (prior to conducting maintenance proce-
the alarm system is in good proportion to expected risks. dures).
In addition, it might be advisable to amend the “Building For room or chamber fumigation, floors, walls, and
Management System” (BMS) with an automatic notifica- ceilings must have non-porous and non-absorbent proper-
tion system that alerts the responsible scientists and ser- ties. An epoxy coating is a standard minimum require-
vice staff in case of any malfunction. This can be done ment for walls and ceilings. In addition, the room or
with a short message service (SMS) notification system, chamber must be leak-tight, with all penetrations ade-
which is highly independent, since it can rely on the bat- quately sealed to prevent the escape of the fumigant.
tery backup of the BMS components. Such a system Biohazard Warning Labels—Biohazard warning labels
would even work in the case of complete power failure. are a must at the entrance to the BSL-3 area and recom-
Containment of Fire-Fighting Liquids—To prevent mended for “critical” areas such as BSCs and other storage
the release of a large amount of potentially contaminated devices for contagious agents. Labels must be clearly visi-
liquids, fire-fighting water will be retained separately. The ble and comprehensible to staff members. Pictorial ele-
facility itself is designed as a sort of retention unit. For ments must be in agreement with international standards.
this purpose, the lower portions of walls (10-12 cm) are
sealed. No floor drains are located in the retention area. Additional Measures in Animal Care Facilities
Fire-fighting water, or larger spills, will be collected with Many of the recommendations given in the following
self-aspirated pumps designated for biosafety clean-up paragraphs as “have to have” are currently under discus-
purposes. sion as requirements for the next revision of Swiss bio-
Power Supply—Airlock, freezers, IVCs, BSCs, the safety legislation. Since the client required the laboratory
BMS and similar devices are of critical importance to to be in accordance with Swiss legislation, these recom-
laboratory safety and function. They must be functional mendations have been turned into requirements in the
concrete example (chapter 6). ment room for the waste water treatment in the floor
Storage units for infected animals are recommended below (Figure 7b).
to be located in a separate area of the facility within the
BSL-3 perimeter. Biohazard warning labels are recom- Construction and Design of the Laboratory
mended for “critical” areas such as solid waste storage. Architectural Measures—We integrated the labora-
They must be placed next to entrance doors. Doors to tory unit into a pre-existing building and applied the
animal care rooms “must” be lockable. “shell-in-a-shell” principle (chapter 4.2.1) by building in-
Solid Waste Management—Autoclave or incineration ner walls. The inner shell was built up as a lightweight
equipment “must” be present in the laboratory. Alkaline construction with its own self-supporting framework. An
liquefaction units are smoke-free and environment- internal ceiling was installed above the laboratory unit to
friendly as compared to small-scale incineration devices. create room for the energy and media supply lines. The
Such a device is acceptable with respect to biosafety pro- inner ceiling is a walkable construction that allows for
vided the process is validated.
easy access to all relevant parts of the installation. We laid
Alternatively, carcasses might be transported as dan-
all lines, pipes and channels from above to avoid wall
gerous goods (class 6.2 according to IATA) to an accred-
penetrations. This way, a correct and almost gas tight line
ited incineration facility. For transport, containers suitable
for class 6.2 transports must be used and the carrier must penetrations could be accomplished.
hold permission for the transportation of dangerous This “open installation concept” allows for easy and
goods. safe access for inspection and maintenance for all compo-
A more pragmatic approach might be the freezing of nents. The safety concept is based on the idea that the
infected carcasses in suitable containers inside the BSL-3 inner shell of the lab suite, as well as each individual
and subsequent batch decontamination of the frozen inner room, is as tight as possible. All inner surfaces
carcasses by autoclaving. This approach is currently under (floor, ceiling, walls) have to be as flawless and resistant to
discussion with the Swiss legal authorities. Sterilized car- aerosol diffusion as possible. All window openings were
casses are allowed to be frozen outside the BSL-3 labora- tightly integrated into the walls using a secure double-
tory until transport to an external incinerator can be ar- pane construction.
ranged. It is crucial; however, to standardise and validate We defined the space between the inner shell and
the decontamination cycle of the autoclave beforehand by the building as lower-level containment. These are:
simultaneously using biological indicator tubes and physi- • The false ceiling
cal test instruments. • The observation gallery
Usage of Individually Ventilated Cages (IVCs)— • The service area of the autoclave; the vestibule. For
Individually ventilated cages (IVC) are not capable of these spaces, a minimum level of leakage must be attained
excluding potential cross-contamination and the release to maintain negative pressure under all weather and wind
of airborne pathogens by one hundred percent. Thus, conditions and in all states of operation. The discharged
IVCs cannot replace personal protective equipment air coming from these rooms will also be emitted via
(PPE), or general safety measures when animals infected
HEPA filters. We arranged and tested all inner rooms
with airborne microorganisms are handled. Appropriate
(including filter station and waste-water sterilisation sta-
filter masks (or respirators) must be worn at all times in-
side the animal unit. To minimise cross-contamination, tion) for and by creating a pressure cascade of individual
IVC models with one-way air supply are highly preferable. levels.
Ventilation and Air-Conditioning—All laboratory
compartments are individually ventilated. The specific air-
Concrete Example: The Novartis Institute conditioning parameters in a given room are based on
for Tropical Diseases (NITD) key values, such as room volume, intended purpose of
use, equipment properties, such as heat dissipation and
To illustrate the reflections above, the construction permanent media supply lines. All data are defined and
of the Novartis Institute for Tropical Diseases (NITD)
filed in room-specific specification data sheets. The room
(www.nitd.novartis.com) in Singapore is described in the
specification data also include factors such as airflow,
following sections. Many of the recommendations pro-
vided above as “have to have” are currently under discus- relative pressure, temperature, humidity, and quality
sion as requirements for the next revision of Swiss bio- specifications.
safety legislation. Since the client required the laboratory To attain a nearly fail-safe high-availability air-
to be in accordance with Swiss legislation, these recom- conditioning system in the level-3 containment, a highly
mendations have been turned into requirements in the redundant air conditioning system with two independent
concrete example. parallel lines has been installed next to the building’s
Figures 7a and b show floor plans of the BSL-3 labo- standard air supply. These two lines are powered by re-
ratory in the 8th floor (Figure 7a), as well as the equip- dundant power lines, run parallel and simultaneously,
Figure 7a
Floor plan of the BSL-3 laboratory level 8 including pressure cascade.
Figure 7b
Floor plan of level 7 including pressure cascade in the equipment room for
the waste water treatment plant, which is part of the BSL-3 containment.
Figure 8
Two of the three HEPA-filter stations for filtration of the exhaust air.
measure against the potential release of aerosols, the dance with ISO 14644/4 (“Clean rooms and associated
waste water inactivation department was integrated into controlled environments—Part 4: Design, construction
the pressure cascade of the containment shell. Under and start up”). To keep pace with a very tight construc-
standard operation conditions, this room can only be tion schedule, testing procedures were sequentially con-
entered through the safety laboratory and the appropriate ducted in coordination with the construction progress.
safety rules must be followed. The test sequences were carried out as following:
Facility for Animal Experiments—Long-term experi- • Room integrity test
ments have to be performed in an environment, where • Measurement of Air Handling Unit (AHU) capacity
each animal holding room is attached to a procedure • Supply air balancing
• Measurement of exhaust fan capacity
room. In those rooms, animals are kept in individually
• Exhaust air balancing
ventilated cages (IVC) (www.biospectrumindia.com/
• Water balancing
content/Bioproduct/10508231.asp). Cages must be • Filter test
equipped with HEPA-filtered air, and air-pressure within • AHU/fan/heater battery/pump performance test
the cages must be adjustable to negative or positive. All • Control system test
animal experiments have to be performed within bio- • Measurement of temperature, relative humidity, and
safety cabinets (BSC), which are also ventilated via HEPA room pressure.
filters. Using IVC cages and BSC prevents the staff from Parts of the qualification checks were already
being infected. Short-term experiments have to be per- completed during the early stages of construction
formed in a room equipped with an IVC rack and a BSC. (tightness of media supply lines; tightness of the duct
The BSC must be placed far from the IVC rack. Animal work, as well as the testing of the individual rooms). We
food pellets, bedding, clean cages, and other consumables have documented the results in a way to make them
used in animal experiments have to be stored in a sepa- comparable to design specifications. The supervision
rate storeroom. team checked the results on the basis of periodic samples.
Continuous Effluent Decontaminator (CED)—The The most relevant technical guidelines during the
Steris CED system is an innovative waste-water decon- qualification process were:
tamination system, designed to decontaminate and inacti- • ISO 14644/3 “Clean rooms and associated con-
vate potentially infectious effluents in a flow- through trolled environments—Part 3: Test methods” (filter-leak
process. The CED system consists of the following basic test, airflow measurements, pressure measurements),
devices: collector tank, decontamination heat exchangers, • The European Standard prEN 13779 “Ventilation
circulation and discharge piping and control system. De- for non-residential buildings—Performance, requirements
for ventilation and room-conditioning systems” (leak
contamination of waste-water is achieved by heating water
tightness of rooms and duct work systems), (a draft of the
in the heat exchangers using saturated steam.
now valid EN 13779 standard)
• The British Guidelines.
Construction
Monitoring—The setup process was attentively ac-
Commissioning
companied by the supervision team. Most of the critical
As soon as all devices were available, they were setup
technical equipment was set up first and tested in a pre-
and checked. The work was carried out under close super-
built mock-up room. Availability of materials, afforda-
vision of the installation qualification team (Installation
bility and practicability were the most important decision-
Qualification: IQ). Start-up sequences for all individual
making factors. The knowledge, skills, and experience of
devices and systems were performed. All tests were carried
staff members onsite are also always basic success factors.
out in the presence of representatives from the sup-
As a key factor of communication the development
plier/manufacturer to optimise and fine-tune all impor-
of the construction was documented in step-by-step proto-
tant operation parameters.
cols, and deviations have been recorded by digital images.
After the successful completion of the setup, we con-
In order to bridge cultural gaps, the protocols were not
only used to establish a documentation of construction, tinued the commissioning process following the Opera-
but were also helpful as a basis for discussion amongst tional Qualification (OQ) and Functional Qualification
staff members, the supervision team, or the authors, re- (FQ) process guidelines, as they are provided by the ISO
spectively. standards. Beforehand, each test procedure was defined
Testing—We defined the testing schedule and proce- in coordination with the installers/manufacturers. We
dures mainly following the WHO instructions. (WHO, always included the following steps and recordings:
2004) The predominant tasks were supervision, control- • System definition and description of function
ling and advising during the qualification procedures. • Test goal, physical target parameters and procedures
Topics, test parameters, and monitoring principles of the • Definition of important preconditions
qualification procedures were primarily defined in accor- • Definition of expected results
• Set-up of test conditions and specifications (How to conditions and exceptional conditions, respectively
start a test? Who has to be informed? Is the test sequence Type and periodicity of routine tests and meas-
in correct order? What are the expected measurement urements
values?) Description of test and measurement procedures
• Required resources (staff, working time, instruments, Required measures and warnings in case of emer-
documents, etc.) gency
• Analysis of test results (Was the test successful? Are Change management procedures and procedures
the results in compliance with expectations and specifica- after deviation from requirements and specifications.
tions?)
• Remarks, explanation, information Instructions for Maintenance
• Date with signature of the responsible engineers For an ordinary standard operation of the safety labo-
Before handing over the whole installation to the ratory, specific test and maintenance procedures have to
owner, we ran a final test series on all external functions, be defined in the maintenance procedures (M-SOPs) and
effects and communication signals. This final test series performed on a regular basis. These maintenance proce-
was designed as an integral test to simulate “status of op- dures have to be periodically conducted in a predefined
eration” realistically and to check for emergency situa- order, as documented in the maintenance plan. Addition-
tions such as failure of critical containment components, ally, the maintenance procedures can be started on an
fire or power failure. The tests also included the switch event basis if deviations from the standard operation pa-
over between standard power and emergency power con- rameters are monitored.
ditions and vice versa. During room qualification, the standard operational
parameters, such as pressure differences, airflow volume,
Documentation air changes per hour, temperature, humidity, filter-
A further key task was to ensure correct and com- leakage rate, also including all tolerance ranges, have to
plete documentation. Construction and function-relevant be standardised. The related values always have to be used
data (including calibration of all devices) as well as proce- as a reference for all follow-up routine tests during main-
dures for operation and maintenance had to be docu- tenance and re-qualification. For document checks, the
mented completely and flawlessly. In accordance with following aspects have been given special attention in
ISO 14644/4 (Clean rooms and associated controlled agreement with the ISO14644/4 (Clean rooms and asso-
environments—Part 4: Design, construction and “start ciated controlled environments—Part 4: Design, construc-
up”) the overview of the whole system should be reflected tion and “start up”):
by the documentation in a clear and easy to understand • Definition of maintenance measures
manner. Documentation must be accessible at all times to • Definition of safety measures before maintenance or
all responsible co-workers involved in start-up procedures, repair works
qualification, handing over and maintenance. Even more • Change management: definition of acceptable
important, the documentation had to clearly and unambi- changes and standardised change procedures;
guously reflect each staff member’s individual role and • Checking requirements and exchange of spare parts
responsibility. The documents provided had to include as well as the rules for the disposal of spare parts, such as
the following details: belts, and filters
• Scheme drawings and description of function, • Definition of all actions, procedures and checks that
schemes of pressure cascading and specification of hy- are required for the standard operation status
giene classes • Consideration of all user-specific and legal require-
• Specification of operation parameters in accordance ments or ordinances to be obeyed.
with the contracted user requirements, as well as the re- All maintenance work under standard operation con-
sults of all relevant tests including all test logs ditions are logged in maintenance reports. These reports
• Drawings, wiring schemes, Process and Instrument have to include the following:
Diagrams (P&ID) schemes, and operation schemes as • Definition of individual maintenance procedures
hard copies as well as electronic data and all amending • Naming and authorisation of maintenance-staff
requirements and agreements referring to the building members
contracts • Date, time, and description of the maintenance job
• Spare-part lists with links and hints for spare-part done
supply and maintenance • List of used spare parts
• Documentation about manufacturers and suppliers • Report log about the condition of the parts of instal-
as well as supply resources lation under maintenance before and after a maintenance
• Comprehensible operation procedures for installa- job.
tions and devices, including the following details: From the time of the start-up sequence, some of the
Start-up and shut-down sequence under standard owner’s responsible co-workers were involved in the quali-
fication process. This way, efficient information transfer ble of transmitting a disease.” NITD successfully obtained
to the owner is guaranteed. such a permit for Mycobacterium tuberculosis as it was tied to
the certification (see “Fire Protection” above). The first
Certification imported M. tuberculosis arrived safely in June 2005.
Apart from having to comply with Novartis’ own License to Possess Veterinary Biologics (for Re-
internal biosafety requirements the BSL-3 unit described search and Development Purposes)—As NITD had also
here had also to be certified by Singapore’s authorities. planed to work with Flaviviruses, such as West Nile Fe-
The latter was completed during a transition period when ver, Yellow Fever and Japanese Encephalitis, another li-
biomedical legislation was under refinement and ratifica- cense was required from the Agro-Food and Veterinary
tion by the Parliament. Some legislation had reference to Authority (AVA). A one-year renewable license was issued
existing biological safety and security; still, it was neither to NITD upon successful completion of a site audit by
complete nor sufficiently comprehensive to regulate all AVA inspectors.
aspects in terms of construction, commissioning and op- License under the Animals & Birds Act; Rules for
eration. Nevertheless, the authorities recognised the im- Animals and Birds—Singapore’s rules for the administra-
portance of the matter and anticipated some important tion and management of animal research facilities were
impending legislation. The resulting paragraphs detail the not released before the end of 2004. Until then, the
key approvals/licenses that were secured for this particu- Agro-Food and Veterinary Authority (AVA) requested
lar BSL-3 unit. In addition, being incorporated within a NITD to comply with the Guidelines on the Care and
BSL-3 facility meant that it was also necessary to obtain Use of Animals for Scientific Purposes developed by the
approval for animal research. National Advisory Committee for Laboratory Animal
Approval as a “Certified Facility” to Work with Research (NACLAR). These guidelines were in accor-
Risk-Group-3 Pathogens—This particular approval was dance with widely accepted scientific, ethical and legal
obtained from the Singapore Ministry of Health (MOH). principles and constituted the best practice in the use and
The MOH is the key administrator of the Biological care of test animals. After a successful site audit in the
Agents and Toxins Act (BATA), released in January 2006. ABSL-3 facility by AVA animal-welfare inspectors, NITD
BATA is now the most important piece of legislation gov- was issued a one-year license.
erning the approval of BSL-3 units as described here. In Gazetting as a “Protected Place” under the Pro-
Singapore, BATA regulates the possession, use, import, tected Areas and Protected Places Act—The Ministry of
transfer, and transportation of biological agents and tox- Home Affairs and Singapore Police Force require any
ins that are known to be hazardous to human health. facility working with certain agents found in the proposed
Although BATA was not in force at the time we applied First Schedule, Part 2 of BATA (see above), to be gazetted
for certification, the MOH leant on BATA guidelines as as a “Protected Place.” “Gazetting” is the Singaporean
closely as possible. MOH also adopted the Laboratory Bio- synonym for publishing. Such agents are defined as risk-
safety Manual, 3rd Edition, published by the World Health group-3 biological agents, which can cause serious dis-
Organisation (WHO) as the national guidelines for bio- eases, but also have the potential for being abused for the
safety compliance. development of biological weapons. Future work with the
For our certification process, the MOH adopted a Yellow Fever virus proposed by NITD fell into this cate-
“stand-back” approach: The MOH maintained its public gory. Based on a security audit by the Ministry’s officials
accountability by creating a legal framework with basic and subsequent enhancement of security installations
requirements. It is the responsibility of the NITD; how- and measures, approval was given to NITD.
ever, to guarantee safe operation of the BSL-3 laboratory.
The certification audit was carried out by a NITD- Summary
appointed and MOH-approved auditor. The audit was
comprised of a three-day program including interviews The handling of pathogenic and/or genetically modi-
with responsible NITD staff members, confirmation of fied organisms requires high levels of safety standards,
technical aspects, verification of documents and filing even more so when handling genetically modified patho-
system, commissioning, as well as site inspections. On the gens. As a consequence of the high developmental pace
final day, the certification audit culminated in a fruitful of modern biotechnology, these safety standards have to
meeting with MOH officials where the key findings of the be continuously adapted.
audit were presented. The project manager, Health and Safety Executive
Import Permit for Infectious Agents—Section 41 of (HSE) and biosafety officers had to take a key role in the
the Infectious Diseases Act administered by the MOH knowledge transfer to staff and in the start up process.
states that “no person shall, without the prior written per- These persons were also involved in the detail planning as
mission of the Director of Medical Services import, or well as in the definition of technical and organisational
bring, or cause to be imported, or brought into Singapore, interfaces. Nowadays, they are equipped to monitor every
any disease causing organism, or any agent of disease capa- deviation from the reference specifications for the stan-
dard operation. This way, they are ready to initiate the the efficient realisation of the certification procedure.
appropriate measures and necessary actions at any time. NITD, represented by the supervision team, was com-
Through the nature of legislation development with mitted to build a safe level 3 biomedical research facility
certain feedback processes, such as in public opinion compliant with international standards. The development
forming, jurisdiction and standardization, there is always process was the result of a close cooperation between gov-
a natural delay between the prevailing demands of mod- ernment authorities and industry. This cooperation
ern biotechnology and the standards reflected in the laws marked a significant step towards a modern and sustain-
and ordinances of modern biosafety legislation. This pub- able biomedical research community in Singapore.
lication describes the build-up, implementation, commis-
sioning and certification of a BSL-3 laboratory in an envi- Acknowledgements
ronment where biosafety legislation is still under develop-
ment. The chosen approach of setting up a safety labora- The authors would like to thank the following au-
tory integrates modern risk assessment strategies with: thorities, institutions, and experts for their collaboration,
1. The requirements of various international biosafety providing necessary information and valuable individual
guidelines help.
2. The development of new safety measures and certifi- • Singaporean authorities: Singapore Ministry of
cation procedures according to international guidelines Health, Agro-Food and Veterinary Authority of Singa-
3. A proactively open communication strategy to the pore.
public and local legal authorities. • Certifier: Dr. Fredrik Elgh, Umea University, Sweden
Besides that, the project had to fit into a very narrow • Project management and support: Mr. Victor Tan
time schedule because of its integration in a WHO pro- Hock Kim, Taikisha Ltd., Singapore, Mr. Chay Kum Soei,
ject. Jurong, Primewide Pte Ltd., Mr. Heinz Gimmel, Gimmel
This publication shall contribute to the rapid devel- Project Management Pte Ltd., Singapore, Mr. Sanjay
opment of modern safety legislation and serve as a pre- Kapil, Jacobs Engineering Pte Ltd. with Nigel Howcutt,
liminary template for future processes in the South Asia Apt Consultancy, Mr. Philip Chanand, Mr. Anil Kumar,
Pacific area. Jurong Primewide Pte Ltd., with Taikisha Ltd.
• Supporting consultants: Dr. Beat Hodel, Mr. Martin
Conclusions Joos, Mr. Phillip Grob, Dr. Felix Gmünder, and Mr.
Marc Schürch as representatives of Basler & Hofmann
The installation of a BSL-3 unit in a drug discovery Consulting Engineers, Zurich, Switzerland, Dr. Peter
environment within a mixed multi-user and multi-tenant Seiler, MPI IB Berlin as BSL-3 animal consultant.
estate presented the supervision team with a complex start- • Suppliers and maintenance services: Steris Finland,
ing position. Operational safety and security, as well as Singapore, Mr. Daniel Chua Lui Fong, Sauter Singapore
user requirements and public perception were subject to PTE Ltd., Mr. Simon Burri, Sauter AG, Basel, Switzer-
conflicting demands. Controversial issues had to be identi- land, Mr. Desmond Tan, Biopointe Ltd., Singapore.
fied and tackled at an early stage. Subsequently, input • Copy editing of the manuscript: Ms. D. U. Brunner,
from numerous branches, such as management, financial c/o Xientra Scientific Services Ltd., Switzerland
support, lab design and engineering, pathogen safety and • Novartis AG, Sponsor and Owner: Prof. Dr. Paul
security and, finally, legal compliance and registration Herrling and Prof. Dr. Alex Matter, Prof. Dr. Helmut
services had to be assessed by the supervision team. Bachmayer and Mr. Thomas Imark, Dr. Calvin Boon, Dr.
All conclusions were merged into an overall imple- Mahesh Nanjundappa, Dr. Kakoli Mukherjee, Dr. Chen
mentation concept and formed the basis of various inno- Yen Liang, Dr. Wouter Schul, and Mr. Eric Lim.
vative project management strategies.
Time restrictions and limitations in the availability of References
skilled craftsmen, as well as materials in the Singaporean
market, made it necessary to transform some European DIN EN 1822-1, Publication date 1998-2007. High efficiency
technical specifications into objective-oriented ones. In particulate air filters (HEPA and ULPA)—Part 1: Classifica-
this situation, instant “out-of-the-box” solutions were in tion, performance testing, marking; German version EN
high demand. 1822-1:1998.
The ultimate prerequisites to start the commissioning DIN EN 779, Publication date: 2003-2005 Particulate air filters
process at the end of the installation phase were purpose- for general ventilation—Determination of the filtration per-
ful communication strategies, gapless documentation, and formance; German version EN 779:2002.
practical staff training. The commissioning process in- DIN EN 13779, Publication date: 2005-05 Ventilation for non-
volved instantaneous “on-the-job training” for mainte- residential buildings—Performance requirements for ventila-
nance and service staff. The quality of documentation and tion and room-conditioning systems; German version EN
the trainings turned out to be indispensable key factors in 13779:2004.
(Draft standard) DIN EN 13779, Publication date: 2005-2007 Care and Use of Laboratory Animals. Washington, DC: Na-
Ventilation for non-residential buildings—Performance re- tional Academy Press.
quirements for ventilation and room-conditioning systems; Novartis Institute for Tropical Diseases. www.nitd.novartis.com
German version prEN 13779:2005.
One North Singapore’s icon of the knowledge economy.
Guidelines of the National Advisory Committee for Laboratory www.one-north.com
Animal Research (NACLAR) in Singapore. (2004). Ministry
The Skan Company, Switzerland, Clean Room and Isolation
of Health, Singapore.
Design. Skan AG. www.skan.ch
ISO 14644/3 Clean rooms and associated controlled environ-
Techniplast Sealsafe Italy. www.biospectrumindia.com/
ments—Part 3: Test methods.
content/Bioproduct/10508231.asp
ISO 14644/4 Clean rooms and associated controlled environ-
World Health Organization (WHO). (2004). Laboratory Biosafety
ments—Part 4: Design, construction and start up.
Manual (3rd ed.).
National Research Council, Institute of Laboratory Animal
World Health Organization (WHO). (2005). Guidance on
Resources Commission on Life Sciences. (1996). Guide for the
Regulations for the Transport of Infectious Substances.
Abstract Background
Recent threats of bioterrorism, outbreaks of previously Presently, very few nations are equipped with stan-
unknown infectious diseases such as Severe Acute Respira- dard BSL-3 or BSL-4 autopsy facilities as such units
tory Syndrome (SARS) and the reemergence of diseases like are expensive to build, operate and maintain correctly.
the Avian Influenza are very real and have caused serious These existing contingency facilities are normally housed
concerns not only for the world-at-large, but also for many in permanent or semi-permanent structures and cannot
be moved to distant locations to deal with emergencies
authorities. This is an even greater concern for the forensic
involving BSL-3 or BSL-4 hazards. While “portable
community as they are generally ill-equipped to deal with morgues” in the form of palletized mortuary supply sys-
highly infectious pathogens due to chronic under funding and tems organized by the U.S. federal government depart-
administrative constraints. The cost for building a Biosafety ment under the Disaster Mortuary Operational Response
Level 4 (BSL-4) facility is exorbitant; such a facility is also Team (DMORT) are available, they have no capacity
very expensive to operate and maintain. Given the state of for biosafety stringency, or for microbiologic diagnosis
funding for most Forensic Centers and Medical Examiner (Nolte, 2003). The lack of a mobile autopsy facility poses
Facilities in the world, having a high containment BSL-4 facil- a very real problem in that bodies infected, or suspected
ity just to carry out autopsy work is highly unlikely. of being infected with RG-3 and RG-4 agents, cannot be
In the course of dealing with the SARS outbreak in Sin- autopsied in remote locations where such practice is most
gapore in 2003, the Centre for Forensic Medicine (CFM) of required. Nolte, Taylor, & Richmond (2001), addressed
the Health Sciences Authority, together with its strategic this problem when they were evaluating the status of
Autopsy Facilities in the United States in their study of
partner, Acre Engineering, developed an innovative solution
“Autopsy Biosafety” in 2001. They recommended that “a
that would meet the requirements set out for a BSL-4 Mobile mobile containment autopsy facility constructed to oper-
Autopsy Facility. This was completed at a fraction of the ate at Biosafety levels 3 or 4 might be useful in providing
cost and in less than half the time spent building such a facility autopsy support to jurisdictions with inadequate facilities
de novo. This paper therefore sets out to present an innova- when they are confronted with contagious or toxic cases.”
tive solution to meet the need for an autopsy facility equipped At the height of the SARS outbreak in Singapore in
to BSL-4 standards that can be mobilized and deployed at 2003, the need for developing a solution that would meet
short notice to conduct autopsies on highly infectious cases at the requirements set out for a BSL-3 or 4 mobile autopsy
distant locations. In particular, it addresses the engineering facility became very apparent and pressing. The challenge
and facilities components of the solution. was to meet the need for providing appropriate facilities