Professional Documents
Culture Documents
1
Housing = 1,600
Transport = 1,500
6,600 = 6,600
Messenger
Salary / month
Salary / month = 1,000
Housing = 800
Transport = 500
2300 = 2,300
47,000/month
Contract duration 12 month
Add 1 month before project and
Add 3 months for defect liability period
Total month 16
16 months x 47,000 = 752,000
Add 10% for insurance and I.T.F = 75,200
827,200
Add 25% for profit and overhead = 206,800
1,034,000
(2) Site Accommodation
The contractor is usually expected to provide and maintain temporary site accommodation for
(i) Supervising consultant on site
(ii) Site agent and site staff
(iii) Hut for workmen
(iv) Storage, shed for materials, tools etc.
2
Site agent 7.5m2
54.5m2 55m2
Circulation space 10% 5.5m2
60.5m2
61m2
61m2 at 9,000 = 549,000
Less resale value of items (about 27%) 149,000
N400,000
Demolish and cart away from site including making good @ 500/m x 61m2 2
= 30,500
(3) Tools
This include items such as shovels, portable drills, wheel barrows, batch boxes, guage etc. smaller tools such as
hammer, trowel, plumb level, plumb lines, paint brushes etc. that are associated with a particular trade are not aloe
for, here. They are usually taken care of in the tool allowance included in the all in-labour rate for such fields. If
the project is large enough to used up small tools such as paint brushes, sand papers etc. then the cost of such are
included in the unit rate for the items that required their use in pricing consideration is given to the cost of
purchasing of the tools less their resale value.
(4) Scaffolding
The total height and the type of construction determined the amount and type of scaffolding required for a project,
the contractor may purchase scaffolding for use in the work. Whatever they may be, in pricing consideration is
usually given to the following.
(a) Hire rate for the duration of the project
(b) Labour cost for erecting scaffolding on site
(c) Labour cost for adopting scaffolding for special uses
3
(d) Labour cost for dismantling scaffolding at the end of the project
(e) Transportation cost for bringing to site and removing from site all scaffolding (f) Profit and overhead
PRICING OF PRELIMINARIES II
4
(iv) Cost of labour and materials for constructing temporary sheds for generators
(v) Cost of dismantling shed, removal and making good
(vi) Cost of transporting generating set to site and removal on completion of project.
(vii) Overhead and profit
(b) Electrical supply from electrical authority mains, pricing will include
(i) Cost of connection to the electrical authority
(ii) Cost of cables, wiring and light fittings
(iii) Cost of electricity bills
(iv) Cost of disconnection on completion of project
(v) Cost of hiring a standby generator in case of electricity failure
(vi) Overhead and profit
(8) Temporary Road
In certain building and civil engineering construction, temporary road have to be constructed from the existing
road to the site in order to get access to and make possible the distribution of materials to various part of the site.
Temporary road may also be required is first worked and priced with the following considerations
(a) Cost of labour during clearing the road
(b) Cost of excavation either by hand or by mechanical plant
(c) Cost of labour and materials in laying laterite, blinding, gravel
(d) Cost of maintaining the road for the duration of the project
(e) Cost of removal of temporary road if not required at completion of all works on site and making good
ground disturbed
(f) Overhead and profits
(9) Temporary Telephone
If the project requires the telephone, the constructor must arrange for telephone communication to be installed on
site for easy communication for the duration of the contract, pricing will include
(a) Cost of telephone installation by telephone organization in this case NITEL
(b) Cost of telephone bills
(c) Cost of maintenance
(d) Cost of disconnection\
(e) Overhead and profit
(10) Control of Traffic and the Additional Cost
Reconstruction and repairing of existing road, lying sewers, water mains etc. in existing roads and construction
works in congested areas may create the necessity for closing part of some road temporarily to traffic. In such
cases the provision of one way traffic control, diversions and access to adjoining houses, shops etc. may become
necessary. The following should be given consideration
(a) control of traffic which involves
(i) Cost of speed breakers
(ii) Cost of constructing barriers
5
(iii) Cost of red flags
(iv) Cost of labour flagging traffic
(v) Cost of providing diversion
(vi) Cost of removal of sign board to adjoining house, shops, garage etc.
(b) The provision of access road to adjoining houses, shops, garages etc
(i) Cost of labour and materials to provide pedestrian and vehicular access to shops, houses, cars and park etc.
(c) Additional cost of work on existing road where traffic is involved (i) Cost of delays to
progress of work due to traffic and congestion
(ii) The presence of existing water mains, cable sewers, culverts etc.
(iii) Watching and lighting the work
(iv) Overhead and profit
(11) Welfare and Safety of Work People
This will comprise the cost of
(a) First aid box
(b) Drugs, antiseptics, bandages etc.
(c) Providing a nurse or medical attendant
(d) Maintaining first aid box
(e) Removal
(f) Protective clothing such as overall, element, nose mask, face mask, ear plug, boot eye shield (industrial
goggle)
(g) Safety equipment such as hose, fire fighting equipment
(h) Overhead and profit
(12) Temporary Fencing, Hoardings, Screeds, Fans Gantries and Similar Items.
Each will comprise the cost of
(a) Labour and materials
(b) Maintenance
(c) Removal and making good
(d) Overhead and profit
6
(14) Removing Rubbish and Site Clearance on Completion of Project.
This involves the cost of
(a) Labour and materials clearing off such rubbish.
(b) Plant, lorry and labour loading such lorry transporting the rubbish from site (c) Labour and materials
cleaning up door, windows etc.
(d) Overhead and profit
7
3.2 Class Workshop
The appendix below is a summary of the bill for the case study project. Students will be expected to appreciate
and be able to work out how preliminary items in the bill are priced and distributed between time or cost related
and fixed charges for the purpose of monthly valuations.
Procedures:
The work book will be made available to students at the beginning of the lecture. Time will be allowed for
students to read and comprehend the notes. Students will then be asked to sit in groups of between 3 and 4 to
discuss their understanding and set up query list on the project.
After about 30 minutes, each group will be required to use the preliminaries breakdown form to identify
percentage allocation of each preliminary item across the table and to provide justification for the allocation on
each item.
Appendix 1 attached shows the tender submission details and actual progress achieved on site for monthly
valuation purposes on a typical construction project.
(a) Allocate the preliminaries to ‘time related” and “lump sums” sections (Use form
Appendix 2).
8
Total Bill No. 1 £30,028.00
£184,610.00
Bill No. 4 Prime Cost Sums
Nominated Sub-Contractor
A Piling £ 8,500.00
B Profit 5% 425.00
C General Attendance Item 170.00
9
D Specialist Landscaping 27,000.00
E Profit 5% 1,350.00
F General attendance Item 600.00
Nominated Suppliers
L Ironmongery 5,000.00
M Profit 5% 250.00
Statutory Undertakings
10
Bill No. 2
Item A complete
Item B complete
Item C complete
Item D complete
Item E complete
Item F 50% complete
Item G 40% complete
Item H 40% complete
Item J 20% complete
Item L 10% complete
Bill No. 3
Item A 20% complete
Item B 20% complete
Item C 40% complete
Item D 40% complete
Bill No. 4
Item A complete
Item D £8,600
Item G £8,000
Item J £6,000
Item L £2,000
Item N complete
Item P complete
Item R complete
Bill No. 5
Variations £9,000.00 agreed.
Materials on Site £6,237 agreed.
The following AI’s were received from the Architect in respect of the following Prime Cost and Provisional
Sums:
1. Accept a quotation of £10122.50 from Keane & Bonney Piling Ltd.
11
It was observed that the Piling nominated sub-contractor had erroneously left out the main contractor’s discount in
their quotation for the works. Effect the necessary corrections before valuation.
3. Accept a quoation of £19012.00 from Kitchen & Sons for the supply of kitchen fittings.
4. Accept a quoation of £13176.00 from Loo Ltd for the supply of sanitary fittings.
5. Accept a quoation of £8820.00 from Smith & Smith for the supply of ironmongery.
12
APPENDIX 2
Plant
Welfare
Site Huts
Telephones
Temporary
Lighting
power and
Programme
Watching
Site Hoarding
Temp Roads
Setting Out
Drying the works
Cleaning Rubbish
Water
Insurance
TOTALS
Questions:
(1) Define prelimiaries and give three examples of a “prelimiary item”
(2) How do contractors price these items?
(3) Define fixed costs and provide five examples of an item you think would be priced as a fixed cost item
(4) Define time related costs and give five examples of preliminary items you think a contractor would price
as a time-related cost.
13
Reference: CIOB (1997) Code of Estimating Practice, 6th Edition. Ascot: CIOB
The preparation of a tender can be divided into six stages.
14
• Period for which the quotation is open for acceptance
Sub-contractors
Photocopies of the relevant parts of the bill of quantities, specifications and if possible copies of drawings, should
be sent out to perspective sub-contractors. Enquires should state clearly:
• The items to be priced
• The terms of the main contract
• The period for which the quotation is open for acceptance
• The plant, materials, attendance etc to be provided by the main contractor
• Anticipated commencement and completion dates
• The form of contract and details from the appendix
• The terms of payment
• Date by which the quotation is to be submitted
• Address and details of the site
15
It must be decided whether:
• All labour can be obtained locally or will it be necessary to recruit for the project.
• Sufficient plant is already owned or is it necessary to purchase/hire additional items.
• It would be desirable to sub-let any further work.
The preliminary programme should also be prepared containing the following information:
• Contract starting and completion dates
• Any work to be done in stages
• Work to be sub-let by main contractor
• Work to be done by nominated sub-contactors (if JCT 98 form)
Following evaluation of the alternatives, risk and scope for profitability the ‘mark up’ is determined and the actual
tender figures calculated. The decision being made within the framework of company policy.
A record of all tenders should be kept together will the results (if known) for future reference.
16
4.10 Action after Submitting a Tender
4.10.1 Action with a successful tender
Check contract documents to ensure that:
• The dates, penalties etc are the same as those contained in the tender documents
• The bills have been copied correctly from the original
• The drawings are those which were circulated with the tender documents
Disseminate information
Information should be made available to those responsible for purchasing, construction planning and plant.
Feedback information
Feedback from site on labour and plant outputs etc, to be kept for future pricing
Cost/Value Reconciliation
At regular intervals during the construction period, the costs at that time should be compared with a meaningful
valuation of work done in order to check that the job is ‘on target’
17
subsidence may be three trust as expensive as normal strip foundations where as pile foundation used to convey
loads to a deeper load bearing strata could be as much as five times as expensive. The cost of excavation in rock
could be five to eight times as expensive as working in normal ground, the provably length of haul in the disposal
of surplus soil also needs consideration. Where ground water is close to the surface of the site, costly pumping
operations may be needed. A wet site may also involve raising temporary sheds and offices on brick bases and
more costly temporary roads. The types of strata will also influence the form and extent of timbering or other
means of supporting that will be needed to the sides of excavations.
18
MAJOR FACTORS AFFECTING TENDER PRICE (5.0)
“Construction cost” is a broad phrase or term and can be interpreted to mean cost of any sort to anyone associated
with construction work. It depends on the point of view let us say you are a contractor, your costs are your
expenditure on labour, materials and plant. The client’s cost of land, consultant fees and so on.
The base cost of construction therefore comprises of expenditure on materials, labour and plant, the quantities of
materials, labour and plant required for a job are determined & attaching prices to these defines the basic
construction cost, but to these are also a variety of factors that affect this basic cost: -
(4) Transportation:
The farther a site is from town, the more expensive will be the construction cost e.g the same building to be
constructed in Barnawa and also near Kaduna Airport will cost differently, the additional cost of transporting
materials, labour and plants to the airport site will increase the cost of construction.
(5) Location:
The standard of living in an area affects the cost of construction. People are willing to pay higher prices for
construction in places like Lagos and Abuja than are to pay in other places like Benin, Kaduna or Enugu.
19
(6) Location of Site: -
The particular location of the site can have significant effect on cost. Remote site may require additional cost for
the provision or access roads and temporary services or the provision of additional security measures. Also, a site
in a congested or restricted area also gives rise to major problems such as delivery & storage of materials and
components, protection of adjoining buildings and the public, restriction on the use of mechanical plants and so on,
all these will increase the cost of construction.
20
- Large contractors have a lot of times publicly owned with many share holders having at least six members
on their board of directors, fleet of cars and equipments, large office space and a lot of staffs of various discipline.
Generally, the larger the firm, the higher their cost. Also, the level of profit expected by the share holder of larger
firms is a lot more than that required by the smaller contractors. The rates for the small contractors therefore tends
to be much lower than for large contractors (e.g AG Ferrero and small firms)
21
PRICIPLES OF ANALYTICAL ESTIMATING (6.0)
Unit Rate
Overheads Profit
22
2. In-Direct –
These workers are self employed or referred to in industry as ‘on the lump’ these are often labour only sub-
contractors without the normal costs of employment along with the other legal protections such as redundancy,
sick pay and minimum notice periods.
Labour may be paid for on an hourly, daily, weekly or piecework basis. Directly employed operatives are usually
paid in accordance with a working rule agreement which will specify the rates and allowances to be paid.
However, some contractors are trying to move away from the national wage bargaining and introduce local wage
rates. Ultimately the actual rates paid for labour will depend on market forces.
6.2.1 Materials
Several factors affect the cost contractors pay for materials.
In the box below highlight the factors you think impact on the price a contractor pays. In the material element of a
unit rate, in addition to the actual cost of the material the estimator must also consider:
• Transportation costs
• Unloading and Stacking costs
• Materials movement on site
• Extra Materials to compensate for:
o Wastage
o Allowance for materials being measured net in B o Q o Loss in consolidation, shrinkage etc
Note: Where prices of materials are described by suppliers as ‘ex works’ this means the price at the factory and
delivery costs will have to be added.
6.2.2 Plant
Plant may be divided into two main categories, the costs of which can be allocated to contracts in differing ways.
Non-Mechanical Plant
Basic items of plant including – barrows, hosepipes, spades, trestles, scaffolding, small powered hand tools etc
With the exception of scaffolding and one or two other items it is virtually impossible to allocate the cost of non-
mechanical plant items to a contract, let alone to a specific unit rate
e.g. a wheelbarrow may be used on several contracts in its lifetime.
The cost may be included in overhead charges as a percentage, as a lump sum in the preliminaries bill or, more
accurately, on longer contracts a list of non-mechanical plant items is prepared, costed and included in the contract
sum.
Mechanical Plant
Mechanical plant such as excavators, lorries, dumpers, mixers etc require a more complex approach. Mechanical
plant can be very expensive. Contractors may buy, hire or lease plant. The purchase of plant must be viewed as an
23
investment on which a return is required. Only detailed analysis will show whether it is in the contractor’s interest
to buy, hire or lease mechanical plant.
6.2.3 Overheads
Overheads may be defined as the cost of maintaining (running) the contractors organisation.
There are two types of overheads:
(1) Head Office
Annual cost of staff salaries, expenses, rents, rates, gas, water, electricity, telephones, office equipment, postage,
insurance, maintenance of buildings and equipment etc. The cost of these items is expressed as a percentage of a
company’s turnover and included in the tender.
6.2.4 Profit
The amount of profit that a contractor can make is determined by a number of factors largely outside the remit of
an estimator. However, in larger companies the senior or managing estimator may be a member of the
management team and in smaller companies / firms the estimator may be a director or the managing director. In
both cases they may be party to, or may have to make commercial decisions regarding profit margins.
Factors affecting profit levels are:
• Market forces of supply and demand
• Amount of competition
• Who the competitor are
• Size / Value of contract • Risk involved in contract
• Interest rates.
Student Questions
1. Define analytical estimating
2. Explain the difference between net and gross unit rates
3. List the elements of a unit rate
4. Identify the organisations, which produce working rule agreements
5. Define non-productive time and holiday credits.
24
BUILD-UP HOURLY RATE FOR PLANT & EQUIPMENT (7.0)
You may use the Wessex Price Book, or other similar price book, for information on the output/productivity of
labour and plant. Materials and plant prices can be obtained from builders' merchants and plant hire firms.
In practice estimators must always use productivity outputs analysed from site feedback and the current cost o f
other resourcs.
In the following unit rate calculations the hourly labour rates used are £9.50 for craft operatives and £7.00 for
labour operatives.
7.2 Groundworks
SAQ 2
Explain how the following factors may affect unit rates for groundworks?
• Type of excavation e.g. trenches, pits, basements
• Ground conditions e.g. clay, sand, soil, rock
• Depth of excavation
• Ground water
• Time of year when excavating
• Mechanical or hand excavation
• Distance and availability of tips
• Estimated bulking of materials
7.2.1 Hand Excavation
Excavation work is usually measured in cubic metres (m3)
Typical labour outputs for excavating in firm earth ;
Reduce levels maximum depth 0.25m 3.15 hours/m3 Trenches max. depth 1.00m
3.25 hours/m3 Basements max. depth 2.00m 3.94
hours/m3 ADD the following factors for other ground conditions ;
25
Example
Excavate trench maximum depth 1.00m in firm earth, unit of measurement m3.
Labour;
£ - p
3.25 hours for a labourer @ 7.00/hour 22 - 75
---------
Net Rate per m3 22 - 75
If you want a Gross Rate add for
overheads and profit, say 10% 2 - 28
----------
Gross Unit Rate per m3 25 - 03
======
TQs 1 - 3
Calculate net unit rates for the following ;
1. Excavate to reduce levels max. depth 0.25m in firm earth,
unit of measure m3
When calculating “all-in” hourly rates for mechanical plant the following items should be considered ;
• Capital cost
• Depreciation
• Interest on capital
• Expected life of plant
• Number of hours worked per annum
• Maintenance • Insurance
26
• Road licence
• Operators wage
• Fuel
• Lubricants
Think about how the above factors will affect the hourly cost of mechanical plant.
Example
The following is one method of calculating the all-in hourly cost of a mechanical excavator. This method is neither
the simplest nor most complex method which can be used but it does produce realistic costs.
Standing Charge £ p
27
Total cost for 5 years divided by total hours worked in five years
£63006 / (1600 hours x 5 years) £7-88
Running Charge
Drivers wages 1856 hours @ £7.50 13,920-00
Fuel 1600 hours x 5 litres/hour x 40p/litre 3,200-00
Lubricants 10% of fuel costs 320-00
-------------
Total for 1600 hours 17,440-00
-------------
28
SAQ 3
The output of the excavator may also be expressed in hours per m3 , what is the output in hours per m3 ?
7.4 Banksmen
Banksmen are usually employed to supervise excavator/s. They check the excavation for obstacles i.e.
underground services, make sure the excavator operator is working to the correct line and level and trim the sides
and bottoms of excavations when necessary.
TQ 5
Recalculate the last rate and include for one banksman supervising two excavators, banksman’s rate £7.00 per
hour.
TQ6
Using the excavator and lorry from the previous example and the following information, calculate the cost per m3
for disposing of excavated material off site
Note ; The following items are all variables (will vary on every contract) therefore a new rate must be
calculated for each contract
Assume ;
16 ton lorry will carry approx. 6.5m3 of bulked clay
Output of excavator 5m3 per hour
Distance to tip 5 miles round trip
Average speed 20 miles per hour
Tipping time 15 minutes
29
Tipping charge £20 per load
The contractor has to decide what is necessary and cost it accordingly. This is referred to as a contractor’s risk
item
The following factors affect the cost of earthwork support ;
• Ground conditions
• Depth of excavation
• Distance between opposing faces of excavation
• Method of support used
Contractors should also consider alternative methods of construction, which may be less expensive e.g. over
excavate and backfill.
Timber used for earthwork support (EWS) can be re-used up to say 6 times therefore the cost of providing the
timber should be divided by the number of uses to obtain a “cost per use”.
Operatives fixing EWS are usually paid an additional allowance for skill and responsibility.
Materials
100 x 100 costs £1-92/m
150 x 100 costs £2-88/m
150 x 150 costs £4-32/m
200 x 50 costs £1-92/m
Labour
Fixing EWS in moderately firm earth to faces of excavation up to 2.00m apart and up to 2.00m deep (see sketch) -
0.77 hours per m2
30
8.1 Surface Excavation
In building up rate for excavation, the following should be considered.
(a) Types of excavation i.e surface or trench excavation
(b) Means of excavation i.e manual or mechanical
(c) Nature of excavation
(d) Volume of excavation (bulking)
(e) Distance of tipping (haulage)
Bulking
Sand 12.5%
Gravel 10%
Clay 133 1/3%
Rock 50%
OUTPUT
Excavation 2.5m3 / labour /day
Spreading and leveling 4.5m3 / labour / day
Wheeling / haulage 8.0m3 / labour / day
Placing of concrete 4m3 / labour / day
Task I:
Surface excavation n.e 300mm deep and average 150mm, considered a gang of 12 labour and the supervisor.
Calculate the cost/m3 given that the supervisor is N1500/day and the labourer
N700/day
Solution Labour cost
1 supervisor @ 1500/day N1500
12 labourer @ 700/day N8,400
Add 5% for tools N495
N10,395
Output of gangs / day = 2.5m3 x 12 = 30m3
31
Add profit and overhead 20% 69.30
Cost/m3 = 415.80
Task II
Cost of spreading and leveling excavated materials n.e 50m from excavation. Consider a gang of 12 labourers and
1 supervisor
Solution
1 Supervisor @ 1500 = N1500
12 labouers @ 700 = N8,400
5% Tools = 495__
10,395
Output gang / day = 4.5 x 12 = 54m3
Loabour cost / m3 = 10,395/54 = 192.50
Add overhead and profit 20% = 38.50
97.33
Task III
Removal of excavated materials using the same distance of cart away is less than or equal to 50m using the same
information used for excavation of surface
Solution
1 Supervisor, 12 labourers and 5% for tools = 10,395
Out out of gang/day 8.0 x 12 = 96m3
Labour cost / m3 = 10,395/96 = 108.28
Add 20% profit and overhead = 21.66
225.94
355.88
When lories / tipper are used the following should be considered
(b) Cost of hire or cost of owning
(c) The capacity of the lorry
(d) Total distance to and fro the hill
(e) Speed of lorry
(f) Tipping time
(g) Labour loading the lorry
(h) Bulking of materials
32
TASK IV
(a) For the cost of hiring plant is 600/hr
(b) Capacity of lorry 6m3
(c) Total distance to and fro is 3km
(d) Speed of lorry 30km/hr
(e) Tipping time 9 minutes
(f) Output of labourer loading the lorry is 2hrs / labour /m 3
(g) Bulking of materials 133 ⅓%
SOLUTION
Volume of excavated material = 6/133 ⅓ x 100 = 4.5m 3 (assume 4 labour) loading time = 4.5m3 x 2hrs
= 2.25hrs
4
Traveling time = 3km x 60m = 6mins
30km/hr
Total time for loading + traveling + tipping
2.25 + 6m + 9
2.25 = 2.15hr + 6m + 9m
Cost of hiring lorry/hr
= 2.5hrs x N600/hr
= N1500/hr
Therefore, cost/m3 = N1500 = 333.33/m3
Labour loading
Cost for 1 labour /m3 = 150/8 x 2.5hr x 4 labour = 187.50
Add 5% for tools = 9.38
196.88
333.33/m3
530.21
Add 20% overhead and profit 106.04
636.25
33
BUILD-UP UNIT RATE FOR CONCRETE WORK I (9.0)
TQ 7
Calculate the cost of mixing a m3 of Grade 15 concrete on site using the following information ;
To produce 1m3 of mixed Grade 15 concrete requires ;
250Kg of cement at £80 per tonne
600Kg of sand at £10 per tonne
1200Kg of aggregate at £9 per tonne
Waste say 5%
Concrete mixer all-in rate £2-50 per hour, output 2m3 per hour
Labour rate £7.20 per hour
Labour out put 0.5m3 per hour
Ready-Mixed Concrete
TQ 8
Calculate the cost per m3 for laying plain concrete 20N/mm2 in foundations over 300mm thick laid against faces
of excavation.
Ready mixed concrete costs £49.00/m3
Waste say 5%
Labour output 1.00 hours/m3
Labour rate £7.20 per hour
SAQ 4
34
What will happen to the labour output if the concrete is laid in foundations 150mm thick? Reinforcement is
measured separately in bills of quantities. Would you expect the unit rate for laying reinforced concrete (excluding
the cost of reinforcement) to differ from the unit rate for plain (unreinforced) concrete for similar items of work
and if so why?
9.2 Reinforcement
Reinforcement may be bar type or mesh/fabric
Waste
Bars are usually delivered to site already cut and bent, if this is the case then allow 1% for loss and damage.
If straight bars are to be cut and bent on site allow 5% for waste.
On complex reinforced concrete work steel fixers are usually paid a craft operatives rate.
When laying straight bars or mesh an enhanced labourers rate is usually paid.
Mesh reinforcement is sheet material therefore allowances have to made for general waste say 2.5% plus an
additional allowance for laps. The percentage to allow for laps will depend on the lap specified e.g. 150mm side
and end laps.
TQs 9-10
Sheets of mesh are approximately 4.80m x 2.40m if they are to be laid with 150mm side and end laps what % must
be allowed for loss in cover due to the laps ?
Mesh reinforcement Ref. A193 in beds laid with 200mm side and end laps.
Calculate the rate per m2.
Mesh costs £14-00 per sheet
Labour 0.05 hours / m2 at £7.20 / hour
Allow say 20p / m2 for spacers and tying wire
35
Task One
In the box below, describe how you think the following factors would impact on cost.
When considering concrete there are two main methods of producing concrete:
7. Protection of un-set and curing concrete 1. Site mixed
concrete
2. Ready mixed concrete
In addition to the method of concrete production when costing concrete work we must also consider concrete
accessories including:
1. Formwork
2. Reinforcement
3. Operatives working with concrete usually receive additional payments for skill and responsibility
4. Items of plant concerned with concrete mixing and placing are usually measured separately.
36
• Ready mixed concrete say £80.59 / m3
• Waste say 5%
• Labour output = 1.00hrs / m3
• Labour rate £8.68 / hr Questions:
1. How would the labour output be affected if the concrete is laid in foundations 150mm thick?
2. What would be the financial impact? (If any)
Qu 1.
Sheets of mesh are approximately 4.80m x 2.40m if they are to be laid with 150mm side and end laps what
percentage must be allowed for loss in cover due to the laps?
Qu 2
Calculate the rate per m2 for laying mesh reinforcement Ref A193 in beds, laid with 200mm side and end laps.
Additional information
• Mesh costs £15.08 per sheet
• Labour 0.05hrs / m2 @ £8.68 / hour
• Allow say 20p / m2 for spacers and tying wire
• Waste on mesh 5%
37
• BUILD-UP UNIT RATE FOR CONCRETE WORK II
38
the cost of reinforcement) to differ from the unit rate for plain (unreinforced) concrete for similar items of work
and if so why?
9.7 Reinforcement
Reinforcement may be bar type or mesh/fabric
Waste
Bars are usually delivered to site already cut and bent, if this is the case then allow 1% for loss and damage.
If straight bars are to be cut and bent on site allow 5% for waste.
On complex reinforced concrete work steel fixers are usually paid a craft operatives rate.
When laying straight bars or mesh an enhanced labourers rate is usually paid.
Mesh reinforcement is sheet material therefore allowances have to made for general waste say 2.5% plus an
additional allowance for laps. The percentage to allow for laps will depend on the lap specified e.g. 150mm side
and end laps.
TQs 9-10
Sheets of mesh are approximately 4.80m x 2.40m if they are to be laid with 150mm side and end laps what % must
be allowed for loss in cover due to the laps ?
Mesh reinforcement Ref. A193 in beds laid with 200mm side and end laps.
Calculate the rate per m2.
Mesh costs £14-00 per sheet
Labour 0.05 hours / m2 at £7.20 / hour
Allow say 20p / m2 for spacers and tying wire
TASK
Example a tonne of cement cost N14,000, sand cost 560/m 3, coarse aggregate cost 900/m3 for a mix of 1:2:4.
Calculate the cost/m3
Solution
1m3 cet will cost 1.44 @ 14,000 = 20,160
2m3 of sand will cost 2 x 560/m3 = 11,120
39
4m3 of aggregate will cost 4 x 900/m3 = 3,600
24,880
7m3 = 24,880
1m3 will cost 24,880 = N3,554.29
7
Add 50% of void and compaction 1,777.14
5,331.44
Add 20% overhead and profit 1066.29
6,397.73
Mix shrinkage broken stone
cement sand agg cement sand agg
tonnes m3 m3 tonnes m3 m3
1:1:2 0.524 0.36 0.72 0.552 0.38 0.76
1:2:4 0.304 0.42 0.84 0.32 0.44 0.88
1:3:6 0.440 0.44 0.88 0.23 0.46 0.92
(void and compaction here have been taken care of)
Plant
Cost of mixer/hr
The cost of owning and operating a 10/7 concrete mixer. Assume initial cost of N150,000, a scrap value of
N10,000
Life span of 6yrs @ 2000 hrs/year
Compute the cost/hr
40
Therefore, cost /m3 = 3,798.16 = N189.91
20m3
Fixing/tonne
Diameter 6 8 10 12 16 20 25 32 40 50
Hours 63 45 35 27.2 22.5 15 12.5 10 8 6
NOTE:
1. Assume 3hrs for unloading 1 tonne of reinforcement
2. Allow 5% waste for cutting form straight length
3. Allow 1% waste reinforcement already cut to shape
41
4. for bars in short length e.g links and stirrups, allow 33% for extra labour
Tying wire/tonne
Diameter 6 8 10 12 16 20 25 32 50
Hours 15 15 12 10 8 8 6 5 4
TASK I
16mmø mild steel bars reinforcement in straight and bent bars in suspended slab – kg
Solution
A Material Labour
A1 16mmø
A2 Tying wire B1 Cutting and bending
A3 Spacers B2 Fixing
A1 Materials/tonne (1000kg)
Assume cost of 16mmø @ 34,000/tonne = 34,000
Unloading and stacking 3hrs@400 = 1,200_
35,200
Allow 5% for waste 1760_
36,960
A2 Tying wire
Assume 8kg @ 60/kg = 480
Allow 5% for waste 24__
504_
A3 Spacers = N1000
Allow 3% waste 30
1030
Material collection
A1 36,960/tonne
A2 504/tonne
A3 1030/tonne)_
38494/tonne
Labour
B1 Cutting and bending
22.5hrs @ 50/hr = 1,125
42
Labour collection
B1 = 1,125
B2 = 1,125
2,250
Summary
43
BUILD-UP UNIT RATE FOR FORMWORK (12.0)
12.1 Formwork
Formwork measures the actual faces of work covered or to be supplied. The following must be taken
2. The kind of finishes required i.e sawn faced or smooth finish, ground finish, biscuit etc. This
determine the types of materials to be used as formwork and the surface from finish required is
removed.
3. the height to be supported. This determine the height of props and types of props.
5. the number of uses required of the formwork this is usually a matter of experience.
In small contract it may be possible to reuse the same formwork twice depending on the repetitive
Materials
Materials Unit Rate
2 x 4 x 12 Length 120
4 x 4 x 12 Length 180
5” nails Kg 135
4” nails Kg 135
3” nails Kg 135
2” nails Kg 150
44
Unloading and stacking 2.5m3/lbour/day = 250
Nails 20%
TASK I
Solution
Materials
A1 1 x 12 x 12 softwoods planks
A2 2 x 4 hardwood battens
A3 4 x 4 hardwood props
A4 4” nails
Labour
B1 Unloading and stacking
B3 Striking
NOTE:
3.6 x 1.2 for the calculation and divide by 4.32m2 after all to arrive at cost/m2. This convenient size
allow for more length of timber piece to be used and there by simplifies the calculation
4 x 12 = 4.8
45
12.00
480.00
12.00m = 3 ⅓ length or 3.33 + 1 = 4 x
3.6m
Assume 3 uses
Cost/use = 2,868 = 956
3
Cost/m2 = 956 = 239
4.32
Labour
Volume of timber
25 x 300 x 3600 x 4nr = 0.108
50 x 100 x 3600 x 2nr = 0.0136
50 x 100 x 1200 x 4nr = 0.24__
0.408
Allow 10% for waste 0.041___
0.449m3
46
Unloading and stacking
47
Summary
Materials = 221.30
Labour = 819.27
1,040.57
48
BUILD-UP UNIT RATE FOR ROOFING (13.0)
13.1 Roofing
Corrugated roofing sheet, operation output /gang / day
Aluminium of galvanized iron unloading + fixing 40m2
49
ASSIGNMENT
50