You are on page 1of 7

RISK ASSESSMENT - DRILLING WHILE PRODUCING & VENTING

Activity Drilling While Well producing & Venting


Location A-9, A-20, A-13 on Alpha
Equipment and
Personnel Involved Alpha Platform installation and facilties, BOP, GERD rig, all rig personnel, production operator and/or other production/facilities personnel, third party personnel w

Relevant HSE Documents Drilling HSE Plan, APCC/BORR Bridging Document, SIMOPS Procedure, BOCP, Well Control Manual, OSCP,
RISK ASSESSMENT
STEP HAZARD - WHO / WHAT
TASK RISK CONSEQUENCE
No. POTENTIAL INCIDENT MAY BE Likelyh
AFFECTED Severity Risk
ood

Activity is normally carried out without permit to


work

Presence of a drilling Rig

40m high may be located close to well


drilled/rigfloor

release of natural gas or other hydrocarbon Fire/ vapor


0
vapours, water vapour, or other gases cloud explosion

toxic or hazardous vapors Burns

1 overpressure or pressurised equipment Fire & Explosion Heat stroke


People Heat stroke
Flaring without Flame (Venting) 4 B High
emergency venting Assets burns Loss of hearing
Abandon
Ignition source (e.g. from lightening in storm) Other Injury or
death
Smoke /emissions (Nitrogen Dioxide, Sulphur
Dioxide, Carbon Dioxide, Carbon Monoxide, Damage to
Particulates) Equipment

equipment failure on venting systems

Heat radiation

Noise

Wind direction

Generators running (Electrical energy)

Dewatering system

Gas leak on platform

Transfer/Lifitng of poorly secured equipment from


Supply Vessel e.g wrong slinging, poorly locked
Injury or death
containers, poorly secured shackles
Falling/Dropped object to Personnel
People
2 Routine Production and Maintenance on platform Personnel struck or 3 B High
Use of defective crane, lifting gear or other Assets
caught between Damage to
equipment
Equipment
Equipment Malfunction

Personnel in No Go Zone

Noise
Noise

Unfavourable Weather conditions

Damage to sea lines

Loss of DP for vessel Potential loss of HC


Collision with platform, rig move vessels, existing containment
well
Injury or death
punch through Fire & Explosion
People to Personnel
Rig Move/Positioning (skidding, preloading, spudding) Well control event
3 Assets 4 B High
Dropped Obejcts Damage/Loss of assets
Env Damage to
Equipment failure sea lines, rig
Assets
Human error
Lack of / Poor Communication Pollution
Adverse weather conditions
Abandon

Leak on rig/ Plugged line from well control


equipment
Collision with producing well while drilling
Pressurized annuli on drilled well
Loss of well control while drilling
Loss of containment
Human error / Personnel not qualified Injury to
Blow-out resulting in toxic
Reservoir pressure Personnel
People gas dispersion
Losses
Assets fire and explosion
4 General Drilling - Simops Unexpected high pressure zone Damage to 4 B high
Env Multiple fatalities
Well control - Equipment failures (BOP) equipment
Pollution
Wrong procedure
reputation
Kick
use of radioactive source
Use of explosives
Maintenance not followed
Hidden energy
Noise
Personnel located inside HP area
Electrical origin (Short circuit)
Hot work (Spark, conduction, convection, radiation)
Equipment overheating
Equipment without EX certification / equipment not
adpated to Zones
Leak on rig/ Plugged line from well control
equipment
Loss of well control while drilling Spills/leaks Injury to
Human error / Personnel not qualified People Burst lines/hoses Personnel
5 Drilling on Rig Floor SIMOPS Well control - Equipment failures (BOP) Assets Fatality or multiple 5 C High
Wrong procedure Env fatalities Damage to
Kick Injuries / Burns Equipment
use of radioactive source
Use of explosives
Maintenance not followed
Fire fighters not properly trained
Acces from platform to Rig compromised
Safety equipment failure (life raft, life vest , BA set,
etc.)
communication failure (Radios / Paging system)
Dropped object from the derrick and fall on
platform

Unsafe lifting operation carried out by crane

Improper use of man basket over the derrick

Failure of lifting equipments

Personnel below lifting trajectory and suspended


load or inside red zone
Injury to
Fatality or multiple Personnel
BOP lifting from rig stump to platform well hatch People
6 Lifting Ops SIMOPS fatalities 4 B High
Assets
Injuries Damage to
Blind and complex lifts
Equipment
Equipment failure (BOP hoist, slings, schakles)

Lifting plan not followed

Mechanical
Potential energy

Gravity

Team Composition:

Reviewed:

Name: Signature
RISK ASSESSMENT - DRILLING WHILE PRODUCING & VENTING ON ALPHA PLATFORM

g, all rig personnel, production operator and/or other production/facilities personnel, third party personnel working on the Rig

IMOPS Procedure, BOCP, Well Control Manual, OSCP,

CONTROL MEASURE/
RECOVERY PREPAREDNESS
ACTION PARTY

Include in PTW, and Tool Box Talk

Select and use proper PPE

The volume of gas vented monitored through Flare meters.

Do not exceed limits of volumes allowd to be vented and Stop venting at certain points of drilling sequence,
eg hammering, hole cleaning, etc…

ESD tests shall be carried out (platform and Flare)

Platform gas detectors and alarms are in place and triggered in case of excessive accumulation of gas on OIM
platform
Platform
Operator
Dedicated platform operator shall always be on the site to monitor flare carry out daily checks and notify in
case of any anomaly e.g. ignition loss

standby vessel with FIFI

Stop work authority to be enforced in case conditions seem unsafe

Implement no Go Zone around flaring area

Follow SIMOPS requirements to obtain approval of RSES before beginning work on the platform
Follow T-card system
OIM
Select and use proper PPE
Maintain good communication with Radio room
Platform
Daily checks by platform operator (SCR room, Generator room, etc.)
Operator
APCC Platform Shutdown and depressurized during rig approch and positioning
Sea bed survey recommendations to follow footprint of former rig
All equipment inspected and certified
Conduct risk assessment
follow PTW procedure
Rig positioning to occur only during day light
Rig move procedure to be followed
use of radio and other tools to maintain good communication
stop if weather not favorable
Rig OIM
Remove non-essnetial persons from rig
SIMOPS Procedures and Risk Assessment for Drilling and Workover Vs Production activities
Vessel Captain
BOCP, Well Control Manual and anti-collision
APCC Spill Contingency plan as reference doc covering drilling activities
Spill Kits and pump available on board
Chemicals properly stored
equipment secured on deck
MSDS available on the rig, LMP and on the boats during transportation
DROP survey prior to start drilling operation. Second retention system. Tools secured
Management and Maintenance systems in place
Rig floor exclusion zone (Red Zone) implemented

Radio opertor on rig in charge to manage the POB


T-card sytem to be strickly followed by personnel
Rig /Drilling/ well control/ APCC procedures, program, Well integrity management system
Trained and competent personnel (IWCF, etc...)
Permit to Work System (Regulation of hot works according to the SIMOPS Matrix and SIMOPS instruction)
Pre-job and Pre-spud meeting including shallow gas section
adjascent wells shutdown and depressurization as per simops procedure
Rig Audit, Acceptance & Inspections to be applied.
Safety equipment back-up, certification by third party
Daily, Weekly, monthly check and testing of equipment - BOP and well control equipment (e.g choke and kill
lines)-Regular testing pressure tested every 2 weeks and function tested every 1 week - 5 yearly certification
of well control equipment
Weekly drills and/or trainings using safety devices
Proper maintenance PMCM
Additional ESD push buttons on Rig (accommodation,Gangway and rig floor)
Well barrier policy - 2 independent barriers required for drilling ahead (drilling mud and BOP)
BOP redundancy-BSR, variable,pipe rams annular preventer
Use of explosives must be done by a specialist only.
RSES
Explosives must be packed in special containers, stored in a safe place (Jettison system, protected against
fire, falling objects etc…) and be fitted with a positioning device to recover them if dropped over board (Buoy)
Rig OIM
The storage of detonators and explosives must be separated from explosives.The containers must be closed
and locked.
No Go Zones applied and respected
PTW and JRA implemented
Specific risk assessment to be done to highlight potential damage, risk and remedial actions regarding well
head and flow lines of adjacent producing wells (Partial Shutdown)
A high voltage electric firing system shall be selected (No radio silence)
Restricted access to rig floor
Mud tank trap to be closed / locked
Rig clinic to be equiped with material as described in the Rig related lists
Stand by supply boats FIFI
Rig Fire water system to be fully operational
Rig life boats to be ready for evacuation
Platform life raft to be ready for launching
Rig / APCC personnel to muster on Rig as primary Muster point
BOCP - OSCP - MEDEVAC - APCC emergency plan + site contingency plan (ERT)
MEDIC to be permanently on rig site
First aiders certified
Use of proper PA and radios for communication
Additional ESD push buttons ( Rig accomodation, Gangway, Rig Floor) to be fully operational
Production platform to be shut in and depressurizedas per simops procedure
Maintenance schedule to be strickly followed for all electrical equipments
Use of anti-spark equipment mandatory inside zone 0/1 (brass hammer)
All equipments inside zone 0/1 to be cerfified EX
Fire equipment certified, inspected regularly
Smoke and heat detection in various locations
Gas detectors on platform
Fire teams to be trained and fire fighters certified
Deluge system under cantilever to avoid fire escalation on platform
RIG OIM
Stand-by boats in the immediate rig vicinities
Daily audits to be carried out by maintenance Dept.
Driller
(SCR room, Generator room etc.)
Daily safety tour
RSES
Regular fire fighting system maintenance
regular drills
Hydrocarbon storage drip pan directly conencted to a tank to prevent spillage
Zero discharge rig
Anomaly reporting system STOP card
Stand by supply boats FIFI
Life boats specification
Muster stations to be managed by competent person
Regular emergency preparedness
Rig abandon to be assessed quickly
Supply boats to be in the immediate rig vicinities

Dropped object programme implemented


Daily/weekly derrick inspection
Reinforced rig floor
Rig floor impact certification
Red zone around rotary table
Double nuts policy in derrick (Drilled + safety pin)
Derrick log book policy
Drop’s bag, design adapted hand tools, etc.
Crane certified and maintenance programme in place
PTW and JSA implemented
Lifting plans (As per APCC vs CDLP Bridging document)
Crane operator certified and able to use STOP practise RSES
Lifting gear certification update
Lifting color coding as per APCC clour coding policy Rig OIM
Daily visual lifting gears inspection
Banksman in place with high visibility jacket Barge Master
Lifting hook to be used to retrieve tag lines
Implement No Go Zone Nobody under the load)
Crane certified and maintenance programme in place
Proper communication between parties
Anomaly reporting system
Platform/adjecent wells shut down
RSES to minimize personnel on upper platform deck during lifting operation
Barricade in place on platforms during work overhead
APCC Must Do rules # 12 to apply
PA/GA announcement
Radio check before lifting

Date: