Timeline of various events occurred in jarwa

Date Events Remarks

3/5/2018 Letter of Award

4/9/2018 Appointed Date

6/15/2018 Request for increase ( alloted time ) In jarwa Reserve 6.00 Am to 3.00 Pm convoys

4/8/2019 Date of Project Completed as per contract agreement

09-04-2019 to 08-10-2019 (180


Information of 1st EOT (1st Extension of Time)
days)

6/12/2019 Information of Collapse of Thoratang Bridge

6/12/2019 Restored Thoratang Bridge

6/12/2019 Collapses on Thoratang Bridge same Day Again

6/15/2019 Ban on Quarry of Material by NGT.

9/2/2019 intimidation of restricted movement of trafic and working hours

09-10-2019 to 09-03-2020
Information of 2nd EOT (2nd Extension of Time)
(153 days)

11/7/2019 Thoratang Bridge Restored & Opened to Traffic (Only for LMV) Light Motor vehicle

11/12/2019 Movement of Our Hot mix plant from Thoratang Bridge intially it is restored for normal vehicles (All type Vehicle)

12/15/2019 repoening of Tendors regarding quarry allotment

3/23/2020 Nation wide lock down due to Covid-19

10-04-2020 to 31-03-2021
Information of 3rd EOT (3rd Extension of Time)
(355 days)

5/6/2020 Realaxation Given by Govt of India for contruction related activities and Contarctor seek permision to work in Jarwa.

6/29/2020 Due to Covid Cases DC Office Staff gets Covid &subsquent delay in obtaining permission to work in tribal area for about 2 days

6/29/2020 Information regarding Intimidation to immediate closure of all acctivities

10/20/2020 Request to extend of working hours from 7AM to 5AM & 3PM TO 5PM (Post -Covid)

3/31/2021 Actual Date of Completion

01-04-2021 to 31-03-2022 Start and End of Defect Liabilty Period

8/10/2022 Performace Security Deposit Released Date