FORMULAS
L=λW
WIP = Throughput x Lead Time
λ = L/W
Throughput =WIP/Lead Time
W= L/ λ
EXAMPLES
1.
How much Work in Progress has the company (in number of orders)?
Solution:
λ = 15/5 L=λW
w=3 L= 15/5 *3
L=? L= 9
2.
How many orders per week can this production can make?
Solution:
L= 9 λ = L/W
W= 3 days λ = 9/3
λ =? λ = 3 (per day)
but since we are finding how many orders per week we will multiply it by 5 since the company works
five days in a week.
3.
How many days or how much time that it consumes for a product to finish?
Solution:
L=9 W= L/ λ
W? W= 3