INSPECTION & TEST PLAN

REF. No. :
Project Name
REV. No. :
DATE: :
PAGE : 1 of 1

ACTIVITY: Acrylic Rubber Filled Coating SP-2


AREA : As per approved shop drawings
LEVEL : As per approved shop drawings
INSPECTION & ACCEPTANCE
ITEM ACTIVITY DESCRIPTION FREQUENCY SPECIFICATION / CRITERIA VERIFICATION
SUBCONT. CONT. COMPANY

1 Subcontractor/Sup. Approval Project Specifications H H R

2 Material Approval Project Specifications H H R

3 Incoming Material Inspection 10 -100% Project Specifications W W W

5 Surface Preparation 10 -100% Project Specifications H W W

6 In Process Inspection 10 -100% Project Specifications H W W

7 Final Inspection 10 -100% Project Specifications H W W

Legend: H – HOLD FOR INSPECTION W – WITNESS INSPECTION S – SURVEILLANCE INSPECTION R - REVIEW

MAIN CONTRACTOR MAIN CONTRACTOR APPROVAL COMPANY APPROVAL


NAME: NAME:

SIGNATURE: SIGNATURE:

DATE: DATE: